HomeMy WebLinkAbout2021-2026 Capital Facilities PlanCity of Auburn Capital Facilities Plan CAPITAL FACILITIES PLAN (2021 – 2026) Adopted by Ordinance No. 6803, December 7, 2020 as part of the City of Auburn Comprehensive Plan City of Auburn 25 West Main Auburn, WA 98001 (253) 931-3000 www.auburnwa.gov City of Auburn Capital Facilities Plan City of Auburn Capital Facilities Plan CAPITAL FACILITIES PLAN 2021 – 2026 TABLE OF CONTENTS Executive Summary ................................................................................................................... 1 1. Introduction Purpose .................................................................................................................................. 7 Statutory Requirement for Capital Facilities Elements ............................................................ 7 Concurrency and Level of Service .......................................................................................... 8 Implementation ....................................................................................................................... 8 2. Goals and Policies 1. Capital Facilities Response to Growth .............................................................................. 11 2. Financial Feasibility .......................................................................................................... 11 3. Public Health and Environment ......................................................................................... 13 4. Consistency with Regional Planning ................................................................................. 13 3. Capital Improvements Introduction ............................................................................................................................ 15 Transportation ........................................................................................................................ 17 Arterial Street (102) Capital Projects ................................................................................. 22 Local Street (103) Capital Projects ................................................................................... 61 Street Preservation Fund (105) Capital Projects ............................................................... 65 Water...................................................................................................................................... 79 Sanitary Sewer ....................................................................................................................... 125 Storm Drainage ...................................................................................................................... 143 Parks, Arts and Recreation ..................................................................................................... 171 General Municipal Buildings ................................................................................................... 195 Community Improvements ...................................................................................................... 207 Airport..................................................................................................................................... 225 Cemetery ................................................................................................................................ 239 Valley Regional Fire Authority ................................................................................................ 243 City of Auburn Capital Facilities Plan City of Auburn Capital Facilities Plan 1 EXECUTIVE SUMMARY A capital facilities element is one of the comprehensive plan elements required by Washington’s Growth Management Act (GMA). Capital facilities generally have long useful lives, significant costs and tend not to be mobile. The GMA requires that capital facilities elements include an inventory of existing capital facilities showing locations and capacities, a forecast of future needs for such capital facilities, proposed locations and capacities of new or expanded capital facilities and at least a six-year plan to finance capital facilities with identified sources of funding. The GMA also requires that the land use element be reassessed if probable funding falls short of existing needs. This document is the City’s six-year Capital Facilities Plan (CFP). The CFP, in conjunction with other City adopted documents, satisfies the GMA requirement for a Capital Facilities Element. It addresses one of the GMA’s basic tenets: to provide adequate facilities to support development in accordance with locally adopted level of service standards. This CFP will enable the City to: (1) make informed decisions about its investment of public dollars, and (2) make timely decisions about maintaining level of service in accordance with this CFP and other adopted plans. CAPITAL FACILITIES PLAN CONTENT This CFP consists of the following: Chapter 1. Introduction Purpose of CFP, statutory requirements, methodology. Chapter 2. Goals and Policies Goals and policies related to the provision of capital facilities. Chapter 3. Capital Improvements Proposed capital projects, which include the financing plan and reconciliation of project capacity to level of service (LOS) standards. This CFP is a companion document to the Capital Facilities Element of the Auburn Comprehensive Plan. The Capital Facilities Element of the Auburn Comprehensive Plan identifies the City’s planning approach and policy framework for the provision of capital facilities. This CFP provides the background inventory, identifies proposed projects and establishes the six-year capital facilities plan for financing capital facilities. The comprehensive plan contains timeframes that are the intended framework for future funding decisions and within which future actions and decisions are intended to occur. However, these timeframes are estimates; depending on factors involved in the processing of applications and project work, and the availability of funding, the timing may change from the included timeframes. The framework does not represent actual commitments by the City of Auburn that may depend on funding resources available. City of Auburn Capital Facilities Plan 2 GROWTH ASSUMPTIONS In planning for capital facilities, contemplation of future growth needs to be considered. The CFP is based on the following City population forecast: Year Population 2020 81,940 2021 83,005 2026 87,239 The population forecasts are based on information from the State of Washington Office of Financial Management (OFM) as well as estimates developed by the City of Auburn Planning and Community Development Department. CAPITAL COSTS OF FACILITIES Based on the analysis of capital improvements contained in this document, the cost of City- owned and managed capital improvements for 2021- 2026 is summarized as follows: Type of Facility 2021 - 2026 Transportation - Arterial (102)42,717,401$ Transportation - Local (103)10,600,000 Transportation - Street (105)15,545,652 Water 45,799,698 Sanitary Sewer 15,936,000 Storm Drainage 21,305,100 Parks, Arts & Recreation 13,583,850 General Municipal Buildings 7,661,320 Community Improvements 8,470,810 Airport 16,491,360 Cemetery 395,000 Total 198,506,191$ City of Auburn Capital Facilities Plan 3 FINANCING FOR CAPITAL FACILITIES The financing plan for the citywide capital improvements includes: Funding Source 2021 - 2026 Capital Facility Grants 17,094,382 Transportation 2,378,000 Parks, Arts & Recreation 590,000 General Municipal Buildings 2,147,240 Community Improvements 655,970 Storm Drainage 225,000 Water 4,480,830 Airport User Fees / Fund Balance 32,640,364 Water 16,516,667 Sewer 21,229,797 Storm Drainage 395,000 Cemetery 298,000 Equipment Rental 408,980 Facilities 2,689,630 Airport Arterial Street Fund 3,090,000 Transportation Arterial Street Preservation Fund 13,525,000 Transportation Local Revitalization Fund 245,000 Community Improvements Bond Proceeds 3,810,900 Airport 8,620,000 Water DWSRF Loan 4,895,000 Water Municipal Parks Fund 300,000 Parks, Arts & Recreation Property Tax 918,500 Parks, Arts & Recreation Mitigation/Impact Fees 19,388,671 Transportation 5,982,350 Parks, Arts & Recreation 850,000 General Municipal Buildings 759,570 Community Improvements REET 1 4,672,340 General Municipal Buildings 2,250,000 Transportation - Local Streets 1,250,000 Parks, Arts & Recreation REET 2 4,469,000 Community Improvements 180,000 Parks, Arts & Recreation 400,000 Transportation - Arterial Streets 1,450,000 Transportation - Local Streets Other Sources 4,765,000 Transportation - Arterial Streets 6,000,000 Transportation - Local Streets 850,000 Community Improvements 5,510,000 Airport 2,575,000 Parks, Arts & Recreation Total 198,506,191$ (Includes grant funding that has not been secured) City of Auburn Capital Facilities Plan 4 SUMMARY OF IMPACTS ON FUTURE OPERATING BUDGETS The forecasted impacts of new capital facilities on the City’s future operating budgets (2022-2027) are as follows: Budget Year:2022 2023 2024 2025 2026 2027 Total 1 Transportation 6,350$ 9,850$ 13,850$ 18,350$ 20,850$ 23,350$ 92,600$ 2 Water - - - - - 600 600 3 Sanitary Sewer - - - - - - - 4 Storm Drainage - - - - - - - 5 Parks, Arts and Recreation 15,000 15,000 17,000 17,000 17,000 22,000 103,000 6 General Municipal Buildings 95,000 95,000 95,000 95,000 95,000 95,000 570,000 7 Community Improvements (137,500) (137,500) (137,500) (127,500) (127,500) (127,500) (795,000) 8 Airport - - 2,000 2,000 4,000 4,000 12,000 9 Cemetery - - - - - - - Total (21,150)$ (17,650)$ (9,650)$ 4,850$ 9,350$ 17,450$ (16,800)$ Project summary details are located on the following pages: Transportation page 77 Water page 124 Parks & Recreation page 193 General Municipal Buildings page 206 Community Improvements page 224 Airport page 238 City of Auburn Capital Facilities Plan 5 LEVEL OF SERVICE (LOS) CONSEQUENCES OF THE CFP Based on the proposed six-year capital projects and the projected population increase of 4,234 (5%) between 2021 and 2026, the LOS for the following City-owned public facilities will change as follows: The LOS for the following facilities will be increased as a result of the CFP, comparing the 2021 LOS to the projected 2026 LOS. CAPITAL FACILITY LOS UNITS 2021 LOS 2026 LOS (Projected) Community Parks Acres per 1,000 Pop.2.83 3.20 Linear Parks Acres per 1,000 Pop.0.20 0.23 Neighborhood Parks Acres per 1,000 Pop.0.78 0.85 The LOS for the following facilities will be maintained as a result of the CFP. CAPITAL FACILITY LOS UNITS 2021 LOS 2026 LOS (Projected) Roads Volume/Capacity Ratio "D""D" Airport % Air Operations Support 100%100% Cemetery Burial Plots per 1,000 Pop.33.00 33.00 Sanitary Sewer Residential GPCPD (Note 1)171.00 171.00 Storm Drainage N/A Water Residential GPCPD (Note 1)230.00 230.00 Note 1: GPCPD = Gallons per Customer per Day The LOS for the following facilities will be decreased as a result of the CFP, comparing the 2021 LOS to the projected 2026 LOS. CAPITAL FACILITY LOS UNITS 2021 LOS 2026 LOS (Projected) General Municipal Buildings Sq. Ft. per 1,000 Pop.3,767.77 3,630.76 Open Space Acres per 1,000 Pop.4.61 4.44 Senior Center Sq. Ft. per 1,000 Pop.146.98 139.85 Special Use Areas Acres per 1,000 Pop.3.06 2.92 Level of Service (LOS) is a common measure used to determine the efficiency or effectiveness of services. For the City of Auburn, LOS targets serves as a means to assess the adequacy of public facilities in meeting the needs of the population for which it serves. City of Auburn Capital Facilities Plan 6 For example, in the case of park space, when there is an increase in population without a corresponding increase in park acreage, the LOS unit of measure (acres per 1,000 population) will decline, indicating a potential need to increase the total amount of park acreage to keep pace with population growth. On the other hand, a slight increase in population, coupled with a large increase in facilities, will result in an increased LOS. For example, facilities such as buildings or burial plots may be constructed or expanded to keep pace with anticipated population growth. While this will have the effect of increasing LOS in the short-term, in the longer-term, the LOS will gradually decline to the targeted level based on forecasted population. The impact of population growth to the LOS for facilities will vary depending on the type of facility and long range planning by the City. CFP ELEMENT SOURCE DOCUMENTS Documents used in preparing this Capital Facilities Plan (CFP) are principally the comprehensive plans for the various public facilities included in this CFP. These individual comprehensive plans provide detailed identification of projects and identify their (projects) proposed funding sources. City documents include: • City-wide Comprehensive Land Use Plan (2015) • City Municipal Airport Master Plan Update (2012-2032) • City Comprehensive Water Plan (2015) • City Comprehensive Transportation Plan (2015) and Six Year Transportation Improvement Program (2021-2026) • City Comprehensive Drainage Plan (2015) • City Comprehensive Sewer Plan (2015) • City 2021-22 Biennial Budget and 2019 Annual Financial Report; and, • City Parks, Recreation & Open Space Plan Update (2015), as well as numerous other planning and financial documents. All documents are available for public inspection at the City of Auburn. City of Auburn Capital Facilities Plan 7 CHAPTER 1 INTRODUCTION PURPOSE The Capital Facilities Plan (CFP) is a 6-year plan (2021-2026) for capital improvements that support the City of Auburn’s current and future growth. In this plan, funding for general government projects is identified. To maintain consistency with individual master and utility comprehensive plans, applicable projects in the 6-year window of those master/utility plans are included in this CFP. The CFP also identifies LOS standards, where applicable, for each public facility. STATUTORY REQUIREMENTS FOR CAPITAL FACILITIES ELEMENTS RCW 36.70A.070(3)(d) requires that the comprehensive plan capital facilities element include “a six-year plan that will finance such capital facilities within projected funding capacities and clearly identifies sources of public money for such purposes.” RCW 36.70A.070(3)(e) requires that all capital facilities have “probable funding” to pay for capital facility needs, or else the City must “reassess the land use element.” In addition, the capital facilities element must include the location and capacity of existing facilities, a forecast of future needs, and their proposed locations and capacities. The State Growth Management Act (GMA) guidelines suggest that this analysis be accomplished for water systems, sanitary sewer systems, storm water facilities, schools, parks and recreation facilities, police and fire protection facilities. The GMA also seeks the selection of level of service standards for capital facilities. As a result, public facilities in the CFP should be based on quantifiable, objective measures of capacity such as traffic volume, capacity per mile of road and acres of park per capita. In some instances, though, level of service may best be expressed in terms of qualitative statements of satisfaction with a particular public facility. Factors that influence local level of service standards include, but are not limited to, community goals, national and local standards, and Federal and State mandates. To be effective, the CFP must be updated on a regular basis. State GMA guidelines suggest that the CFP be updated at least every two years. With this in mind, the City will follow these guidelines and update the CFP at least every two years, incorporating the capital facilities improvements in the City’s biennial budget process. CONCURRENCY AND LEVEL OF SERVICE City of Auburn Capital Facilities Plan 8 Concurrency The GMA requires that jurisdictions have certain capital facilities in place or available within a specified time frame when development occurs. This concept is called concurrency. Under the GMA, concurrency is required for transportation facilities and is recommended by the State for certain other public facilities, namely potable water and sanitary sewer. Concurrency has a direct relationship to level of service. The importance of concurrency to capital facilities planning is that development may be denied if it reduces the level of service for a capital facility below the locally adopted minimum. The level of service is unique for each type of facility and is presented in the subsequent sections. Explanation of Level of Service As indicated earlier, the GMA requires that level of service be established for certain transportation facilities for the purposes of applying concurrency to development proposals. The State GMA guidelines recommend the adoption of level of service standards for other capital facilities to measure the provision of adequate public facilities. Typically, measures of level of service are expressed as ratios of facility capacity to demand (i.e., actual or potential users). Table 1-1 lists generic examples of level of service measures for some capital facilities: TABLE 1-1 Sample Level of Service Measurements The need for capital facilities is largely determined by a community’s adopted LOS standards and whether or not the community has formally designated capital facilities, other than transportation, as necessary for development to meet the concurrency test. The CFP itself is therefore largely influenced by the selection of the level of service standards. Level of service standards are measures of the quality of life in the City. The standards should be based on the City’s vision of its future and its values. IMPLEMENTATION Implementation of the CFP requires constant monitoring and evaluation. The CFP is sensitive to funding and revenue availability and therefore needs to be constantly monitored against variations in available resources. To facilitate its implementation, the CFP should be kept current. Type of Facility Sample Level of Service Measure General Municipal Buildings Square feet per 1,000 population Parks Acres per 1,000 population Roads and Streets Ratio of actual volume to design capacity Sewer / Water Gallons per customer per day City of Auburn Capital Facilities Plan 9 Update of Capital Facilities Plan Perhaps the most desirable way to keep the CFP current is to update it regularly so the six - year plan is a rolling CFP. Again, the State recommends that the CFP be updated at least biennially. The City of Auburn will seek to update the CFP at least biennially in conjunction with the budget process. Future updates will consider: A. Revision of population projections, including annexations; B. Update of inventory of public facilities; C. Update of costs of public facilities; D. Update of public facilities requirements analysis (actual level of service compared to adopted standards); E. Update of revenue forecasts; F. Revise and develop capital improvement projects for the next six fiscal years; and, G. Update analysis of financial capacity. Amendments to the CFP, including amendments to level of service standards, capital projects, and/or the financing plan sources of revenue are all actions that can keep the CFP current and relevant to City decision-making. City of Auburn Capital Facilities Plan 10 City of Auburn Capital Facilities Plan 11 CHAPTER 2 GOALS AND POLICIES This chapter identifies goals and policies specific to the City’s provision of capital facilities. Goal 1 Provide a variety of responses to the demands of growth on public facilities. Policy 1.1 Establish land use patterns that optimize the use of public facilities. Policy 1.2 Provide additional public facility capacity when existing facilities are used to their maximum level of efficiency (consistent with adopted standards for level of service). Policy 1.3 Encourage development where new public facilities can be provided in an efficient manner. Policy 1.4 Exempt the following from the concurrency management program: 1.4.1 Development vested by RCW 19.27.095, 58.17.033 or 58.17.170. 1.4.2 Development that creates no added impact on public facilities. 1.4.3 Expansions of existing development that were disclosed and tested for concurrency as part of the original application. Goal 2 Provide needed public facilities that are within the ability of the City to fund or within the City’s authority to require others to provide. Policy 2.1 Establish level of service standards that are achievable with the financing plan of this Capital Facilities Plan. Policy 2.2 Base the financing plan for public facilities on realistic estimates of current local revenues and external revenues that are reasonably anticipated to be received by the City. Policy 2.3 Match revenue sources to capital projects based on sound fiscal policies. 2.3.1 The City shall continue to fund utility costs through utility enterprise funds, based on user fees and grants. Public facilities included in utilities are sewer, solid waste, storm drainage, and water. 2.3.2 Where feasible pursue joint venture facility construction, construction timing, and other facility coordination measures for City provided facilities, as well as with school districts and other potential partners in developing public facilities. 2.3.3 The City shall continue to assist through direct participation, LIDs and payback agreements, where appropriate and financially feasible. Where funding is available, the City may participate in developer initiated facility extensions or improvements, but only to the extent that the improvements benefit the broader public interest, and are consistent with the policies of this Capital Facilities Plan. City of Auburn Capital Facilities Plan 12 Policy 2.4 If the projected funding is inadequate to finance needed public facilities and utilities based on adopted level of service standards and forecasted growth, the City will do one or more of the following to achieve a balance between available revenue and needed public facilities: 2.4.1 Lower the level of service standards; 2.4.2 Increase the amount of revenue from existing sources; 2.4.3 Adopt new sources of revenue; 2.4.4 Require developers to provide such facilities at their own expense; and/or 2.4.5 Amend the Land Use Element to reduce the need for additional public facilities. Policy 2.5 Both existing and future development will pay for the costs of needed capital improvements. 2.5.1 Ensure that existing development pays for capital improvements that reduce or eliminate existing deficiencies, and pays for some or all of the cost to replace obsolete or worn out facilities. Existing development may also pay a portion of the cost of capital improvements needed by future development. Existing development’s payments may take the form of user fees, charges for services, special assessments and taxes. 2.5.2 Ensure that future development pays a proportionate share of the cost of new facilities that it requires. Future development may also pay a portion of the cost to replace obsolete or worn-out facilities. Future development’s payments may take the form of voluntary contributions for the benefit of any public facility, impact fees, mitigation payments, capacity fees, dedications of land, provision of public facilities, and future payments of user’s fees, charges for services, special assessments and taxes. Policy 2.6 The City will determine the priority of public facility capital improvements using the following criteria as general guidelines. Any revenue source that cannot be used for the highest priority will be used beginning with the highest priority for which the revenue can legally be expended. 2.6.1 Projects that eliminate hazardous conditions. 2.6.2 Refurbishment of existing facilities that contribute to achieving or maintaining standards for adopted level of service. 2.6.3 New or expanded facilities that reduce or eliminate deficiencies in level of service for existing demand. 2.6.4 New or expanded facilities that provide the adopted level of service for new development and redevelopment during the next six fiscal years. 2.6.5 Capital improvements that significantly reduce the operating cost of providing a service or facility, or otherwise mitigate impacts of public facilities on future operating budgets. City of Auburn Capital Facilities Plan 13 2.6.6 Capital improvements that contribute to stabilizing and developing the economy of the City. 2.6.7 Project priorities may also involve additional criteria that are unique to each type of public facility, as described in other elements of this Comprehensive Plan. Policy 2.7 Ensure that the ongoing operating and maintenance costs of a capital facility are financially feasible prior to constructing the facility. Goal 3 Protect public health, environmental quality, and neighborhood stability and viability through the appropriate design and installation of public facilities. Policy 3.1 Promote conservation of energy, water and other natural resources in the location and design of public facilities. Policy 3.2 Require the separation of sanitary and storm sewer facilities wherever combined sewers may be discovered. Policy 3.3 Practice efficient and environmentally responsible maintenance and operating procedures. Policy 3.4 The siting, design, construction and improvement of all public buildings shall be done in full compliance with the Americans with Disabilities Act (ADA). Policy 3.5 Promote economic and community stability and growth through strategic investments in public facilities and public private/partnerships. Goal 4 Make the Capital Facilities Plan consistent with other elements of the comprehensive plan, and - to the extent feasible - with other city, county, regional and state adopted plans. Policy 4.1 Ensure that the growth and development assumptions used in the Capital Facilities Plan are consistent with similar assumptions in other elements of the comprehensive plan. Policy 4.2 Coordinate with non-city providers of public facilities on a joint program for maintaining applicable level of service standards, concurrency requirements, funding and construction of public facilities. Goal 5 Provide public facilities that provide a sense of community that is inclusive of diverse populations. Policy 5.1 Contribute to community pride and foster a sense of community through provision of public facilities that create a community-gathering place for neighbors, family and friends. Policy 5.2 Through provision of public facilities, offer a broad range of activities promoting social interactions especially with new residents. Policy 5.3 Provide maximum flexibility and multiple uses through design of public facilities that are adaptable to changing interests. Policy 5.4 Provide a community center facility that is financially feasible, affordable for participants, and can generate revenue to offset a portion of the operating costs. City of Auburn Capital Facilities Plan 14 City of Auburn Capital Facilities Plan 15 CHAPTER 3 CAPITAL IMPROVEMENTS 1. INTRODUCTION This CFP includes City capital improvement projects and the financing plan to pay for those projects. It also contains the inventory of existing City facilities, and identifies level of service standards, where applicable. Each type of City public facility is presented in a separate subsection that follows a standard format. Throughout this section, t ables of data are identified with abbreviations that correspond to the type of facility. For example, Table W-1 refers to Table 1 for Water (Supply and Distribution). Each abbreviation corresponds to the name of the type of facility. 1. Narrative Summary This is an overview of the data, with sections devoted to Current Facilities, Level of Service, Capital Facilities Projects and Financing, and Impact on Future Operating Budgets. 2. Inventory of Facilities (Table X-1) This is a list of existing capital facilities, including the name, capacity (for reference to level of service), and location. This table also includes any proposed capital projects and the planned inventory total through December 31, 2026. 3. Capital Projects and Financing Plan (Table X-2, X-2A and X-2B) This list of capital improvements identifies existing deficiencies, identifies facilities needed for future growth, and identifies the need to repair or replace obsolete or worn out facilities through December 31, 2026. Each list shows the proposed financing plan followed by individual worksheets showing the project detail. 4. Impact on Future Operating Budgets (Table X-3) This is a list of capital projects and the forecasted impacts on the City’s future operating budgets (2022 – 2027). City of Auburn Capital Facilities Plan 16 City of Auburn Capital Facilities Plan 17 TRANSPORTATION Current Facilities Roadways: The City’s street system consists of a network of approximately 252 miles of arterials, collectors, local streets and alleys. Existing non-motorized facilities include a mix of trails, sidewalks, and both dedicated and shared bicycle facilities. Signals and ITS: The City’s transportation system also includes ninety-five traffic signals, a Traffic Control Center employing Intelligent Transportation Systems (ITS), which centrally directs the signals, more than 76 CCTV cameras, and various traffic beacons all communicating on a network of copper wire and fiber optic cable. The City also has two roundabouts. Transit: King County Metro Transit, Sound Transit and Pierce Transit serve the Auburn area. Auburn is currently served by eight Metro, two Sound Transit, and one Pierce Transit bus route. In addition, Sound Transit “Sounder” commuter trains provide peak hour and midday service at the Auburn Station. The Sounder also provides special event service to selected sporting events. Park and ride facilities and the Auburn Station support bus and rail service. Level of Service (LOS) Washington's Growth Management Act (GMA) requires Level of Service (LOS) standards for both arterials and transit routes. The GMA requires that each jurisdiction's LOS standards be coordinated within the region and be supported by local ordinance, but the actual standards and the methods used are determined by each local jurisdiction. Under GMA, the focus is on the performance of the whole road system, not on individual intersections or roadways. LOS standards are a tool to help keep the transportation system in balance with the needs of forecast population growth and development. Table T-1a summarizes the LOS definitions. City of Auburn Capital Facilities Plan 18 Table T-1a Definition of Urban Street Level of Service (LOS) LOS A - describes primarily free flow operations at average travel speeds, usually about 90 percent of the free flow speed for the given street class. Vehicles are completely unimpeded in their ability to maneuver within the traffic stream. Control delay at signalized intersections is minimal. LOS B - describes reasonably unimpeded operations at average travel speeds, usually about 70 percent of the free flow speed for the street class. The ability to maneuver within the traffic stream is only slightly restricted, and stopped delays are not bothersome. LOS C - describes stable conditions; however, ability to maneuver and change lanes in midblock locations may be more restricted than in LOS B, and longer queues, adverse signal coordination, or both may contribute to lower average travel speeds of about 50 percent of the free flow speed for the street class. LOS D - borders on a range in which small increases in flow may cause substantial increases in delay and decreases in travel speed. LOS D may be due to adverse signal progression, inappropriate signal timing, high volumes, or some combination of these factors. Average travel speeds are about 40 percent of free flow speed. LOS E - is characterized by significant delays and average travel speeds of 33 percent or less of the free flow speed. Such operations are caused by a combination of adverse progression, high signal density, high volumes, extensive delays at critical intersections, and inappropriate signal timing. LOS F - is characterized by urban street flow at extremely low speeds, typically one-third to one-fourth of the free flow speed. Intersection congestion is likely at critical signalized locations, with high delays, high volumes and extensive queuing. Source: 2010 Highway Capacity Manual, Special Report 209, Transportation Research Board, Washington, D.C. 2010, page 10-5 A methodology and set of standards have been drafted for the City of Auburn Comprehensive Plan. The standards help determine concurrency (i.e., balance) between the transportation and land use elements of the City’s Comprehensive Plan, as required by the GMA. The City has four choices if it is determined that standards cannot be met. • Modify the land use plan, placing tighter controls on the amount and type of development to reduce traffic. • Construct additional transportation facilities to support increased travel demand from new development. • Implement Transportation Demand Management (TDM) measures to increase use of non- single occupant vehicle travel modes. • Relax the LOS standards; the City can lower its level of service standards to encourage further growth and minimize the need for additional transportation facilities. The transportation/land-use balance will be monitored through the City's Concurrency Management System as part of the State Environmental Policy Act (SEPA). Transportation concurrency will be evaluated for key facilities and on a system-wide basis. The City can then identify locations where standards are not anticipated to be met in the future and identify appropriate improvements. At the project level, the SEPA process will continue to guide the more specific planning and analysis efforts. City of Auburn Capital Facilities Plan 19 Level of Service Standards LOS standards can help identify where and when transportation improvements are needed, and when development or growth will affect system operations. LOS provides a standard below which a transportation facility or system is not considered adequate. LOS standards can also be used to evaluate the impact of proposed developments on the surrounding street system. They can assure that all developments are served by a safe, efficient and cost-effective street system. They can also be used to disclose impacts, identify remedial actions, and apportion costs between public and private sources. The LOS standards shown in Table T-1b apply to the facility’s location and its functional classification. A more detailed description of the level of service methodology is provided in the City of Auburn Comprehensive Transportation Plan (2020), Chapter 5, Policy LOS-02. Table T- 1b Draft Roadway Capacity/Congestion LOS Standards Roadway/Intersection Maximum V/C Ratio/LOS Arterial Corridor D* Signalized Intersection D Unsignalized Intersection D *Unless otherwise specified in Chapter 2 of the City of Auburn Comprehensive Transportation Plan, 2020 LOS standards are also the basis of an equitable traffic impact fee system, which require developments to pay a portion of the costs for capacity improvements to the transportation infrastructure. In 2001, the City implemented a traffic impact fee program. The purpose of the fee is to mitigate traffic impacts more equitably while making the costs of development more predictable to developers. In 2007, the City implemented an additional transportation impact fee to address the impacts of heavy truck usage on the City’s transportation system. Both fees are updated annually so that the fees are consistent with current project costs. Measuring Transportation System Performance The level of service for street segments or links is analyzed with two primary purposes in mind. First, this site-specific LOS can be used, with the help of a travel demand model, to evaluate areas of congestion within a transportation network, leading to the development of a long-range transportation facilities plan. Second, arterial corridor LOS analysis can be used to assess concurrency or if facilities are meeting the LOS standards. The City of Auburn currently uses Highway Capacity Manual methodologies to calculate levels of service. For arterials LOS are based on average travel speeds along a defined corridor. City of Auburn Capital Facilities Plan 20 Table T-1c shows the 25 defined street corridors, LOS standards and most recent calculated LOS. TABLE T- 1c Auburn Corridor Level of Service – Existing 2014 Weekday PM Peak Hour LOS ID Corridor From To Standard*NB/EB SB/WB 1 Auburn Way N 15th St NE S 277th St E C C 2 Auburn Way N E Main St 15th St NE E D D 3 Auburn Way S E Main St M St SE F C D 4 Auburn Way S M St SE Academy Dr SE D B C 5 M St / Harvey Auburn Way N E Main St E D D 6 M St / Harvey E Main St Auburn Way S E D C 7 37th St NE / NW W Valley Hwy Auburn Way N E C C 8 15th St NE / NW W Valley Hwy Auburn Way N F**D D 9 Auburn Ave / A St 6th St SE E Valley Access Rd D B C 10 Main St West Valley Hwy R St D D D 11 15th St SW West Valley Hwy C St SW E D D 12 C St SW Ellingson Rd SR - 18 D B C 13 West Valley Hwy 37th St NE 15th St NE E B C 14 S 277th St Frontage Rd L St NE E C C 15 R St SE / Kersey Way Howard Rd Lake Tapps Pkwy D B B 16 Lake Tapps Pkwy East Valley Hwy Kersey Way SE D C C 17 A St NW / B St NW 3rd St NW S 277th St D C B 18 8th St NE / Lea Hill Rd Harvey Rd 124th Ave SE E C B 19 SE 312th St / 132nd Ave SE 124th Ave SE SR - 18 D B B 20 105th Pl SE / SE 320th St Lea Hill Rd 124th Ave SE D A C 21 Lakeland Hills Way SE Lake Tapps Pkwy A St SE E D C 22 29th St SE / Riverwalk Dr A St SE Auburn Way S D D C 23 3rd St SW / Cross St C St Auburn Way S F F E 24 41st St SE / Ellingson Rd A St SE C St SE F F F 25 West Valley Hwy 15th St NW 15th St SW E D E * **Total travel time in the eastbound direction cannot exceed 1,000 seconds for this corridor to meet the LOS Standards Corridor segments within Downtown Auburn may operate at LOS E in accordance with the Auburn Downtown Plan. All other arterial and collector corridors must operate at LOS D or better, unless otherwise indicated. 2014 LOS City of Auburn Capital Facilities Plan 21 Concurrency (Adequate Public Facilities) Concurrency involves matching public facilities and new development. The GMA extends concurrency to transportation facilities by requiring that new development be served by adequate roads and public transportation service, and that development is not permitted to cause these transportation facilities to operate below level of service standards that are adopted by local governments in their comprehensive plans. In compliance with the GMA, adequate transportation system facilities must be available within six years of the time of occupancy and use of new development. Capital Facilities Projects and Financing The City’s transportation facilities include projects totaling $68,863,053. Tables T-2, T-2A and T-2B show the proposed financing plan followed by individual worksheets showing the project detail. Impact on Future Operating Budgets As Table T-3 shows, operating budget impacts of $312,900 are forecasted for transportation facilities during the six years 2022 – 2027. City of Auburn Capital Facilities Plan 22 TABLE T- 2 CAPITAL FACILITIES PLAN PROJECTS AND FINANCING TRANSPORTATION – ARTERIAL STREET 2021 2022 2023 2024 2025 2026 Total Page Capacity Projects: 27 Harvey Road & 8th Street NE Intersection Improvements Long-Term Debt 83,700 83,300 82,794 82,382 81,990 81,589 495,755 Funding Sources: Unrestricted Street Revenue - - - - - - - Grants - - - - - - - Traffic Impact Fees 83,700 83,300 82,794 82,382 81,990 81,589 495,755 28 Lea Hill Road/112th Ave SE Roundabout Capital Costs - - - 350,000 420,000 2,200,000 2,970,000 Funding Sources: Unrestricted Street Revenue - - - - - - - Grants (Unsecured)- - - - - 1,100,000 1,100,000 Traffic Impact Fees - - - 350,000 420,000 1,100,000 1,870,000 29 29th Street SE & R Street SE Intersection Improvements Capital Costs 750,000 500,000 250,000 3,500,000 - - 5,000,000 Funding Sources: Unrestricted Street Revenue - - - - - - - Grants (Unsecured)- - - - - - - Traffic Impact Fees 750,000 500,000 250,000 3,500,000 - - 5,000,000 30 R Street SE & 21st Street SE Intersection Safety Improvements Capital Costs - - 250,000 100,000 750,000 - 1,100,000 Funding Sources: Unrestricted Street Revenue - - - - - - - Grants (Unsecured)- - - - 500,000 - 500,000 Traffic Impact Fees - - 250,000 100,000 250,000 - 600,000 31 Auburn Way S and 6th Street SE Capital Costs - - - 130,000 25,000 630,000 785,000 Funding Sources: Unrestricted Street Revenue - - - - - - - Grants (Unsecured)- - - - - 505,000 505,000 Traffic Impact Fees - - - 130,000 25,000 125,000 280,000 32 SE 304th Street/132nd Avenue SE Roundabout Capital Costs - - 250,000 50,000 1,200,000 - 1,500,000 Funding Sources: Unrestricted Street Revenue - - - - - - - Grants (Unsecured)- - - - - - - Traffic Impact Fees - - 250,000 50,000 1,200,000 - 1,500,000 33 10th Street NW/A Street NW Intersection Improvements Capital Costs - 200,000 650,000 - - - 850,000 Funding Sources: Unrestricted Street Revenue - - - - - - - Traffic Impact Fees - 200,000 650,000 - - - 850,000 34 F Street SE Non-Motorized Improvements (Downtown to Les Gove) Capital Costs 10,000 - - - - - 10,000 Funding Sources: Unrestricted Street Revenue 10,000 - - - - - 10,000 Traffic Impact Fees - - - - - - - 35 Evergreen Heights Safe Routes to School Improvements, Phase 1 & 2 Capital Costs - - - - - 410,000 410,000 Funding Sources: Unrestricted Street Revenue - - - - - 410,000 410,000 Other - - - - - - - Traffic Impact Fees - - - - - - - City of Auburn Capital Facilities Plan 23 TABLE T- 2 (continued) 2021 2022 2023 2024 2025 2026 Total Page Capacity Projects: 36 Riverwalk Drive SE Non-Motorized Improvements Capital Costs 200,000 950,000 - - - - 1,150,000 Funding Sources: Unrestricted Street Revenue 20,000 250,000 - - - - 270,000 Grants 180,000 450,000 - - - - 630,000 Other -MIT - 250,000 - - - - 250,000 37 Stewart Road - Sumner (Lake Tapps Parkway Corridor) Capital Costs - - - 150,000 - - 150,000 Funding Sources: Unrestricted Street Revenue - - - - - - - Grants - - - - - - - Traffic MitigationFees - - - 150,000 - - 150,000 38 M Street Underpass (3rd St SE to 8th St SE) Long-Term Debt 123,200 122,900 122,550 122,258 121,965 121,673 734,546 Funding Sources: Unrestricted Street Revenue - - - - - - - Grants (Unsecured)- - - - - - - Traffic Impact Fees 123,200 122,900 122,550 122,258 121,965 121,673 734,546 39 A Street Loop Capital Costs - 300,000 167,000 1,465,000 - - 1,932,000 Funding Sources: Unrestricted Street Revenue - - - - - - - Grants (Unsecured)- - - 1,125,000 - - 1,125,000 Traffic Impact Fees - 300,000 167,000 - - - 467,000 Other - - - 340,000 - - 340,000 40 A Street NW, Phase 2 (W Main St to 3rd St NW) Capital Costs - - - 350,000 2,650,000 - 3,000,000 Funding Sources: Unrestricted Street Revenue - - - - - - - Traffic Impact Fees - - - 150,000 - - 150,000 Grants (Unsecured)- - - 200,000 1,325,000 - 1,525,000 Other (Other Agencies)- - - - 1,325,000 - 1,325,000 41 Auburn Way S Improvements (Hemlock St SE to Poplar St SE) Capital Costs 1,500,000 750,000 5,580,120 2,800,000 - - 10,630,120 Funding Sources: Unrestricted Street Revenue - - - - - - - Traffic Impact Fees 851,250 750,000 1,830,120 1,300,000 - - 4,731,370 Grants 648,750 - 3,000,000 1,500,000 - - 5,148,750 Other (Other Agencies)- - 750,000 - - - 750,000 42 M Street NE (E Main St to 4th St NE) Capital Costs - 375,000 50,000 2,485,000 - - 2,910,000 Funding Sources: Unrestricted Street Revenue - 120,000 50,000 400,000 - - 570,000 Arterial Street Fund 105 - 185,000 - 1,220,000 - - 1,405,000 REET 2 - - - 400,000 - - 400,000 Traffic Impact Fees - 70,000 - 465,000 - - 535,000 Other - - - - - - - 43 49th Street NE (Auburn Way N to D St NE) Capital Costs 500,000 1,500,000 - - - - 2,000,000 Funding Sources: Unrestricted Street Revenue - - - - - - - Grants - - - - - - - Other 500,000 1,500,000 - - - - 2,000,000 City of Auburn Capital Facilities Plan 24 TABLE T- 2 (continued) 2021 2022 2023 2024 2025 2026 Total Page Capacity Projects: 44 46th Place S Realignment Capital Costs - - - - 375,000 675,000 1,050,000 Funding Sources: Unrestricted Street Revenue - - - - - - - Grants - - - - 300,000 540,000 840,000 Traffic Impact Fees - - - - 75,000 135,000 210,000 45 124th Ave SE Corridor Improvements Phase 2 Capital Costs - - - - - 400,000 400,000 Funding Sources: Unrestricted Street Revenue - - - - - - - Grants - - - - - - - Traffic Impact Fees - - - - - 400,000 400,000 46 Regional Growth Center Access Improvements Capital Costs 410,000 100,000 1,500,000 - - - 2,010,000 Funding Sources: Unrestricted Street Revenue - - - - - - - Grants 325,000 - 1,300,000 - - - 1,625,000 Traffic Impact Fees 85,000 100,000 200,000 - - - 385,000 47 Stewart Road - City of Pacific (Lake Tapps Parkway Corridor) Capital Costs 100,000 - - - - - 100,000 Funding Sources: Unrestricted Street Revenue - - - - - - - Grants - - - - - - - Traffic MitigationFees 100,000 - - - - - 100,000 48 East Valley Highway Widening Capital Costs - - - - - 300,000 300,000 Funding Sources: Unrestricted Street Revenue - - - - - - - Grants - - - - - 200,000 200,000 Traffic Impact Fees - - - - - 100,000 100,000 49 Garden Avenue Realignment Capital Costs 150,000 500,000 - - - - 650,000 Funding Sources: Unrestricted Street Revenue - - - - - - - Grants - - - - - - - Traffic Impact Fees 150,000 500,000 - - - - 650,000 50 A Street NW - Phase 1 (3rd St NW to 14th St NW) Capital Costs 25,000 25,000 - - - - 50,000 Funding Sources: Unrestricted Street Revenue - - - - - - - Grants - - - - - - - Traffic Impact Fees 25,000 25,000 - - - - 50,000 51 S 272nd/277th St Corridor Capacity & Non-Motorized Trail Improvements Capital Costs 20,000 20,000 20,000 20,000 20,000 20,000 120,000 Funding Sources: Unrestricted Street Revenue - - - - - - - Traffic Impact Fees 20,000 20,000 20,000 20,000 20,000 20,000 120,000 Other - - - - - - - 52 A Street SE Corridor Study Capital Costs 10,000 - - - - - 10,000 Funding Sources: Unrestricted Street Revenue - - - - - - - Grants - - - - - - - Traffic Impact Fees 10,000 - - - - - 10,000 Subtotal, Capacity Projects: Capital Costs 3,861,900 5,406,200 8,902,464 11,584,640 5,623,955 4,818,262 40,197,421 City of Auburn Capital Facilities Plan 25 TABLE T- 2 (continued) 2021 2022 2023 2024 2025 2026 Total Page Non-Capacity Projects: 53 Auburn Way N/1st Street NE Signal Replacement Capital Costs 575,000 - - - - - 575,000 Funding Sources: Unrestricted Street Revenue 525,000 - - - - - 525,000 Arterial Street Preservation 50,000 - - - - - 50,000 54 ITS Dynamic Message Signs Capital Costs - - - - - 20,000 20,000 Funding Sources: Unrestricted Street Revenue - - - - - 20,000 20,000 Grants - - - - - - - 55 Auburn Avenue/E Main Street Signal Replacement Capital Costs - - - - - 150,000 150,000 Funding Sources: Unrestricted Street Revenue - - - - - 150,000 150,000 Grants - - - - - - - 56 Citywide Pedestrian Accessibility & Safety Program Capital Costs 50,000 100,000 100,000 100,000 100,000 100,000 550,000 Funding Sources: Unrestricted Street Revenue 50,000 100,000 100,000 100,000 100,000 100,000 550,000 Other - - - - - - - 57 Citywide Arterial Bicycle & Safety Improvements Capital Costs 100,000 - 100,000 - 100,000 - 300,000 Funding Sources: Unrestricted Street Revenue 100,000 - 100,000 - 100,000 - 300,000 Other - - - - - - - 58 Downtown Transit Center Access Improvements Capital Costs - 125,000 - - - - 125,000 Funding Sources: Unrestricted Street Revenue - 25,000 - - - - 25,000 Other (Sound Transit)- 100,000 - - - - 100,000 59 M Street SE Sidewalk Improvements Capital Costs 669,980 - - - - - 669,980 Funding Sources: Unrestricted Street Revenue 250,000 - - - - - 250,000 Grants (Unsecured)419,980 - - - - - 419,980 Other - - - - - - - 60 Auburn Way S (SR-164) Poplar Curve Safety Improvements Capital Costs 10,000 - - - - - 10,000 Funding Sources: Unrestricted Street Revenue 10,000 - - - - - 10,000 Grants (Unsecured)- - - - - - - Other - - - - - - - Subtotal, Non-Capacity Projects: Capital Costs 1,424,980 245,000 220,000 120,000 220,000 290,000 2,519,980 City of Auburn Capital Facilities Plan 26 TABLE T- 2 (continued) 2021 2022 2023 2024 2025 2026 Total SUMMARY: CAPITAL COSTS Capacity Projects 3,655,000 5,200,000 8,697,120 11,380,000 5,420,000 4,615,000 38,967,120 Non-Capacity Projects 1,424,980 245,000 220,000 120,000 220,000 290,000 2,519,980 Long-Term Debt 206,900 206,200 205,344 204,640 203,955 203,262 1,230,301 Total Costs 5,286,880 5,651,200 9,122,464 11,704,640 5,843,955 5,108,262 42,717,401 FUNDING SOURCES: Unrestricted Street Revenue 965,000 495,000 250,000 500,000 200,000 680,000 3,090,000 Grants 1,573,730 450,000 4,300,000 2,825,000 2,125,000 2,345,000 13,618,730 Traffic Impact Fees 2,098,150 2,671,200 3,822,464 6,269,640 2,193,955 2,083,262 19,138,671 Traffic Mitigation Fees 100,000 - - 150,000 - - 250,000 Arterial Street Fund 105 50,000 185,000 - 1,220,000 - - 1,455,000 REET - - - 400,000 - - 400,000 Other (Other Agencies)500,000 1,850,000 750,000 340,000 1,325,000 - 4,765,000 Total Funding 5,286,880 5,651,200 9,122,464 11,704,640 5,843,955 5,108,262 42,717,401 * Mitigation agreements, impact fees, contributions, other agencies, other funds City of Auburn Capital Facilities Plan 27 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: Harvey Rd NE/8th St NE Intersection Improvements TIP# I-5 Project No:cp0611 Project Type:Capacity Project Manager:None LOS Corridor ID# 5, 19 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - - - Grants- Secured (Fed,State,Local)- - - - - Traffic Impact Fees (Debt Service)861,178 84,000 83,700 83,300 1,028,878 Traffic Impact Fees 204,500 204,500 PWTF 1,527,300 1,527,300 2,592,978 84,000 83,700 83,300 2,760,678 Capital Expenditures: Design 327,500 - - - 327,500 Right of Way 200,400 - - - 200,400 Construction 1,203,900 - - - 1,203,900 Long Term Debt - PWTF 861,178 84,000 83,700 83,300 1,028,878 2,592,978 84,000 83,700 83,300 2,760,678 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Grants- Secured (Fed,State,Local)- - - - - Traffic Impact Fees (Debt Service)82,794 82,382 81,990 81,589 495,755 Traffic Impact Fees - - - - - PWTF - - - - - 82,794 82,382 81,990 81,589 495,755 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - Long Term Debt - PWTF 82,794 82,382 81,990 81,589 495,755 82,794 82,382 81,990 81,589 495,755 Grants / Other Sources: Total Funding Sources: Total Funding Sources: Total Expenditures: Total Expenditures: Forecasted Project Cost: Description: The project constructed one eastbound through/right turn-lane on 8th St NE to the west of Harvey Rd and modified traffic signals and traffic channelization to accommodate the new lane. The additional lane reduced traffic delays and queuing at the intersection of Harvey Rd and 8th St NE in all directions. This project also reconstructed M St NE from 4th St NE to 8th St NE, a segment of roadway approximately 0.3 miles long with a four-lane cross-section. The reconstruction addressed the existing poor pavement condition and completed sidewalk gaps. . Progress Summary: Project was completed in 2010. Ongoing budget is for Public Works Trust Fund Loan debt payments scheduled through 2028. Future Impact on Operating Budget: N/A City of Auburn Capital Facilities Plan 28 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: Lea Hill Road/112th Ave SE Roundabout TIP# I-6 Project No:cpxxxx Project Type:Capacity, Safety Project Manager:TBD LOS Corridor ID# 19 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - - - Grants- Unsecured - - - - - Traffic Impact Fees - - - - - Other - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Grants- Unsecured - - - 1,100,000 1,100,000 Traffic Impact Fees - 350,000 420,000 1,100,000 1,870,000 Other - - - - - - 350,000 420,000 2,200,000 2,970,000 Capital Expenditures: Design - 350,000 - - 350,000 Right of Way - - 420,000 - 420,000 Construction - - - 2,200,000 2,200,000 - 350,000 420,000 2,200,000 2,970,000 Grants / Other Sources: Description: The project will construct a single-lane roundabout at the 112th Avenue SE intersection with Lea Hill Road. The intersection is currently stop-controlled on the 112th Avenue SE approach. The project will also implement turn restrictions at the Lea Hill Road intersection with 105th Place SE, and remove the existing span wire traffic signal. The project will improve traffic operations, safety and non-motorized access. Progress Summary: The Lea Hill Road Corridor study was completed during 2020. This project is based on the study recommendations. Future Impact on Operating Budget: The annual maintenance cost for this project is estimated to be $1,000. Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Total Expenditures: City of Auburn Capital Facilities Plan 29 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: 29th St SE/R St SE Intersection Improvements TIP# I-8 Project No:asbd30 Project Type:Capacity Project Manager:TBD LOS Corridor ID# 16, 27 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - - - Grants- Unsecured - - - - - Traffic Impact Fees - - 750,000 500,000 750,000 REET - - - - - Other - - - - - - - 750,000 500,000 750,000 Capital Expenditures: Design - - 750,000 250,000 - Right of Way - - - 250,000 - Construction - - - - - - 750,000 500,000 750,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Grants- Unsecured - - - - - Traffic Impact Fees 250,000 3,500,000 - - 5,000,000 REET - - - - - Other - - - - - 250,000 3,500,000 - - 5,000,000 Capital Expenditures: Design - - - - 1,000,000 Right of Way 250,000 - - - 500,000 Construction - 3,500,000 - - 3,500,000 250,000 3,500,000 - - 5,000,000 Grants / Other Sources: Description: The project will construct a second southbound through lane between 22nd Street SE and 33rd Street SE and a new signal at the 29th Street SE intersection. The improvements are needed to address the existing LOS deficiency at this intersection during the weekday PM peak hour. Progress Summary: The R Street Corridor study was completed during 2020. This project is based on the study recommendations. Future Impact on Operating Budget: The additional annual maintenance cost for this project is estimated to be $500. Replacing the traffic signal will reduce on- going maintenance costs to replace parts and equipment that have reached the end of their service life. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 30 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: R Street SE & 21st Street SE Intersection Safety Improvements TIP# I-10 Project No:CP1918 Project Type:Capacity, Safety Project Manager:James Webb LOS Corridor ID# 16 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - - - Grants- Unsecured - - - - - Traffic Impact Fees - - - - - REET2 - - - - - Other - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Grants- Unsecured - - 500,000 - 500,000 Traffic Impact Fees 250,000 100,000 250,000 - 600,000 REET2 - - - - - Other - - - - - 250,000 100,000 750,000 - 1,100,000 Capital Expenditures: Design 250,000 - - - 250,000 Right of Way - 100,000 - - 100,000 Construction - - 750,000 - 750,000 250,000 100,000 750,000 - 1,100,000 Grants / Other Sources: Total Expenditures: Description: The project will construct a single lane roundabout in place of the existing east/west stop-control on 21st Street SE. The project is needed to address an existing LOS deficiency, and will improve safety at the intersection. Progress Summary: This improvement was recommended in the R Street Corridor study which was completed during 2020. Future Impact on Operating Budget: The annual maintenance cost for this project is estimated to be $1,000. Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 31 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: Auburn Way S and 6th Street SE TIP# I-11 Project No:cpxxx Project Type:Capacity, Safety Project Manager:TBD LOS Corridor ID# 3 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - - - Grants- Unsecured - - - - - Traffic Impact Fees - - - - - Other - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Grants- Unsecured - - - 505,000 505,000 Traffic Impact Fees - 130,000 25,000 125,000 280,000 Other - - - - - - 130,000 25,000 630,000 785,000 Capital Expenditures: Design - 130,000 - - 130,000 Right of Way - - 25,000 - 25,000 Construction - - - 630,000 630,000 - 130,000 25,000 630,000 785,000 Grants / Other Sources: Description: The project will construct a dedicated southbound right-turn pocket on Auburn Way S at 6th Street SE. The project will address an existing level of service deficiency at the intersection. Progress Summary: Federal grant funding for construction is proposed to be applied for in 2022. If awarded construction would occur in 2025. Future Impact on Operating Budget: The annual maintenance cost for this project is estimated to be $500. Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Total Expenditures: City of Auburn Capital Facilities Plan 32 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: SE 304th Street/132nd Avenue SE Roundabout TIP# I-13 Project No:cpxxxx Project Type:Capacity Project Manager:TBD LOS Corridor ID# 23, 25 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - - - Grants- Unsecured - - - - - Traffic Impact Fees - - - - - Other - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Grants- Unsecured - - - - - Traffic Impact Fees 250,000 50,000 1,200,000 - 1,500,000 Other - - - - - 250,000 50,000 1,200,000 - 1,500,000 Capital Expenditures: Design 250,000 - - - 250,000 Right of Way - 50,000 - - 50,000 Construction - - 1,200,000 - 1,200,000 250,000 50,000 1,200,000 - 1,500,000 Grants / Other Sources: Description: The project will construct a single-lane roundabout at the SE 304th Street intersection with 132nd Avenue SE on Lea Hill. The roundabout will replace the existing stop-controlled on the SE 304th Street approach. The project is needed to address a level of service deficiency at the intersection. Progress Summary: Future Impact on Operating Budget: The annual maintenance cost for this project is estimated to be $1,000. Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 33 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: 10th Street NW/A Street NW Intersection Improvements TIP# I-15 Project No:asbd36 Project Type:Capacity, Safety Project Manager:TBD LOS Corridor ID# N/A Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - - - Grants- Unsecured - - - - - Traffic Impact Fees - - - 200,000 - REET2 - - - - - Other - - - - - - - - 200,000 - Capital Expenditures: Design - - - 200,000 - Right of Way - - - - - Construction - - - - - - - - 200,000 - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Grants- Unsecured - - - - - Traffic Impact Fees 650,000 - - - 850,000 REET2 - - - - - Other - - - - - 650,000 - - - 850,000 Capital Expenditures: Design - - - - 200,000 Right of Way - - - - - Construction 650,000 - - - 650,000 650,000 - - - 850,000 Grants / Other Sources: Total Expenditures: Description: The project will construct a new traffic signal in place of the existing stop-control on the 10th Street NW approach. The project is needed to address a level of service deficiency at the intersection. Progress Summary: Future Impact on Operating Budget: The annual maintenance cost for this project is estimated to be $1,000. Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 34 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: F Street SE Non-Motorized Improvements (Downtown to Les Gove) TIP# N-5 Project No:cp1416 Project Type:Capacity, Non-Motorized Project Manager:Seth Wickstrom LOS Corridor ID# N/A Activity: 2020 YE 2017 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue 40,000 359,000 10,000 - 409,000 Grants- Secured Federal 494,770 2,025,230 - - 2,520,000 Grants-Unsecured Federal - - - - - Traffic Impact Fees 160,583 538,584 - - 699,167 Other - - - - - 695,353 2,922,814 10,000 - 3,628,167 Capital Expenditures: Design 653,373 - - - 653,373 Right of Way 41,980 1,541 - - 43,521 Construction - 2,921,273 10,000 - 2,931,273 695,353 2,922,814 10,000 - 3,628,167 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - 10,000 Grants- Unsecured (Fed)- - - - - Grants-Unsecured Federal - - - - - Traffic Impact Fees - - - - - Other - - - - - - - - - 10,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 10,000 - - - - 10,000 Grants / Other Sources: Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Description: The F St SE project includes pavement rehabilitation, installation of curbs, gutters, bike lanes, sidewalks, ADA improvements, utility undergrounding, LED street lighting, wayfinding signage and a "Bicycle Boulevard" designation of roadway connections between Auburn City Hall and the Les Gove Park Campus. This project improves mobility and safety along the corridor and will complete a gap in the non-motorized network between Auburn's Downtown and the Les Gove Community Campus. The major infrastructure improvements are approximately 0.3 miles long and the "Bicycle Boulevard" improvements are just over a mile long. Progress Summary: Preliminary design and survey work was completed in 2009. Federal Grant was secured in 2014 for design and ROW phases. Design phase was initiated in 2015. Construction grant secured in 2018. Project construction is underway in 2020. Funds shown in 2021 are a placeholder for a potential 2020 project budget carryforward. Future Impact on Operating Budget: The annual maintenance cost for this project is estimated to be $4,100. City of Auburn Capital Facilities Plan 35 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: Evergreen Heights Safe Routes to School Improvements, Phase 1 & 2 TIP# N-8 Project No:asbd14, cp1810 Project Type:Capacity, Non-Motorized Project Manager:Jacob Sweeting LOS Corridor ID# 37 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue 24,500 - - - 24,500 Grants- Unsecured - - - - - Mitigation Fees 100,000 - - - 100,000 Other (Auburn Sch. Dist.)122,500 - - - 122,500 Traffic Impact Fees - - - - - 247,000 - - - 247,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction 247,000 - - - 247,000 247,000 - - - 247,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - 410,000 410,000 Grants- Unsecured - - - - - Mitigation Fees - - - - - Other (Auburn Sch. Dist.)- - - - - Traffic Impact Fees - - - - - - - - 410,000 410,000 Capital Expenditures: Design - - - 200,000 200,000 Right of Way - - - 210,000 210,000 Construction - - - - - - - - 410,000 410,000 Grants / Other Sources: Auburn School District partnership includes direct financial contribution and ROW dedication. Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: Total Funding Sources: Description: Phase 1 of the project included the vertical realignment of S 316th Street along the school frontage to address a sight- distance problem associated with the school driveways and at the intersection with 56th Avenue S. This improvement was constructed by the school district as part of their half street improvements associated with on-site improvements to the school. Phase 2 of the project will realign the 56th Avenue S approach to S 316th Street to the east to remove the offset between the street approach and school driveway, and a roundabout will be constructed at the S 316th Street/56th Avenue S intersection replacing the existing all-way stop-control. Other project elements include street lighting and required storm water system improvements. Progress Summary: A partnership with the Auburn School District was created for the Phase 1 improvements, which were completed in 2019. Future Impact on Operating Budget: This project will have no impact on the operating budget for street maintenance. City of Auburn Capital Facilities Plan 36 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: Riverwalk Drive SE Non-Motorized Improvements TIP# N-9 Project No:asbd26 Project Type:Capacity, Non-Motorized Project Manager:TBD LOS Corridor ID# 27 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - 20,000 250,000 20,000 Grants- Unsecured (Fed,State,Local)- - 180,000 450,000 180,000 Traffic Impact Fees - - - - - REET2 - - - - - Other (MIT)- - - 250,000 - - - 200,000 950,000 200,000 Capital Expenditures: Design - - 200,000 - 200,000 Right of Way - - - - - Construction - - - 950,000 - - - 200,000 950,000 200,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - 270,000 Grants- Unsecured (Fed,State,Local)- - - - 630,000 Traffic Impact Fees - - - - - REET2 - - - - - Other (MIT)- - - - 250,000 - - - - 1,150,000 Capital Expenditures: Design - - - - 200,000 Right of Way - - - - - Construction - - - - 950,000 - - - - 1,150,000 Grants / Other Sources: Total Expenditures: Description: The project will construct sidewalks, street lighting, and related storm improvements along the east side of Riverwalk Drive SE between Auburn Way S and Howard Road SE. This project will close a major gap in the sidewalk system and ties into the proposed improvements on Auburn Way South. The project will also install a RRFB at the intersection with Howard Road. The project is proposed to be in partnership with the Muckleshoot Indian Tribe. Progress Summary: Grant funding was applied for in 2020. If awarded, design will begin in 2021. Future Impact on Operating Budget: The annual maintenance cost for this project is estimated to be $2,000. Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 37 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: Stewart Road - Sumner (Lake Tapps Parkway Corridor)TIP# R-2 Project No:N/A Project Type:Capacity Project Manager:City of Sumner LOS Corridor ID# N/A Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - - - Grants- Secured (Fed,State,Local)- - - - - Traffic Impact Fees - - - - - REET2 - - - - - Traffic Mitigation Fees - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Grants- Secured (Fed,State,Local)- - - - - Traffic Impact Fees - - - - - REET2 - - - - - Traffic Mitigation Fees - 150,000 - - 150,000 - 150,000 - - 150,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - 150,000 - - 150,000 - 150,000 - - 150,000 Grants / Other Sources: Total Expenditures: Description: This is a City of Sumner project to widen the Stewart Road (Lake Tapps Parkway) Corridor. The project will replace the existing bridge over the White River with a new wider one. Completion of this corridor widening is expected to significantly relieve traffic congestion in Auburn along the A St SE and C St SW corridors. Progress Summary: City of Sumner has initiated preliminary road design and is seeking grant funding to complete the project. Future Impact on Operating Budget: This project will have no impact on the operating budget for street maintenance. Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 38 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: M Street Underpass (3rd St SE to 8th St SE) TIP# R-3 Project No:c201a0 Project Type:Capacity Project Manager:Ryan Vondrak LOS Corridor ID# 6 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - Grants- Secured (Fed,State,Local)9,696,313 - - - 9,696,313 REET2 1,140,001 - - - 1,140,001 Traffic Impact Fees (Construction)4,162,000 - - - 4,162,000 Traffic Impact Fees (Debt Service)767,428 123,428 123,200 122,900 1,014,056 Traffic Mitigation Fees 660,000 - - - 660,000 PWTFL (30 years)3,284,857 - - - 3,284,857 Other Sources (Other Agencies)*3,126,104 - - - 3,126,104 22,836,703 123,428 123,200 122,900 23,083,331 Capital Expenditures: Design 2,688,924 - - - 2,688,924 Right of Way 3,358,443 - - - 3,358,443 Construction 16,021,908 - - - 16,021,908 PWTFL Debt Service 767,428 123,428 123,200 122,900 1,014,056 22,836,703 123,428 123,200 122,900 23,083,331 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Grants- Secured (Fed,State,Local)- - - - - REET2 - - - - - Traffic Impact Fees (Construction)- - - - - Traffic Impact Fees (Debt Service)122,550 122,258 121,965 121,673 734,546 Traffic Mitigation Fees - - - - - PWTFL (30 years)- - - - - Other Sources (Other Agencies)*- - - - - 122,550 122,258 121,965 121,673 734,546 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - PWTFL Debt Service 122,550 122,258 121,965 121,673 734,546 122,550 122,258 121,965 121,673 734,546 Total Funding Sources: Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: Grants / Other Sources: Other Agencies are King County Metro Sewer, Port of Seattle, Port of Tacoma, and BNSF Railway Description: Construction of a grade separated railroad crossing of M Street SE at the BNSF Stampede Pass tracks. Progress Summary: Construction was completed in 2014. Debt Service is scheduled each year through 2041. Future Impact on Operating Budget: N/A City of Auburn Capital Facilities Plan 39 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: A Street Loop TIP# R-4 Project No:asbd32 Project Type:Capacity Project Manager:TBD LOS Corridor ID# N/A Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - - - Unsecured Grant - - - - - Traffic Impact Fees - - - 300,000 - Other (Sound Transit)- - - - - - - 300,000 - Capital Expenditures: Design - - - 300,000 300,000 Right of Way - - - - - Construction - - - - - - - - 300,000 - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Unsecured Grant - 1,125,000 - - 1,125,000 Traffic Impact Fees 167,000 - - - 467,000 Other (Sound Transit)340,000 - - 340,000 167,000 1,465,000 - - 1,932,000 Capital Expenditures: Design - - - - 300,000 Right of Way 167,000 - - - 167,000 Construction - 1,465,000 - - 1,465,000 167,000 1,465,000 - - 1,932,000 Grants / Other Sources:Interlocal funding from Sound Transit Total Funding Sources: Description: The project will construct a new one-way (eastbound) roadway connection between A Street SW/S Division Street and A Street SE. The new intersection with A Street SE will allow an unsignalized right-turn movement onto southbound A Street SE, providing an alternative to the intersection of 3rd Street SE and A Street SE, which does not meet adopted LOS standards. The roadway will be constructed as a complete street to accommodate non-motorized road users. Progress Summary: Sound Transit has provided $340,000 towards the construction phase as mitigation for the second parking garage. Grant applications for both state and federal funding have been submitted in 2020. Future Impact on Operating Budget: The annual maintenance cost for this project is estimated to be $1,000. Total Funding Sources: Total Expenditures: Total Expenditures: Forecasted Project Cost: City of Auburn Capital Facilities Plan 40 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: A Street NW, Phase 2 (W Main St to 3rd St NW) TIP# R-5 Project No:cpxxx Project Type:Capacity Project Manager:TBD LOS Corridor ID# 18 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - - Unsecured Grant - - - - - Traffic Impact Fees - - - - - REET2 - - - - - Other - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Unsecured Grant - 200,000 1,325,000 - 1,525,000 Traffic Impact Fees - 150,000 - - 150,000 REET2 - - - - - Other - - 1,325,000 1,325,000 - 350,000 2,650,000 - 3,000,000 Capital Expenditures: Design - 250,000 - - 250,000 Right of Way - 100,000 - - 100,000 Construction - - 2,650,000 - 2,650,000 - 350,000 2,650,000 - 3,000,000 Grants / Other Sources: Total Expenditures: Description: The project will widen A Street NW to create a three-lane roadway section between W Main St and 3rd St NW. This project will improve the connection between the A St NW Extension, (Phase 1) and Auburn Station and Central Business District. This project could be partially or fully funded by development and/or Sound Transit's parking garage/access improvements. The project is approximately 0.2 miles long. Progress Summary: Future Impact on Operating Budget: The annual maintenance cost for this project is estimated to be $500. Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 41 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: Auburn Way S Improvements (Hemlock St SE to Poplar St SE)TIP# R-6 Project No:cp1622 Project Type:Capacity Project Manager:Jeff Bender LOS Corridor ID# 4 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - - Grants- Secured (Federal)13,025 635,725 648,750 - 1,297,500 Traffic Impact Fees 6,246 95,004 851,250 750,000 952,500 REET2 - - - - - Other - - - - - 19,271 730,729 1,500,000 750,000 2,250,000 Capital Expenditures: Design - 750,000 750,000 - 1,500,000 Right of Way - - 750,000 750,000 750,000 Construction - - - - - 750,000 1,500,000 750,000 2,250,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Grants- Secured (Federal)3,000,000 1,500,000 - - 5,148,750 Traffic Impact Fees 1,830,120 1,300,000 - - 4,731,370 REET2 - - - - - Other 750,000 - - 750,000 5,580,120 2,800,000 - - 10,630,120 Capital Expenditures: Design - - - - 750,000 Right of Way - - - - 1,500,000 Construction 5,580,120 2,800,000 - - 8,380,120 5,580,120 2,800,000 - - 10,630,120 Grants / Other Sources: Total Expenditures: Description: The project will widen Auburn Way S between Hemlock St SE and Poplar St SE to accommodate two general purpose lanes in each direction, turn lanes, access management where feasible, U-turns, curb, gutter, sidewalk, illumination, transit stop improvements, a new traffic signal in the vicinity of Chinook Elementary School, Intelligent Transportation Systems, streetscape and storm improvements. The project length is approximately 0.4 miles. The project is needed to address traffic operations issues along the corridor. Progress Summary: The project will extend corridor improvements along Auburn Way S recently completed under previous projects. Grant funding for the design phase was awarded in 2019. Grant funding for the construction phase was applied for in 2020. Coordination with the Auburn School District related to the replacement of Chinook Elementary School is in progress. Future Impact on Operating Budget: The annual maintenance cost for this project is estimated to be $2,500. Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 42 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: M Street NE (E Main St to 4th St NE) TIP# R-7 Project No:asbd12 Project Type:Capacity Project Manager:TBD LOS Corridor ID# 5 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - 120,000 - Arterial Street Fund (105)- - - 185,000 - REET 2 - - - - - Traffic Impact Fees - - - 70,000 - Other - - - - - - - - 375,000 - Capital Expenditures: Design - - - 375,000 - Right of Way - - - - - Construction - - - - - - - - 375,000 - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue 50,000 400,000 - - 570,000 Arterial Street Fund (105)- 1,220,000 - - 1,405,000 REET 2 - 400,000 - - 400,000 Traffic Impact Fees - 465,000 - - 535,000 Other - - - - - 50,000 2,485,000 - - 2,910,000 Capital Expenditures: Design - - - - 375,000 Right of Way 50,000 - - - 50,000 Construction - 2,485,000 - - 2,485,000 50,000 2,485,000 - - 2,910,000 Grants / Other Sources: Description: This project will construct a complete four/five-lane street section on M St NE from south of E Main St to 4th St NE, and reconstruct the signal at E Main St. The project is needed to improve traffic operations along the M Street NE corridor, and replace the existing pavement which is in poor condition. Progress Summary: Future Impact on Operating Budget: The annual maintenance cost for this project is estimated to be $500. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 43 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: 49th Street NE (Auburn Way N to D St NE)TIP # R-8 Project No:asbd38 Project Type:Capacity Project Manager:TBD LOS Corridor ID# N/A Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - - - Grants- Secured (Fed,State,Local)- - - - - Traffic Impact Fees - - - - - Other Sources - Developer - - 500,000 1,500,000 500,000 - - 500,000 1,500,000 500,000 Capital Expenditures: Design - - 350,000 - 350,000 Right of Way - - 150,000 - 150,000 Construction - - - 1,500,000 - - - 500,000 1,500,000 500,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Grants- Secured (Fed,State,Local)- - - - - Traffic Impact Fees - - - - - Other Sources - Developer - - - - 2,000,000 - - - - 2,000,000 Capital Expenditures: Design - - - - 350,000 Right of Way - - - - 150,000 Construction - - - - 1,500,000 - - - - 2,000,000 Grants / Other Sources: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Total Expenditures: Description: This project will construct the build-out of 49th Street NE between Auburn Way N and D Street NE. The improvements are funded by private development. Progress Summary: Conceptual design and development agreement for funding underway in 2020. Future Impact on Operating Budget: The annual maintenance cost for this project is estimated to be $500. City of Auburn Capital Facilities Plan 44 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: 46th Place S Realignment TIP# R-9 Project No:cpxxx Project Type:Capacity, Safety Project Manager:TBD LOS Corridor ID# N/A Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - - - Grants- Unsecured - - - - - REET 2 - - - - - Traffic Impact Fees - - - - - Other Sources - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Grants- Unsecured - - 300,000 540,000 840,000 REET 2 - - - - - Traffic Impact Fees - - 75,000 135,000 210,000 Other Sources - - - - - - - 375,000 675,000 1,050,000 Capital Expenditures: Design - - 125,000 - 125,000 Right of Way - - 250,000 - 250,000 Construction - - - 675,000 675,000 - - 375,000 675,000 1,050,000 Grants / Other Sources: Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Description: The project will realign 46th Place S to the south of S 321st Street. The realignment will move the 46th Place S intersection with S 321st Street approximately 350 feet to the east of the current location. This will create two T-intersections (44th Avenue S and 46th Place S) in place of the existing four-leg intersection. The existing 46th Place S will be dead-ended to the south of S 321st Street. The project will improve safety and traffic operations at the intersections. Progress Summary: A portion of the right-of-way for the realigned roadway was dedicated as part of an adjacent development project. Future Impact on Operating Budget: The annual maintenance cost for this project is estimated to be $1,000. City of Auburn Capital Facilities Plan 45 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: 124th Ave SE Corridor Improvements (SE 312th to SE 318th)TIP# R-11 Project No:asbd01 Project Type:Capacity Project Manager:TBD LOS Corridor ID# 23 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - - - Grants- Unsecured Federal - - - - - Traffic Impact Fees - - - - - Other - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Grants- Unsecured Federal - - - - - Traffic Impact Fees - - - 400,000 400,000 Other - - - - - - - - 400,000 400,000 Capital Expenditures: Design - - - 400,000 400,000 Right of Way - - - - - Construction - - - - - - - - 400,000 400,000 Grants / Other Sources: Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: Total Funding Sources: Description: This project will widen 124th Avenue SE to create a four-lane section with bicycle and pedestrian facilities SE 318th St and SE 312th St. The project will also construct improvements at the SE 312th St/124th Ave SE intersection (including adding bike lanes, dual westbound left-turn lanes, dual southbound through-lanes, a northbound right-turn pocket, ITS improvements, and pedestrian safety improvements). The project is needed to improve traffic operations along the corridor and to accommodate all travel modes. Progress Summary: Phase 1 improvements between SE 318th and SE 316th were completed by GRC in 2012. Future Impact on Operating Budget: The annual maintenance cost for this project is estimated to be $1,000. City of Auburn Capital Facilities Plan 46 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: Regional Growth Center Access Improvements TIP# R-16 Project No:asbd24 Project Type:Capacity Project Manager:TBD LOS Corridor ID# N/A Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - - - Grants- Secured - - 325,000 - 325,000 Traffic Impact Fees - - 85,000 100,000 85,000 REET2 - - - - - Other - - - - - - - 410,000 100,000 410,000 Capital Expenditures: Design - - 410,000 - 410,000 Right of Way - - - 100,000 - Construction - - - - - - - 410,000 100,000 410,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Grants- Secured 1,300,000 - - - 1,625,000 Traffic Impact Fees 200,000 - - - 385,000 REET2 - - - - - Other - - - - - 1,500,000 - - - 2,010,000 Capital Expenditures: Design - - - - 410,000 Right of Way - - - - 100,000 Construction 1,500,000 - - - 1,500,000 1,500,000 - - - 2,010,000 Grants / Other Sources: Total Expenditures: Description: The project will construct a northbound left-turn lane and a northbound/southbound crosswalk at the 3rd Street NE/Auburn Avenue intersection, and realign the 4th Street NE/Auburn Way N intersection to eliminate the split phase signal operation improving circulation and access. The project will improve traffic operations, safety, and circulation for both vehicles and non-motorized users. Progress Summary: Grant funding for the design and construction phases was awarded from Sound Transit in 2019. Future Impact on Operating Budget: The annual maintenance cost for this project is estimated to be $500. Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 47 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: Stewart Road - City of Pacific (Lake Tapps Parkway Corridor)TIP# R-24 Project No:asbd25 Project Type:Capacity Project Manager:City of Pacific LOS Corridor ID# N/A Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - - - Grants- Secured (Fed,State,Local)- - - - - Traffic Impact Fees - - - - - REET2 - - - - - Traffic Mitigation Fees - - 100,000 - 100,000 - - 100,000 - 100,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - 100,000 - 100,000 - - 100,000 - 100,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Grants- Secured (Fed,State,Local)- - - - - Traffic Impact Fees - - - - - REET2 - - - - - Traffic Mitigation Fees - - - - 100,000 - - - - 100,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 100,000 - - - - 100,000 Grants / Other Sources: Total Expenditures: Description: This is a City of Pacific project to widen the Stewart Road (Lake Tapps Parkway) Corridor. This is the final segment of widening in the City of Pacific which will tie in with the City of Sumner's planned final widening segment and new bridge over the White River. Completion of this corridor widening is expected to significantly relieve traffic congestion in Auburn along the A St SE and C St SW corridors. Progress Summary: City of Pacific is in the process of completing the design phase and environmental permitting for the project. Construction is currently planned for 2021/22. Future Impact on Operating Budget: There is no future impact to Auburn's operating budgets. Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 48 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: East Valley Highway Widening TIP # R-26 Project No:cpxxxx Project Type:Capacity Project Manager:TBD LOS Corridor ID# Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - - - Unsecured Grant - - - - - Traffic Impact Fees - - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Unsecured Grant - - - 200,000 200,000 Traffic Impact Fees - - - 100,000 100,000 - - - - 300,000 300,000 Capital Expenditures: Design - - - 300,000 300,000 Right of Way - - - - - Construction - - - - - - - - 300,000 300,000 Grants / Other Sources: Description: This project will widen E Valley Highway between Lakeland Hills Way and Terrace View Drive SE, approximately 0.6 miles. The roadway will have a four/five lane cross section with a trail connection along the east side. Other project elements include storm improvement, illumination and ITS. The project will provide congestion relief along the corridor and provide access for non-motorized users. Progress Summary: Future Impact on Operating Budget: The annual maintenance cost for this project is estimated to be $2,500. Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Total Expenditures: City of Auburn Capital Facilities Plan 49 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: Garden Avenue Realignment TIP # R-27 Project No:cp2022 Project Type:Capacity Project Manager:TBD LOS Corridor ID# 19 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - - - Grants- Secured (Fed,State,Local)- - - - - Traffic Impact Fees - 150,000 150,000 500,000 300,000 - 150,000 150,000 500,000 300,000 Capital Expenditures: Design - 150,000 - - 150,000 Right of Way - - 150,000 - 150,000 Construction - - - 500,000 - - 150,000 150,000 500,000 300,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Grants- Secured (Fed,State,Local)- - - - - Traffic Impact Fees - - - - 650,000 - - - - 650,000 Capital Expenditures: Design - - - - - Right of Way - - - - 150,000 Construction - - - - 500,000 - - - - 650,000 Grants / Other Sources: Description: The project will construct a new east/west connection between Garden Avenue and 104th Avenue SE, and will cul-de-sac Garden Avenue to the north of 8th Street NE. This will improve traffic operations and safety along 8th Street NE. Progress Summary: The previous project title (Lea Hill Rd Segment 1A) was updated based on recommendations of the Lea Hill Corridor Study in 2020. In 2016, a parcel at the intersection of Garden Avenue and 320th/8th Street was purchased for the project. In 2016, right-of-way was dedicated for a portion of the new east/west roadway as part of an adjacent development project. Additional property acquisition underway in 2020. Future Impact on Operating Budget: The annual maintenance cost for this project is estimated to be $1,000. Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Total Expenditures: City of Auburn Capital Facilities Plan 50 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: A Street NW - Phase 1 (3rd St NW to 14th St NW) TIP# S-1 Project No:c207a0 Project Type:Capacity, Environmental Monitoring Project Manager:Tim Carlaw LOS Corridor ID# 18 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue 123,276 - - - 123,276 Grants- Secured (Fed,State)6,562,702 - - - 6,562,702 Traffic Impact Fees 1,288,115 25,000 25,000 25,000 1,338,115 Other Sources -Multicare Contribution 383,381 - - - 383,381 8,357,474 25,000 25,000 25,000 8,407,474 Capital Expenditures: Design 2,247,331 - - - 2,247,331 Right of Way 821,341 - - - 821,341 Construction 5,000,640 - - - 5,000,640 Environmental 288,162 25,000 25,000 25,000 338,162 8,357,474 25,000 25,000 25,000 8,407,474 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Grants- Secured (Fed,State)- - - - - Traffic Impact Fees - - - - 50,000 Other Sources -Multicare Contribution - - - - - - - - - 50,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - Environmental - - - - 50,000 - - - - 50,000 Grants / Other Sources: Description: The project constructed a new multi-lane arterial from 3rd Street NW to 14th Street NW completing a missing link along the corridor. This project improves mobility and was tied to corridor development. The project length was approximately three- quarters of a mile. The City purchased ROW from the northern property owner. If the property develops any access to A St NW, some or a portion of those funds may be reimbursed to the City (total cost was $251,000). Progress Summary: Pre-design was completed prior to 2007. Final design and environmental permitting were completed in 2011 and construction was completed in 2013. Major plantings are scheduled in 2015 as part of the wetland monitoring that is required to continue until 2023. Future Impact on Operating Budget: N/A Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 51 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: S 272nd/277th St Corridor Capacity & Non-Motorized Trail Improvements TIP# S-2 Project No:cp1821 Project Type:Capacity, Environmental Monitoring Project Manager:Tim Carlaw LOS Corridor ID# 15 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - - - Grants- Secured Federal - - - - - Grants- Secured State - - - - - Traffic Impact Fees 16,027 20,000 20,000 20,000 56,027 Other (Development Funds)*- - - - - Other - - - - - 16,027 20,000 20,000 20,000 56,027 Capital Expenditures: Design - - - - - Right of Way - - - - - Environmental 16,027 20,000 20,000 20,000 56,027 Construction - - - - - 16,027 20,000 20,000 20,000 56,027 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Grants- Secured State - - - - - Traffic Impact Fees 20,000 20,000 20,000 20,000 120,000 Other (Development Funds)*- - - - - Other - - - - - 20,000 20,000 20,000 20,000 120,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Environmental 20,000 20,000 20,000 20,000 120,000 Construction - - - - - 20,000 20,000 20,000 20,000 120,000 Grants / Other Sources: Description: This project will complete the environmental monitoring requirements related to the S 277th St corridor widening project between Auburn Way North and l St NE. Progress Summary: The 10 year monitoring period began in 2018 after final completion and continue through 2028. Future Impact on Operating Budget: N/A Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 52 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: A Street SE Corridor Study TIP# S-3 Project No:CP1110 Project Type:Capacity, Safety Project Manager:James Webb LOS Corridor ID# 10, 34 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue 1,230 - - 1,230 Grants- Secured (Fed,State,Local)- - - - - Traffic Impact Fees - 105,000 10,000 - 115,000 REET2 - - - - - Other - - - - - 1,230 105,000 10,000 - 116,230 Capital Expenditures: Design 1,230 105,000 10,000 - 116,230 Right of Way - - - - - Construction - - - - - 1,230 105,000 10,000 - 116,230 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - - Grants- Secured (Fed,State,Local)- - - - - Traffic Impact Fees - - - - 10,000 REET2 - - - - - Other - - - - - - - - - 10,000 Capital Expenditures: Design - - - - 10,000 Right of Way - - - - - Construction - - - - - - - - - 10,000 Grants / Other Sources: Total Expenditures: Description: Study the A Street SE corridor between 6th Street SE and Lakeland Hills Way SE, including 41st Street SE from D Street SE to C Street SW. The study will review safety, access, and traffic operations. Progress Summary: The study is underway in 2020. Funds shown in 2021 are a placeholder for a potential 2020 project budget carryforward. Future Impact on Operating Budget: This project will have no impact on the operating budget for street maintenance. Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 53 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: Auburn Way N/1st Street NE Signal Replacement TIP# I-1 Project No:CP1927 Project Type:Non-Capacity Project Manager:Matt Larson LOS Corridor ID# N/A Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue 11,513 200,000 525,000 - 736,513 Arterial Preservation Fund (105)- - 50,000 - 50,000 Grants- Unsecured (Fed & State)- - - - - Traffic Impact Fees - - - - - Other Sources - - - - - 11,513 200,000 575,000 - 786,513 Capital Expenditures: Design 11,513 150,000 - - 161,513 Right of Way - 50,000 - - 50,000 Construction - - 575,000 - 575,000 11,513 200,000 575,000 - 786,513 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - 525,000 Arterial Preservation Fund (105)- - - - Grants- Unsecured (Fed & State)- - - - - Traffic Impact Fees - - - - - Other Sources - - - - - - - - - 525,000 Capital Expenditures: Design - - - - Right of Way - - - - - Construction - - - 575,000 - - - - 575,000 Grants / Other Sources: Total Expenditures: Description: The project will replace the existing traffic signal at the Auburn Way N/1st Street NE signal. The signal was constructed in 1968 and is approaching the end of its service life. The project scope also includes the construction of ADA improvements, curb-bulbs, and storm improvements. Progress Summary: Project design underway in 2020. Future Impact on Operating Budget: Replacing the traffic signal will reduce on-going maintenance costs to replace parts and equipment that have reached the end of their service life. Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 54 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: ITS Dynamic Message Signs TIP# I-3 Project No:asbd16, cp1701, cp1912 Project Type:Non-Capacity (ITS) Project Manager:Seth Wickstrom LOS Corridor ID# N/A Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue 224,320 125,000 - 349,320 Grants- Unsecured Federal - - - - - REET 97,500 - - - 97,500 PWTFL - - - - - Other (MIT)- - - - - 321,820 125,000 - - 446,820 Capital Expenditures: Design 32,500 - - - 32,500 Right of Way - - - - - Construction 289,320 125,000 - - 414,320 321,820 125,000 - - 446,820 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - 20,000 20,000 Grants- Unsecured Federal - - - - - REET - - - - - PWTFL - - - - - Other (MIT)- - - - - - - - 20,000 20,000 Capital Expenditures: Design - - - 20,000 20,000 Right of Way - - - - - Construction - - - - - - - - 20,000 20,000 Grants / Other Sources: Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: Total Funding Sources: Description: The program constructs Dynamic Message Signs at various locations throughout the City. Dynamic message signs are an important tool for communicating with roadway users in real time. Priority locations for sign placement are based on the Comprehensive Transportation Plans ITS map and include S. 277th, Auburn Way N, Auburn Way S, W Valley Highway, E Valley Highway, Lake Tapps Parkway, 15th St NW, and Lea Hill Rd. Progress Summary: The first two signs (Auburn Way S and S 277th Street) have been completed. The sign on 15th Street NW is currently in design and will be constructed during 2020. Future Impact on Operating Budget: The annual maintenance and operational costs for this project is estimated to be $750 per sign. City of Auburn Capital Facilities Plan 55 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: Auburn Avenue/E Main Street Signal Replacement TIP# I-7 Project No:cpxxxx Project Type:Non-Capacity Project Manager:TBD LOS Corridor ID# N/A Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - - - Grants- Unsecured (Fed & State)- - - - - Traffic Impact Fees - - - - - Other Sources - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - 150,000 150,000 Grants- Unsecured (Fed & State)- - - - - Traffic Impact Fees - - - - - Other Sources - - - - - - - - 150,000 150,000 Capital Expenditures: Design - - 150,000 150,000 Right of Way - - - - - Construction - - - - - - - 150,000 150,000 Grants / Other Sources: Total Expenditures: Description: This program will replace the existing traffic signal at the Auburn Avenue/E Main Street signal, which was constructed in 1968. The project scope also includes the construction of ADA improvements. Progress Summary: Future Impact on Operating Budget: Replacing the traffic signal will reduce on-going maintenance costs to replace parts and equipment that have reached the end of their service life. Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 56 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: Citywide Pedestrian Accessibility and Safety Program TIP# N-1 Project No:asbd08, cp1816, cp1804, cp1902 Project Type:Non-Capacity (Annual) Project Manager:James Webb LOS Corridor ID# N/A Activity: Previous 2 Years 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue 73,030 225,084 50,000 100,000 348,114 Grants- Secured (Fed,State,Local)- - - - - REET - - - - - Traffic Impact Fees - - - - - Other - - - - - 73,030 225,084 50,000 100,000 348,114 Capital Expenditures: Design 65,139 20,000 5,000 10,000 90,139 Right of Way - - Construction 7,891 205,084 45,000 90,000 257,975 73,030 225,084 50,000 100,000 348,114 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue 100,000 100,000 100,000 100,000 550,000 Grants- Secured (Fed,State,Local)- - - - - REET - - - - - Traffic Impact Fees - - - - - Other - - - - - 100,000 100,000 100,000 100,000 550,000 Capital Expenditures: Design 10,000 10,000 10,000 10,000 55,000 Right of Way - Construction 90,000 90,000 90,000 90,000 495,000 100,000 100,000 100,000 100,000 550,000 Grants / Other Sources: Description: The program will construct small pedestrian improvement projects at locations throughout the City. Projects are prioritized annually based on pedestrian demands, existing deficiencies, and citizen requests. Program funds reflect remaining budget after allocations to specific pedestrian accessibility and safety projects. Progress Summary: Future Impact on Operating Budget: This project will have no impact on the operating budget for street maintenance. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 57 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: Citywide Arterial Bicycle & Safety Improvements TIP# N-3 Project No:asbd07, cp1910 Project Type:Non-Capacity (Safety) Project Manager:Various LOS Corridor ID# N/A Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue 4,188 - 100,000 - 104,188 Grants- Secured (Fed,State,Local)- - - - - REET - - - - - Traffic Impact Fees - - - - - Other - - - - - 4,188 - 100,000 - 104,188 Capital Expenditures: Design - - 10,000 - 10,000 Right of Way - - - - - Construction 4,188 - 90,000 - 94,188 4,188 - 100,000 - 104,188 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue 100,000 - 100,000 - 300,000 Grants- Secured (Fed,State,Local)- - - - - REET - - - - - Traffic Impact Fees - - - - - Other - - - - - 100,000 - 100,000 - 300,000 Capital Expenditures: Design 10,000 - 10,000 - 30,000 Right of Way - - - - - Construction 90,000 - 90,000 - 270,000 100,000 - 100,000 - 300,000 Grants / Other Sources: Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Description: The program will construct bicycle and safety improvements on classified roadways throughout the City. Projects are prioritized bi-annually based upon field studies and community feedback. Progress Summary: Future Impact on Operating Budget: This project will have no impact on the operating budget for street maintenance. City of Auburn Capital Facilities Plan 58 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: Downtown Transit Center Access Improvements TIP# N-6 Project No:asbd28 Project Type:Non-Capacity, Transit Project Manager:TBD LOS Corridor ID# N/A Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - - - 25,000 - Grants- Unsecured (Fed,State,Local)- - - - - Traffic Impact Fees - - - - - REET2 - - - - - Other (King County Metro)- - - 100,000 - - - - 125,000 - Capital Expenditures: Design - - - 15,000 - Right of Way - - - - - Construction - - - 110,000 - - - - 125,000 - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - 25,000 Grants- Unsecured (Fed,State,Local)- - - - - Traffic Impact Fees - - - - - REET2 - - - - - Other (King County Metro)- - - - 100,000 - - - - 125,000 Capital Expenditures: Design - - - - 15,000 Right of Way - - - - - Construction - - - - 110,000 - - - - 125,000 Grants / Other Sources: Total Expenditures: Description: The project will reconstruct the channelization and curb radii to improve the turning radius for transit vehicles at the northeast corner of A St SW/2nd St SW. Progress Summary: The ROW needed to accommodate this improvement was dedicated by the adjacent development project. Future Impact on Operating Budget: This project will have no impact on the operating budget for street maintenance. Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 59 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: M Street SE Sidewalk Improvements TIP# N-10 Project No:CP2012 Project Type: Non-Capacity, Non-Motorized Project Manager:Luis Barba LOS Corridor ID# N/A Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue - 14,980 250,000 - 264,980 Secured Grant - 30,020 419,980 - 450,000 Traffic Impact Fees - - - - - Other - - - - - - 45,000 669,980 - 714,980 Capital Expenditures: Design - 45,000 - - 45,000 Right of Way - - - - - Construction - - 669,980 - 669,980 - 45,000 669,980 - 714,980 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - 250,000 Secured Grant - - - - 419,980 Traffic Impact Fees - - - - - Other - - - - - - - - - 669,980 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 669,980 - - - - 669,980 Grants / Other Sources: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Total Expenditures: Description: The project will construct sidewalks along the M Street SE corridor between Auburn Way S and 8th Street SE. The project will complete the missing sections of sidewalk along the west side of M Street SE between Auburn Way S and 8th Street SE, and will complete the missing segments of sidewalk along the east side between Auburn Way S and 12th Street SE. The project will construct approximately 2,000 linear feet of new sidewalk to match adjacent widths. The project will also construct ADA compliant curb ramps and relocate existing utility poles and overhead signage to provide ADA access. Progress Summary: Grant funding for the project was awarded by TIB in 2019. The design phase was initiated in 2020 and construction anticipated to be completed during 2021. Future Impact on Operating Budget: This project will have no impact on the operating budget for street maintenance. City of Auburn Capital Facilities Plan 60 ARTERIAL STREET FUND (102)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: Auburn Way S (SR-164) Poplar Curve Safety Improvements TIP# R-15 Project No:cp1901 Project Type:Non-Capacity, Safety Project Manager:Jeff Bender LOS Corridor ID# 4 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Street Revenue 5,500 - 10,000 - 15,500 Secured State Grant 24,654 238,046 - 262,700 Traffic Impact Fees - - - - - Other - - - - - 30,154 238,046 10,000 - 278,200 Capital Expenditures: Design 30,154 33,303 - - 63,457 Right of Way - 204,743 - - 204,743 Construction - - 10,000 10,000 30,154 238,046 10,000 - 278,200 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Street Revenue - - - - 10,000 Secured State Grant - - - - - Traffic Impact Fees - - - - - Other - - - - - - - - - 10,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 10,000 - - - - 10,000 Grants / Other Sources: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Total Expenditures: Description: This project will complete design and construct safety improvements at the curve along Auburn Way S in the vicinity of the intersection with Poplar Street. The improvements would include, illumination, electronic curve ahead warning signage, a high-friction surface treatment for the pavement, guardrail and driveway improvements. Progress Summary: Grant funding was awarded in 2018 that allowed design to start in 2019 with construction in 2020. Funds shown in 2021 are for anticipated carryforward. Future Impact on Operating Budget: This project will have no impact on the operating budget for street maintenance. City of Auburn Capital Facilities Plan 61 TABLE T- 2A CAPITAL FACILITIES PLAN PROJECTS AND FINANCING TRANSPORTATION – LOCAL STREET 2021 2022 2023 2024 2025 2026 Total Capacity Projects: None - Page # Non-Capacity Projects: 62 Local Street Improvement Program Capital Costs - 150,000 1,650,000 1,650,000 1,650,000 1,650,000 6,750,000 Funding Sources: Fund Balance - - - - - - - Transfer In (W/S/SWM Utility)- 150,000 150,000 150,000 150,000 150,000 750,000 To Be Determined - - 1,500,000 1,500,000 1,500,000 1,500,000 6,000,000 Other REET 2 - - - - - - - 63 2021 Local Street Preservation Project Capital Costs 2,200,000 - - - - - 2,200,000 Funding Sources: Fund Balance - - - - - - - Transfer In (W/S/SWM Utility)- - - - - - - Other REET 1 1,500,000 - - - - - 1,500,000 Other REET 2 700,000 - - - - - 700,000 64 2022 Local Street Preservation Project Capital Costs 150,000 1,500,000 - - - - 1,650,000 Funding Sources: Fund Balance - - - - - - - Transfer In (W/S/SWM Utility)150,000 - - - - - 150,000 Other REET 1 - 750,000 - - - - 750,000 Other REET 2 - 750,000 - - - - 750,000 SUMMARY: CAPITAL COSTS Capacity Projects - - - - - - - Non-Capacity Projects 2,350,000 1,650,000 1,650,000 1,650,000 1,650,000 1,650,000 10,600,000 Total Costs 2,350,000 1,650,000 1,650,000 1,650,000 1,650,000 1,650,000 10,600,000 FUNDING SOURCES: Fund Balance - - - - - - - Transfer In (W/S/SWM Utility)150,000 150,000 150,000 150,000 150,000 150,000 900,000 To Be Determined - - 1,500,000 1,500,000 1,500,000 1,500,000 6,000,000 Other REET 1 1,500,000 750,000 - - - - 2,250,000 Other REET 2 700,000 750,000 - - - - 1,450,000 Total Funding 2,350,000 1,650,000 1,650,000 1,650,000 1,650,000 1,650,000 10,600,000 City of Auburn Capital Facilities Plan 62 LOCAL STREET FUND (103)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: Local Street Improvement Program TIP# P-2 Project No:sobd02, cp1614, cp1717, cp1725, cp1726, cp1925 Project Type:Non-Capacity, Preservation Project Manager:Kenneth Clark LOS Corridor ID# N/A Activity: (Previous 2Yrs.)2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Local Street Fund - 650,000 - - 650,000 Transfer In (Utilities)300,000 150,000 - 150,000 450,000 Sales Tax on Construction 2,644,476 - - - 2,644,476 To Be Determined - - - - - REET 1 - - - - - REET 2 1,750,000 1,050,000 - - 2,800,000 4,694,476 1,850,000 - 150,000 6,544,476 Capital Expenditures: Design 339,818 525,000 - 150,000 864,818 Right of Way - - - - - Construction 4,354,658 1,325,000 - - 5,679,658 4,694,476 1,850,000 - 150,000 6,544,476 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Local Street Fund - - - - - Transfer In (Utilities)150,000 150,000 150,000 150,000 750,000 Sales Tax on Construction - - - - - To Be Determined 1,500,000 1,500,000 1,500,000 1,500,000 6,000,000 REET 1 - - - - - REET 2 - - - - - 1,650,000 1,650,000 1,650,000 1,650,000 6,750,000 Capital Expenditures: Design 500,000 500,000 500,000 500,000 2,150,000 Right of Way - - - - - Construction 1,150,000 1,150,000 1,150,000 1,150,000 4,600,000 1,650,000 1,650,000 1,650,000 1,650,000 6,750,000 Grants / Other Sources: Description: The program preserves local (unclassified) streets. Individual projects may include crack sealing, asphalt patching, pre- leveling, asphalt overlays and roadway reconstruction. The program also funds the biennial collection of pavement condition ratings, conducted in even numbered years. Beginning in 2019 REET funding was dedicated by council to this program. Beyond 2022, funding for this program is shown as other because a dedicated funding source has not yet been identified, and the use of REET to fund the program is not sustainable in the long-term. Program funds reflect remaining budget after allocations to specific arterial street preservation projects which are included as separate projects. Progress Summary: This program has successfully completed overlays, chip seals and complete reconstructions since 2005. The program will focus on completing reconstruction needs in addition to regular maintenance treatments. Future Impact on Operating Budget: This project is anticipated to reduce the operating budget for street maintenance. Total Funding Sources: Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: City of Auburn Capital Facilities Plan 63 LOCAL STREET FUND (103)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: 2021 Local Street Preservation Project TIP# P-7 Project No:cp2019 Project Type:Non-Capacity, Preservation Project Manager:Kim Truong LOS Corridor ID# N/A Activity: (Previous 2Yrs.)2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Local Street Fund - - - - - Transfer In (Utilities)- - - - - Sales Tax on Construction - - - - - REET 1 - - 1,500,000 - 1,500,000 REET 2 - - 700,000 - 700,000 - - 2,200,000 - 2,200,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - 2,200,000 - 2,200,000 - - 2,200,000 - 2,200,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Local Street Fund - - - - - Transfer In (Utilities)- - - - - Sales Tax on Construction - - - - - REET 1 - - - - 1,500,000 REET 2 - - - - 700,000 - - - - 2,200,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 2,200,000 - - - - 2,200,000 Grants / Other Sources: Total Funding Sources: Total Expenditures: Description: This project will reconstruct G Street SE (from East Main Street to 4th Street SE) and grind and overlay the Riverwalk/Forest Ridge Neighborhood. The scope of work includes the following: full-depth roadway replacement and/or grind and overlay and any needed utility improvements within the project limits. Progress Summary: Project design underway in 2020. REET funds shown include $700k carry forward of 2020 funds from project CP1925 - 2020 Local Street Preservation Project and $1.5M of new REET funding in 2021. Future Impact on Operating Budget: This project is anticipated to reduce the operating budget for street maintenance. Total Funding Sources: Total Expenditures: Forecasted Project Cost: City of Auburn Capital Facilities Plan 64 LOCAL STREET FUND (103)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: 2022 Local Street Preservation Project TIP# P-8 Project No:cp2101 Project Type:Non-Capacity, Preservation Project Manager:TBD LOS Corridor ID# N/A Activity: (Previous 2Yrs.)2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Local Street Fund - - - - - Transfer In (Utilities)- - 150,000 - 150,000 Sales Tax on Construction - - - - - REET 1 - - - 750,000 - REET 2 - - - 750,000 - - - 150,000 1,500,000 150,000 Capital Expenditures: Design - - 150,000 - 150,000 Right of Way - - - - - Construction - - - 1,500,000 - - - 150,000 1,500,000 150,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Local Street Fund - - - - - Transfer In (Utilities)- - - - 150,000 Sales Tax on Construction - - - - - REET 1 - - - - 750,000 REET 2 - - - - 750,000 - - - - 1,650,000 Capital Expenditures: Design - - - - 150,000 Right of Way - - - - - Construction - - - - 1,500,000 - - - - 1,650,000 Grants / Other Sources: Total Funding Sources: Total Expenditures: Description: This project will reconstruct I Street SE (from East Main Street to 4th Street SE). The scope of work includes the following: full-depth roadway replacement and any needed utility improvements within the project limits. Progress Summary: Future Impact on Operating Budget: This project is anticipated to reduce the operating budget for street maintenance. Total Funding Sources: Total Expenditures: Forecasted Project Cost: City of Auburn Capital Facilities Plan 65 TABLE T- 2B CAPITAL FACILITIES PLAN PROJECTS AND FINANCING TRANSPORTATION – STREET PRESERVATION 2021 2022 2023 2024 2025 2026 Total Capacity Projects: None - Page Non-Capacity Projects: 67 Arterial Street Preservation Program Capital Costs 327,500 1,650,000 606,728 599,514 2,100,000 2,200,000 7,483,742 Funding Sources: Fund Balance 327,500 1,650,000 606,728 599,514 2,100,000 2,200,000 7,483,742 REET 2 -Streets - - - - - - - Utility Tax - - - - - - - 68 Auburn Way N Preservation Phase 2 (8th St NE to 22nd St NE) Capital Costs 10,000 - - - - - 10,000 Funding Sources: Fund Balance 10,000 - - - - - 10,000 Grants - - - - - - - Utility Tax - - - - - - - 69 Auburn Way N Preservation Phase 3 (4th St SE to 8th St NE ) Capital Costs 10,000 - - - - - 10,000 Funding Sources: Fund Balance 10,000 - - - - - 10,000 Grants - - - - - - - 70 2nd Street SE Preservation Capital Costs 868,750 - - - - - 868,750 Funding Sources: Fund Balance 347,500 - - - - - 347,500 Grants 521,250 - - - - - 521,250 71 Lake Tapps Pkwy/Sumner-Tapps Hwy E Preservation Capital Costs - 25,000 75,000 1,284,356 - - 1,384,356 Funding Sources: Fund Balance - 25,000 75,000 534,356 - - 634,356 Grants - - - 750,000 - - 750,000 72 Lea Hill Bridge Deck Preservation Capital Costs 100,000 - - - - - 100,000 Funding Sources: Fund Balance - - - - - - - Grants 100,000 - - - - - 100,000 73 A St SE Preservation (37th Street SE to Lakeland Hills Way) Capital Costs - 25,000 100,000 1,732,260 - - 1,857,260 Funding Sources: Fund Balance - 25,000 100,000 866,130 - - 991,130 Grants - - - 866,130 - - 866,130 74 C Street SW Preservation (W Main St to GSA Signal) Capital Costs 25,000 100,000 2,236,544 - - - 2,361,544 Funding Sources: Fund Balance 25,000 100,000 1,118,272 - - - 1,243,272 Grants - - 1,118,272 - - - 1,118,272 75 Lakeland Hill Way Preservation (57th Drive SE to Lake Tapps Pkwy) Capital Costs 1,350,000 - - - - - 1,350,000 Funding Sources: Fund Balance 1,350,000 - - - - - 1,350,000 Grants - - - - - - - 76 3rd Street SW Bridges Deck Preservation Capital Costs 120,000 - - - - - 120,000 Funding Sources: Fund Balance - - - - - - - Grants 120,000 - - - - - 120,000 Note: Financial plan utilizes the following order for use of funds to finance projects: grant revenues (if available), utility tax revenues and fund balance. City of Auburn Capital Facilities Plan 66 TABLE T- 2B (continued) 2021 2022 2023 2024 2025 2026 Total SUMMARY: CAPITAL COSTS Capacity Projects - - - - - - - Non-Capacity Projects 2,811,250 1,800,000 3,018,272 3,616,130 2,100,000 2,200,000 15,545,652 Total Costs 2,811,250 1,800,000 3,018,272 3,616,130 2,100,000 2,200,000 15,545,652 FUNDING SOURCES: Fund Balance 2,070,000 1,800,000 1,900,000 2,000,000 2,100,000 2,200,000 12,070,000 Grants 741,250 - 1,118,272 1,616,130 - - 3,475,652 REET 2 -Streets - - - - - - - Total Funding 2,811,250 1,800,000 3,018,272 3,616,130 2,100,000 2,200,000 15,545,652 City of Auburn Capital Facilities Plan 67 ARTERIAL STREET PRESERVATION FUND (105)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Funds Project Title: Arterial Street Preservation Program TIP# P-1 Project No:Varies annually, spbd01, cp1520, cp1718, cp1725, cp1803, cp1829, cp1926 Project Type:Non-Capacity, Preservation Project Manager:Kenneth Clark LOS Corridor ID# N/A Activity: (Previous 2 Years)2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Arterial Preservation Fund 27,332 2,200,000 327,500 1,650,000 2,554,832 Utility Tax 1,538,600 - - - 1,538,600 REET2 -Streets 1,948,779 - - - 1,948,779 Other -Development Fees 79,343 Grants -Federal 652,858 - - - 652,858 4,246,912 2,200,000 327,500 1,650,000 6,695,069 Capital Expenditures: Design 180,205 330,000 49,125 247,500 559,330 Right of Way - - - - - Construction 4,066,707 1,870,000 278,375 1,402,500 6,215,082 4,246,912 2,200,000 327,500 1,650,000 6,774,412 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Arterial Preservation Fund 606,728 599,514 2,100,000 2,200,000 7,483,742 Utility Tax - - - - - REET2 -Streets - - - - - Grants -Federal - - - - - 606,728 599,514 2,100,000 2,200,000 7,483,742 Capital Expenditures: Design 91,009 89,927 315,000 330,000 1,122,561 Right of Way - - - - - Construction 515,719 509,587 1,785,000 1,870,000 6,361,181 606,728 599,514 2,100,000 2,200,000 7,483,742 Grants / Other Sources: Description: The program preserves classified streets throughout the City. Individual projects may include a combination of crack seal, overlays, rebuilds, and spot repairs. The program also funds the biennial collection of pavement condition ratings. This program is funded through a 1% utility tax that was adopted by City Council in 2008. Program funds reflect remaining budget after allocations to specific arterial street preservation projects which are included as separate projects in this TIP. Progress Summary: The 2020 construction cycle includes the reconstruction of 15th Street NW between West Valley Highway and Terrace Drive. The project will also overlay 15th Street NW between West Valley Highway and SR 167. A crack seal project of arterial and collector streets is also proposed. Future Impact on Operating Budget: This program is anticipated to reduce the operating budget for street maintenance. Total Funding Sources: Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: City of Auburn Capital Facilities Plan 68 ARTERIAL STREET PRESERVATION FUND (105)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: Auburn Way N Preservation Phase 2 (8th St NE to 22nd St NE)TIP# P-1 Project No:cp1903 Project Type:Non-Capacity, Preservation Project Manager:Luis Barba LOS Corridor ID# 1/2 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Arterial Preservation Fund 123,206 398,000 10,000 - 531,206 Secured Federal Grants - 1,100,000 - - 1,100,000 Utility Tax - - - - - Bond proceeds - - - - - 123,206 1,498,000 10,000 - 1,631,206 Capital Expenditures: Design 123,206 30,500 - - 153,706 Right of Way - - - - - Construction - 1,467,500 10,000 - 1,477,500 123,206 1,498,000 10,000 - 1,631,206 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Arterial Preservation Fund - - - - 10,000 Secured Federal Grants - - - - - Utility Tax - - - - - Bond proceeds - - - - - - - - - 10,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 10,000 - - - - 10,000 Grants / Other Sources: Description: This project will grind and overlay Auburn Way N from 8th Street NE to 22nd Street NE, remove unused driveways, and upgrade all curb ramps and pedestrian signals to meet ADA requirements. Progress Summary: Federal grant funding was awarded in 2016 and adjusted in 2019 to shift funds to A Street SE Preservation project (CP1819) to assist WSDOT with funds obligation targets. Project construction is underway in 2020. Funds shown in 2021 are a placeholder for a potential 2020 project budget carryforward. Future Impact on Operating Budget: This project is anticipated to reduce the operating budget for street maintenance. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 69 ARTERIAL STREET PRESERVATION FUND (105)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: Auburn Way N Preservation Phase 3 (4th St SE to 8th St NE )TIP# P-1 Project No:cp1904 Project Type:Non-Capacity, Preservation Project Manager:Luis Barba LOS Corridor ID# 2 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Arterial Preservation Fund 16,648 948,551 10,000 - 975,199 Secured Federal Grants 100,078 875,062 - - 975,140 Utility Tax - - - - - Bond proceeds - - - - - 116,726 1,823,613 10,000 - 1,950,339 Capital Expenditures: Design 116,726 57,888 - - 174,614 Right of Way - - - - - Construction - 1,765,725 10,000 - 1,775,725 116,726 1,823,613 10,000 - 1,950,339 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Arterial Preservation Fund - - - - 10,000 Secured Federal Grants - - - - - Utility Tax - - - - - Bond proceeds - - - - - - - - - 10,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 10,000 - - - - 10,000 Grants / Other Sources: Description: This project will grind and overlay Auburn Way N from approximately 8th Street NE to approximately 4th St SE, remove unused driveways, and upgrade all curb ramps and pedestrian signals to meet ADA requirements. Progress Summary: Federal Grant funding was awarded in 2016. Project construction is underway in 2020. Funds shown in 2021 are a placeholder for a potential 2020 project budget carryforward. Future Impact on Operating Budget: This project is anticipated to reduce the operating budget for street maintenance. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 70 ARTERIAL STREET PRESERVATION FUND (105)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Funds Project Title: 2nd Street SE Preservation TIP# P-3 Project No:CP2003 Project Type:Non-Capacity, Preservation Project Manager:Jai Carter Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Arterial Preservation Fund - 46,000 347,500 - 393,500 Secured State Grant - 69,000 521,250 - 590,250 Utility Tax - - - - - Bond proceeds - - - - - - 115,000 868,750 - 983,750 Capital Expenditures: Design - 115,000 - - 115,000 Right of Way - - - - - Construction - - 868,750 - 868,750 - 115,000 868,750 - 983,750 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Arterial Preservation Fund - - - - 347,500 Secured State Grant - - - - 521,250 Utility Tax - - - - - Bond proceeds - - - - - - - - - 868,750 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 868,750 - - - - 868,750 Grants / Other Sources: Total Expenditures: Description: This project will reconstruct 2nd Street SE between A Street SE and Auburn Way S. The reconstruction will utilize full depth reclamation techniques. The project will also address fixed objects located within the clear zone, remove barriers to ADA access, and install new LED street lighting. Progress Summary: Grant funding for this project was awarded by TIB in 2019. The design phase started in 2020. Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Future Impact on Operating Budget: This project is anticipated to reduce the operating budget for street maintenance. City of Auburn Capital Facilities Plan 71 ARTERIAL STREET PRESERVATION FUND (105)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Funds Project Title: Lake Tapps Pkwy/Sumner-Tapps Hwy E Preservation TIP# P-6 Project No:spbd08 Project Type:Non-Capacity, Preservation Project Manager:TBD Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Arterial Preservation Fund - - 25,000 - Unsecured Grant - - - - - Utility Tax - - - - - Bond proceeds - - - - - - - - 25,000 - Capital Expenditures: Design - - - - Right of Way - - - 25,000 - Construction - - - - - - - - 25,000 - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Arterial Preservation Fund 75,000 534,356 - - 634,356 Unsecured Grant - 750,000 - - 750,000 Utility Tax - - - - - Bond proceeds - - - - - 75,000 1,284,356 - - 1,384,356 Capital Expenditures: Design 50,000 - - - 50,000 Right of Way 25,000 - - - 50,000 Construction 1,284,356 - - 1,284,356 75,000 1,284,356 - - 1,384,356 Grants / Other Sources: Total Expenditures: Description: The project will grind and overlay the Lake Tapps Parkway/Sumner-Tapps Highway E corridor from the intersection of Lake Tapps Parkway with Lakeland Hills Way to the intersection of Sumner-Tapps Highway E with 16th Street E (the Auburn City limit). Portions of the corridor include a center two-way left-turn lane which does not require preservation and would be omitted from the grind and overlay. The project scope also includes upgrades to ADA curb ramps and pedestrian push buttons, and replacement of vehicle detection at signalized intersections. Progress Summary: An application for grant funding for the project was submitted in 2020. If awarded, design will begin in 2022 and construction in 2024. Future Impact on Operating Budget: This project is anticipated to reduce the operating budget for street maintenance. Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 72 ARTERIAL STREET PRESERVATION FUND (105)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Funds Project Title: Lea Hill Bridge Deck Preservation TIP# P-9 Project No:CP2007 Project Type:Non-Capacity, Preservation Project Manager:Kim Truong Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Arterial Preservation Fund - - - - - Secured Federal Grant - 547,850 100,000 - 647,850 Utility Tax - - - - - Bond proceeds - - - - - - 547,850 100,000 - 647,850 Capital Expenditures: Design - 80,000 - 80,000 Right of Way - - - - - Construction - 467,850 100,000 567,850 - 547,850 100,000 - 647,850 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Arterial Preservation Fund - - - - - Secured Federal Grant - - - - 100,000 Utility Tax - - - - - Bond proceeds - - - - - - - - - 100,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 100,000 - - - - 100,000 Grants / Other Sources: Total Expenditures: Description: This project will grind and overlay the bridge deck in an effort to extend the overall service life of the bridge. Progress Summary: Grant funding was awarded in 2020. Future Impact on Operating Budget: This project is anticipated to reduce the operating budget for street maintenance. Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 73 ARTERIAL STREET PRESERVATION FUND (105)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: A St SE Preservation (37th Street SE to Lakeland Hills Way)TIP# P-10 Project No:spbd09 Project Type:Non-Capacity, Preservation Project Manager:TBD LOS Corridor ID# 10 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Arterial Preservation Fund - - - 25,000 - Unsecured Grants - - - - - Utility Tax - - - - - Bond proceeds - - - - - - - - 25,000 - Capital Expenditures: Design - - - 25,000 - Right of Way - - - - - Construction - - - - - - - - 25,000 - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Arterial Preservation Fund 100,000 866,130 - - 991,130 Unsecured Grants - 866,130 - - 866,130 Utility Tax - - - - - Bond proceeds - - - - - 100,000 1,732,260 - - 1,857,260 Capital Expenditures: Design 75,000 - - - 100,000 Right of Way 25,000 - - - 25,000 Construction - 1,732,260 - - 1,732,260 100,000 1,732,260 - - 1,857,260 Grants / Other Sources: Description: The project will grind and overlay A Street SE from 37th Street SE to the Auburn/Pacific City Limit and from the Pacific/Auburn City Limit to the intersection with Lakeland Hills Way). The project also includes ADA upgrades to curb ramps, pedestrian push buttons, and replacement of vehicle detection loops. Progress Summary: An application for grant funding for the construction phase of this project was submitted in 2020. Future Impact on Operating Budget: This project is anticipated to reduce the operating budget for street maintenance. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 74 ARTERIAL STREET PRESERVATION FUND (105)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: C Street SW Preservation (W Main St to GSA Signal)TIP# P-11 Project No:spbd06 Project Type:Non-Capacity, Preservation Project Manager:TBD LOS Corridor ID# 13 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Arterial Preservation Fund - - 25,000 100,000 25,000 Unsecured Grants - - - - - Utility Tax - - - - - Bond proceeds - - - - - - - 25,000 100,000 25,000 Capital Expenditures: Design - - 25,000 75,000 25,000 Right of Way - - - 25,000 - Construction - - - - - - - 25,000 100,000 25,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Arterial Preservation Fund 1,118,272 - - - 1,243,272 Unsecured Grants 1,118,272 - - - 1,118,272 Utility Tax - - - - - Bond proceeds - - - - - 2,236,544 - - - 2,361,544 Capital Expenditures: Design - - - - 100,000 Right of Way - - - - 25,000 Construction 2,236,544 - - - 2,236,544 2,236,544 - - - 2,361,544 Grants / Other Sources: Description: The project will grind and overlay C Street SW from W Main Street to the GSA signal (approximately 2,000 feet to the south of 15th Street SW). The project also includes ADA upgrades to curb ramps and pedestrian push buttons, and replacement of vehicle detection loops. Progress Summary: An application for grant funding for the construction phase of this project was submitted in 2020. Future Impact on Operating Budget: This project is anticipated to reduce the operating budget for street maintenance. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 75 ARTERIAL STREET PRESERVATION FUND (105)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Fund Project Title: Lakeland Hill Way Preservation (57th Drive SE to Lake Tapps Pkwy)TIP# P-12 Project No:cp2011 Project Type:Non-Capacity, Preservation Project Manager:Seth Wickstrom LOS Corridor ID# 26 Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Arterial Preservation Fund - 100,000 1,350,000 - 1,450,000 Secured Federal Grants - - - - - Utility Tax - - - - - Bond proceeds - - - - - - 100,000 1,350,000 - 1,450,000 Capital Expenditures: Design - 100,000 - - 100,000 Right of Way - - - - - Construction - - 1,350,000 - 1,350,000 - 100,000 1,350,000 - 1,450,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Arterial Preservation Fund - - - - 1,350,000 Secured Federal Grants - - - - - Utility Tax - - - - - Bond proceeds - - - - - - - - - 1,350,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 1,350,000 - - - - 1,350,000 Grants / Other Sources: Description: The project will grind, patch, and overlay Lakeland Hills Way from 57th Drive SE to Lake Tapps Pkwy. The project also includes ADA upgrades to curb ramps and replacement of vehicle detection loops. Progress Summary: Grant funding for the construction phase of this project was awarded in 2018. However, to assist the region in meeting obligation targets for Federal funding, the grant funds awarded for this project were re-allocated to the Auburn Way Phase 2 and Phase 3 preservation projects to be completed in 2020. The re-allocation requires that the City commits to completing this project as originally planned using non-federal funding sources. Additional project scope added in 2020 to continute grind and overlay east from Lake Tapps Parkway to 72nd Street SE. Future Impact on Operating Budget: This project is anticipated to reduce the operating budget for street maintenance. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 76 ARTERIAL STREET PRESERVATION FUND (105)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Special Revenue Funds Project Title: 3rd Street SW Bridges Deck Preservation TIP# P-13 Project No:CP2006 Project Type:Non-Capacity, Preservation Project Manager:Kim Truong Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Arterial Preservation Fund - - - - - Secured Federal Grant - 523,540 120,000 - 643,540 Utility Tax - - - - - Bond proceeds - - - - - - 523,540 120,000 - 643,540 Capital Expenditures: Design - 120,000 - - 120,000 Right of Way - - - - - Construction - 403,540 120,000 - 523,540 - 523,540 120,000 - 643,540 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Arterial Preservation Fund - - - - - Secured Federal Grant - - - - 120,000 Utility Tax - - - - - Bond proceeds - - - - - - - - - 120,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 120,000 - - - - 120,000 Grants / Other Sources: Total Expenditures: Description: This project will seal and overlay the 3rd Street SW bridge decks in an effort to extend the overall service life of the bridges. The following bridges are included in the project: 3rd Street off-ramp, 3rd Street SW over the BNSF tracks, and 3rd Street SW over A Street SW. Progress Summary: Grant funding was awarded in 2020. Future Impact on Operating Budget: This project is anticipated to reduce the operating budget for street maintenance. Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 77 TABLE T-3 SUMMARY OF IMPACTS ON FUTURE OPERATING BUDGETS Project:2022 2023 2024 2025 2026 2027 Total 1 Lea Hill Road/112th Ave SE Roundabout -$ -$ -$ -$ -$ 1,000$ 1,000$ 2 29th St SE & R St SE Intersection Imp.- - - 500 500 500 1,500 3 R St SE & 21st St SE Int. Safety Imp.- - - - 1,000 1,000 2,000 4 Auburn Way S & 6th Street SE - - - - - 500 500 5 SE 304th Street/132nd Avenue SE Roundabout - - - - 1,000 1,000 2,000 6 10th St NW & A St NW Intersection Imp.- - 1,000 1,000 1,000 1,000 4,000 7 F Street SE, Downtown to Les Gove 4,100 4,100 4,100 4,100 4,100 4,100 24,600 8 Riverwalk Dr SE Non-Motorized Imp.- 2,000 2,000 2,000 2,000 2,000 10,000 9 A Street Loop - - - 1,000 1,000 1,000 3,000 10 A Street NW, Phase 2 (W Main St to 3rd St NW)- - - - 500 500 1,000 11 AWS Imp. -Hemlock St SE to Poplar St SE - - - 2,500 2,500 2,500 7,500 12 M Street NE, E. Main to 4th - - - 500 500 500 1,500 13 49th Street NE (AWN to D St NE)- 500 500 500 500 500 2,500 14 46th Place S Realignment - - - - - 1,000 1,000 15 Regional Growth Center Access Imp.- - 500 500 500 500 2,000 16 East Valley Highway Widening - - 2,500 2,500 2,500 2,500 10,000 17 Garden Garden Avenue Re-Alignment - 1,000 1,000 1,000 1,000 1,000 5,000 18 ITS Dynamic Message Signs 2,250 2,250 2,250 2,250 2,250 2,250 13,500 Total 6,350$ 9,850$ 13,850$ 18,350$ 20,850$ 23,350$ 92,600$ City of Auburn Capital Facilities Plan 78 City of Auburn Capital Facilities Plan 79 WATER Current Facilities The City of Auburn water utility provides water supply, treatment, transmission, storage, distribution, and service connections to in-City residences and businesses. The City also provides water to the City of Algona and Lake Meridian Water District under wholesale agreements. The water system consists of wells, springs and interties for source; chlorination stations and corrosion control for treatment; pump stations, pressure reducing stations and pipelines for transmission; and steel and concrete enclosed reservoirs for storage. Table W-1, “Facilities Inventory”, lists the facilities along with their current capacities and approximate locations. Level of Service (LOS) The City’s Comprehensive Water Plan summarizes the design criteria and service polices for the City’s water distribution system. Capital Facilities Projects and Financing The City of Auburn’s water system anticipates eight capacity projects in the amount of $15,151,757 and twenty-eight non-capacity projects totaling $30,647,941 for a 6-year planning expectation total of $45,799,698. The financing plan is shown in Table W-2 followed by individual worksheets showing the project details. The capacity projects will increase water supply quantities, storage, and distribution for growth of retail customers. The non-capacity projects will provide for pipeline improvements and replacements, delivery pressure improvements, water quality enhancements, comprehensive and resource management planning, pump station upgrades, telemetry system improvements, and meter upgrades. Impact on Future Operating Budgets As Table W-3 shows, operating budget impacts of $600 are forecasted for water supply and distribution facilities during the six years 2022 – 2027. City of Auburn Capital Facilities Plan 80 TABLE W-1 Facilities Inventory Water Facilities CAPACITY FACILITY WATER RIGHT (MGD - max rate)LOCATION Water Supply: Coal Creek Springs Certificate 857 9.70<2.52>*3401 Stuck River Rd Well 1 Certificate 3560-A 3.17 1136 M St SE Well 2 G1-00277 C 3.46 1109 5th St NE Well 3A G1-23629 C 4.03 401 37th St SE Well 3B (Included Above)(Included Above)401 37th St SE Well 4 G1-20391 C 4.03 950 25th St SE Well 5 G1-23633 C 1.44 5530 James Ave SE Well 5A (Included Above)(Included Above)5401 Olive Way SE Well 5B (Included Above)(Included Above)West end of 62nd Ct SE Well 6 (Supplemental to Wells 1, 2, 3A, 3B, 4)5.04 (supplemental)1109 5th St NE Well 7 (Supplemental to Wells 1, 2, 3A, 3B, 4)5.04 (supplemental)405 E St NE West Hill Springs Claim (1973 File Date)0.9 1900 15th St NW Ext Supply Total (MGD)26.73 Available for Use 24.21 * Denotes deduction of 1,750 gpm (Qi/2,824 ac-ft/yr) to comply with the provisions of the Muckleshoot-Auburn Stipulated Agreement. CAPACITY FACILITY (MGD)LOCATION SERVICE AREA Intertie Tacoma B Street NW 3.2 3240 B St NW Valley Service Area Tacoma 132nd Ave SE 3.2 29598 132nd Ave SE Lea Hill Service Area Intertie Total (MGD)6.4 CAPACITY FACILITY (MG)LOCATION SERVICE AREA Storage Facilities: Academy Reservoir 8A 1.2 5031 Auburn Way S Academy Service Area Academy Reservoir 8B 1.5 5031 Auburn Way S Academy Service Area Lakeland Hills Reservoir 5 1.0 1326 57th Dr SE Lakeland Hills Svc Area Lakeland Hills Reservoir 6 1.0 5718 Francis Ct SE Lakeland Hills Svc Area Lea Hill Reservoir 4A 1.0 30502 132nd Ave SE Lea Hill Service Area Lea Hill Reservoir 4B 1.5 30502 132nd Ave SE Lea Hill Service Area Valley Reservoir 1 5.0 2003 Auburn Way S Valley Service Area Valley Reservoir 2 3.6 32115 105th Place S Valley Service Area Storage Total (MG)15.8 CITY OF AUBURN WATER SYSTEM City of Auburn Capital Facilities Plan 81 TABLE W-1 (continued) Facilities Inventory Water Facilities CAPACITY FACILITY (GPM)LOCATION Booster Pump Stations: Academy 1: 2 pumps 800 2004 Auburn Way S Academy 2: 2 pumps 1,500 2004 Auburn Way S Academy East: 6 pumps 2,820 5031 Auburn Way S Green River: 4 pumps 4,680 29621 Green River Rd SE Intertie: 7 pumps 4,830 30502 132nd Ave SE Lakeland Hills: 5 pumps 3,200 1118 57th Place SE Lea Hill: 3 pumps 2,100 10406 Lea Hill Rd SE Terrace View: 3 pumps 1,500 6134 Alexander Place SE Wilderness Game Farm Pk: 2 pumps 1,050 2401 Stuck River Rd CAPACITY Primary Valve FACILITY (PSI - Inlet/Outlet)LOCATION Pressure Reducing Stations: Serves Valley Pressure Zone: 25th Street SE #1110-10 N/C 25th St SE & K St SE B Street Intertie 88/55 3300 B St NW Green River Pump Station N/C 29621 Green River Rd SE Howard Road CCF #1011-10 82/65 Howard Rd Howard Road CCF By-Pass #1011-20 -Howard Rd (Bypass) Lea Hill Pump Station N/C 10406 Lea Hill Rd SE Riverwalk # 1111-10 115/80 Riverwalk Dr SE & Howard Rd Riverwalk # 1111-20 90/50 2204 27th St. SE Serves Lea Hill: 132nd Avenue Intertie 150/70 132nd Ave SE & 295th St Amber View North #711-10 150/65 105th Pl SE & 320th Pl Amber View South #711-20 142/60 106th Pl SE Near Reservoir 2 Carriage Square Upper #611-30 145/50 Lea Hill Rd & 107 Pl Cobble Creek Lower #411-20 86/40 SE 304th Pl & SE 101st Place Cobble Creek Upper #411-10 94/55 104th Ave SE (South of 303rd Road) Lea Hill #412-10 84/45 SE 298th Place & 109 Ave SE Lea Hill #412-30 N/C 300 Block & 108th Ave SE Lea Hill #511-10 87/45 304th St. SE and 108th Ave SE Lea Hill #512-10 80/60 304th St. SE and 110th Pl SE Serves Academy: Academy Pump Station N/C 2004 Auburn Way S Auburn Way South #1011-30 130/80 2003 Auburn Way S Auburn Way South #1114-10 88/55 4500 Auburn Way S Lemon Tree -5031 Auburn Way S City of Auburn Capital Facilities Plan 82 TABLE W-1 (continued) Facilities Inventory Water Facilities CAPACITY Primary Valve FACILITY (PSI - Inlet/Outlet)LOCATION Serves Lakeland Hills: Lakeland Hills #1309-10 120/55 Mill Pond Dr @ Oravetz Rd Lakeland Hills #1310-10 130/55 Mill Pond Dr & Mill Pond Loop Lakeland Hills #1310-20 108/36 Kennedy Ave SE River Rock Lakeland Hills #1409-10 N/C Oravetz & Lakeland Hills Way Lakeland Hills #1409-20 120/56 47th SE & Lakeland Hills Way Lakeland Hills #1409-30 95/70 Lakeland Hills Way & 51st St SE Lakeland Hills #1409-40 84/55 Mill Pond Dr & Lakeland Hills Way Lakeland Hills #1410-10 103/50 5018 Mill Pond Dr Lakeland Hills #1410-20 N/C 51st St. SE east of Mill Pond Loop Lakeland Hills #1410-30 125/70 Nathan Ave & Highland Dr Lakeland Hills #1410-40 82/55 5203 Quincy Ave SE Lakeland Hills #1411-10 80/42 Bennett Ave & 56th Ave SE Lakeland Hills #1411-20 82/55 5310 Bennett Ave SE Lakeland Hills #1411-30 155/73 5100 Kersey Way Lakeland Hills #1411-40 82/52 2305 54th St SE Lakeland Hills #1411-50 85/44 5253 Wesley Ave SE Lakeland Hills #1411-60 90/64 5233 Victoria Avenue Lakeland Hills #1412-10 82/55 5539 Franklin Ave SE Lakeland Hills #1412-20 75/40 Kersey Way SE School Lakeland Hills #1509-10 174/60 Terrace View Lower (6170) Lakeland Hills #1509-20 160/73 Terrace View Middle (5960) Lakeland Hills #1509-30 138/47 Terrace View Upper (5810) Lakeland Hills #1509-40 230/90 Terrace View & Alexander Place SE Lakeland Hills #1510-10 N/C Lakeland Hills Way & Evergreen Way N/C - Normally Closed CAPACITY FACILITY (GPM)LOCATION Corrosion Control: Howard Road 5,550 2101 Howard Rd SE Fulmer Field 9,375 1113 5th St NE Chlorination Stations: Coal Creek Springs Station 5,000 (gravity feed)3401 Stuck River Rd West Hill Springs Station 625 (gravity feed)1900 15th St NW Well 1 2,200 1136 M St SE Well 4 2,600 950 25th St SE Well 5A 180 5401 Olive Ave SE Well 5B 600 1100 63rd St SE FACILITY CAPACITY LOCATION Water Supply: Braunwood Satellite 1 0.03 MGD 4501 47th St SE Storage Facilities: Braunwood Satellite 1 0.03 MG 4501 47th St SE Booster Pump Stations: Braunwood: 3 Pumps 2.0 GPM 4501 47th St SE BRAUNWOOD SATELLITE WATER SYSTEM City of Auburn Capital Facilities Plan 83 TABLE W-2 CAPITAL FACILITIES PLAN PROJECTS AND FINANCING WATER DIVISION 2021 2022 2023 2024 2025 2026 Total Page Capacity Projects: 88 Cascade Water Alliance Water Purchase Capital Costs 934,810 934,810 934,805 934,805 934,805 934,805 5,608,840 Funding Sources: Water Fund 934,810 934,810 934,805 934,805 934,805 934,805 5,608,840 Bond Proceeds - - - - - - - 89 Academy Pump Station #1 Pump Replacement Capital Costs 3,000,000 609,500 - - - - 3,609,500 Funding Sources: Water Fund - 609,500 - - - - 609,500 Bond Proceeds 3,000,000 - - - - - 3,000,000 90 Coal Creek Springs Rehabilitation Capital Costs - - - - - 1,125,509 1,125,509 Funding Sources: Water Fund - - - - - 1,125,509 1,125,509 Bond Proceeds - - - - - - - 91 Algona Well 1 Decommissioning Capital Costs - - 50,000 - - - 50,000 Funding Sources: Water Fund - - 50,000 - - - 50,000 Bond Proceeds - - - - - - - 92 Annual Distribution System Improvements Program Capital Costs - - 300,000 1,000,000 300,000 1,000,000 2,600,000 Funding Sources: Water Fund - - 300,000 1,000,000 300,000 1,000,000 2,600,000 Bond Proceeds - - - - - - - 93 Howard Road CCTF Expansion Capital Costs - - - - - 348,908 348,908 Funding Sources: Water Fund - - - - - 348,908 348,908 Bond Proceeds - - - - - - - 94 Valley Service Area Reservoir No. 3 Capital Costs - 50,000 - - - 700,000 750,000 Funding Sources: Water Fund - 50,000 - - - 700,000 750,000 Bond Proceeds - - - - - - - 95 Well 5/5A Upgrades Capital Costs - - - - 947,000 112,000 1,059,000 Funding Sources: Water Fund - - - - 947,000 112,000 1,059,000 Bond Proceeds - - - - - - - Subtotal, Capacity Projects: Capital Costs 3,934,810 1,594,310 1,284,805 1,934,805 2,181,805 4,221,222 15,151,757 City of Auburn Capital Facilities Plan 84 TABLE W-2 (continued) 2021 2022 2023 2024 2025 2026 Total Non-Capacity Projects: 96 Well Inspection and Redevelopment Program Capital Costs - 185,000 - - 200,000 - 385,000 Funding Sources: Water Fund - 185,000 - - 200,000 - 385,000 Bond Proceeds - - - - - - - 97 Water Repair & Replacements Capital Costs - 100,000 1,000,000 300,000 1,000,000 300,000 2,700,000 Funding Sources: Water Fund - - 1,000,000 300,000 1,000,000 300,000 2,600,000 Bond Proceeds - 100,000 - - - - 100,000 98 Street Utility Improvements Capital Costs - 200,000 1,000,000 1,000,000 1,000,000 1,000,000 4,200,000 Funding Sources: Water Fund - 200,000 1,000,000 1,000,000 1,000,000 1,000,000 4,200,000 Bond Proceeds - - - - - - - 99 Reservoir Seismic Rehabilitation Capital Costs - - - 262,000 - 298,000 560,000 Funding Sources: Water Fund - - - 262,000 - 298,000 560,000 Bond Proceeds - - - - - - - 100 Intertie Booster Pump Station Improvements Capital Costs - - - - - 250,000 250,000 Funding Sources: Water Fund - - - - - 250,000 250,000 Bond Proceeds - - - - - - - 101 Reservoir Painting Capital Costs - - - - - 1,747,026 1,747,026 Funding Sources: Water Fund - - - - - 1,747,026 1,747,026 Bond Proceeds - - - - - - - 102 Coal Creek Springs Transmission Main Replacement Capital Costs 10,000 2,425,000 - - - - 2,435,000 Funding Sources: Water Fund 10,000 - - - - - 10,000 Grant - 225,000 - - - - 225,000 DWSRF Loan - 2,200,000 - - - - 2,200,000 Bond Proceeds - - - - - - - 103 F Street SE Non-Motorized Improvements Capital Costs 10,000 - - - - - 10,000 Funding Sources: Water Fund 10,000 - - - - - 10,000 Bond Proceeds - - - - - - - 104 Reservoir Repair and Replacements Capital Costs 50,000 62,000 64,000 66,000 68,000 70,000 380,000 Funding Sources: Water Fund 50,000 62,000 64,000 66,000 68,000 70,000 380,000 Bond Proceeds - - - - - - - 105 Pipeline Asset Management Study Capital Costs 10,000 - - - - - 10,000 Funding Sources: Water Fund 10,000 - - - - - 10,000 Bond Proceeds - - - - - - - City of Auburn Capital Facilities Plan 85 TABLE W-2 (continued) 2021 2022 2023 2024 2025 2026 Total Non-Capacity Projects: 106 2021 Local Street Reconstruction Capital Costs 2,520,000 - - - - - 2,520,000 Funding Sources: Water Fund - - - - - - - Bond Proceeds 2,520,000 - - - - - 2,520,000 107 2022 Local Street Reconstruction Capital Costs 50,000 800,000 - - - - 850,000 Funding Sources: Water Fund 50,000 100,000 - - - - 150,000 Bond Proceeds - 700,000 - - - - 700,000 108 M Street NE Widening Capital Costs - 37,000 - 320,000 - - 357,000 Funding Sources: Water Fund - 37,000 - 320,000 - - 357,000 Bond Proceeds - - - - - - - 109 Auburn Way South - Hemlock Street SE to Poplar Street SE Capital Costs - - 2,176,000 256,000 - - 2,432,000 Funding Sources: Water Fund - - 2,176,000 256,000 - - 2,432,000 Bond Proceeds - - - - - - - 110 Water Trench Patches Program Capital Costs 150,000 155,000 160,000 165,000 170,000 175,000 975,000 Funding Sources: Water Fund 150,000 155,000 160,000 165,000 170,000 175,000 975,000 Bond Proceeds - - - - - - - 111 Lea Hill Pump Station Replacement Capital Costs - - - - 491,000 746,333 1,237,333 Funding Sources: Water Fund - - - - 491,000 746,333 1,237,333 Bond Proceeds - - - - - - - 112 Deduct Meter Replacement Program Capital Costs 515,000 485,000 - - - - 1,000,000 Funding Sources: Water Fund - 100,000 - - - - 100,000 Bond Proceeds 515,000 385,000 - - - - 900,000 113 Comprehensive Water Plan Capital Costs - 263,000 251,000 20,000 - - 534,000 Funding Sources: Water Fund - 263,000 251,000 20,000 - - 534,000 Bond Proceeds - - - - - - - 114 Lea Hill AC Main Replacement Capital Costs 10,000 - - - - - 10,000 Funding Sources: Water Fund 10,000 - - - - - 10,000 Bond Proceeds - - - - - - - 115 Reservoir 2 Valves Capital Costs - 240,000 760,000 - - - 1,000,000 Funding Sources: Water Fund - 240,000 760,000 - - - 1,000,000 Bond Proceeds - - - - - - - City of Auburn Capital Facilities Plan 86 TABLE W-2 (continued) 2021 2022 2023 2024 2025 2026 Total Non-Capacity Projects: 116 104th Park Development (104th to 102nd Water Main Loop) Capital Costs 250,000 - - - - - 250,000 Funding Sources: Water Fund 250,000 - - - - - 250,000 Bond Proceeds - - - - - - - 117 Garden Avenue Realignment Capital Costs 55,000 440,000 - - - - 495,000 Funding Sources: Water Fund 55,000 440,000 - - - - 495,000 Grants - - - - - - - 118 Lead Service Line Replacement Capital Costs 2,900,000 1,600,000 - - - - 4,500,000 Funding Sources: Water Fund - 405,000 - - - - 405,000 Bond Proceeds 205,000 1,195,000 - - - - 1,400,000 DWSRF Loan 2,695,000 - - - - - 2,695,000 119 Well 4 Pump Improvements Capital Costs 147,000 830,000 - - - - 977,000 Funding Sources: Water Fund 147,000 830,000 - - - - 977,000 Bond Proceeds - - - - - - - 120 Water Resources Protection Program (Wellhead Protection) Capital Costs 26,800 27,700 28,500 29,400 30,200 31,200 173,800 Funding Sources: Water Fund 26,800 27,700 28,500 29,400 30,200 31,200 173,800 Bond Proceeds - - - - - - - 121 Game Farm Park Pump Station/Distribution System Improvements Capital Costs - - - - - 69,782 69,782 Funding Sources: Water Fund - - - - - 69,782 69,782 Bond Proceeds - - - - - - - 122 Meter Vault Replacement Capital Costs 10,000 - - - - - 10,000 Funding Sources: Water Fund 10,000 - - - - - 10,000 Bond Proceeds - - - - - - - 123 West Hill Springs Water Quality Improvements Capital Costs - - - 100,000 480,000 - 580,000 Funding Sources: Water Fund - - - 100,000 480,000 - 580,000 Bond Proceeds - - - - - - - Subtotal, Non-Capacity Projects: Capital Costs 6,713,800 7,849,700 5,439,500 2,518,400 3,439,200 4,687,341 30,647,941 City of Auburn Capital Facilities Plan 87 TABLE W-2 (continued) SUMMARY: 2021 2022 2023 2024 2025 2026 Total CAPITAL COSTS Capacity Projects 3,934,810 1,594,310 1,284,805 1,934,805 2,181,805 4,221,222 15,151,757 Non-Capacity Projects 6,713,800 7,849,700 5,439,500 2,518,400 3,439,200 4,687,341 30,647,941 Total Costs 10,648,610 9,444,010 6,724,305 4,453,205 5,621,005 8,908,563 45,799,698 FUNDING SOURCES: Water Fund 1,713,610 4,639,010 6,724,305 4,453,205 5,621,005 8,908,563 32,059,698 DWSRF Loan 2,695,000 2,200,000 - - - - 4,895,000 Grants - 225,000 - - - - 225,000 Bond Proceeds 6,240,000 2,380,000 - - - - 8,620,000 Total Funding 10,648,610 9,444,010 6,724,305 4,453,205 5,621,005 8,908,563 45,799,698 City of Auburn Capital Facilities Plan 88 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Cascade Water Alliance Water Purchase Project No:cp1914 Project Type:Capacity Project Manager:Susan Fenhaus Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue 252,586 934,805 934,810 934,810 2,122,201 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 252,586 934,805 934,810 934,810 2,122,201 Capital Expenditures: Water Supply Purchase 252,586 934,805 934,810 934,810 2,122,201 Right of Way - - - - - Construction - - - - - 252,586 934,805 934,810 934,810 2,122,201 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue 934,805 934,805 934,805 934,805 5,608,840 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 934,805 934,805 934,805 934,805 5,608,840 Capital Expenditures: Water Supply Purchase 934,805 934,805 934,805 934,805 5,608,840 Right of Way - - - - - Construction - - - - - 934,805 934,805 934,805 934,805 5,608,840 Financing of System Development Charges for the right to purchase water from Tacoma Public Utilities through the Second Supply Pipeline to meet future projected demand, based on agreements with Cascade Water Alliance. Council approved the agreements for permanent and reserve wholesale supply in September 2013. A new agreement with Tacoma was executed in 2014. Budget reflects purchase of permanent supply - payments of $934,805 will continue from 2020 through 2029. Reserve supply will not be purchased and is not included. Comprehensive Plan project S-04. Progress Summary: Ongoing payments through 2029 Future Impact on Operating Budget: None Total Funding Sources: Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: City of Auburn Capital Facilities Plan 89 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Academy Pump Station #1 Pump Replacement Project No:cp1916 Project Type:Capacity Project Manager:Jeff Bender Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - - - 609,500 609,500 Grants (Fed,State,Local)- - - - - Bond Proceeds 71,479 671,500 3,000,000 - 3,742,979 Other - - - - - 71,479 671,500 3,000,000 609,500 4,352,479 Capital Expenditures: Design 71,479 671,500 - - 742,979 Right of Way - - - - - Construction - 3,000,000 609,500 3,609,500 71,479 671,500 3,000,000 609,500 4,352,479 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - - - 609,500 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - 3,000,000 Other - - - - - - - - - 3,609,500 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 3,609,500 - - - - 3,609,500 The pump station is reaching the end of its useful life. The project will construct a new pump station with 4 pumps to meet peak demands and fire flow requirements. Pump station #1 will be removed and pump station #2 will be used for storage after the pumps are removed. Preliminary design found it to be more cost effective to build a new pump station and decommission both existing pump stations. The backup power generator will be replaced. Comprehensive Plan project PS-07. Progress Summary: In 2018, project costs were escalated at 3% per year from 2015 to year of construction. Design underway in 2020. Future Impact on Operating Budget: No significant impact. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 90 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Coal Creek Springs Rehabilitation Project No:wabd07 Project Type:Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - 50,000 - - 50,000 Grants (Fed,State,Local)- - - - - PWTFL - - - - - Bond Proceeds - - - - - - 50,000 - - 50,000 Capital Expenditures: Design - 50,000 - - 50,000 Right of Way - - - - - Construction - - - - - - 50,000 - - 50,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - - 1,125,509 1,125,509 Grants (Fed,State,Local)- - - - - PWTFL - - - - - Bond Proceeds - - - - - - - - 1,125,509 1,125,509 Capital Expenditures: Design - - - 500,000 500,000 Right of Way - - - - - Construction - - - 625,509 625,509 - - - 1,125,509 1,125,509 Rehabilitation of the Coal Creek Springs middle collector will improve capacity of the springs resulting in greater utilization of the water right. Comprehensive Plan project S-09. Progress Summary: In 2018, project costs were esclated at 3% per year from 2015 to year of construction. Future Impact on Operating Budget: No significant impact. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 91 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Algona Well 1 Decommissioning Project No:wabd08 Project Type:Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - 50,000 - - 50,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - 50,000 - - 50,000 Capital Expenditures: Design - 50,000 - - 50,000 Right of Way - - - - - Construction - - - - - - 50,000 - - 50,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue 50,000 - - - 50,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 50,000 - - - 50,000 Capital Expenditures: Design 50,000 - - - 50,000 Right of Way - - - - - Construction - - - - - 50,000 - - - 50,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: The Algona well has been temporarily abandoned and all related facilities removed. This project will have the well properly decommissioned by a State of Washington-licensed well driller, once the water rights have been transferred to an alternate source. Comprehensive Plan project S-14. Progress Summary: Future Impact on Operating Budget: No significant impact. City of Auburn Capital Facilities Plan 92 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Annual Distribution System Improvements Program Project No:wabd09, cp1819, cp1904 Project Type:Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue 300,000 - - - 300,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 300,000 - - - 300,000 Capital Expenditures: Design 300,000 - - - 300,000 Right of Way - - - - - Construction - - - - - 300,000 - - - 300,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue 300,000 1,000,000 300,000 1,000,000 2,600,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 300,000 1,000,000 300,000 1,000,000 2,600,000 Capital Expenditures: Design 300,000 - 300,000 - 600,000 Right of Way - - - - - Construction - 1,000,000 - 1,000,000 2,000,000 300,000 1,000,000 300,000 1,000,000 2,600,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Program to fund capacity-related improvements to the water distribution system to address low pressures during peak hour demand and fire flows. Comprehensive Plan project D-02. Progress Summary: Future Impact on Operating Budget: No significant impact. City of Auburn Capital Facilities Plan 93 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Howard Road CCTF Expansion Project No:cpxxxx Project Type:Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - - - - - Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - - 348,908 348,908 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - 348,908 348,908 Capital Expenditures: Design - - - 348,908 348,908 Right of Way - - - - - Construction - - - - - - - - 348,908 348,908 With the completion of the Coal Creek Springs Rehabilitation, the Howard Road Corrosion Control Treatment Facility will exceed its current capacity. This project will add one aeration tower and one blower pump to match the existing towers and blowers. Comprehensive Plan project S-18. Progress Summary: In 2018, project costs were escalated at 3% per year from 2015 to year of construction. Preliminary planning underway in 2020. Future Impact on Operating Budget: The annual maintenance cost is estimated to be approximately $600. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 94 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Valley Service Area Reservoir No. 3 Project No:wabd26 Project Type:Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - - - 50,000 - Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - 50,000 - Capital Expenditures: Design - - - 50,000 - Right of Way - - - - - Construction - - - - - - - 50,000 - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - - 700,000 750,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - 700,000 750,000 Capital Expenditures: Design - - - - 50,000 Property Acquisition - - - 700,000 700,000 Construction - - - - - - - 700,000 750,000 A new 1 million gallon storage facility is needed to meet future storage requirements in the Valley Service Area. Comprehensive Plan project R-04. Progress Summary: Project costs were escalated in 2018 at 3% per year from 2015 to year of construction. Reservoir siting study will be conducted in 2022, with property acquisition in 2026. Design of the project will be completed in 2028, with construction in 2028-2029. Future Impact on Operating Budget: No significant Impact Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 95 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Well 5/5A Upgrades Project No:cpxxx Project Type:Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - - - - - Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - 947,000 112,000 1,059,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - 947,000 112,000 1,059,000 Capital Expenditures: Design - - - 112,000 112,000 Right of Way - - 947,000 - 947,000 Construction - - - - - - - 947,000 112,000 1,059,000 This project was identified in the 2016 Facilities Evaluation Study. Well 5 is in need of a new building, backup generator, chlorination, pump, and hydrologic investigation to evaluate the well's production. Due to the small size of the existing site, the acquisition of an adjacent parcel may be required. The Facilities Evaluation Study also identified the need for a new pump and motor in Well 5A. Comprehensive Plan project S-06. Progress Summary: In 2018, project costs were escalated at 3% per year from 2015 to year of construction. The hydrologic study and property acquisition are anticipated to begin in 2025. Future Impact on Operating Budget: No significant Impact Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 96 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Well Inspection and Redevelopment Program Project No:wabd11 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - 150,000 - 185,000 150,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - 150,000 - 185,000 150,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - 150,000 - 185,000 150,000 - 150,000 - 185,000 150,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - 200,000 - 385,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - 200,000 - 385,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - 200,000 - 385,000 - - 200,000 - 385,000 No significant impact. Program for inspection and redevelopment of supply wells and springs necessary to ensure production at maximum capacity for efficient utilization. Comprehensive Plan project S-07. Progress Summary: 2020 funds are estimated carryforward from 2019 budget. Future Impact on Operating Budget: Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 97 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Water Repair & Replacements Project No:wabd02 Project Type:Non-Capacity (R&R) Project Manager:Various Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - - - - - Grants (Fed,State,Local)- - - - - Bond Proceeds - 170,000 - 100,000 170,000 Other - - - - - - 170,000 - 100,000 170,000 Capital Expenditures: Design - 170,000 - 100,000 170,000 Right of Way - - - - - Construction - - - - - - 170,000 - 100,000 170,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue 1,000,000 300,000 1,000,000 300,000 2,600,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - 100,000 Other - - - - - 1,000,000 300,000 1,000,000 300,000 2,700,000 Capital Expenditures: Design - 300,000 - 300,000 700,000 Right of Way - - - - - Construction 1,000,000 - 1,000,000 - 2,000,000 1,000,000 300,000 1,000,000 300,000 2,700,000 Total Funding Sources: Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: Program to fund distribution system repair and replacement projects required for meeting peak demands and reducing system losses. Projects will be coordinated with the streets and other utility projects. Comprehensive Plan project D-09. Progress Summary: Future Impact on Operating Budget: No significant impact. City of Auburn Capital Facilities Plan 98 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Street Utility Improvements Project No:wabd01 Project Type:Non-Capacity Project Manager:Various Description: Progress Summary: CP1926 was funded under this program and will be completed in 2020. No significant impact Activity: (Previous 2 Years)2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue 1,500,000 - - 200,000 1,500,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - 500,000 - - 500,000 Other - - - - - Total Funding Sources:1,500,000 500,000 - 200,000 2,000,000 Capital Expenditures: Design 100,000 - - - 100,000 Right of Way - - - - - Construction 1,400,000 500,000 - 200,000 1,900,000 Total Expenditures:1,500,000 500,000 - 200,000 2,000,000 Forecasted Project Cost: Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue 1,000,000 1,000,000 1,000,000 1,000,000 4,200,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - Total Funding Sources:1,000,000 1,000,000 1,000,000 1,000,000 4,200,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction 1,000,000 1,000,000 1,000,000 1,000,000 4,200,000 Total Expenditures:1,000,000 1,000,000 1,000,000 1,000,000 4,200,000 Water main improvements in coordination with the Local Street Preservation Program and general arterial street improvements. Comprehensive Plan project D-06. Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 99 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Reservoir Seismic Rehabilitation Project No:wabd16 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - 86,000 - - 86,000 Grants -Unsecured Federal - - - - - PWTFL - - - - - Bond Proceeds - - - - - - 86,000 - - 86,000 Capital Expenditures: Design - 86,000 - - 86,000 Right of Way - - - - - Construction - - - - - - 86,000 - - 86,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - 262,000 - 298,000 560,000 Grants -Unsecured Federal - - - - - PWTFL - - - - - Bond Proceeds - - - - - - 262,000 - 298,000 560,000 Capital Expenditures: Design - 65,000 - 88,000 153,000 Right of Way - - - - - Construction - 197,000 - 210,000 407,000 - 262,000 - 298,000 560,000 Install seismic control valves on outlet piping of Reservoirs 4A, 4B, 8A, and 8B. This project will include a study to identify work to be completed at each site, and to further define project costs at each site. Costs for the remaining reservoirs will be updated based on the study. Seismic control valve for Reservoir 2 is a separate project. Comprehensive Plan project R-06. Progress Summary: In 2018, project costs were escalated at 3% per year from 2015 to year of construction. The study to identify the work to be completed at each site is underway in 2020. Individual sites will be planned based on the study results. 2020 funds are estimated carryforward from 2019 budget. Future Impact on Operating Budget: No significant impact Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 100 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Intertie Booster Pump Station Improvements Project No:wabd05 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - - - - - Grants (Fed,State,Local)- - - - - PWTFL - - - - - Bond Proceeds - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - - 250,000 250,000 Grants (Fed,State,Local)- - - - - PWTFL - - - - - Bond Proceeds - - - - - - - - 250,000 250,000 Capital Expenditures: Design - - - 250,000 250,000 Right of Way - - - - - Construction - - - - - - - - 250,000 250,000 Project will provide additional piping and modify the existing Intertie/ Lea Hill Booster pump station building to utilize the existing Intertie pumps for the Boosted zone. The project will also add pressure reducing valves and control valves at Lea Hill reservoirs, and system valves to provide efficient operation of the 132nd Ave Tacoma Intertie. Comprehensive Plan projects D-06, and PS-04. Progress Summary: In 2018, project costs were escalated at 3% per year from 2015 to year of construction. Future Impact on Operating Budget: No significant impact Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 101 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Reservoir Painting Project No:cpxxxx Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - - - - - Grants (Fed,State,Local)- - - - - PWTFL - - - - - Bond Proceeds - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - - 1,747,026 1,747,026 Grants (Fed,State,Local)- - - - - PWTFL - - - - - Bond Proceeds - - - - - - - - 1,747,026 1,747,026 Capital Expenditures: Design - - - 227,026 227,026 Right of Way - - - - - Construction - - - 1,520,000 1,520,000 - - - 1,747,026 1,747,026 Maintenance of reservoirs requires periodic painting to protect the steel and increase the useful life of the reservoir. Comprehensive Plan project R-05. Progress Summary: In 2018, project costs were escalated at 3% per year from 2015 to year of construction. Future Impact on Operating Budget: No significant impact Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 102 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Coal Creek Springs Transmission Main Replacement Project No:cp1603 Project Type:Non-Capacity Project Manager:Seth Wickstrom Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue 95,673 230,847 10,000 - 336,520 Parks Grants (State)- - - 225,000 - DWSRF Loan 204,179 95,821 - 2,200,000 300,000 Bond Proceeds - - - - - 299,852 326,668 10,000 2,425,000 636,520 Capital Expenditures: Design 299,852 326,668 10,000 - 636,520 Right of Way - - - - - Construction - - - 2,425,000 - 299,852 326,668 10,000 2,425,000 636,520 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - - - 10,000 Parks Grants (State)- - - - 225,000 DWSRF Loan - - - - 2,200,000 Bond Proceeds - - - - - - - - - 2,435,000 Capital Expenditures: Design - - - - 10,000 Right of Way - - - - - Construction - - - - 2,425,000 - - - - 2,435,000 The facilities evaluation study conducted in 2013-2014 found a suspected leak on the 24" steel transmission main crossing the White River. This project will provide for full replacement of the river crossing via a pedistrian bridge. Parks Department will participate in the project by providing funding from grants for the trail connections to the bridge. This option eliminates the deep blow-off and allows more flexibility for expansion. A future project would rehabilitate the existing crossing for redundancy. Comprehensive Plan project D-11. Progress Summary: Design underway in 2019 and 2020. A DWSRF loan was applied for in 2020 for construction in 2022. Future Impact on Operating Budget: No significant impact Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 103 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: F Street SE Non-Motorized Improvements Project No:cp1416 Project Type:Non-Capacity Project Manager:Seth Wickstrom Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue 15,172 55,708 10,000 - 80,880 Grants (Fed,State,Local)- - - - - PWTFL - - - - - Bond Proceeds - 334,000 - - 334,000 15,172 389,708 10,000 - 414,880 Capital Expenditures: Design 15,172 - - - 15,172 Right of Way - - - - - Construction - 389,708 10,000 - 399,708 15,172 389,708 10,000 - 414,880 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - - - 10,000 Grants (Fed,State,Local)- - - - - PWTFL - - - - - Bond Proceeds - - - - - - - - - 10,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 10,000 - - - - 10,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Water main improvements constructed in conjunction with F Street SE street improvements. Comprehensive Plan project D-06. Progress Summary: Construction underway in 2020. Future Impact on Operating Budget: No significant impact City of Auburn Capital Facilities Plan 104 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Reservoir Repair and Replacements Project No:wabd12 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue 50,000 50,000 50,000 62,000 150,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 50,000 50,000 50,000 62,000 150,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction 50,000 50,000 50,000 62,000 150,000 50,000 50,000 50,000 62,000 150,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue 64,000 66,000 68,000 70,000 380,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 64,000 66,000 68,000 70,000 380,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction 64,000 66,000 68,000 70,000 380,000 64,000 66,000 68,000 70,000 380,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: General reservoir maintenance and minor improvements. Comprehensive Plan project R-03. Progress Summary: In 2018, project costs were escalated at 3% per year from 2015 to year of construction. Future Impact on Operating Budget: No significant impact. City of Auburn Capital Facilities Plan 105 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Pipeline Asset Management Study Project No:cp1934 Project Type:Non-Capacity Project Manager:Fenhaus Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - 106,000 10,000 - 116,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - 106,000 10,000 - 116,000 Capital Expenditures: Design - 106,000 10,000 - 116,000 Right of Way - - - - - Construction - - - - - - 106,000 10,000 - 116,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - - - 10,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 10,000 Capital Expenditures: Design - - - - 10,000 Right of Way - - - - - Construction - - - - - - - - - 10,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Pipeline asset management study will identify the remaining useful life of water mains in the system, prioritize pipe replacements, and develop replacement costs to phase in the replacements. Transmission and distribution mains along Auburn Way South, C St SW, Lea Hill Road and West Hill Springs will be evaluated. Comprehensive Plan project D-10. Progress Summary: In 2018, project costs were escalated at 3% per year from 2015 to year of completion. Assessment underway in 2020. Future Impact on Operating Budget: No significant impact. City of Auburn Capital Facilities Plan 106 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: 2021 Local Street Reconstruction Project No:cp2019 Project Type:Non-Capacity Project Manager:Kim Troung Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - - - - - Grants (Fed,State,Local)- - - - - Bond Proceeds - 100,000 2,520,000 - 2,620,000 Other - - - - - - 100,000 2,520,000 - 2,620,000 Capital Expenditures: Design - 100,000 - - 100,000 Right of Way - - - - - Construction - - 2,520,000 - 2,520,000 - 100,000 2,520,000 - 2,620,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - - - - Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - 2,520,000 Other - - - - - - - - - 2,520,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 2,520,000 - - - - 2,520,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: This project will construct water main improvements on G Street SE between E. Main Street and 4th Street SE and in various streets in the Riverwalk neighborhood. The improvements are coordination with the 2021 Local Street Preservation project and include replacing 1,250 feet of 4" cast iron pipe with 8" ductile iron water main and 43 services on G ST SE. and replacement of 4,360 feet of 6" cast iron pipe and 730 feet of 4" cast iron with 8" ductile iron main and 110 services in the Riverwalk area. Comprehensive Plan project D-06. Progress Summary: Project design underway in 2020. Future Impact on Operating Budget: No significant impact City of Auburn Capital Facilities Plan 107 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: 2022 Local Street Reconstruction Project No:cp2101 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - - 50,000 100,000 50,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - 700,000 - Other - - - - - - - 50,000 800,000 50,000 Capital Expenditures: Design - - - - - Right of Way - - 50,000 - 50,000 Construction - - - 800,000 - - - 50,000 800,000 50,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - - - 150,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - 700,000 Other - - - - - - - - - 850,000 Capital Expenditures: Design - - - - - Right of Way - - - - 50,000 Construction - - - - 800,000 - - - - 850,000 This project will construct water main improvements on I Street SE from E. Main Street to 4th Street SE as part of the 2022 Local Street Preservation project. Improvements include replacement of 1,250 feet of 4" cast iron pipe with 8" ductile iron water main and 40 services. Comprehensive Plan project D-06. Progress Summary: Project scoping and preliminary design underway in 2020. Future Impact on Operating Budget: No significant impact Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 108 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: M Street NE Widening Project No:wabd13 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - - - 37,000 - Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - 37,000 - Capital Expenditures: Design - - - 37,000 - Right of Way - - - - - Construction - - - - - - - - 37,000 - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - 320,000 - - 357,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - 320,000 - - 357,000 Capital Expenditures: Design - - - - 37,000 Right of Way - - - - - Construction - 320,000 - - 320,000 - 320,000 - - 357,000 Water main improvements constructed in conjunction with streets project: M ST NE widening (E Main to 4th St NE). Work includes replacing 26 services, connecting to existing 12" ductile main, and abandoning 6" cast main in place. Comprehensive Plan project D-06. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Progress Summary: In 2018, project costs were escalated at 3% per year from 2015 to year of construction. Future Impact on Operating Budget: No significant Impact City of Auburn Capital Facilities Plan 109 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Auburn Way South - Hemlock Street SE to Poplar Street SE Project No:cp1622 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - 66,000 - 66,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - 66,000 - - 66,000 Capital Expenditures: Design - 66,000 - 66,000 Right of Way - - - - - Construction - - - - - - 66,000 - - 66,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue 2,176,000 256,000 - - 2,432,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 2,176,000 256,000 - - 2,432,000 Capital Expenditures: Design - - - - - Right of Way - - - - Construction 2,176,000 256,000 - - 2,432,000 2,176,000 256,000 - - 2,432,000 Water main improvements constructed in conjunction with Auburn Way South street improvements. Project will replace approximately 2,300 feet of 10" cast iron line with 12" ductile Iron water main. Comprehensive Plan project D-06. Progress Summary: In 2018, project costs were escalated at 3% per year from 2015 to year of construction. Design underway in 2020 in conjunction with Auburn School District's Chinook Middle School Replacement project. Future Impact on Operating Budget: No significant Impact Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 110 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Water Trench Patches Program Project No:wabd28 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - - 150,000 155,000 150,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - 150,000 155,000 150,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - 150,000 155,000 150,000 - - 150,000 155,000 150,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue 160,000 165,000 170,000 175,000 975,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 160,000 165,000 170,000 175,000 975,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction 160,000 165,000 170,000 175,000 975,000 160,000 165,000 170,000 175,000 975,000 This program provides annual funding for roadway restoration of trench patches from water leak repair and water service installation that are beyond the scope of work done by maintenance staff. Progress Summary: Program was developed in 2020 to adhere to pavement restoration requirements in the City Engineering Design standards. Future Impact on Operating Budget: No significant impact Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 111 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Lea Hill Pump Station Replacement Project No:wabd18 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - - - - - Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - 491,000 746,333 1,237,333 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - 491,000 746,333 1,237,333 Capital Expenditures: Design - - 491,000 - 491,000 Right of Way - - - - - Construction - - - 746,333 746,333 - - 491,000 746,333 1,237,333 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Lea Hill pump station will be reconstructed to provide redundant pumped supply to the Lea Hill area. If the Green River Pump Station is out of service for maintenance, a redundant pump station would avoid the need to purchase more expensive regional surface water through the 132nd Intertie. The pump station needs to be relocated from its current location on the shoulder of Lea Hill Road at the base of a steep hill for safety and reliability considerations. The project will also construct approximately 900 feet of 12" transmission main along Lea Hill Rd from Garden Avenue to the existing pump station site. Comprehensive Plan project PS-10. Progress Summary: In 2018, project costs were escalated at 3% per year from 2015 to year of construction. Property acquisition underway in 2020 under Garden Ave Realignment project. Future Impact on Operating Budget: No significant Impact City of Auburn Capital Facilities Plan 112 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Deduct Meter Replacement Program Project No:cp1917 Project Type:Non-Capacity Project Manager:Jeff Bender Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue 24,000 12,500 - 100,000 36,500 Grants (Fed,State,Local)- - - - - Bond Proceeds - 476,000 515,000 385,000 991,000 Other - - - - - 24,000 488,500 515,000 485,000 1,027,500 Capital Expenditures: Design 24,000 12,500 15,000 - 51,500 Right of Way - - - - - Construction - 476,000 500,000 485,000 976,000 24,000 488,500 515,000 485,000 1,027,500 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - - - 100,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - 900,000 Other - - - - - - - - - 1,000,000 Capital Expenditures: Design - - - - 15,000 Right of Way - - - - - Construction - 985,000 - - - - 1,000,000 Approximately 200 non-single family irrigation meters within the water system are connected to the customer's supply line on the customer side of the domestic meter, instead of being directly connected to the water main. Since sewer charges for non-single family customers are based on the domestic water meter reading and irrigation water does not use the sewer system, customers ask to have the irrigation use deducted from their overall domestic use for sewer billing purposes. Thus, irrigation meters installed after the domestic meter are referred to as "deduct meters". To improve the billing process, increase staff efficiencies and eliminate manual calculations in the billing process this project will re-install the irrigation meters to directly connect to the main. Deduct meters will be converted to irrigation meters to more equitably bill water usage. Progress Summary: Construction was planned and budgeted to be completed in 4 years. Recent bids indicate the original cost estimate was low. The budget was increased in 2021 and 2022, and the project will be completed in 3 years (2020-2022). Future Impact on Operating Budget: No significant impact. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 113 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Comprehensive Water Plan Project No:wabd25 Project Type:Non-Capacity Project Manager:Susan Fenhaus Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - 122,000 - 263,000 122,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - 122,000 - 263,000 122,000 Capital Expenditures: Design - 122,000 - 263,000 122,000 Right of Way - - - - - Construction - - - - - - 122,000 - 263,000 122,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue 251,000 20,000 - - 534,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 251,000 20,000 - - 534,000 Capital Expenditures: Design 251,000 20,000 - - 534,000 Right of Way - - - - - Construction - - - - - 251,000 20,000 - - 534,000 Update the Comprehensive Water Plan as required by Washington Department of Health (DOH) by May 2022. DOH changed WAC to require a 10-year planning period which is an increase from the 6-year period. Our current plan was approved before the code change, but was written to include the 10-year period in anticipation of the revised code. We will provide letter to DOH requesting extension of approved plan by the end of 2021. The letter will include a report of the demand forecast compared to actual demand, and report of the capital improvement plan. If the extension is approved, our next complete plan will be due in 2025. However, the water plan will need to be updated in conjunction with the City's Comprehensive Plan due in 2024. Progress Summary: Request for current plan extension will be completed in 2021. Future Impact on Operating Budget: No significant impact. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 114 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Lea Hill AC Main Replacement Project No:cp1929 Project Type:Non-Capacity Project Manager:Jai Carter Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - 440,000 10,000 - 450,000 Grants (Fed,State,Local)- - - - - Bond Proceeds 31,450 2,466,550 - - 2,498,000 Other - - - - - 31,450 2,906,550 10,000 - 2,948,000 Capital Expenditures: Design 31,450 240,000 - - 271,450 Right of Way - - - - - Construction - 2,666,550 10,000 - 2,676,550 31,450 2,906,550 10,000 - 2,948,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - - - 10,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 10,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 10,000 - - - - 10,000 Distribution system repair and replacement project required for meeting peak demands and reducing system losses. Project will replace asbestos cement (AC) water main in the Lea Hill service area. Progress Summary: Construction underway in 2020. Future Impact on Operating Budget: No significant Impact Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 115 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Reservoir 2 Valves Project No:wabd29 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - - - 240,000 - Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - 240,000 - Capital Expenditures: Design - - - 240,000 - Right of Way - - - - - Construction - - - - - - - - 240,000 - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue 760,000 - - - 1,000,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 760,000 - - - 1,000,000 Capital Expenditures: Design - - - - 240,000 Right of Way - - - - - Construction 760,000 - - - 760,000 760,000 - - - 1,000,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: This project will replace the existing 20" supply valve with a seismic control valve, and replace the 12" drain valve at Reservoir 2. Both valves will be installed in a vault. This project was identified as a maintenance issue due to limited access to the valves. The addition of a seismic control will improve the resiliency of the distribution system. Progress Summary: Future Impact on Operating Budget: No significant impact City of Auburn Capital Facilities Plan 116 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: 104th Park Development (104th to 102nd Water Main Loop) Project No:cp1619 Project Type:Non-Capacity Project Manager:Jamie Kelly Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - 50,000 250,000 - 300,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - 50,000 250,000 - 300,000 Capital Expenditures: Design - 50,000 - - 50,000 Right of Way - - - - - Construction - - 250,000 - 250,000 - 50,000 250,000 - 300,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - - - 250,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 250,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 250,000 - - - - 250,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: This project will construct a water main between 102nd Avenue SE and 104 Avenue SE is part of a Parks Department project that is developing a new City park. The new water main will eliminate convert the existing dead-end system to a looped system, as recommended by the Comprehensive Plan. Progress Summary: Project design underway in 2020. Future Impact on Operating Budget: No significant impact City of Auburn Capital Facilities Plan 117 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Garden Avenue Realignment Project No:cp2022 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - 400,000 55,000 440,000 455,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - 400,000 55,000 440,000 455,000 Capital Expenditures: Design - - 55,000 - 55,000 Right of Way - 400,000 - - 400,000 Construction - - - 440,000 - - 400,000 55,000 440,000 455,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - - - 495,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 495,000 Capital Expenditures: Design - - - - 55,000 Right of Way - - - - - Construction - - - - 440,000 - - - - 495,000 This project will construct water improvements as part of the Garden Avenue Realignment transportation project. The improvements incude installation of 1,000 feet of 12" transmission main from the 20" existing main in 8th St NE along Garden Avenue to the location of a future new booster pump station site on property to be purchased on 102nd Ave SE, and then back to 8th St NE. Progress Summary: Property acquisition underway in 2020 to support Lea Hill pump station project. Future Impact on Operating Budget: No significant impact Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 118 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Lead Service Line Replacement Project No:cp1922 Project Type:Non-Capacity Project Manager:Jai Carter Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - - - 405,000 - Grants (Fed,State,Local)- - - - - Bond Proceeds - - 205,000 1,195,000 205,000 DWSRF 12,532 292,468 2,695,000 3,000,000 12,532 292,468 2,900,000 1,600,000 3,205,000 Capital Expenditures: Design 12,532 292,468 - - 305,000 Right of Way - - - - - Construction - - 2,900,000 1,600,000 2,900,000 12,532 292,468 2,900,000 1,600,000 3,205,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - - - 405,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - 1,400,000 DWSRF - - - - 2,695,000 - - - - 4,500,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 4,500,000 - - - - 4,500,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: The City has approximately 1,000 service lines with a lead goose-neck connection at the main. State and Federal agencies are planning a 15 year period for utilities to remove all lead service lines. This project will remove lead service lines and construct associated roadway restoration throughout the City. Any additional lead service lines that are not removed and replaced with this project will be replaced as part of future rehabilitation and replacement projects. Progress Summary: City received a Drinking Water State Revolving Fund (DWSRF) loan for replacement of the lead service lines. Design underway in 2020. Future Impact on Operating Budget: No significant Impact City of Auburn Capital Facilities Plan 119 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Well 4 Pump Improvements Project No:cp2021 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - - 147,000 830,000 147,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - 147,000 830,000 147,000 Capital Expenditures: Design - - 147,000 - 147,000 Right of Way - - - - - Construction - - - 830,000 - - - 147,000 830,000 147,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - - - 977,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 977,000 Capital Expenditures: Design - - - - 147,000 Right of Way - - - - - Construction - - - - 830,000 - - - - 977,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: This project was identified in the Facilities Evaluation Study. The project will include a comprehensive investigation and evaluation of the well operation. Findings from the evaluation will likely result in replacing the generator with a larger unit, possibly replacing the motor soft starter with a varible frequency drive (VFD), and replacing aging control valves, gate valves, and air relief system. Comprehensive Plan project S-22. Progress Summary: In 2018, project costs were escalated at 3% per year from 2015 to year of construction. Design underway in 2020. Future Impact on Operating Budget: No significant Impact City of Auburn Capital Facilities Plan 120 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Water Resources Protection Program (Wellhead Protection) Project No:wabd23 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - 51,400 26,800 27,700 78,200 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - 51,400 26,800 27,700 78,200 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - 51,400 26,800 27,700 78,200 - 51,400 26,800 27,700 78,200 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue 28,500 29,400 30,200 31,200 173,800 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 28,500 29,400 30,200 31,200 173,800 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction 28,500 29,400 30,200 31,200 173,800 28,500 29,400 30,200 31,200 173,800 Annual funding for implementing strategies identified in the Wellhead Protection Plan. Although some tasks will be performed as part of the water operations budget, other tasks will require consultants with expertise in review and investigation of contaminant sites and other environmental databases, development of spill response plans, and leaking underground storage tanks. Comprehensive Plan project S-08. Progress Summary: In 2018, project costs were escalated at 3% per year from 2015 to year of completion. Future Impact on Operating Budget: No significant Impact Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 121 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Game Farm Park Pump Station/Distribution System Improvements Project No:cpxxxx Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - - - - - Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - - 69,782 69,782 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - 69,782 69,782 Capital Expenditures: Design - - - 69,782 69,782 Right of Way - - - - - Construction - - - - - - - - 69,782 69,782 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: The pumps at Game Farm Wilderness Park are in need of replacement, and the building need repairs. This project was identified in the 2015 Comprehensive Plan as occurring in the short to mid term, or by 2025. Installation of new water main crossing the White River to eliminate the pump station was identified as being completed by 2035. The Coal Creek Springs Transmission Main project will add a pipe crossing the White River to be used for installation of a water main for Game Farm Wilderness Park. Completion of the river crossing will enable the water main project to be completed sooner and eliminate the need for pump station improvements. This project will install new main within the Game Farm Park from the existing 8" near the amphitheater to the river crossing, and from the river crossing to the existing pump station in the Wilderness area. The project will also decommission the existing pump station. Comprehensive Plan project D16. Progress Summary: In 2018, project costs were escalated at 3% per year from 2015 to year of completion. Future Impact on Operating Budget: No significant Impact City of Auburn Capital Facilities Plan 122 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Meter Vault Replacement Project No:cp1807 Project Type:Non-Capacity Project Manager:Seth Wickstrom Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue 326,400 10,000 - 336,400 Grants (Fed,State,Local)- - - - - Bond Proceeds 120,101 779,899 - - 900,000 Other - - - - - 120,101 1,106,299 10,000 - 1,236,400 Capital Expenditures: Design 120,101 - - - 120,101 Right of Way - - - - - Construction - 1,106,299 10,000 - 1,116,299 120,101 1,106,299 10,000 - 1,236,400 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - - - - 10,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 10,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 10,000 - - - - 10,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Large meter vaults at Washington Elementary School, Cascade Middle School (2 vaults), Forest Ridge Townhomes, Green River Estates, and Neely Station have lids that are unsafe and vaults that are in need of repair. Project will replace the vaults and upgrade piping as needed. Progress Summary: Construction underway in 2020. Future Impact on Operating Budget: No significant Impact City of Auburn Capital Facilities Plan 123 WATER FUND (460)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: West Hill Springs Water Quality Improvements Project No:cpxxx Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Water Revenue - - - - - Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Water Revenue - 100,000 480,000 - 580,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - 100,000 480,000 - 580,000 Capital Expenditures: Design - 100,000 - - 100,000 Right of Way - - - - - Construction - - 480,000 - 480,000 - 100,000 480,000 - 580,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: The aging chlorination building at West Hill Springs will be replaced and a new liquid chlorination system will be installed. Additionally, aeration to adjust pH will be required. Comprehensive Plan project S-12. Progress Summary: In 2018, project costs were escalated at 3% per year from 2015 to year of completion. Additional cost refinement will be needed due to the need for additional improvements not originally identified in the Comprehensive Plan. Future Impact on Operating Budget: No significant Impact City of Auburn Capital Facilities Plan 124 TABLE W-3 Impact on Future Operating Budgets WATER Project:2022 2023 2024 2025 2026 2027 Total 1 Howard Road Corrosion Control Treatment Facility Expansion -$ -$ -$ -$ -$ 600$ 600$ Total -$ -$ -$ -$ -$ 600$ 600$ City of Auburn Capital Facilities Plan 125 SANITARY SEWER Current Facilities The City’s sanitary sewer service area encompasses approximately 28-square miles that are primarily within the City limits, but includes a total of approximately ½ square mile within Auburn’s Proposed Annexation area (PAA). The City contracts with King County for sewage treatment and disposal. The City’s Sanitary Sewer Utility is responsible for the collection and transmission of wastewater to the King County trunk lines. The City’s current inventory of approximately 215 miles of sewer lines serves the City’s sewer service area. Table S-1, Facilities Inventory, lists the sewage collection and transmission facilities along with their capacities and locations. Level of Service (LOS) The Comprehensive Sewerage Plan for the Sewerage Collection System summarizes the level of service (LOS), or design criteria, for the City’s sewage collection system. These standards represent the average quantities of sewage that the system is designated to accommodate for residential, industrial, and commercial development. Capital Facilities Projects and Financing Investments in the City’s sewage collection facilities include primarily non-capacity improvements and replacement projects. Anticipated projects include replacement of aging sewer pipes and manholes in conjunction with arterial and local street improvements, replacement of pipe identified through the sewer program’s condition assessment process, replacement of the Rainier Ridge Pump station, and updating the Comprehensive Sewer Plan. Additionally the City will continue to monitor flow rates, primarily within the Valley Basin area to help identify specific areas of the City that show high levels of inflow and infiltration. The City of Auburn’s sewer system anticipates costs for thirteen non-capacity projects totaling $15,936,000. Table S-2 shows the proposed financing plan followed by individual worksheets showing the project detail. Impact on Future Operating Budgets There are no operating budget impacts forecasted for sanitary sewer facilities during the six years 2022 – 2027. City of Auburn Capital Facilities Plan 126 TABLE S-1 Facilities Inventory Sewage Facilities CAPACITY FACILITY (MGD)LOCATION Pump Stations: 8th Street 0.26 900 8th Street NE 22nd Street 0.79 1950 22nd Street NE Area 19 0.47 800 71st Street SE Auburn 40 0.63 4159 O Place NE Dogwood 0.43 1423 Dogwood Street SE Ellingson 2.20 100 41st Street SE F Street 0.86 1700 F Street SE Hudson 0.76 6408 S 287th Street North Tapps 0.73 2610 Lake Tapps Pkwy SE Peasley Ridge 0.36 5225 South 320th Street Promenade 0.25 12900 SE 312th Street R Street 0.14 600 R Street NE Rainier Ridge 0.29 31809 125th Place SE Riverside 0.58 13900 104th Avenue SE Terrace View 0.94 104 60th Street SE Valley Meadows 0.18 2022 4th Street SE Verdana 2.88 11807 SE 296th Place (Kent, WA) FACILITY Pipe Size LOCATION River Crossings: Inverted Syphon 8 & 12 Inch Green River & 26th Street NE 8th Street Bridge 14 Inch Green River & 8th Street NE City of Auburn Capital Facilities Plan 127 TABLE S-2 CAPITAL FACILITIES PLAN PROJECTS AND FINANCING SANITARY SEWER DIVISION 2021 2022 2023 2024 2025 2026 Total Page Non-Capacity Projects: 129 Sanitary Sewer Repair & Replacement Program Capital Costs - 300,000 1,500,000 300,000 1,500,000 300,000 3,900,000 Funding Sources: Sewer Fund - 300,000 1,500,000 300,000 1,500,000 300,000 3,900,000 Bond Proceeds - - - - - - - 130 Street Utility Improvements Capital Costs 200,000 200,000 200,000 200,000 200,000 200,000 1,200,000 Funding Sources: Sewer Fund 200,000 200,000 200,000 200,000 200,000 200,000 1,200,000 Bond Proceeds - - - - - - - 131 Vactor Decant Facility Capital Costs 180,000 - - - - - 180,000 Funding Sources: Sewer Fund 180,000 - - - - - 180,000 Bond Proceeds - - - - - - - 132 Manhole Ring and Cover Replacement Capital Costs 80,000 80,000 80,000 80,000 80,000 80,000 480,000 Funding Sources: Sewer Fund 80,000 80,000 80,000 80,000 80,000 80,000 480,000 Bond Proceeds - - - - - - - 133 Sewer Pump Station Replacement/Improvement Program Capital Costs - - 255,000 525,000 2,900,000 - 3,680,000 Funding Sources: Sewer Fund - - 255,000 525,000 2,900,000 - 3,680,000 Bond Proceeds - - - - - - - 134 Pump Station Electrical Improvements Capital Costs 10,000 - - - - - 10,000 Funding Sources: Sewer Fund 10,000 - - - - - 10,000 Bond Proceeds - - - - - - - 135 Inflow and Infiltration Study Capital Costs 163,000 167,000 172,000 - - - 502,000 Funding Sources: Sewer Fund 163,000 167,000 172,000 - - - 502,000 Bond Proceeds - - - - - - - 136 Comprehensive Sewer Plan Update Capital Costs 40,000 140,000 50,000 20,000 - - 250,000 Funding Sources: Sewer Fund 40,000 140,000 50,000 20,000 - - 250,000 Bond Proceeds - - - - - - - City of Auburn Capital Facilities Plan 128 TABLE S-2 (continued) 2021 2022 2023 2024 2025 2026 Total Page Non-Capacity Projects: 137 F Street SE Non-Motorized Improvements Capital Costs 10,000 - - - - - 10,000 Funding Sources: Sewer Fund 10,000 - - - - - 10,000 Bond Proceeds - - - - - - - 138 M Street NE Widening Capital Costs - 12,000 - 112,000 - - 124,000 Funding Sources: Sewer Fund - 12,000 - 112,000 - - 124,000 Bond Proceeds - - - - - - - 139 Rainier Ridge Pump Station Rehabilitation/Replacement Capital Costs 450,000 2,900,000 - - - - 3,350,000 Funding Sources: Sewer Fund 450,000 2,900,000 - - - - 3,350,000 Bond Proceeds - - - - - - - 140 2nd Street SE Preservation Capital Costs 150,000 - - - - - 150,000 Funding Sources: Sewer Fund 150,000 - - - - - 150,000 Bond Proceeds - - - - - - - 141 2021 Sewer Repair and Replacement Capital Costs 2,100,000 - - - - - 2,100,000 Funding Sources: Sewer Fund 2,100,000 - - - - - 2,100,000 Bond Proceeds - - - - - - - Subtotal, Non-Capacity Projects: Capital Costs 3,383,000 3,799,000 2,257,000 1,237,000 4,680,000 580,000 15,936,000 SUMMARY: CAPITAL COSTS Capacity Projects - - - - - - - Non-Capacity Projects 3,383,000 3,799,000 2,257,000 1,237,000 4,680,000 580,000 15,936,000 Total Costs 3,383,000 3,799,000 2,257,000 1,237,000 4,680,000 580,000 15,936,000 FUNDING SOURCES: Utility Funds (Sewer)3,383,000 3,799,000 2,257,000 1,237,000 4,680,000 580,000 15,936,000 Bond Proceeds - - - - - - - Total Funding 3,383,000 3,799,000 2,257,000 1,237,000 4,680,000 580,000 15,936,000 City of Auburn Capital Facilities Plan 129 SEWER FUND (461)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Sanitary Sewer Repair & Replacement/System Improvements Program Project No:sebd01 Project Type: Project Manager:Bob Elwell Description: Activity: (Previous 2 Yrs.)2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Sewer Revenue - 300,000 - Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - 300,000 - Capital Expenditures: Design - - - 250,000 - Right of Way - - - 20,000 - Construction - - - 30,000 - - - - 300,000 - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Sewer Revenue 1,500,000 300,000 1,500,000 300,000 3,900,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 1,500,000 300,000 1,500,000 300,000 3,900,000 Capital Expenditures: Design 150,000 250,000 150,000 250,000 1,050,000 Right of Way - 20,000 - 20,000 60,000 Construction 1,350,000 30,000 1,350,000 30,000 2,790,000 1,500,000 300,000 1,500,000 300,000 3,900,000 Non-Capacity (Repair and Replacement) Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: This should slightly decrease the operating budget by correcting the problems that require operation staff's attention. Repair and replace (R&R) broken sewer mains and other facilities. These lines will be identified through television inspection and routine cleaning. This program includes funding for R&R projects which have not been identified as a separate R&R project or are not associated transportation projects. Anticipated projects include bi-annual, stand-alone, repair and replacement projects for sewer lines which are broken, misaligned, "bellied" or otherwise require an inordinate amount of maintenance effort or present a risk of backup or trench failure, and facilities which generate consistent odor complaints. Additionally, system improvements which enhance the ability to maintain service are included here. Comprehensive Plan Project #1. Progress Summary: 21 Sites were identified 2017. Funds from this program were transferred to CP1805 - 2019 Sewer Repair and Replacement project which used those funds to complete four of the sites using cured in place pipe (CIPP) lining. 2020 and 2021 funds will be used to complete the remaining sites as part of project CP2010. Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 130 SEWER FUND (461)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Street Utility Improvements Project No:sebd02 Project Type: Project Manager:Bob Elwell Description: Activity: (Previous 2 Yrs.)2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Sewer Revenue - - 200,000 200,000 200,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - 200,000 200,000 200,000 Capital Expenditures: Design 30,000 30,000 30,000 Right of Way - - - Construction 170,000 170,000 170,000 - - 200,000 200,000 200,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Sewer Revenue 200,000 200,000 200,000 200,000 1,200,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 200,000 200,000 200,000 200,000 1,200,000 Capital Expenditures: Design 30,000 30,000 30,000 30,000 180,000 Right of Way - - - - - Construction 170,000 170,000 170,000 170,000 1,020,000 200,000 200,000 200,000 200,000 1,200,000 Non Capacity (Repair and Replacement) Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: No significant Impact Sewer system repair and replacements in coordination with trasnportation projects. Comprehensive Plan Project #2. Progress Summary: Ongoing Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 131 SEWER FUND (461)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Sewer Vactor Decant Facility Project No:sebd03 Project Type: Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Sewer Revenue - - 180,000 - 180,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - 180,000 - 180,000 Capital Expenditures: Design - - 180,000 - 180,000 Right of Way/Property Acquisition - - - - - Construction - - - - - - - 180,000 - 180,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Sewer Revenue - - - - 180,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 180,000 Capital Expenditures: Design - - - - 180,000 Right of Way/Property Acquisition - - - - - Construction - - - - - - - - - 180,000 Non-Capacity (Improvements) Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: This project could decrease the future operating budget by reducing the expenses associated with hauling saturated waste to the County landfill. Currently the City hauls vactored sewage waste to the County landfill on a biweekly basis. The sewage sludge is considerably wet, thus Utility funds are paying for the disposal of water. This project consists of a study/analysis to assess the City’s vactor disposal method and identify a cost-effective alternative to the status quo. Possible recommendations may include maintaining current operations, constructing a gravity decant facility, incorporating special equipment into the vactor truck to increase decanting ability, purchasing specialized dewatering machinery, or collaborating with neighboring utilities for the shared use of facilities and equipment. Comprehensive Plan Project #3. Progress Summary: Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 132 SEWER FUND (461)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Manhole Ring and Cover Replacement Project No:sebd04 Project Type: Project Manager:Bob Elwell Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Sewer Revenue - - 80,000 80,000 80,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - 80,000 80,000 80,000 Capital Expenditures: Design - - 8,000 8,000 8,000 Right of Way/Property Acquisition - - - - - Construction - - 72,000 72,000 72,000 - - 80,000 80,000 80,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Sewer Revenue 80,000 80,000 80,000 80,000 480,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 80,000 80,000 80,000 80,000 480,000 Capital Expenditures: Design 8,000 8,000 8,000 8,000 48,000 Right of Way/Property Acquisition - - - - - Construction 72,000 72,000 72,000 72,000 432,000 80,000 80,000 80,000 80,000 480,000 Total Funding Sources: Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: This project could decrease the future operating budget by reducing the need for staff to respond to loose manholes or lids. Non-Capacity (Repair and Replacement) As manholes and roads age and their condition deteriorates, access covers and the rings in which they sit can become loose and/or misaligned, and can become a road hazard requiring maintenance staff attention and increasing the City's liability. This annual project will replace approximately 50 sewer manhole rings and covers to maintain access to the sewer system and to decrease the likelihood of the manholes becoming road hazards. In some years, this replacement will be as a stand-alone project, and in some years many of these replacements will be in conjunction with other City capital projects. Comprehensive Plan Project #7. Progress Summary: Ongoing Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 133 SEWER FUND (461)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Sewer Pump Station Replacement/Improvement Program Project No:sebd05 Project Type: Project Manager:Bob Elwell Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Sewer Revenue - - - - - Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way/Property Acquisition - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Sewer Revenue 255,000 525,000 2,900,000 - 3,680,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 255,000 525,000 2,900,000 - 3,680,000 Capital Expenditures: Design 255,000 525,000 230,000 - 1,010,000 Right of Way/Property Acquisition - - - - - Construction - - 2,670,000 - 2,670,000 255,000 525,000 2,900,000 - 3,680,000 Total Funding Sources: Total Expenditures: Non-Capacity (Repair and Replacement/Improvements) Total Funding Sources: Total Expenditures: Forecasted Project Cost: The Sewer Utility's infrastructure currently consists of 17 public sewer pump stations that range in age from 1 to over 50 years old. As those stations age, and utility operations change, considerations such as station condition, component condition, capacity, reliability, and safety suggest that stations be upgraded, rehabilitated, and replaced. This program fund will provide funding to meet those needs over the next six years. Comprehensive Plan Project #4. Progress Summary: Following the results of the systematic pump station evaluation study, the 2017-2022 funds for this program were divided into the Pump Station Electrical Improvements project (for common improvements at many stations) and the Pump Station Replacement project (for Rainier Ridge) As future considerations of reliability, capacity, and condition are evaluated, and specific projects are developed, these funds will be designated for those projects. In 2018, the program cost was adjusted to reflect escalation of 3% per year from 2017. Future Impact on Operating Budget: This project will not have a significant effect on operating budget. City of Auburn Capital Facilities Plan 134 SEWER FUND (461)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Pump Station Electrical Improvements Project No:cp1812 Project Type: Project Manager:Jeff Bender Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Sewer Revenue 29,429 1,133,055 10,000 - 1,172,484 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 29,429 1,133,055 10,000 - 1,172,484 Capital Expenditures: Design 6,692 226,656 - - 233,348 Right of Way - - - - - Construction - 906,399 10,000 - 916,399 6,692 1,133,055 10,000 - 1,149,747 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Sewer Revenue - - - - 10,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 10,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 10,000 - - - - 10,000 This project will not have a significant effect on operating budget. Non-capacity This project will design and construction improvements to the City's sewer pump stations' electrical systems that were identifed by the 2016 Pump Station Condition Assessment Project. The additions and modifications are intended to increase employee safety as well as operational efficiency. They include adding dry well control panel disconnects, bringing intrinsically safe wiring up to code, organizing, labelling, and dressing out control panel boxes, adding dry well HMI computer screens, creating uniform as-built wiring diagrams for each station, as well as several other modifications identified for specific stations. Funding for this project was derived from the Sewer Pump Station Replacement/Improvement program (sebd05). Progress Summary: For reasons of efficiency in design and constructions, some elements of the design applicable to all the stations and the specific design and construction of improvements for the 22nd Street and 'R' Street Pump Stations were completed as part of CP1719. Specific design for the remainder of the project will begin in 2019, and the project will be complete in 2021. In 2018, the program cost was adjusted to reflect escalation of 3% per year from 2017. Future Impact on Operating Budget: Total Funding Sources: Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: City of Auburn Capital Facilities Plan 135 SEWER FUND (461)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Inflow and Infiltration Study Project No:sebd11 Project Type: Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Sewer Revenue - 312,000 163,000 167,000 475,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - 312,000 163,000 167,000 475,000 Capital Expenditures: Design/Analysis - 312,000 163,000 167,000 475,000 Right of Way/Property Acquisition - - - - - Construction - - - - - - 312,000 163,000 167,000 475,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Sewer Revenue 172,000 - - - 502,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 172,000 - - - 502,000 Capital Expenditures: Design/Analysis 172,000 - - - 502,000 Right of Way/Property Acquisition - - - - - Construction - - - - - 172,000 - - - 502,000 Total Funding Sources: Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: This project will not have a significant effect on operating budget. Non-Capacity (Improvement) This project will assess portions of the City Sewer Service Area for infiltration/inflow (I/I) values. Excessive localized I/I can be an indicator of poor sewer main and side sewer conditions and could contribute to capacity issues in the future. This project will monitor flow in the collection system over several years. This data will then be used to help identify repair and replacement needs, modeling purposes, and for I/I assessment in future updates to the Comprehensive Sewer Plan. Comprehensive Plan Project #9. Progress Summary: In 2018, the program cost was adjusted to reflect escalation of 3% per year from 2014. Initial flow monitors were installed in May, 2020 with additional monitors to be added in September/October, 2020. Monitoring locations in future years will be determined based on the results of the initial phase of monitoring. The next two years of data collection coincides with King County's flow monitoring program which will allow the data to be shared and correlated. Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 136 SEWER FUND (461)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Comprehensive Sewer Plan Update Project No:sebd12 Project Type: Project Manager:Bob Elwell Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Sewer Revenue - - 40,000 140,000 40,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - 40,000 140,000 40,000 Capital Expenditures: Design - - 40,000 140,000 40,000 Right of Way/Property Acquisition - - - - - Construction - - - - - - - 40,000 140,000 40,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Sewer Revenue 50,000 20,000 - - 250,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 50,000 20,000 - - 250,000 Capital Expenditures: Design 50,000 20,000 - - 250,000 Right of Way/Property Acquisition - - - - - Construction - - - - - 50,000 20,000 - - 250,000 Total Funding Sources: Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Non-Capacity (Repair and Replacement/Improvement) This project will not have a significant effect on operating budget. This project will prepare an update to the City's Sewer Comprehensive Plan to be adopted by City Council as part of the City's overall Comprehensive Plan to be completed by June 2024. City staff will prepare portions of the plan and will engage consultants to complete some of the tasks including hydraulic modeling, financial analysis, and cost estimation. Comprehensive Plan Project #10. Progress Summary: The deadline for completion of the City's Comprehensive Plan has been extended from June 2023 to June 2024. Preliminary project planning underway in 2020. Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 137 SEWER FUND (461)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: F Street SE Non-Motorized Improvements Project No:cp1416 Project Type: Project Manager:Seth Wickstrom Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Sewer Revenue 14,463 163,200 10,000 - 187,663 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 14,463 163,200 10,000 - 187,663 Capital Expenditures: Design 14,463 5,000 - 19,463 Right of Way/Property Acquisition - - - - - Construction - 158,200 10,000 - 168,200 14,463 163,200 10,000 - 187,663 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Sewer Revenue - - - - 10,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 10,000 Capital Expenditures: Design - - - - - Right of Way/Property Acquisition - - - - - Construction - - - - 10,000 - - - - 10,000 Total Funding Sources: Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: This project saves money and avoids damage to the new roadway that could occur if the pipe was not replaced and experienced a failure of blockage. Non-Capacity (Repair and Replacement) Replace approximately 420 LF of 15"-18" diameter clay pipe as part of the City's transportation project: F Street SE Non- Motorized Improvements project. Constructing this project in association with a road improvement project reduces costs and avoids damage to the new roadway that would occur if the pipe was not replaced and experienced a failure or blockage. Progress Summary: Project construction underway in 2020. Funds shown in 2021 are a placeholder for a potential 2020 project budget carryforward. Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 138 SEWER FUND (461)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: M Street NE Widening Project No:sebd08 Project Type: Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Sewer Revenue - - - 12,000 - Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - 12,000 - Capital Expenditures: Design - - - 12,000 12,000 Right of Way - - - - - Construction - - - - - - - - 12,000 - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Sewer Revenue - 112,000 - - 124,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - 112,000 - - 124,000 Capital Expenditures: Design - 12,000 - - 24,000 Right of Way - - - - - Construction - 100,000 - - 100,000 - 112,000 - - 124,000 Total Funding Sources: Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: No significant Impact Non-Capacity Replace approximately 170 LF of 12" and 20 LF of 8" vitrified clay sewer line in M St NE between Main Street and 1st St NE and replace approximately 100 LF of 8" PVC between 2nd and 3rd Street NE to repair a belly at the downstream end of the pipe in conjunction with street improvements. Progress Summary: Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 139 SEWER FUND (461)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Rainier Ridge Pump Station Rehabilitation/Replacement Project No:cp2009 Project Type: Project Manager:Jai Carter Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Sewer Revenue - 65,000 450,000 2,900,000 515,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - 65,000 450,000 2,900,000 515,000 Capital Expenditures: Design - 65,000 450,000 220,000 515,000 Right of Way - - - - - Construction - - - 2,680,000 - - 65,000 450,000 2,900,000 515,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Sewer Revenue - - - - 3,350,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 3,350,000 Capital Expenditures: Design - - - - 670,000 Right of Way - - - - - Construction - - - - 2,680,000 - - - - 3,350,000 This project will not have a significant effect on operating budget. Non-capacity The Rainer Ridge Pump Station was constructed in 1980. Most of the property within its tributary basin has been fully developed, and the station has very little excess capacity. As such, there is a very short response time in the event of a pump failure, especially during peak use. Additionally, the PVC force main has had several breaks, and should be replaced. The initial phase of this project will examine the alternatives of rehabilitating the station, replacing major components, or replacing the entire station. The proposed funding assumes a complete replacement, and will be adjusted pending the alternatives analysis. Funding for this project was derived from the Sewer Pump Station Replacement/Improvement program (sebd05). Progress Summary: The 2016 Pump Station Evaluation project identified both the 22nd Street and Rainier Ridge Pump Stations to be rehabilitated or replaced. While 22nd Street was initially considered the more critical of the two, several improvements have been made to that station which has increased its useful life, so rehabilitation/replacement of Rainier Ridge became the more critical task. In 2018, the program cost was adjusted to reflect escalation of 3% per year from 2017. Future Impact on Operating Budget: Total Funding Sources: Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: City of Auburn Capital Facilities Plan 140 SEWER FUND (461)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: 2nd Street SE Preservation Project No:CP2003 Project Type: Project Manager:Jai Carter Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Sewer Revenue - 30,000 150,000 - 180,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - 30,000 150,000 - 180,000 Capital Expenditures: Design - 30,000 10,000 - 40,000 Right of Way - - - - Construction - - 140,000 - 140,000 - 30,000 150,000 - 180,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Sewer Revenue - - - - 150,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 150,000 Capital Expenditures: Design - - - - 10,000 Right of Way - - - - - Construction - - - - 140,000 - - - - 150,000 No significant impact Non-capacity This project replaces approximately 450 LF of 8” concrete sewer line with 8” PVC and replaces 2 manholes as part of a street reconstruction project for 2nd Street SE between A Street SE and Auburn Way South. Progress Summary: City was awarded transportation grant funding in 2019 and the project design began in 2020. Sewer funds for this project will be transferred from sebd02 (2020), with a $30,000 in-fund transfer, and $150,000 "rebudgeting" in 2021. Future Impact on Operating Budget: Total Funding Sources: Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: City of Auburn Capital Facilities Plan 141 SEWER FUND (461)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: 2021 Sewer Repair and Replacement Project No:CP2010 Project Type: Project Manager:Jai Carter Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Sewer Revenue - 300,000 2,100,000 - 2,400,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - 300,000 2,100,000 - 2,400,000 Capital Expenditures: Design - 300,000 100,000 - 400,000 Right of Way - - - - Construction - - 2,000,000 - 2,000,000 - 300,000 2,100,000 - 2,400,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Sewer Revenue - - - - 2,100,000 Grants (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 2,100,000 Capital Expenditures: Design - - - - 100,000 Right of Way - - - - - Construction - - - - 2,000,000 - - - - 2,100,000 Total Funding Sources: Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: This project should slightly decrease the operating budget by correcting the problems that require operation staff's attention. Non-capacity This project is a continuation of the 2019 Sewer R&R project (CP1805), and proposes to complete the design and construction of the repairs not completed during the construction phase of that project and to add three new sites. This project plans to replace a total of approximately 2585 LF of 8”-10” diameter sewer line at 9 separate sites, and to complete 10 spot repairs. Progress Summary: Project design began in 2020. The 2021 budget for project has been increased by $600,000 over the previously programmed $1,500,000 based on unspent funds budgeted in 2020 for project CP1805. Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 142 City of Auburn Capital Facilities Plan 143 STORM DRAINAGE Current Facilities The City’s storm drainage service area encompasses the municipal boundaries of the City. For management purposes, the service area is divided into 59 drainage sub-basins. The City’s drainage system consists of a combination of closed conveyance pipes and open ditch conveyance facilities, with seven pumping stations. Table SD-1 Facilities Inventory lists the facilities along with their current capacities and location. Level of Service (LOS) The City’s Comprehensive Drainage Plan summarizes the level of service (LOS), or design criteria, for the City’s storm drainage system. Generally, these standards represent a 25- year/24-hour design storm capacity within the 59 drainage sub-basins. Capital Facilities Projects and Financing The City’s storm drainage facilities anticipate one capacity project in the amount of $208,100 and twenty non-capacity projects totaling $21,097,000 for a six-year planning expectation total of $21,305,100. Table SD-2 shows the proposed financing plan followed by individual worksheets showing the project detail. Impact on Future Operating Budgets There are no operating budget impacts forecasted for storm drainage facilities during the six years 2022 – 2027. City of Auburn Capital Facilities Plan 144 TABLE SD-1 Facilities Inventory Storm Drainage Facilities Feet of Feet of FACILITY Acres Pipeline Open Channels LOCATION Drainage Basins: A 562 38,226 1,440 See City of Auburn's AA 410 17,179 3,479 Comprehensive Drainage AAA 296 3,031 5,187 Plan, Dec. 2015 AZ 779 70,921 18,314 B 865 104,655 0 BB 15 1,626 0 BBB 73 0 0 C 836 91,901 5,842 CC 242 2,595 0 CCC 986 72,192 18,492 D 168 20,973 177 DD 231 30 0 DDD 63 4,047 0 E 726 59,724 8,478 EE 563 3,611 0 F 83 9,731 0 FF 361 2,719 1358 G 134 20,090 0 GG 226 4,923 413 H 561 43,362 614 HH 392 0 0 I 238 28,161 3,081 II 305 0 0 J 255 5,096 1,571 JJ 1,185 36,581 3,177 K 268 14,715 22 KK 391 0 0 L 87 14,483 3,747 LL 198 117 2,586 LS 1,138 78,592 13,392 M 547 39,958 6,796 MM 332 1,949 184 N 128 10,582 0 NN 562 11,913 6,058 NNN 175 2,717 705 O 176 19,431 2,368 OO 1,397 51,884 17,648 P 189 8,161 1,368 PP 110 1,459 0 PPP 161 3,863 2,091 QQ 334 13,313 3,777 CAPACITY City of Auburn Capital Facilities Plan 145 TABLE SD-1 (continued) Facilities Inventory Storm Drainage Facilities Feet of Feet of FACILITY Acres Pipeline Open Channels LOCATION R 55 7,221 0 RR 249 12,038 673 S 287 17,121 2,227 SS 333 20,929 2,140 T 698 94,609 4,026 TT 137 2,076 1,254 U 365 10,934 0 UU 456 20,304 3,430 V 662 38,491 7,182 W 289 37,158 5,041 WC 101 10,099 0 WW 71 1,176 1,708 X 40 3,616 0 YY 326 20,244 3,756 YYY 105 155 639 Z 70 9,678 0 ZZ 935 59,355 19,262 ZZZ 238 0 0 Total 22,165 1,279,715 183,703 FACILITY (GPM)LOCATION Pump Stations: Brannan Park Pump Station #4 20,200 Brannan Park White River Pump Station 17,700 5000 block A Street SE Emerald Corp. Park Pump Station 6,500 C Street NE near 42nd Street M St SE Grade Separation 1,500 328 M St SE A Street SE Pump Station 1,380 A Street SE near SR-18 and BNRR overpass West Main Street Pump Station 1,200 1420 West Main Street Auburn Way S Pump Station #3 1,000 Auburn Way S near SR-18 and BNRR overpass CAPACITY City of Auburn Capital Facilities Plan 146 TABLE SD-2 CAPITAL FACILITIES PLAN PROJECTS AND FINANCING STORM DRAINAGE DIVISION 2021 2022 2023 2024 2025 2026 Total Page Capacity Projects: 149 37th St. NW Storm Improvement Capital Costs 208,100 - - - - - 208,100 Funding Sources: Storm Fund 26,130 - - - - - 26,130 King Co. Opportunity Fund 181,970 - - - - - 181,970 Subtotal, Capacity Projects: Capital Costs 208,100 - - - - - 208,100 Non-Capacity Projects: 150 Pipeline Repair & Replacement Program Capital Costs 324,000 125,000 1,250,000 125,000 1,250,000 125,000 3,199,000 Funding Sources: Storm Fund 324,000 125,000 1,250,000 125,000 1,250,000 125,000 3,199,000 Bond Proceeds - - - - - - - 151 2021 Storm Renewal & Replacement Project Capital Costs 1,000,000 - - - - - 1,000,000 Funding Sources: Storm Fund 926,000 - - - - - 926,000 Pierce Co. Opportunity Fund 74,000 - - - - - 74,000 Bond Proceeds - - - - - - - 152 30th Street NE Area Flooding, Phase 3 Capital Costs - - - - 673,000 2,244,000 2,917,000 Funding Sources: Storm Fund - - - - 673,000 2,244,000 2,917,000 Bond Proceeds - - - - - - - 153 Street Utility Improvements Capital Costs 250,000 250,000 250,000 250,000 250,000 250,000 1,500,000 Funding Sources: Storm Fund 250,000 250,000 250,000 250,000 250,000 250,000 1,500,000 Bond Proceeds - - - - - - - 154 2021 Local Street Preservation - G Street SE and Riverwalk/Forest Ridge Capital Costs 440,000 - - - - - 440,000 Funding Sources: Storm Fund 440,000 - - - - - 440,000 Bond Proceeds - - - - - - - 155 AWN Preservation Project Phase 3 Capital Costs 10,000 - - - - - 10,000 Funding Sources: Storm Fund 10,000 - - - - - 10,000 Bond Proceeds - - - - - - - City of Auburn Capital Facilities Plan 147 TABLE SD-2 (continued) 2021 2022 2023 2024 2025 2026 Total Page Non-Capacity Projects: 156 Comprehensive Storm Drainage Plan Update Capital Costs 40,000 140,000 50,000 20,000 - - 250,000 Funding Sources: Storm Fund 40,000 140,000 50,000 20,000 - - 250,000 Bond Proceeds - - - - - - - 157 Vegetation Sorting Facility Capital Costs 902,000 - - - - - 902,000 Funding Sources: Storm Fund 902,000 - - - - - 902,000 Bond Proceeds - - - - - - - 158 Auburn Municipal Airport Runway Enhancements Capital Costs 10,000 - - - - - 10,000 Funding Sources: Storm Fund 10,000 - - - - - 10,000 Bond Proceeds - - - - - - - 159 North Airport Area Improvements Capital Costs 175,000 1,100,000 - - - - 1,275,000 Funding Sources: Storm Fund 175,000 1,100,000 - - - - 1,275,000 Bond Proceeds - - - - - - - 160 D St. SE Storm Improvement Capital Costs 508,000 1,742,000 - - - - 2,250,000 Funding Sources: Storm Fund 508,000 1,742,000 - - - - 2,250,000 Bond Proceeds - - - - - - - 161 S. 330th St. & 46th Pl. S. Storm Improvement Capital Costs 294,000 - - - - - 294,000 Funding Sources: Storm Fund 294,000 - - - - - 294,000 Bond Proceeds - - - - - - - 162 23rd Street SE Storm Improvement Capital Costs 174,000 596,000 - - - - 770,000 Funding Sources: Storm Fund 174,000 596,000 - - - - 770,000 Bond Proceeds - - - - - - - 163 Riverwalk Drive SE Non-Motorized Improvements Capital Costs 68,000 454,000 - - - - 522,000 Funding Sources: Storm Fund 68,000 454,000 - - - - 522,000 Bond Proceeds - - - - - - - 164 S. 314th St. & 54th Ave S. Storm Improvement Ph. 1 Capital Costs - 102,000 416,000 - - - 518,000 Funding Sources: Storm Fund - 102,000 416,000 - - - 518,000 Bond Proceeds - - - - - - - City of Auburn Capital Facilities Plan 148 TABLE SD-2 (continued) 2021 2022 2023 2024 2025 2026 Total Page Non-Capacity Projects: 165 S. 314th St. & 54th Ave S. Storm Improvement Ph. 2 Capital Costs - - 115,000 281,000 - - 396,000 Funding Sources: Storm Fund - - 115,000 281,000 - - 396,000 Bond Proceeds - - - - - - - 166 M Street NE Widening Capital Costs - 50,000 - 350,000 - - 400,000 Funding Sources: Storm Fund - 50,000 - 350,000 - - 400,000 Bond Proceeds - - - - - - - 167 West Main Street Pump Station Upgrade Capital Costs - - 850,000 2,914,000 - - 3,764,000 Funding Sources: Storm Fund - - 850,000 2,514,000 - - 3,364,000 King Co. Opportunity Fund - - - 400,000 - - 400,000 168 Manhole & Catchbasin Frame and Grate Replacement Capital Costs 80,000 80,000 80,000 80,000 80,000 80,000 480,000 Funding Sources: Storm Fund 80,000 80,000 80,000 80,000 80,000 80,000 480,000 Bond Proceeds - - - - - - - 169 Auburn Way North and 1st St NE Signal Replacement Capital Costs 200,000 - - - - - 200,000 Funding Sources: Storm Fund 200,000 - - - - - 200,000 Bond Proceeds - - - - - - - Subtotal, Non-Capacity Projects: Capital Costs 4,475,000 4,639,000 3,011,000 4,020,000 2,253,000 2,699,000 21,097,000 2020 2021 2022 2023 2024 2025 Total SUMMARY: CAPITAL COSTS Capacity Projects 208,100 - - - - - 208,100 Non-Capacity Projects 4,475,000 4,639,000 3,011,000 4,020,000 2,253,000 2,699,000 21,097,000 Total Costs 4,683,100 4,639,000 3,011,000 4,020,000 2,253,000 2,699,000 21,305,100 FUNDING SOURCES: Storm Fund 4,427,130 4,639,000 3,011,000 3,620,000 2,253,000 2,699,000 20,649,130 King Co. Opportunity Fund 181,970 - - 400,000 - - 581,970 Pierce Co. Opportunity Fund 74,000 - - - - - 74,000 Bond Proceeds - - - - - - - Total Funding 4,683,100 4,639,000 3,011,000 4,020,000 2,253,000 2,699,000 21,305,100 City of Auburn Capital Facilities Plan 149 STORM DRAINAGE FUND (462)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title:37th St. NW Storm Improvement Project No:cp1724 Project Type:Capacity Project Manager:Luis Barba Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Storm Revenue 7,845 30,000 26,130 - 63,975 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - King County Opportunity Grant 28,035 - 181,970 - 210,005 35,880 30,000 208,100 - 273,980 Capital Expenditures: Design 35,880 30,000 - - 65,880 Right of Way - - - - - Construction - - 208,100 - 208,100 35,880 30,000 208,100 - 273,980 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Storm Revenue - - - - 26,130 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - King County Opportunity Grant - - - - 181,970 - - - - 208,100 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 208,100 - - - - 208,100 Grants / Other Sources: King County Opportunity Grant This project will replace the damaged and eroded existing pipes spanning the PSE substation access driveway in vicinity of 37th ST. NE near I St NW. During periods of prolonged heavy flows, this side channel to Mill Creek exceeds the capacity of the combined culverts and backs up onto 37th St. NW and also impacts the Interurban Trail. Comprehensive Plan Project #2 Progress Summary: The city has been awarded a $210,000 King County Opportunity Grant. Hydraulic modeling and preliminary culvert design and initial meetings with the permitting agencies have been completed. Coordination with PSE is ongoing to establish the available location of the culvert spanning the substation driveway. Future Impact on Operating Budget: None Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 150 STORM DRAINAGE FUND (462)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Pipeline Repair & Replacement Program Project No:sdbd03 Project Type:Non-Capacity Project Manager:TBD Description: Activity: (Previous 2 Years)2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Storm Revenue 942,092 - 324,000 125,000 1,266,092 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 942,092 - 324,000 125,000 1,266,092 Capital Expenditures: Design 187,891 - - 125,000 187,891 Right of Way - - - - - Construction 754,201 - 324,000 - 1,078,201 942,092 - 324,000 125,000 1,266,092 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Storm Revenue 1,250,000 125,000 1,250,000 125,000 3,199,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 1,250,000 125,000 1,250,000 125,000 3,199,000 Capital Expenditures: Design - 125,000 - 125,000 375,000 Right of Way - - - - - Construction 1,250,000 - 1,250,000 - 2,824,000 1,250,000 125,000 1,250,000 125,000 3,199,000 This program provides funding for projects involving replacement of existing infrastructure. These projects support street repairs and other utility replacement programs, requiring coordination. This program recently funded the 2018 Storm Repair & Replacement Project (cp1823). Comprehensive Plan Project #1. Progress Summary: Construction of project CP1823 underway in 2020. Future Impact on Operating Budget: Repair and replacement of aging infrastructure should reduce operating costs. Total Funding Sources: Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: City of Auburn Capital Facilities Plan 151 STORM DRAINAGE FUND (462)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title:2021 Storm Renewal & Replacement Project Project No:cp2017 Project Type:Non-Capacity Project Manager:Luis Barba Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Storm Revenue - 100,000 926,000 - 1,026,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Pierce County FCZD Opportunity Fund - - 74,000 - 74,000 - 100,000 1,000,000 - 1,100,000 Capital Expenditures: Design - 100,000 - - 100,000 Right of Way - - - - Construction - 1,000,000 - 1,000,000 - 100,000 1,000,000 - 1,100,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Storm Revenue - - - - 926,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Pierce County FCZD Opportunity Fund - - - - 74,000 - - - - 1,000,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 1,000,000 - - - - 1,000,000 Lower maintenance costs due to reducing stormwater runoff onto roadways and sidewalks. This project will provide improvements to the existing storm drainage system to eliminate known drainage issues and reduce maintenance at six sites: Eastpoint Storm Pond, Mountain View Cemetery, SE 304th Street at 108th Ave SE, A St NE near 7th St NE, S 316th Street near 55th Ave S, and south side of Mill Pond Drive near Oravetz Rd. Progress Summary: Project design underway in 2020. Future Impact on Operating Budget: Total Funding Sources: Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: City of Auburn Capital Facilities Plan 152 STORM DRAINAGE FUND (462)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: 30th Street NE Area Flooding, Phase 3 Project No:cpxxxx Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Storm Revenue - - - - - Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Storm Revenue - - 673,000 2,244,000 2,917,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - 673,000 2,244,000 2,917,000 Capital Expenditures: Design - - 673,000 - 673,000 Right of Way - - - - - Construction - - - 2,244,000 2,244,000 - - 673,000 2,244,000 2,917,000 This project will reduce potential flooding in C St. NE by redirecting wet weather high flows southward to the 42-inch diameter (Phase 1) storm drain in 30th St. NE. By redirecting the C St. NE drainage into the Brannan Park system, these flows would no longer be affected by high water levels in Mill Creek. To avoid deepening the Phase 1 gravity line (and extensive retrofits to the Brannan Park pump station), this project would include a wet weather pump station and force main connection to 30th St. NE. The upgraded 42-inch diameter pipe in 30th St. NE would have sufficient capacity for these additional flows. Key components of Phase 3 include: Wet weather pump station (estimated capacity of 4.5 to 7 cfs), 1,730 feet of 15-inch diameter force main; Diversion structure in C St. NE for pump station. Comprehensive Plan Project #4B. Progress Summary: This project was moved from 2023-2024 to 2024-2025 to balance storn funding requirements throughout the capital facilities plan. In 2020, the program cost was adjusted to reflect escalation of 3% per year from 2015. Future Impact on Operating Budget: Impacts are expected to increase due to high level of maintenance required for pump stations. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 153 STORM DRAINAGE FUND (462)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Street Utility Improvements Project No:sdbd04 Project Type:Non Capacity Project Manager:TBD Description: Activity: Previous 2 years 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Storm Revenue 200,000 20,000 250,000 250,000 470,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 200,000 20,000 250,000 250,000 470,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction 200,000 20,000 250,000 250,000 470,000 200,000 20,000 250,000 250,000 470,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Storm Revenue 250,000 250,000 250,000 250,000 1,500,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 250,000 250,000 250,000 250,000 1,500,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction 250,000 250,000 250,000 250,000 1,500,000 250,000 250,000 250,000 250,000 1,500,000 Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: Total Funding Sources: Storm system repair and replacements in coordination with trasnportation projects. Comprehensive Plan Project #12. Progress Summary: In 2020, this program is funding the AWN Preservation Project Phase 3 (cp1904). Future Impact on Operating Budget: No significant Impact. City of Auburn Capital Facilities Plan 154 STORM DRAINAGE FUND (462)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: 2021 Local Street Preservation - G Street SE and Riverwalk/Forest Ridge Project No:cp2019 Project Type:Non-Capacity Project Manager:Troung Description: Activity: (Previous 2 Years)2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Storm Revenue - 60,000 440,000 - 500,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - 60,000 440,000 - 500,000 Capital Expenditures: Design - 60,000 - - 60,000 Right of Way - - - - - Construction - - 440,000 - 440,000 - 60,000 440,000 - 500,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Storm Revenue - - - - 440,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 440,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 440,000 - - - - 440,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: This improvement will replace undersized and deteriorated storm line with the street project. Approximately 1150 feet of 12" storm line with catchbasins and manholes will be constructed. Progress Summary: Conceptual level design underway in 2020. Future Impact on Operating Budget: Repair and replacement of aging infrastructure should reduce operating costs. City of Auburn Capital Facilities Plan 155 STORM DRAINAGE FUND (462)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: AWN Preservation Project Phase 3 Project No:cp1904 Project Type:Non Capacity Project Manager:TBD Description: Activity: Previous 2 years 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Storm Revenue - 190,000 10,000 - 200,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - 190,000 10,000 - 200,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - 190,000 10,000 - 200,000 - 190,000 10,000 - 200,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Storm Revenue - - - - 10,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 10,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 10,000 - - - - 10,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: This improvement will construct storm improvements with transportation project CP1904 - AWN Preservation Project Phase 3, including eliminating cross connection(s) and installing new pipe and manhole(s). Progress Summary: Funding from Street Utility Improvements Program sdbd04 ($90,000) and from Drainage Assessment Program sdbd07 ($100,000). Project construction underway in 2020. Future Impact on Operating Budget: No significant Impact. City of Auburn Capital Facilities Plan 156 STORM DRAINAGE FUND (462)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Comprehensive Storm Drainage Plan Update Project No:sdbd16 Project Type:Non-Capacity Project Manager:Tim Carlaw Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Storm Revenue - - 40,000 140,000 40,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - 40,000 140,000 40,000 Capital Expenditures: Design - - 40,000 140,000 40,000 Right of Way - - - - - Construction - - - - - - - 40,000 140,000 40,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Storm Revenue 50,000 20,000 - - 250,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 50,000 20,000 - - 250,000 Capital Expenditures: Design 50,000 20,000 - - 250,000 Right of Way - - - - - Construction - - - - - 50,000 20,000 - - 250,000 None This project will prepare an update to the City's Storm Drainage Comprehensive Plan to be adopted by City Council as part of the City's overall Comprehensive Plan to be completed by June 2024. City staff will prepare portions of the plan and will engage consultants to complete some of the tasks including hydraulic modeling, financial analysis, and cost estimation. Comprehensive Plan Project #9. Progress Summary: In 2018, the project costs were escalated an average of 3% per year from 2015 to the year of completion.The deadline for completion of the City's Comprehensive Plan has been extended from June 2023 to June 2024. Preliminary project planning underway in 2020. Future Impact on Operating Budget: Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 157 STORM DRAINAGE FUND (462)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title:Vegetation Sorting Facility Project No:sdbd12 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Storm Revenue - 64,000 902,000 - 966,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - 64,000 902,000 - 966,000 Capital Expenditures: Design - 64,000 64,000 - 128,000 Acquisition - - 750,000 - 750,000 Construction/Equipment - - 88,000 - 88,000 - 64,000 902,000 - 966,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Storm Revenue - - - - 902,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 902,000 Capital Expenditures: Design - - - - 64,000 Acquisition - - - - 750,000 Construction/Equipment - - - - 88,000 - - - - 902,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: This project will prepare an evaluation of the benefits and costs of acquiring property to use as a vegetation sorting facility prior to disposal or reuse of materials from storm drainage maintenance activities (e.g., pond and ditch cleaning). The evaluation will identify potential use of a sorting facility by other City departments and by neighboring jurisdictions as a regional facility. If evaluation shows a reasonable benefit/cost ratio, the project implementation proceed with property acquisition and site improvements to construct the vegetation sorting facility. Cost includes bin barriers and sorting equipment to facilitate materials handling and separation. Comprehensive Plan Project #10. Progress Summary: In 2018, the project costs were escalated an average of 3% per year from 2015 to the year of completion. Preliminary project scoping underway in 2020. Future Impact on Operating Budget: Overall operating costs should decrease as a result of improved efficiency from the sorting facility. City of Auburn Capital Facilities Plan 158 STORM DRAINAGE FUND (462)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title:Auburn Municipal Airport Runway Enhancements Project No:cp1516 Project Type:Non-Capacity Project Manager:Wickstrom Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Storm Revenue - 127,500 10,000 - 137,500 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - 127,500 10,000 - 137,500 Capital Expenditures: Design - 12,500 - - 12,500 Right of Way - - - - - Construction - 115,000 10,000 - 125,000 - 127,500 10,000 - 137,500 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Storm Revenue - - - - 10,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 10,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - 10,000 - - - - 10,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Comprehensive Plan Project #6 includes excavating additional storage capacity in Pond I, replacing the existing inlet pipe to Pond I at a lower elevation to direct additional flow into Pond I, and installing a backflow preventer at the outlet from the pond. Subsequent storm modeling has indicated that excess storage exists within the 4 open ponds at the airport but requires a larger inlet pipe to deliver greater flows into the ponds to maximize the storage. The scope of the project has been revised to include installation of 150 feet of 30" storm pipe to improve the inlet into Pond I, and 390 feet of 15" storm pipe to direct flows from the north hanger area into Pond I. The new underground stormwater detention system is being constructed as part of, and funded by, the runway extension. Progress Summary: Project construction underway in 2020 as a change order for with project CP1516 - Airport Runway Enhancements. Future Impact on Operating Budget: None City of Auburn Capital Facilities Plan 159 STORM DRAINAGE FUND (462)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title:North Airport Area Improvements Project No:cp2026 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Storm Revenue - - 175,000 1,100,000 175,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - 175,000 1,100,000 175,000 Capital Expenditures: Design - - 175,000 - 175,000 Right of Way - - - - - Construction - - - 1,100,000 - - - 175,000 1,100,000 175,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Storm Revenue - - - - 1,275,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 1,275,000 Capital Expenditures: Design - - - - 175,000 Right of Way - - - - - Construction - - - 1,100,000 - - - - 1,275,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: This project will eliminate Pond F and underground Pond G within subsurface chambers. Storm modeling for the north auburn airport area has determined that overall storage capacity is sufficient and will eliminate the existing bird netting and vegetation management for these two ponds. Progress Summary: The scope of this project has been revised to include the undergrounding of a portion of the open detention storage ponds at the Airport. The origional project which included replacing the existing inlet pipe to Pond I at a lower elevation to capture additional flow is being constructed with a change order for CP1516 and will be completed in 2020. This will reduce the potential for flooding occurence in this area. Future Impact on Operating Budget: Eliminating Pond F and undergrounding Pond G will significantly reduce the costs to maintain the bird netting and vegetation management within the ponds. City of Auburn Capital Facilities Plan 160 STORM DRAINAGE FUND (462)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title:D St. SE Storm Improvement Project No:sdbd18 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Storm Revenue - - 508,000 1,742,000 508,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - 508,000 1,742,000 508,000 Capital Expenditures: Design - - 508,000 - 508,000 Right of Way - - - - - Construction - - - 1,742,000 - - - 508,000 1,742,000 508,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Storm Revenue - - - - 2,250,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 2,250,000 Capital Expenditures: Design - - - - 508,000 Right of Way - - - - - Construction - - - - 1,742,000 - - - - 2,250,000 This project will Install approximately 990 L.F. 30-inch, 630 L.F. 24-inch and 1230 L.F. 12-inch of new gravity storm drain pipe to convey the 25-year flow along D Street SE from a flooding area that caused by failing dry wells located near the intersection of D Street SE and 25th Street SE. Additionally, the project will install approximately 380 LF 12-inch gravity storm drain pipe in F Street SE from 27th to 26th Street SE to complete a missing line connection. Both of these systems direct flows to the existing 21st Street storm pond. Comprehensive Plan Project #7. Progress Summary: in 2018, project costs were escalated at 3% per year from 2015 to the year of construction. Future Impact on Operating Budget: Operating expenses are expected to decrease with the elimination of existing drywells. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 161 STORM DRAINAGE FUND (462)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title:S. 330th St. & 46th Pl. S. Storm Improvement Project No:cp2018 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Storm Revenue - 85,000 294,000 - 379,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - 85,000 294,000 - 379,000 Capital Expenditures: Design - 70,000 - 70,000 Easement - 15,000 - - 15,000 Construction - - 294,000 - 294,000 - 85,000 294,000 - 379,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Storm Revenue - - - - 294,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 294,000 Capital Expenditures: Design - - - - - Easement - - - - - Construction - - - - 294,000 - - - - 294,000 As part of the City's efforts to improve the drainage system in the West Hill annexation area, this project construct improvements near S. 330th Street and 46th Place S. where public storm drainage currently discharges within a large open ditch. The improvement will re-route the drainage within the right-of-way to the existing outfall. Comprehensive Plan Project #5A. Progress Summary: In 2018, project costs were escalated at 3% per year from 2015 to the year of construction. Project design underway in 2020. Future Impact on Operating Budget: None Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 162 STORM DRAINAGE FUND (462)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title:23rd Street SE Storm Improvement Project No:sdbd17 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Storm Revenue - - 174,000 596,000 174,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - 174,000 596,000 174,000 Capital Expenditures: Design - - 174,000 - 174,000 Right of Way - - - - - Construction - - - 596,000 - - - 174,000 596,000 174,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Storm Revenue - - - - 770,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 770,000 Capital Expenditures: Design - - - - 174,000 Right of Way - - - - - Construction - - - - 596,000 - - - - 770,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: This project will improve existing drainage conditions in vicinity of 23rd St. SE & K St. SE. Phase 1 includes installation of 600 LF of 15-inch line along K St. SE from 23rd St. SE to 21st St. SE to alleviate flooding associated with the pedestrian entrance to Pioneer Elementary School. Phase 2 includes installation of 560 LF of 18-inch line along 23rd St. SE from F St. SE to K St. SE. to convey flows to the F St. SE trunkline for discharge into the 21st St. SE regional infiltration facility. Phases 1 and 2 will be constructed simultaneously. Comprehensive Plan Project #8 (Phase 1+2). Progress Summary: In 2020, the project costs were escalated at 3% per year from 2015 to the year of construction. In 2020, the project implementation has been moved from 2020 to 2021 to coordinate with the redevelopment of Pioneer Elementary School. Future Impact on Operating Budget: None City of Auburn Capital Facilities Plan 163 STORM DRAINAGE FUND (462)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title:Riverwalk Drive SE Non-Motorized Improvements Project No:sdbd14 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Storm Revenue - - 68,000 454,000 68,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - 68,000 454,000 68,000 Capital Expenditures: Design - - 68,000 - 68,000 Right of Way - - - - - Construction - - - 454,000 - - - 68,000 454,000 68,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Storm Revenue - - - - 522,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 522,000 Capital Expenditures: Design - - - - 68,000 Right of Way - - - - - Construction - - - - 454,000 - - - - 522,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: This project will construct large diameter storm piping to replace the existing roadside ditch, and expand the Riverwalk ponds to accommodate increased capacity due to the lost infiltration of the upstream ditch along Riverwalk Drive. The project will be implemented as part of the transportation project that will construct sidewalks along the east side of Riverwalk Drive SE from Howard Road and Auburn Way South. Progress Summary: In 2020, the City applied Grant funding for the transportation portion of the project (sidewalks) and the City continues working with the Muckleshoot Indian Tribe to establish partnership and potential funding. Future Impact on Operating Budget: Maintenance costs should decrease as a result of the project. City of Auburn Capital Facilities Plan 164 STORM DRAINAGE FUND (462)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title:S. 314th St. & 54th Ave S. Storm Improvement Ph. 1 Project No:sdbd19 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Storm Revenue - - - 102,000 - Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - 102,000 - Capital Expenditures: Design - - - 102,000 - Right of Way - - - - - Construction - - - - - - - - 102,000 - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Storm Revenue 416,000 - - - 518,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 416,000 - - - 518,000 Capital Expenditures: Design - - - - 102,000 Right of Way - - - - - Construction 416,000 - - - 416,000 416,000 - - - 518,000 As part of the City's efforts to improve the drainage system in the West Hill annexation area, this project will construct improvements near S. 314th Street. and 54th Avenue S. to redirect flows and implement Low Impact Development (LIID) techniques. Comprehensive Project #5B Phase 1. Progress Summary: In 2018, project costs were escalated at 3% per year from 2015 to the year of construction. Future Impact on Operating Budget: None Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 165 STORM DRAINAGE FUND (462)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title:S. 314th St. & 54th Ave S. Storm Improvement Ph. 2 Project No:cpXXXX Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Storm Revenue - - - - - Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Storm Revenue 115,000 281,000 - - 396,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 115,000 281,000 - - 396,000 Capital Expenditures: Design 89,000 - - - 89,000 Right of Way 26,000 - - - 26,000 Construction - 281,000 - - 281,000 115,000 281,000 - - 396,000 As part of the City's efforts to improve the drainage system in the West Hill annexation area, this project will construct near. S 314th Street and 54th Avenue S. to route the public storm drainage through a new easement and pipe to the downstream system. Comprehensive Drainage Plan Project #5B Phase 2. Progress Summary: In 2018, project costs were escalated at 3% per year from 2015 to the year of construction. Future Impact on Operating Budget: None Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 166 STORM DRAINAGE FUND (462)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title:M Street NE Widening Project No:sdbd20 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Storm Revenue - - 50,000 - Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - 50,000 - Capital Expenditures: Design - - - 50,000 - Right of Way - - - - - Construction - - - - - - - - 50,000 - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Storm Revenue - 350,000 - - 400,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - 350,000 - - 400,000 Capital Expenditures: Design - - - - 50,000 Right of Way - - - - - Construction - 350,000 - - 350,000 - 350,000 - - 400,000 None This project will construction replace approximately 450 L.F. of undersized and deteriorated storm drain pipe and install approximatey 300 feet of new storm drain pipe with catch basins and manholes storm line. The project will be implemented as part of the transportation project: M Street NE Widening from E. Main Street to 4th Street NE. Progress Summary: Project scope developed in 2020. Future Impact on Operating Budget: Total Funding Sources: Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: City of Auburn Capital Facilities Plan 167 STORM DRAINAGE FUND (462)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title:West Main Street Pump Station Upgrade Project No:sdbd11 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2020 Budget Project Total Unrestricted Storm Revenue - - - - - Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Storm Revenue 850,000 2,514,000 - - 3,364,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - King County Opportunity Fund - 400,000 - - 400,000 850,000 2,914,000 - - 3,764,000 Capital Expenditures: Design 850,000 - - - 850,000 Right of Way - - - - - Construction - 2,914,000 - - 2,914,000 850,000 2,914,000 - - 3,764,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: This project will upgrade the existing pump station by providing a redundant pump, force main, and outlet to meet level of service goals. Comprehensive Plan Project #1. Progress Summary: In 2018, project costs were escalated at 3% per year from 2015 to the year of construction. In 2020, project implementation was moved from 2022-2023 to 2023-2024 for balance funding in the capital facilities plan period. Future Impact on Operating Budget: None City of Auburn Capital Facilities Plan 168 STORM DRAINAGE FUND (462)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title:Manhole & Catchbasin Frame and Grate Replacement Project No:sdbd21 Project Type:Non-Capacity (Repair and Replacement) Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Storm Revenue - 80,000 80,000 80,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - 80,000 80,000 80,000 Capital Expenditures: Design - 8,000 8,000 8,000 Right of Way - - - - Construction - 72,000 72,000 72,000 - - 80,000 80,000 80,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Storm Revenue 80,000 80,000 80,000 80,000 480,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - 80,000 80,000 80,000 80,000 480,000 Capital Expenditures: Design 8,000 8,000 8,000 8,000 48,000 Right of Way - - - - - Construction 72,000 72,000 72,000 72,000 432,000 80,000 80,000 80,000 80,000 480,000 Reduced risk of road hazard claims. As manholes & catchbasins age and their condition deteriorates, frame and grates can become loose and/or misoriented, or due to age are not meeting standards. This annual project will replace approximately 50 storm manhole and catchbasin frame and grates to maintain access to the storm system and to decrease the likelihood of the manholes becoming road hazards. In some years, this replacement will be as a stand-alone project, and in some years many of these replacements will be in conjunction with other City capital projects. Progress Summary: New program Future Impact on Operating Budget: Total Funding Sources: Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: City of Auburn Capital Facilities Plan 169 STORM DRAINAGE FUND (462)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title:Auburn Way North and 1st St NE Signal Replacement Project No:cp1927 Project Type:Non-Capacity Project Manager:Koshman Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Storm Revenue - 200,000 - 200,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - 200,000 - 200,000 Capital Expenditures: Design - - - - Right of Way - - - - Construction - 200,000 - 200,000 - - 200,000 - 200,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Storm Revenue - - - - 200,000 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other - - - - - - - - - 200,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 200,000 - - - - 200,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: This project addresses an existing storm-to-sanitary sewer cross connection(s) at the intersection of Auburn Way North and 1st Street SE with installation of new 12" storm pipes and manholes. The project is being implement with the transportation project that is replacing the traffic signal and curb ramps at the intersection. Progress Summary: Project design underway in 2020. Future Impact on Operating Budget: None City of Auburn Capital Facilities Plan 170 City of Auburn Capital Facilities Plan 171 PARKS, ARTS AND RECREATION Current Facilities The City of Auburn’s park system consists of a total of 953.39 acres of neighborhood and community parks, special use areas, open space and linear parks (trails). Table PR – 1 “Facilities Inventory” lists all park and recreation land in the City’s park system along with their current capacity and location. Level of Service (LOS) The current LOS provided by the City’s park system represents the existing inventory of City- owned park acres divided by the 2021 projected City population of 83,005. This equates to 0.78 acres per 1,000 population for neighborhood parks, 2.83 acres per 1,000 population for community parks, 0.20 acres for linear parks, 4.61 acres for open space, and 3.06 acres for special use areas. The proposed LOS provided by the City’s park system represents the planned 2026 inventory of City-owned park acres divided by the 2026 projected City population of 87,239. This equates to 0.85 acres per 1,000 population for neighborhood parks, 3.20 acres per 1,000 population for community parks, 0.23 acres per 1,000 population for linear parks, 4.44 acres per 1,000 population for open space, and 2.92 acres per 1,000 population for special use areas. Capital Facilities Projects and Financing Parks and Recreation facilities include eleven capacity projects at a cost of $12,843,850 and five non-capacity projects totaling $740,000 for a 6-year planning total of $13,583,850. Table PR – 2 shows the proposed financing plan followed by individual worksheets showing the project detail. Impact on Future Operating Budgets As Table PR – 3 shows, operating budget impacts of $103,000 are forecasted for parks and recreation facilities during the six years 2022 – 2027. City of Auburn Capital Facilities Plan 172 TABLE PR-1 Facilities Inventory Parks, Arts and Recreation, Land CAPACITY FACILITY (Acres)LOCATION Neighborhood Parks: Existing Inventory: 21st Street Playground 0.17 405 21st St. SE Auburndale Park 9.74 31802 108th Ave. SE Ballard Park 0.68 1612 37th Way SE Cameron Park 3.85 3727 Lemon Tree Lane Cedar Lane Park 8.36 1002 25th St. SE Dorothy Bothell Park 4.35 1087 Evergreen Way SE Dykstra Park 1.67 1487 22nd St. NE Forest Villa mini-park 0.21 1647 Fir St. SE Gaines Park 1.33 1008 Pike St. NW Indian Tom Park 0.42 1316 6th St. NE Jornada Park 1.89 1433 U Ct. NW Kersey 3 Park A 2.73 5480 Charlotte Ave. SE Kersey 3 Park B 0.79 5530 Udall Ave. SE Lakeland Hills Park 5.06 1401 Evergreen Way SE Lea Hill Courts 1.18 32121 105th Pl. SE Lewis Lake Nature Park 9.25 32054 58th Ave. S Riversands Park 1.76 5014 Pike St NE Rotary Park 3.89 2635 Alpine St. NE Scootie Brown Park 1.68 1403 Henry Rd. NE Shaughnessy Park 3.46 3302 21st St. SE Terminal Park 1.22 1292 C St. SE Village Square 1.10 12111 SE 310th St. Total Neighborhood Parks 64.79 Proposed Capacity Projects: Auburndale II Park 9.35 29700 118th Street SE Total Proposed Capacity Projects 9.35 2026 Projected Inventory Total - Neighborhood Parks -74.14 Community Parks: Existing Inventory: Brannan Park 21.68 1019 28th St. NE Fulmer Field 5.04 1101 5th St. NE Game Farm Park 57.20 3030 R St. SE Game Farm Wilderness Park 48.50 2407 Stuck River Dr. SE GSA Park 5.31 413 15th St. SW Isaac Evans Park 19.87 29627 Green River Road NE Lea Hill Park 5.26 31693 124th Ave. SE Les Gove Park 26.07 910 9th St. SE Mill Pond 4.20 4582 Mill Pond Dr, SE Roegner Park 19.22 601 Oravetz Road Sunset Park 15.15 1420 69th St SE Veteran's Memorial Park 7.67 405 E St. NE Total Community Parks 235.17 Proposed Capacity Projects: 104th Avenue SE 14.73 31495 104th Ave. SE Jacobson Tree Farm 29.30 29387 132nd Ave SE Total Proposed Capacity Projects 44.03 2026 Projected Inventory Total - Community Parks -279.20 City of Auburn Capital Facilities Plan 173 TABLE PR-1 (continued) Linear Parks: Existing Inventory: Interurban Trail 9.14 804 West Main St. Lake Tapps Parkway Trail 2.36 1420 69th St SE Lakeland Hills Trail 1.66 1087 Evergreen Way SE Reddington Levee Trail 2.50 1019 28th St NE White River Trail 0.93 601 Oravetz St. NE Total Linear Parks 16.59 Proposed Capacity Projects: Green River Trail 0.83 277th to Reddington Levee Trail Jacobsen Tree Farm to Green River Trail 2.75 White River Trail Extension 0.05 Total Proposed Capacity Projects 3.63 2026 Projected Inventory Total - Linear Parks -20.22 Special Use Areas: Existing Inventory: Auburn Environmental Park 16.84 413 Western Ave NW B Street Plaza 0.10 148 East Main St. Bicentennial Park 1.07 502 Auburn Way S. Centennial Viewpoint Park 0.70 402 Mountain View Dr. City Hall Plaza 1.10 25 West Main St. Clark Plaza 0.25 1420 Auburn Way N. Community Garden A 1.04 1030 8th St. NE Fenster/Green River Access 12.58 10502 Auburn Black Diamond Road Golf Course 139.71 29630 Green River Road SE Mountain View Cemetery 60.00 2020 Mountain View Dr. Olson Canyon Farmstead 20.00 28728 Green River Road Pioneer Cemetery 0.76 802 Auburn Way N, Plaza Park 0.19 2 West Main St. Slaughter Memorial 0.02 2988 Auburn Way N. Total Special Use Areas 254.36 Proposed Capacity Projects: None - Total Proposed Capacity Projects - 2026 Projected Inventory Total - Special Use Areas -254.36 Open Space Areas: Existing Inventory: Auburn Environmental Park Open Space 190.91 413 Western Ave. NW Clark Property 26.68 TBD Game Farm Open Space 26.00 3030 R St. SE Golf Course Open Space 40.98 29630 Green River Road SE Lakeland Hills Nature Area 46.07 500 182nd Ave. S Olson Canyon Open Space 47.00 28728 Green River Road Qares Property 0.99 TBD Riverpoint Open Space 3.85 1450 32nd St. NE Total Open Space Areas 382.48 Proposed Capacity Projects: West Hill Park Open Space 5.00 TBD Total Proposed Capacity Projects 5.00 2026 Projected Inventory Total - Open Space Areas -387.48 City of Auburn Capital Facilities Plan 174 TABLE PR-2 CAPITAL FACILITIES PLAN PROJECTS AND FINANCING PARKS, ARTS and RECREATION (Municipal Parks Construction Fund) 2021 2022 2023 2024 2025 2026 Total Page Capacity Projects: 177 Park Acquisitions/Development Capital Costs 30,000 30,000 50,000 125,000 125,000 125,000 485,000 Funding Sources: Fund Balance - - - - - - - Grants (Fed,State,Local)- - - - - - - Bond Proceeds - - - - - - - KC Prop 2 30,000 30,000 50,000 125,000 125,000 125,000 485,000 178 Jacobsen Tree Farm Development Capital Costs - 3,415,050 - - 5,000,000 - 8,415,050 Funding Sources: Fund Balance - - - - - - - Grants (Fed,State,Local)- 500,000 - - 1,000,000 - 1,500,000 KC Prop 2 - 333,500 - - - - 333,500 Other (TBD)- - - - 2,000,000 - 2,000,000 Park Impact Fees - 2,581,550 - - 2,000,000 - 4,581,550 179 West Hill Park Acquisition Capital Costs 800,000 - - - - - 800,000 Funding Sources: Fund Balance - - - - - - - Grants (Fed,State,Local)400,000 - - - - - 400,000 Park Impact Fees 400,000 - - - - - 400,000 180 Game Farm Park Improvements Capital Costs 1,000,000 - - - - - 1,000,000 Funding Sources: Park Mitigation Fees - - - - - - - Grants (Fed,State,Local)- - - - - - - REET 1 1,000,000 - - - - - 1,000,000 Park Impact Fees - - - - - - - 181 Auburndale Park Capital Costs 100,000 - - - - - 100,000 Funding Sources: Fund Balance - - - - - - - KC Prop 2 - - - - - - - Park Impact Fees 100,000 - - - - - 100,000 182 Auburndale Park II Capital Costs - - 575,000 - - - 575,000 Funding Sources: Fund Balance - - - - - - - Grants (Fed,State,Local)- - - - - - - Other - - 575,000 - - - 575,000 183 Sunset Park Improvements Capital Costs 177,800 - - - - - 177,800 Funding Sources: Fund Balance - - - - - - - Park Impact Fees 177,800 - - - - - 177,800 Other (Contributions)- - - - - - - 184 Cedar Lanes Bike Park Capital Costs 341,000 - - - - - 341,000 Funding Sources: Fund Balance - - - - - - - Grants (Fed,State,Local)118,000 - - 118,000 Park Impact Fees 223,000 - - - - - 223,000 City of Auburn Capital Facilities Plan 175 TABLE PR-2 (continued) 2021 2022 2023 2024 2025 2026 Total Page Capacity Projects: 185 BPA Trail on Lea Hill Capital Costs - - 150,000 - - - 150,000 Funding Sources: Fund Balance - - - - - - - Grants (Fed,State,Local)- - 150,000 - - - 150,000 KC Prop 2 - - - - - - - 186 Lakeland Hills Nature Area Capital Costs - - 25,000 - 75,000 100,000 200,000 Funding Sources: Fund Balance - - - - - - - Park Mitigation Fees - - - - - - - Park Impact Fees - - 25,000 - 75,000 100,000 200,000 187 Miscellaneous Parks Improvements Capital Costs 100,000 100,000 100,000 100,000 100,000 100,000 600,000 Funding Sources: Fund Balance 50,000 50,000 50,000 50,000 50,000 50,000 300,000 Grants (Fed,State,Local)- - - - - - - REET 2 - - - - - - - Park Impact Fees 50,000 50,000 50,000 50,000 50,000 50,000 300,000 Subtotal, Capacity Projects: Capital Costs 2,548,800 3,545,050 900,000 225,000 5,300,000 325,000 12,843,850 Page Non-Capacity Projects: 188 Cameron Park Capital Costs - - 55,000 - 55,000 - 110,000 Funding Sources: Fund Balance - - - - - - - Grants (Fed,State,Local)- - 55,000 - 55,000 - 110,000 Other - - - - - - - 189 Fulmer Park Playground Replacement Capital Costs - 150,000 - - - - 150,000 Funding Sources: Fund Balance - - - - - - - Grants (Private)- 50,000 - - - - 50,000 KC Prop 2 - 100,000 - - - - 100,000 190 Lea Hill Mini Soccer Field Turf Replacement Capital Costs 50,000 - - - - - 50,000 Funding Sources: Fund Balance - - - - - - - Grants (Fed,State,Local)50,000 - - - - - 50,000 Other - - - - - - - City of Auburn Capital Facilities Plan 176 TABLE PR-2 (continued) 2021 2022 2023 2024 2025 2026 Total Page Non-Capacity Projects: 191 Fairway Drainage Improvement Capital Costs 30,000 30,000 30,000 30,000 30,000 30,000 180,000 Funding Sources: Fund Balance - - - - - - - Grants (Fed,State,Local)- - - - - - - REET 2 30,000 30,000 30,000 30,000 30,000 30,000 180,000 192 Community Center Parking Lot Improvements Capital Costs 250,000 - - - - - 250,000 Funding Sources: Fund Balance - - - - - - - Grants (Fed,State,Local)- - - - - - - REET 1 250,000 - - - - - 250,000 Subtotal, Non-Capacity Projects: Capital Costs 330,000 180,000 85,000 30,000 85,000 30,000 740,000 2021 2022 2023 2024 2025 2026 Total SUMMARY: CAPITAL COSTS Capacity Projects 2,548,800 3,545,050 900,000 225,000 5,300,000 325,000 12,843,850 Non-Capacity Projects 330,000 180,000 85,000 30,000 85,000 30,000 740,000 Total Costs 2,878,800 3,725,050 985,000 255,000 5,385,000 355,000 13,583,850 FUNDING SOURCES: Fund Balance 50,000 50,000 50,000 50,000 50,000 50,000 300,000 Grants (Fed,State,Local)568,000 500,000 205,000 - 1,055,000 - 2,328,000 Grants -Private - 50,000 - - - - 50,000 KC Prop 2 30,000 463,500 50,000 125,000 125,000 125,000 918,500 Parks Impact 950,800 2,631,550 75,000 50,000 2,125,000 150,000 5,982,350 Parks Mitigation - - - - - - - REET 1 1,250,000 - - - - - 1,250,000 REET 2 30,000 30,000 30,000 30,000 30,000 30,000 180,000 Other - - 575,000 - 2,000,000 - 2,575,000 Total Funding 2,878,800 3,725,050 985,000 255,000 5,385,000 355,000 13,583,850 City of Auburn Capital Facilities Plan 177 MUNICIPAL PARKS CONSTRUCTION FUND (321)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Park Acquisitions/Development Project No:gpbd04 Project Type:Capacity Project Manager:Daryl Faber Description: Activity: (Previous 2 Yrs.)2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Fund 321 -Unrestricted Fund Balance - - - - - Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - REET1 - 656,790 - - 656,790 KC Prop 2 - 65,516 30,000 30,000 95,516 - 722,306 30,000 30,000 752,306 Capital Expenditures: Design - - - - - Acquisition 722,306 30,000 30,000 752,306 Construction - - - - - - 722,306 30,000 30,000 752,306 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Fund 321 -Unrestricted Fund Balance - - - - - Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - REET1 - - - - - KC Prop 2 50,000 125,000 125,000 125,000 485,000 50,000 125,000 125,000 125,000 485,000 Capital Expenditures: Design - - - - - Acquisition 50,000 125,000 125,000 125,000 485,000 Construction - - - - - 50,000 125,000 125,000 125,000 485,000 Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: Total Funding Sources: None Land and other property acquisitions to occur based on demand and deficiencies including parks, open space, trails, corridors and recreational facilities. Progress Summary: The City purchased the Auburn Avenue Theater in 2020 Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 178 MUNICIPAL PARKS CONSTRUCTION FUND (321)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Jacobsen Tree Farm Development Project No:cp0609, cp2020 Project Type:Capacity Project Manager:Daryl Faber Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Fund 321 -Unrestricted Fund Balance 25,321 - - - 25,321 Grants- Unsecured State - - - 500,000 - King County Prop 2 - 14,000 - 333,500 14,000 Park Impact Fees - - - 2,581,550 - Other (TBD)- - - - 25,321 14,000 - 3,415,050 39,321 Capital Expenditures: Design 25,321 14,000 - 300,000 39,321 Right of Way - - - - - Construction - - - 3,115,050 - 25,321 14,000 - 3,415,050 39,321 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Fund 321 -Unrestricted Fund Balance - - - - - Grants- Unsecured State - - 1,000,000 - 1,500,000 King County Prop 2 - - - - 333,500 Park Impact Fees - 2,000,000 4,581,550 Other (TBD)- - 2,000,000 - 2,000,000 - - 5,000,000 - 8,415,050 Capital Expenditures: Design - - 500,000 - 800,000 Right of Way - - - - - Construction - - 4,500,000 - 7,615,050 - - 5,000,000 - 8,415,050 Total Funding Sources: Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: Develop the 29.3 acre site into a Community Park. A Master Plan for the park was completed in 2009 and will serve as a roadmap for development of the site. The newly annexed Lea Hill area of the City is deficient in park acreage. Progress Summary: Future Impact on Operating Budget: No significant impact due to master plan. Future park development will result in maintenance and utility expenses undeterminable at this time. City of Auburn Capital Facilities Plan 179 MUNICIPAL PARKS CONSTRUCTION FUND (321)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: West Hill Park Acquisition Project No:gpbd27 Project Type:Capacity Project Manager:Jamie Kelly Description: Progress Summary: None Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Municipal Parks Construction Fund - - - - - KCCF Grant (Unsecured)- - 400,000 - 400,000 Bond Proceeds - - - - - REET - - - - - Park Impact Fees - - 400,000 - 400,000 Total Funding Sources:- - 800,000 - 800,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Acquisition - - 800,000 - 800,000 Total Expenditures:- - 800,000 - 800,000 Forecasted Project Cost: Total 2023 2024 2025 2026 2021-2026 Funding Sources: Municipal Parks Construction Fund - - - - - KCCF Grant (Unsecured)- - - - 400,000 Bond Proceeds - - - - - REET - - - - - Park Impact Fees - - - - 400,000 Total Funding Sources:- - - - 800,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Acquisition - - - - 800,000 Total Expenditures:- - - - 800,000 Grant funding will be from the King County Conservation Futures Grant. Acquire property on the West Hill for future park development. Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 180 MUNICIPAL PARKS CONSTRUCTION FUND (321)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Game Farm Park Improvements Project No:gpbd08, cp1720, cp1924 Project Type:Capacity Project Manager:Daryl Faber Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Fund 321 -Unrestricted Fund Balance 13,431 - - 13,431 Grants- Unsecured State - - - - - Grants- Secured Local -KCYSF - 150,000 - 150,000 REET - - 1,000,000 - 1,000,000 Other (Park Mitigation Fee)- - - - - Other (Park Impact Fee)40,000 294,010 - - 334,010 53,431 444,010 1,000,000 - 1,497,441 Capital Expenditures: Design - - 40,000 - 40,000 Right of Way - - - - - Construction 53,431 444,010 960,000 - 1,457,441 53,431 444,010 1,000,000 - 1,497,441 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Fund 321 -Unrestricted Fund Balance - - - - - Grants- Unsecured State - - - - - Grants- Secured Local -KCYSF - - - - - REET - - - - 1,000,000 Other (Park Mitigation Fee)- - - - - Other (Park Impact Fee)- - - - - - - - - 1,000,000 Capital Expenditures: Design - - - - 40,000 Right of Way - - - - - Construction - - - - 960,000 - - - - 1,000,000 Grants / Other Sources: King County Youth Sports Facilities Grant Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: Total Funding Sources: None Improve interior lighting and pathways and provide access from the newly acquired property on southwest corner of the park. The project will also replace synthetic turf on two full sized soccer fields. Progress Summary: Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 181 MUNICIPAL PARKS CONSTRUCTION FUND (321)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Auburndale Park Project No:gpbd01 Project Type:Capacity Project Manager:Daryl Faber Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Fund 321 -Unrestricted Fund Balance - - - - - Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other (Park Impact Fee)- - 100,000 - 100,000 Other (KC Prop 2)- - - - - - 100,000 - 100,000 Capital Expenditures: Design - - 5,000 - 5,000 Right of Way - - - - - Construction - - 95,000 - 95,000 - - 100,000 - 100,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Fund 321 -Unrestricted Fund Balance - - - - - Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Other (Park Impact Fee)- - - - 100,000 Other (KC Prop 2)- - - - - - - - - 100,000 Capital Expenditures: Design - - - - 5,000 Right of Way - - - - - Construction - - - - 95,000 - - - - 100,000 Progress Summary: Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: Total Funding Sources: Utilities would increase by $5,000 Develop a Master Plan for the Park, install an irrigation system, new play structure and improve signage. Create an entrance to the park from the east via 110th Ave SE to allow access from the adjacent neighborhoods. Construct new section of trail in the western portion of the park. Progress Summary: Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 182 MUNICIPAL PARKS CONSTRUCTION FUND (321)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Auburndale Park II Project No:gpbd05 Project Type:Capacity Project Manager:Daryl Faber Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Fund 321 -Unrestricted Fund Balance - - - - - Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - REET - - - - - Other TBD - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Fund 321 -Unrestricted Fund Balance - - - - - Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - REET - - - - - Other TBD 575,000 - - - 575,000 575,000 - - - 575,000 Capital Expenditures: Design 75,000 - - - 75,000 Right of Way - - - - - Construction 500,000 - - - 500,000 575,000 - - - 575,000 Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: Total Funding Sources: Description: Develop a Master Plan, improve the existing trail system and install signage and play structure. Progress Summary: Future Impact on Operating Budget: Increased utility costs of $2,000 City of Auburn Capital Facilities Plan 183 MUNICIPAL PARKS CONSTRUCTION FUND (321)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Sunset Park Improvements Project No:cp1921 Project Type:Capacity Project Manager:Daryl Faber Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Fund 321 -Unrestricted Fund Balance - - - - - Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Park Impact Fees 22,235 - 177,800 - 200,035 Other -Contributions & Donations - - - - - 22,235 - 177,800 - 200,035 Capital Expenditures: Design - - 15,000 - 15,000 Right of Way - - - - - Construction 22,235 - 162,800 - 185,035 22,235 - 177,800 - 200,035 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Fund 321 -Unrestricted Fund Balance - - - - - Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Park Impact Fees - - - - 177,800 Other -Contributions & Donations - - - - - - - - - 177,800 Capital Expenditures: Design - - - - 15,000 Right of Way - - - - - Construction - - - - 162,800 - - - - 177,800 Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: Total Funding Sources: Description: Expand playground area to include spray park and additional play activities. Coordinate improvements with service club and Lakeland Hills Homeowners Association. Progress Summary: Future Impact on Operating Budget: Increase in Utilities of $10,000 per year City of Auburn Capital Facilities Plan 184 MUNICIPAL PARKS CONSTRUCTION FUND (321)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Cedar Lanes Bike Park Project No:gpbd28 Project Type:Capacity Project Manager:Jamie Kelly Description: Progress Summary: None Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Municipal Parks Construction Fund - - - - - KC Youth Sports Grant (Secured)- - 118,000 - 118,000 Bond Proceeds - - - - - REET - - - - - Park Impact Fees - - 223,000 - 223,000 Total Funding Sources:- - 341,000 - 341,000 Capital Expenditures: Design - - 15,000 - 15,000 Right of Way - - - - - Construction - - 326,000 - 326,000 Total Expenditures:- - 341,000 - 341,000 Forecasted Project Cost: Total 2023 2024 2025 2026 2021-2026 Funding Sources: Municipal Parks Construction Fund - - - - - KC Youth Sports Grant (Secured)- - - - 118,000 Bond Proceeds - - - - - REET - - - - - Park Impact Fees - - - - 223,000 Total Funding Sources:- - - - 341,000 Capital Expenditures: Design - - - - 15,000 Right of Way - - - - - Construction - - - - 326,000 Total Expenditures:- - - - 341,000 Costruct a bike park and restroom at Cedar Lanes Park. Bike park to inlcude an asphalt pump track and skills course. Pedestrian trails in the park will also be improved Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 185 MUNICIPAL PARKS CONSTRUCTION FUND (321)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: BPA Trail on Lea Hill Project No:gpbd23 Project Type:Capacity Project Manager:Daryl Faber Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Fund 321 -Unrestricted Fund Balance - - - - - Grants- Unsecured (State RCO)- - - - Bond Proceeds - - - - - REET - - - - - Other (KC Prop. 2)*- - - - - - - - - - Capital Expenditures: Predesign - - - - Design - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Fund 321 -Unrestricted Fund Balance - - - - - Grants- Unsecured (State RCO)150,000 - - - 150,000 Bond Proceeds - - - - - REET - - - - - Other (KC Prop. 2)*- - - - - 150,000 - - - 150,000 Capital Expenditures: Predesign 25,000 - - - 25,000 Design 125,000 - - - 125,000 Construction - - - - - 150,000 - - - 150,000 Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: Total Funding Sources: None Develop a feasibility study related to constructability of a pedestrian trail linking the Jacobsen Tree Farm site to the west end of Lea Hill. This trail would follow the alignment of the Bonneville Power Administration (BPA) transmission lines from 132nd to 108th Avenue SE. Construction would be in phases based on constructability. Progress Summary: Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 186 MUNICIPAL PARKS CONSTRUCTION FUND (321)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Lakeland Hills Nature Area Project No:gpbd11 Project Type:Capacity Project Manager:Daryl Faber Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Fund 321 -Unrestricted Fund Balance - - - - - Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Park Impact Fees - - - - Park Mitigation Fees - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Fund 321 -Unrestricted Fund Balance - - - - - Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - Park Impact Fees 25,000 - 75,000 100,000 200,000 Park Mitigation Fees - - - - - 25,000 - 75,000 100,000 200,000 Capital Expenditures: Design 25,000 - - - 25,000 Right of Way - - - - - Construction - - 75,000 100,000 175,000 25,000 - 75,000 100,000 200,000 Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: Total Funding Sources: Increased maintenance costs of $5,000 Complete Master Plan to include the development and construction of an environmental community park. Trails, fencing, parking and visitor amenities are included in the project. Progress Summary: Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 187 MUNICIPAL PARKS CONSTRUCTION FUND (321)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Miscellaneous Parks Improvements Project No:gpbd03 Project Type:Capacity/Non-Capacity Project Manager:Daryl Faber Description: Activity: (Previous 2 Yrs.)2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Fund 321 -Unrestricted Fund Balance 30,715 80,000 50,000 50,000 160,715 Grants- Unsecured State - - - - - Local Grant - - - - - REET 2 - - - - - Other (Park Impact Fee)- 63,869 50,000 50,000 113,869 30,715 143,869 100,000 100,000 274,584 Capital Expenditures: Professional Services - - - - - Right of Way - - - - - Construction 30,715 143,869 100,000 100,000 274,584 30,715 143,869 100,000 100,000 274,584 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Fund 321 -Unrestricted Fund Balance 50,000 50,000 50,000 50,000 300,000 Grants- Unsecured State - - - - - Local Grant - - - - - REET 2 - - - - - Other (Park Impact Fee)*50,000 50,000 50,000 50,000 300,000 100,000 100,000 100,000 100,000 600,000 Capital Expenditures: Professional Services - - - - - Right of Way - - - - - Construction 100,000 100,000 100,000 100,000 600,000 100,000 100,000 100,000 100,000 600,000 Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: Total Funding Sources: None Minor park improvements including shelters, roofs, playgrounds, irrigation and restrooms. Progress Summary: Project funding includes the Mill Pond Dock Improvement (cp1915) in 2019 and the Brannan Park Kompan Soccer Field improvements (cp1706) in 2018 Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 188 MUNICIPAL PARKS CONSTRUCTION FUND (321)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Cameron Park Project No:gpbd24 Project Type:Non-Capacity Project Manager:Daryl Faber Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Fund 321 -Unrestricted Fund Balance - - - - - Grants- Unsecured Local - - - - - Bond Proceeds - - - - - REET - - - - - Other - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Fund 321 -Unrestricted Fund Balance - - - - - Grants- Unsecured Local 55,000 - 55,000 - 110,000 Bond Proceeds - - - - - REET - - - - - Other - - - - - 55,000 - 55,000 - 110,000 Capital Expenditures: Design 5,000 - 5,000 - 10,000 Right of Way - - - - - Construction 50,000 - 50,000 - 100,000 55,000 - 55,000 - 110,000 Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: Total Funding Sources: None This project will improve the pedestrian trail and add landscape and fencing to serve as buffer to the neighborhood and play structure. This project is identified in the Parks Improvement Plan. Progress Summary: Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 189 MUNICIPAL PARKS CONSTRUCTION FUND (321)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Fulmer Park Playground Replacement Project No:gpbd25 Project Type:Non-Capacity Project Manager:Jamie Kelly Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Municipal Parks Construction Fund - - - - - Grants- Kaboom - - - 50,000 - Bond Proceeds - - - - - REET - - - - - KC Prop 2 - - - 100,000 - - - - 150,000 - Capital Expenditures: Design - - - 7,500 - Right of Way - - - - - Construction - - - 142,500 - - - - 150,000 - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Municipal Parks Construction Fund - - - - - Grants- Kaboom - - - - 50,000 Bond Proceeds - - - - - REET - - - - - KC Prop 2 - - - - 100,000 - - - - 150,000 Capital Expenditures: Design - - - - 7,500 Right of Way - - - - - Construction - - - - 142,500 - - - - 150,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Replace aging playground. Progress Summary: Future Impact on Operating Budget: None City of Auburn Capital Facilities Plan 190 MUNICIPAL PARKS CONSTRUCTION FUND (321)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Lea Hill Mini Soccer Field Turf Replacement Project No:gpbd26 Project Type:Non-Capacity Project Manager:Daryl Faber Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Municipal Parks Construction Fund - - - - - Grants- Unsecured (Interlocal KCYSFG)- - 50,000 - 50,000 REET - - - - - Other - - - - - - - 50,000 - 50,000 Capital Expenditures: Design - - 2,500 - 2,500 Right of Way - - - - - Construction - - 47,500 - 47,500 - - 50,000 - 50,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Municipal Parks Construction Fund - - - - - Grants- Unsecured (Interlocal KCYSFG)- - - - 50,000 REET - - - - - Other - - - - - - - - - 50,000 Capital Expenditures: Design - - - - 2,500 Right of Way - - - - - Construction - - - - 47,500 - - - - 50,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Replace synthetic turf in the Kompan mini soccer field. Based on heavy use of this facility surface replacement is expected to be needed at approximate 5 year intervals. Progress Summary: Future Impact on Operating Budget: None City of Auburn Capital Facilities Plan 191 MUNICIPAL PARKS CONSTRUCTION FUND (321)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Fairway Drainage Improvement Project No:gpbd19, cp1911, cp2002 Project Type:Non-capacity Project Manager:Daryl Faber Description: Activity: (Previous 2 Yrs.)2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Municipal Parks Construction Fund 1,623 - - - 1,623 Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - REET 59,958 30,000 30,000 30,000 119,958 Other - - - - - 61,581 30,000 30,000 30,000 121,581 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction 61,581 30,000 30,000 30,000 121,581 61,581 30,000 30,000 30,000 121,581 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Municipal Parks Construction Fund - - - - - Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - REET 30,000 30,000 30,000 30,000 180,000 Other - - - - - 30,000 30,000 30,000 30,000 180,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction 30,000 30,000 30,000 30,000 180,000 30,000 30,000 30,000 30,000 180,000 Apply top dressing sand to the first five fairways in order to firm up these landing areas so that the holes are playable year round. Sand will be applied with a three yard topdressing machine. Sand will be applied bi/weekly at a tenth of an inch of sand throughout the fairways. Fairways will start to show improvements once four inches of sand are applied. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Progress Summary: Future Impact on Operating Budget: None City of Auburn Capital Facilities Plan 192 MUNICIPAL PARKS CONSTRUCTION FUND (321)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Community Center Parking Lot Improvements Project No:gpbd29 Project Type:Non-Capacity Project Manager:Jamie Kelly Description: Progress Summary: None Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Municipal Parks Construction Fund - - - - - Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - REET - - 250,000 - 250,000 Other - - - - - Total Funding Sources:- - 250,000 - 250,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - 250,000 - 250,000 Total Expenditures:- - 250,000 - 250,000 Forecasted Project Cost: Total 2023 2024 2025 2026 2021-2026 Funding Sources: Municipal Parks Construction Fund - - - - - Grants- Secured (Fed,State,Local)- - - - - Bond Proceeds - - - - - REET - - - - 250,000 Other - - - - - Total Funding Sources:- - - - 250,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 250,000 Total Expenditures:- - - - 250,000 Resurface the main drive that serves the Community and Event Center at Les Gove Park. The existing pervious concrete surface is deteriorated from weather and heavy use. Parks staff will work with Public Works and industry professionals to determine appropriate surfacing. Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 193 TABLE PR-3 Impact on Future Operating Budgets PARKS, ARTS & RECREATION - MUNICIPAL PARKS CONSTRUCTION Project:2022 2023 2024 2025 2026 2027 Total 1 Auburndale Park 5,000$ 5,000$ 5,000$ 5,000$ 5,000$ 5,000$ 30,000$ - 2 Auburndale Park II - - 2,000 2,000 2,000 2,000 8,000 3 Sunset Park 10,000 10,000 10,000 10,000 10,000 10,000 60,000 - - 4 Lakeland Hills Nature Area - - - - - 5,000 5,000 Total 15,000$ 15,000$ 17,000$ 17,000$ 17,000$ 22,000$ 103,000$ City of Auburn Capital Facilities Plan 194 SENIOR CENTER Current Facilities The City of Auburn currently has one Senior Center. Table PR-5 Facilities Inventory lists the facility along with its current capacity and location. Level of Service (LOS) The current LOS of 146.98 square feet per 1,000 population is based on the existing inventory divided by the 2021 citywide population of 83,005. The proposed LOS of 139.85 square feet per 1,000 population is based on the projected inventory divided by the 2026-projected citywide population of 87,239. Capital Facilities Projects and Financing The CFP does not include any senior center capital facilities projects during 2021-2026 Impact on Future Operating Budgets There are no operating budget impacts forecasted for the senior center facility during the six years 2022 – 2027. TABLE PR-5 Facilities Inventory Senior Center CAPACITY FACILITY (Square Feet)LOCATION Existing Inventory: Senior Center 12,200 808 9th Street SE Total Existing Inventory 12,200 Proposed Capacity Projects: None - Total Proposed Capacity Projects - 2026 Projected Inventory Total 12,200 City of Auburn Capital Facilities Plan 195 GENERAL MUNICIPAL BUILDINGS Current Facilities The current inventory of City government administration and operations facilities include 207,629 square feet for general government operations, 66,469 square feet for police services, and 38,646 square feet for fire protection, for a total of 312,744 square feet. Table GM – 1 “Facilities Inventory” lists the facilities along with their current capacity and location. Level of Service (LOS) The current LOS of 3,767.77 square feet per 1,000 population is based on the existing inventory divided by the 2021 citywide population of 83,005. The proposed LOS of 3,630.76 square feet per 1,000 population is based on the projected inventory divided by the 2026-projected citywide population of 87,239. Capital Facilities Projects and Financing The City’s General Municipal Building facilities include six capital projects at a cost of $3,719,820 and debt service at a cost of $3,941,500 for a total of $7,661,320. The major projects include (1) $1,440,000 for the Auburn Arts & Culture Center Renovation, (2) $470,000 for Equipment Rental Vehicle Maintenance Bay (3) $320,000 for M&O Fuel Tank and $3,941,500 for City Hall Annex debt service costs. Table GM – 2 shows the proposed financing plan followed by individual worksheets showing the project detail. Impact on Future Operating Budgets As Table GM-3 shows, operating budget impacts of $570,000 are forecasted for General Municipal buildings facilities during the six years 2022 - 2027. City of Auburn Capital Facilities Plan 196 TABLE GM-1 Facilities Inventory General Municipal Buildings CAPACITY FACILITY (Square Feet)LOCATION Existing Inventory: General Government: City Hall 61,721 25 W Main Street City Hall Annex 45,034 1 W Main Street City Maintenance & Operations Facility 17,940 1305 C Street SW Community Center 13,973 910 9th Street SE Municipal Court (Justice Center-Leased to King County)12,200 340 E Main Street Activity Center 10,074 910 9th Street SE Auburn Arts & Culture Center 8,744 100 Auburn Avenue Auburn Avenue Theater 7,560 10 Auburn Avenue Youth Center 7,132 910 9th Street SE Auburn Valley Humane Society -(Leased to AVHS)5,900 4910 A Street GSA Building 5,580 2905 C Street SW #815 R Street Building 4,977 2840 Riverwalk Drive Les Gove Storage Building 4,044 910 9th Street SE Street Waste Handling Facility 2,750 1305 C Street SW Total 207,629 Police: Gun range 32,880 1600 Block 15th St NW Headquarters (Justice Center)24,800 340 E Main Street R Street Building (Leased to Puget Sound Theft Task Force)4,789 2840 Riverwalk Drive Seized vehicle parking stalls 3,000 2905 C Street SW GSA Building 1,000 2905 C Street SW #815 Total 66,469 Fire: Stations: GSA Station #35 16,526 2905 C Street SW North Station #31 12,220 1101 D Street NE South Station #32 5,200 1951 R Street SE Other Facilities: North Station Maint. Facility 4,700 1101 D Street NE Total 38,646 Total Existing Inventory 312,744 Proposed Capacity Projects: Maintenance & Operations New Maintenance Bay 4,000 Total Proposed Capacity Projects 4,000 2026 Projected Inventory Total 316,744 City of Auburn Capital Facilities Plan 197 TABLE GM-2 CAPITAL FACILITIES PLAN PROJECTS AND FINANCING GENERAL MUNICIPAL BUILDINGS 2021 2022 2023 2024 2025 2026 Total Page Capacity Projects: 199 Auburn Arts & Culture Center Renovation Capital Costs 440,000 - 1,000,000 - - - 1,440,000 Funding Sources: Fund Balance - - - - - - - Grants 90,000 - 500,000 - - - 590,000 Other (Cumulative Reserve F122)- - - - - - - Other Park Impact Fees 350,000 - 500,000 - - - 850,000 Subtotal, Capacity Projects: Capital Costs 440,000 - 1,000,000 - - - 1,440,000 Non-Capacity Projects: 200 M & O Vehicle Storage Bay Improvements Capital Costs 200,000 - - - - - 200,000 Funding Sources: Equipment Rental Fund 55,000 - - - - - 55,000 Operating Transfer -Water 48,334 - - - - - 48,334 Operating Transfer -Sewer 48,333 - - - - - 48,333 Operating Transfer -Storm 48,333 - - - - - 48,333 201 Equipment Rental Vehicle Maintenance Bay Capital Costs 470,000 - - - - - 470,000 Funding Sources: Equipment Rental Fund 123,000 - - - - - 123,000 Operating Transfer -Water 115,666 - - - - - 115,666 Operating Transfer -Sewer 115,667 - - - - - 115,667 Operating Transfer -Storm 115,667 - - - - - 115,667 202 M&O Fuel Tank Replacement Capital Costs 320,000 - - - - - 320,000 Funding Sources: Equipment Rental Fund 80,000 - - - - - 80,000 Operating Transfer -Water 80,000 - - - - - 80,000 Operating Transfer -Sewer 80,000 - - - - - 80,000 Operating Transfer -Storm 80,000 - - - - - 80,000 203 M&O Lunchroom Expansion Capital Costs 150,000 - - - - - 150,000 Funding Sources: Equipment Rental Fund 40,000 - - - - - 40,000 Operating Transfer -Water 36,666 - - - - - 36,666 Operating Transfer -Sewer 36,667 - - - - - 36,667 Operating Transfer -Storm 36,667 - - - - - 36,667 204 HVAC Equipment Replacement Capital Costs 1,102,310 37,510 - - - - 1,139,820 Funding Sources: Operating Transfer -Facilities 371,470 37,510 - - - - 408,980 REET 1 730,840 - - - - - 730,840 City of Auburn Capital Facilities Plan 198 TABLE GM-2 (continued) 2021 2022 2023 2024 2025 2026 Total Page Non-Capacity Projects: 205 City Hall Annex Long-Term Debt 656,600 658,000 656,400 656,900 657,000 656,600 3,941,500 Funding Sources: REET 1 656,600 658,000 656,400 656,900 657,000 656,600 3,941,500 Subtotal, Non-Capacity Projects: Capital Costs 2,242,310 37,510 - - - - 2,279,820 SUMMARY: CAPITAL COSTS Capacity Projects 440,000 - 1,000,000 - - - 1,440,000 Non-Capacity Projects 2,242,310 37,510 - - - - 2,279,820 Long-Term Debt 656,600 658,000 656,400 656,900 657,000 656,600 3,941,500 Total Costs 3,338,910 695,510 1,656,400 656,900 657,000 656,600 7,661,320 FUNDING SOURCES: Equipment Rental Fund 298,000 - - - - - 298,000 Operating Transfer -Water 280,666 - - - - - 280,666 Operating Transfer -Sewer 280,667 - - - - - 280,667 Operating Transfer -Storm 280,667 - - - - - 280,667 Operating Transfer -Facilities 371,470 37,510 - - - - 408,980 Grants 90,000 - 500,000 - - - 590,000 Cumulative Reserve Fund 122 - - - - - - - Park Impact Fees 350,000 - 500,000 - - - 850,000 REET 1 1,387,440 658,000 656,400 656,900 657,000 656,600 4,672,340 Total Funding 3,338,910 695,510 1,656,400 656,900 657,000 656,600 7,661,320 City of Auburn Capital Facilities Plan 199 CAPITAL IMPROVEMENT FUND (328)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Auburn Arts & Culture Center Renovation Project No:cp1612 Project Type:Capacity Project Manager:Daryl Faber Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Fund Balance - - - - Grants- Secured (State)- 400,000 90,000 - 490,000 Grants- Secured (Local)264,042 143,808 - - 407,850 Grants - Local Unsecured - - - - Other -(Cumulative Reserve)- 42,200 - - 42,200 REET - - - - - Other (Park Impact Fee)5,418 494,582 350,000 - 850,000 269,460 1,080,590 440,000 - 1,790,050 Capital Expenditures: Design 66,021 55,000 - - 121,021 Right of Way - - - - - Construction 203,439 1,025,590 440,000 - 1,669,029 269,460 1,080,590 440,000 - 1,790,050 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Fund Balance - - - - - Grants- Secured (State)- - - - 90,000 Grants- Secured (Local)- - - - - Grants - Local Unsecured 500,000 - - - 500,000 Other -(Cumulative Reserve)- - - - - REET - - - - - Other (Park Impact Fee)500,000 - - - 850,000 1,000,000 - - - 1,440,000 Capital Expenditures: Design 75,000 - - - 75,000 Right of Way - - - - - Construction 925,000 - - - 1,365,000 1,000,000 - - - 1,440,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Renovation to the property and building located at 20 Auburn Avenue (100 Auburn Avenue) Building for the creation of an Arts & Culture Center in downtown Auburn. The renovation of this building will allow increased access to the arts for all of Auburn residents and visitors. Having a dedicated Art Center alongside the Auburn Avenue Theater performing arts series has the potential to transform Auburn into an arts tourism destination within the South Puget Sound. This project is a high priority for the City of Auburn and the purchase of this important building was completed in 2016. Progress Summary: The City has secured $898,000 in grant funding. The historic window restoration was completed in 2018, interior demolition started in 2019, and final renovation designs completed in 2020. It is anticipated that Phase 1 renovation of the main floor will begin in 2020 and continue through 2021. As a landmark building, exterior renovations must maintain the historic character of the building. Phase 2 renovations for the basement are expected to begin in 2023 at which time the City intends to apply for additional grant funds. Future Impact on Operating Budget: The annual operating budget fiscal impact is estimated to be $95,000. City of Auburn Capital Facilities Plan 200 EQUIPMENT RENTAL FUND (560)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: M&O Vehicle Storage Bay Improvements Project No:cp0711 Project Type: Project Manager:Tyler Thompson Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Equip. Rental Revenue 5,451 - 55,000 - 60,451 REET 1 - - - - - Other (Water, Sewer, Storm)- - 145,000 - 145,000 5,451 - 200,000 - 205,451 Capital Expenditures: Design - - 10,000 - 10,000 Right of Way - - - - - Construction 5,451 190,000 - 195,451 5,451 - 200,000 - 205,451 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Equip. Rental Revenue - - - - 55,000 REET 1 - - - - - Other (Water, Sewer, Storm)- - - - 145,000 - - - - 200,000 Capital Expenditures: Design - - - - 10,000 Right of Way - - - - - Construction - - - - 190,000 - - - - 200,000 Non-Capacity Total Funding Sources: Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: Enclose the 8 existing bays to provide necessary weather protection for street sweepers, vactors, sanding, and snow plow equipment. Construct storage shed to facilitate removal of portable containers, improving space utilization and traffic flow throughout M&O. Progress Summary: Future Impact on Operating Budget: None City of Auburn Capital Facilities Plan 201 EQUIPMENT RENTAL FUND (560)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Equipment Rental Vehicle Maintenance Bay Project No:cp1223 Project Type: Project Manager:Tyler Thompson Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Equip. Rental Revenue 29,276 - 123,000 - 152,276 REET 1 - - - - - Other (Water, Sewer, Storm)- - 347,000 - 347,000 29,276 - 470,000 - 499,276 Capital Expenditures: Design - - 22,000 - 22,000 Right of Way - - - - - Construction 29,276 448,000 - 477,276 29,276 - 470,000 - 499,276 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Equip. Rental Revenue - - - - 123,000 REET 1 - - - - - Other (Water, Sewer, Storm)- - - - 347,000 - - - - 470,000 Capital Expenditures: Design - - - - 22,000 Right of Way - - - - - Construction - - - - 448,000 - - - - 470,000 Non-Capacity Build additional vehicle bay at Equipment Rental shop for heavy equipment and large vehicles to improve efficiency and remove choke points. Adding a large vehicle bay with a large vehicle lift will enable us to perform inspections and maintenance on more than one large vehicle at a time, this becomes extremely important during emergency operations such as snow and ice events. The City currently has 2.5 maintenance bays, this project will add one more maintenance bay for a total of 3.5 bays. Progress Summary: Future Impact on Operating Budget: None Total Funding Sources: Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: City of Auburn Capital Facilities Plan 202 EQUIPMENT RENTAL FUND (560)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: M&O Fuel Tank Replacement Project No:erbd01 Project Type: Project Manager:Tyler Thompson Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Equip. Rental Revenue - - 80,000 - 80,000 REET 1 - - - - Other (Water, Sewer, Storm)- 240,000 - 240,000 - - 320,000 - 320,000 Capital Expenditures: Design - 25,000 - 25,000 Right of Way - - - - - Construction - 295,000 - 295,000 - - 320,000 - 320,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Equip. Rental Revenue - - - - 80,000 REET 1 - - - - - Other (Water, Sewer, Storm)- - - - 240,000 - - - - 320,000 Capital Expenditures: Design - - - - 25,000 Right of Way - - - - - Construction - - - - 295,000 - - - - 320,000 Total Funding Sources: Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: This project should reduce the operating budget due to lower maintenance and inspection costs. Non-Capacity Replace three 10,000 gallon underground tanks with new above ground tanks. The existing tanks were installed in 1989 and are single wall fiberglass tanks. It will be a benefit to the City to have the tanks above ground in the future due to the reduced maintenance and inspection cost. Progress Summary: Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 203 EQUIPMENT RENTAL FUND (560)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: M&O Lunchroom Expansion Project No:erbd02 Project Type: Project Manager:Tyler Thompson Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Equip. Rental Revenue - - 40,000 - 40,000 REET 1 - - - - - Other (Water, Sewer, Storm)- - 110,000 - 110,000 - - 150,000 - 150,000 Capital Expenditures: Design - - 10,000 - 10,000 Right of Way - - - - - Construction - 140,000 - 140,000 - - 150,000 - 150,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Equip. Rental Revenue - - - - 40,000 REET 1 - - - - - Other (Water, Sewer, Storm)- - - - 110,000 - - - - 150,000 Capital Expenditures: Design - - - - 10,000 Right of Way - - - - - Construction - - - - 140,000 - - - - 150,000 Total Funding Sources: Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: None Non-Capacity Expansion of the current lunchroom by redesigning the area to accommodate All-Staff meetings, provide for a training facility, lunch room and also serve as the Department Operations Center (DOC) during an emergency event. In addition, the design will include sliding doors which will allow the area to serve two purposes at once, for example, one half of the room being used as a DOC and the other half open to employees to use as a lunch/break room. Progress Summary: Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 204 CAPITAL IMPROVEMENT FUND (328)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: HVAC Equipment Replacement Project No:gcbd17 Project Type:Non-Capacity Project Manager:Lisa Moore Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Fund Balance - - - - Grants - Unsecured State - - - - - Grants - Local Unsecured - - - - - REET 1 - - 730,840 730,840 Facilities Fund-Transfer In - - 371,470 37,510 371,470 - - 1,102,310 37,510 1,102,310 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - 1,102,310 37,510 1,102,310 - - 1,102,310 37,510 1,102,310 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Fund Balance - - - - - Grants - Unsecured State - - - - - Grants - Local Unsecured - - - - - REET 1 - - - - 730,840 Facilities Fund-Transfer In - - - - 408,980 - - - - 1,139,820 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 1,139,820 - - - - 1,139,820 Replace HVAC Equipment at City Hall, Auburn Senior Center, Mountain View Cemetery, Arts & Culture Center building, Maintenance and Operations building and the Auburn Avenue Theater. Progress Summary: Future Impact on Operating Budget: This project will reduce operating costs through energy conservation and reduced maintenance and repair. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 205 CAPITAL IMPROVEMENT FUND (328)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: City Hall Annex Project No: Project Type: Project Manager: Description: Activity: (Previous 2 Yrs.)2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Fund Balance - - - - - Grants - Secured (Fed,State,Local)- - - - - REET 1 1,315,311 658,700 656,600 658,000 2,630,611 1,315,311 658,700 656,600 658,000 2,630,611 Capital Expenditures: Design - - - - - Construction - - - - - Long-Term Debt Service 1,315,311 658,700 656,600 658,000 2,630,611 1,315,311 658,700 656,600 658,000 2,630,611 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Fund Balance - - - - - Grants - Secured (Fed,State,Local)- - - - - REET 1 656,400 656,900 657,000 656,600 3,941,500 656,400 656,900 657,000 656,600 3,941,500 Capital Expenditures: Design - - - - - Construction - - - - - Long-Term Debt Service 656,400 656,900 657,000 656,600 3,941,500 656,400 656,900 657,000 656,600 3,941,500 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: To pay scheduled debt service costs on 2010 General Obligation bonds issued for the City Hall Annex. Progress Summary: Future Impact on Operating Budget: N/A City of Auburn Capital Facilities Plan 206 TABLE GM-3 Impact on Future Operating Budgets GENERAL MUNICIPAL BUILDINGS Project:2022 2023 2024 2025 2026 2027 Total 1 Auburn Arts & Culture Ctr. Renovation 95,000$ 95,000$ 95,000$ 95,000$ 95,000$ 95,000$ 570,000$ Total 95,000$ 95,000$ 95,000$ 95,000$ 95,000$ 95,000$ 570,000$ City of Auburn Capital Facilities Plan 207 COMMUNITY IMPROVEMENTS Current Facilities Community Improvements include sidewalk and traffic signal improvements, neighborhood traffic calming program, Main Street urban design improvements, public art and phase two of the Auburn Environmental Park Boardwalk project. Level of Service (LOS) No Level of Service for community improvement projects have been identified at this time. Capital Facilities Projects and Financing The City’s proposed Community Improvements include thirteen capital projects at a cost of $7,138,810 and debt service at a cost of 1,332,000 for a total of $8,470,810. Table CI-2 shows the proposed financing plan followed by individual work sheets showing the project detail. Impact on Future Operating Budgets As Table CI-3 shows, because of the City Street light LED retrofit program the operating budget will save approximately $795,000 for community improvement facilities during the six years 2022-2027. City of Auburn Capital Facilities Plan 208 TABLE CI-2 CAPITAL FACILITIES PLAN PROJECTS AND FINANCING COMMUNITY IMPROVEMENTS 2021 2022 2023 2024 2025 2026 Total Page Capacity Projects: 210 Auburn Way South (SR-164) - Southside Sidewalk Improvements Capital Costs - 95,000 750,000 - - - 845,000 Funding Sources: Capital Improvement Fund - - - - - - - Grants - 80,000 600,000 - - - 680,000 REET 2 - 15,000 150,000 - - - 165,000 211 104th Ave. Park Development Capital Costs 1,030,500 - - - - - 1,030,500 Funding Sources: Capital Improvement Fund - - - - - - - Grants 565,000 - - - - - 565,000 Other Park Impact Fees 465,500 - - - - - 465,500 212 Downtown Plaza Park Capital Costs 377,700 - - - - - 377,700 Funding Sources: Capital Improvement Fund - - - - - - - Other Park Impact Fees 145,230 - - - - - 145,230 Other -Developer Fees 232,470 - - - - - 232,470 Subtotal, Capacity Projects: Capital Costs 1,408,200 95,000 750,000 - - - 2,253,200 Non-Capacity Projects: 213 Public Art Capital Costs 30,000 30,000 30,000 30,000 30,000 30,000 180,000 Funding Sources: Capital Improvement Fund - - - - - - - REET 2 30,000 30,000 30,000 30,000 30,000 30,000 180,000 214 Citywide ADA & Sidewalk Improvements Capital Costs 185,000 - 200,000 200,000 200,000 200,000 985,000 Funding Sources: Capital Improvement Fund - REET 2 185,000 - 200,000 200,000 200,000 200,000 985,000 215 Lea Hill Safe Routes to Schools Capital Costs 70,000 950,000 - - - - 1,020,000 Funding Sources: Grants 55,000 700,000 - - - - 755,000 REET2 15,000 200,000 - 215,000 Other -Auburn School Dist.- 50,000 - - - - 50,000 216 Annual Traffic Signal Replacement & Improvements Capital Costs 200,000 100,000 200,000 100,000 200,000 200,000 1,000,000 Funding Sources: Capital Improvement Fund - - - - - - - REET 2 200,000 100,000 200,000 100,000 200,000 200,000 1,000,000 217 Citywide Street Lighting Improvements Capital Costs 50,000 50,000 50,000 50,000 50,000 50,000 300,000 Funding Sources: Capital Improvement Fund - - - - - - - REET 2 50,000 50,000 50,000 50,000 50,000 50,000 300,000 City of Auburn Capital Facilities Plan 209 TABLE CI-2 (continued) 2021 2022 2023 2024 2025 2026 Total Page Non-Capacity Projects: 218 City Street Lighting LED Retrofit Capital Costs 39,010 - - - - - 39,010 Funding Sources: Grants 2,010 - - - - - 2,010 REET 2 37,000 - - - - - 37,000 219 Neighborhood Traffic Calming Program Capital Costs 10,000 10,000 10,000 50,000 50,000 50,000 180,000 Funding Sources: Capital Improvement Fund - - - - - - - REET 2 10,000 10,000 10,000 50,000 50,000 50,000 180,000 220 City Wetland Mitigation Projects Capital Costs 36,600 5,000 5,000 5,000 5,000 5,000 61,600 Funding Sources: Capital Improvement Fund - - - - - - - Other (Fund 124-Wetland Mit.)36,600 5,000 5,000 5,000 5,000 5,000 61,600 221 Auburn Environmental Park Boardwalk -Phase 2 Capital Costs - - 75,000 800,000 - - 875,000 Funding Sources: Capital Improvement Fund - - - - - - - REET 2 - - 75,000 - - - 75,000 Other - To Be Determined - - - 800,000 - - 800,000 222 City Downtown Public Parking Lot Reconfiguration Capital Costs 245,000 - - - - - 245,000 Funding Sources: Local Revitalization Fund 245,000 - - - - - 245,000 Other - To Be Determined - - - - - - - 223 Local Revitalization Long Term Debt 225,000 223,700 222,000 219,800 222,300 219,200 1,332,000 Funding Sources: REET 2 225,000 223,700 222,000 219,800 222,300 219,200 1,332,000 Subtotal, Non-Capacity Projects: Capital Costs 865,610 1,145,000 570,000 1,235,000 535,000 535,000 4,885,610 SUMMARY: CAPITAL COSTS Capacity Projects 1,408,200 95,000 750,000 - - - 2,253,200 Non-Capacity Projects 865,610 1,145,000 570,000 1,235,000 535,000 535,000 4,885,610 Long-Term Debt 225,000 223,700 222,000 219,800 222,300 219,200 1,332,000 Total Costs 2,498,810 1,463,700 1,542,000 1,454,800 757,300 754,200 8,470,810 FUNDING SOURCES: Capital Improvement Fund 328 - - - - - - - Local Revitalization Fund 330 245,000 - - - - - 245,000 Grants 767,240 780,000 600,000 - - - 2,147,240 REET 2 752,000 628,700 937,000 649,800 752,300 749,200 4,469,000 Other -To Be Determined - - - 800,000 - - 800,000 Other -Auburn School Dist.- 50,000 - - - - 50,000 Other (Fund 124-Parks Impact)697,970 - - - - - 697,970 Other (Fund 124-Wetland Mit.)36,600 5,000 5,000 5,000 5,000 5,000 61,600 Total Funding 2,498,810 1,463,700 1,542,000 1,454,800 757,300 754,200 8,470,810 City of Auburn Capital Facilities Plan 210 CAPITAL IMPROVEMENT FUND (328)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Auburn Way South (SR-164) - Southside Sidewalk Improvements TIP# N-7 Project No:gcbd10 Project Type:Capacity, Non-motorized, Safety Project Manager:TBD Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Fund Balance - - - - - Grants - Unsecured - - - 80,000 - REET 2 - - - 15,000 - Other (Fund 102)- - - - - - - - 95,000 - Capital Expenditures: Design - - - 95,000 - Right of Way - - - - - Construction - - - - - - - 95,000 - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Fund Balance - - - - - Grants - Unsecured 600,000 - - - 680,000 REET 2 150,000 - - - 165,000 Other (Fund 102)- - - - - 750,000 - - - 845,000 Capital Expenditures: Design - - - - 95,000 Right of Way - - - - - Construction 750,000 - - - 750,000 750,000 - - - 845,000 Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Total Expenditures: Description: The project will construct missing sidewalk along the south side of Auburn Way S. The existing sidewalk along the south side currently ends at the intersection with Howard Road and restarts to the west of the intersection with Muckleshoot Plaza. The sidewalk gap extends for approximately 1,700 feet. The project also includes a Rapid Flashing Rectangular Beacon (RRFB) across Howard Road to provide a connection from the existing non-motorized facilities to the proposed improvements. Progress Summary: Grant funding for the project will be applied for in 2020. Depending on the funding source the design phase could occur in 2021 with construction of the improvements in 2022, or the design phase could start in 2023 with construction of the improvements in 2024. REET funding shown in the previous CFP in 2021 and 2022 has been moved to 2022 and 2023 respectively in this CFP, without any proposed increase. Future Impact on Operating Budget: This project will have no impact on the operating budget for street maintenance. City of Auburn Capital Facilities Plan 211 CAPITAL IMPROVEMENT FUND (328)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: 104th Ave. Park Development Project No: cp1619 Project Type: Capacity Project Manager: Jamie Kelly Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Cap Improve - - - - - Grants - Secured State - - 565,000 - 565,000 REET2 2,424 - - - 2,424 Other -Park Impact Fees 16,559 50,000 465,500 - 532,059 18,983 50,000 1,030,500 - 1,099,483 Capital Expenditures: Design 18,983 50,000 30,500 - 99,483 Construction - - 1,000,000 - 1,000,000 Long-Term Debt Service - - - - 18,983 50,000 1,030,500 - 1,099,483 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Cap Improve - - - - - Grants - Secured State - - - - 565,000 REET2 - - - - - Other -Park Impact Fees - - - - 465,500 - - - - 1,030,500 Capital Expenditures: Design - - - - 30,500 Construction - - - - 1,000,000 Long-Term Debt Service - - - - - - - - - 1,030,500 Complete Master Plan and construct park improvements identified in the Master Plan. Anticipated improvements include parking, trails, restroom, and playground. Work associated with permit approvals is also included in the budget. Progress Summary: The City was awarded a State grant from RCO where funds became available in June 2019. Park staff is currently working with design consultant team and Public Works to design the project. Design is anticipated to be completed in early 2021, and construction in Spring/Summer 2021. Future Impact on Operating Budget: The annual impact on the operating budget is estimated to be $10,000 for temporary wages and $2,500 for supplies. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 212 CAPITAL IMPROVEMENT FUND (328)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Downtown Plaza Park Project No:cp2016 Project Type:Capacity Project Manager:Jamie Kelly Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Cap Imp.- - - - - Developer Fees - 32,160 232,470 - 264,630 Other -Park Impact Fees - - 145,230 - 145,230 - 32,160 377,700 - 409,860 Capital Expenditures: Design - 32,160 17,025 - 49,185 Construction - - 360,675 - 360,675 Long-Term Debt Service - - - - - 32,160 377,700 - 409,860 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Cap Imp.- - - - - Developer Fees - - - - 232,470 Other -Park Impact Fees - - - - 145,230 - - - - 377,700 Capital Expenditures: Design - - - - 17,025 Construction - - - - 360,675 Long-Term Debt Service - - - - - - - - - 377,700 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: This project will renovate and improve the plaza area across from City Hall. Improvements will complement the new commercial building store fronts on the adjacent property that is being constructed in 2020. Improvement will include, but not be limited to seating, plantings, surfacing, and public art. Progress Summary: Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 213 CAPITAL IMPROVEMENT FUND (328)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Public Art Project No: gcbd05, cp1818 Project Type: Non-Capacity Project Manager: Julie Krueger Description: Activity: (Previous 2 Years)2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Fund Balance - - - - Grants - Secured (Fed,State,Local)- - - - - REET 2 163,000 97,500 30,000 30,000 290,500 Other - - - - - 163,000 97,500 30,000 30,000 290,500 Capital Expenditures: Design 62,500 - - - 62,500 Right of Way - - - - - Construction 100,500 97,500 30,000 30,000 228,000 163,000 97,500 30,000 30,000 290,500 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Fund Balance - - - - - Grants - Secured (Fed,State,Local)- - - - - REET 2 30,000 30,000 30,000 30,000 180,000 Other - - - - - 30,000 30,000 30,000 30,000 180,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction 30,000 30,000 30,000 30,000 180,000 30,000 30,000 30,000 30,000 180,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: None The City designates $30,000 annually toward the purchase of public art, for placement at designated locations throughout the City. Progress Summary: Arts Commission will meet to assess future needs and seek approval from City Council on placement. Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 214 CAPITAL IMPROVEMENT FUND (328)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Citywide ADA & Sidewalk Improvements TIP# N-2 Project No:cp1710, cp1804, cp1815, cp1902 gcbd01 Project Type:Non-Capacity (Annual) Project Manager:James Webb LOS Corridor ID# N/A Activity: (Previous 2 Yrs.)2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Fund Balance - - - - - Grants -Unsecured State 263,250 - - - 263,250 REET 2 376,595 200,000 185,000 - 761,595 Other 40,000 - - - 40,000 679,845 200,000 185,000 - 1,064,845 Capital Expenditures: Design 88,713 20,000 20,000 - 128,713 Right of Way - - - - - Construction 591,132 180,000 165,000 - 936,132 679,845 200,000 185,000 - 1,064,845 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Fund Balance - - - - - Grants -Unsecured State - - - - - REET 2 200,000 200,000 200,000 200,000 985,000 Other - - - - - 200,000 200,000 200,000 200,000 985,000 Capital Expenditures: Design 20,000 20,000 20,000 20,000 100,000 Right of Way - - - - - Construction 180,000 180,000 180,000 180,000 885,000 200,000 200,000 200,000 200,000 985,000 Description: The program will construct citywide accessibility improvements to the public right-of-way sidewalk system including adding/upgrading curb ramps, removing barriers to access and completing gaps. Projects are prioritized annually based on pedestrian demands, existing deficiencies, and citizen requests. Program funds reflect remaining budget after allocations to specific ADA and sidewalk improvement projects. Progress Summary: REET funding shown in the previous CFP in this program in 2021 and 2022 have been included in the Lea Hill Safe Routes to School Project (a project being completed under this program), without any increase. Future Impact on Operating Budget: This project will have no impact on the operating budget for street maintenance. Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 215 CAPITAL IMPROVEMENT FUND (328)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Lea Hill Safe Routes to Schools TIP# N-11 Project No:gcbd16 Project Type:Non-Motorized Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Fund Balance - - - - - Grants - Unsecured - - 55,000 700,000 55,000 Contributions - - - REET 2 - - 15,000 200,000 15,000 Other (ASD)- - - 50,000 - - - 70,000 950,000 70,000 Capital Expenditures: Design - - 70,000 - 70,000 Construction - - - - - Long-Term Debt Service - - - 950,000 - - - 70,000 950,000 70,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Fund Balance - - - - - Grants - Unsecured - - - - 755,000 Contributions - - - - - REET 2 - - - - 215,000 Other (ASD)- - - - 50,000 - - - - 1,020,000 Capital Expenditures: Design - - - - 70,000 Construction - - - - - Long-Term Debt Service - - - - 950,000 - - - - 1,020,000 Grants / Other Sources: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Total Expenditures: The project will construct non-motorized improvements along SE 304th St from Hazelwood Elementary School extending east to 124th Ave SE, and along the west side of 124th Ave SE to the south of SE 304th St. The project will complete multiple gaps in the existing non-motorized network. The project will also construct curb and gutter, ADA compliant curb ramps, driveways aprons and retaining walls associated with the new sidewalks. Utility poles will need to be relocated to accommodate the proposed sidewalk alignment in some locations. Additional lighting is proposed for pedestrian safety and will be incorporated onto existing/relocated utility poles, and an RRFB will be installed at the SE 304th St intersection with 116th Ave SE. Ancillary work, including but not limited to, property restoration, grading, storm upgrades, school zone beacon relocation, channelization, fencing, landscaping and mailbox relocation will be addressed with the project. Progress Summary: Grant funding will be applied for in 2020. If secured, the design phase will be started in 2021 and construction completed during 2022. REET funding included in the previous CFP under the Citywide ADA & Sidewalk Improvements Project (gcbd01) are shown in this project and the corresponding reduction in REET funds are reflected in gcbd01. Future Impact on Operating Budget: This project will have no impact on the operating budget for street maintenance. City of Auburn Capital Facilities Plan 216 CAPITAL IMPROVEMENT FUND (328)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Annual Traffic Signal Replacement & Improvements TIP# I-2 Project No:cp1813, cp1906, cp2004, gcbd07 Project Type:Non-Capacity (Annual) Project Manager:Scott Nutter LOS Corridor ID# N/A Activity: (Previous 2 Yrs.)2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Fund Balance - - - - - Grants - Unsecured (Fed,State,Local)- - - - - REET 2 278,443 100,000 200,000 100,000 578,443 Other - - - - - 278,443 100,000 200,000 100,000 578,443 Capital Expenditures: Design 22,877 - - - 22,877 Right of Way - - - - - Construction 255,566 100,000 200,000 100,000 555,566 278,443 100,000 200,000 100,000 578,443 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Fund Balance - - - - - Grants - Unsecured (Fed,State,Local)- - - - - REET 2 200,000 100,000 200,000 200,000 1,000,000 Other - - - - - 200,000 100,000 200,000 200,000 1,000,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction 200,000 100,000 200,000 200,000 1,000,000 200,000 100,000 200,000 200,000 1,000,000 Description: The program will replace end of life capital facilities replacement for traffic signal and Intelligent Transportation System equipment including cabinets, video detection cameras, field network devices, traffic cameras, battery backup components, and other related equipment. The program also includes minor safety improvements, operations improvements, and Accessible Pedestrian Signal Improvements based on the requirements of the Americans with Disabilities Act (ADA). Progress Summary: Project continues to complete various intersection improvements. REET funding in 2022 and 2024 has been reduced annually by $100k from what was approved in the previous CFP. Future Impact on Operating Budget: This project will have a positive impact on the operating budget for street maintenance, reducing maintenance costs. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 217 CAPITAL IMPROVEMENT FUND (328)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Citywide Street Lighting Improvements TIP# I-4 Project No: cp1928, cp2005, gcbd09 Project Type:Non-Capacity Project Manager:Scott Nutter Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Fund Balance - - - - - Grants - Secured (Fed,State,Local)- - - - - REET 2 33,725 50,000 50,000 50,000 133,725 33,725 50,000 50,000 50,000 133,725 Capital Expenditures: Design - - - - - Construction 33,725 50,000 50,000 50,000 133,725 Long-Term Debt Service - - - - - 33,725 50,000 50,000 50,000 133,725 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Fund Balance - - - - - Grants - - - - - REET 2 50,000 50,000 50,000 50,000 300,000 50,000 50,000 50,000 50,000 300,000 Capital Expenditures: Design - - - - - Construction 50,000 50,000 50,000 50,000 300,000 Long-Term Debt Service - - - - - 50,000 50,000 50,000 50,000 300,000 The project constructs lighting improvements throughout the City, including upgrading decorative street lights not converted to LED with the 2020 conversion project, and installing new street lights. Progress Summary: Annual REET funding reduced by $50,000 since previous approved CFP. Future Impact on Operating Budget: New street lights installed with this program will increase the City's street light power costs but this increase will be offset by decreased power costs as existing standard street lights are converted to LED. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 218 CAPITAL IMPROVEMENT FUND (328)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: City Street Light LED Retrofit TIP# I-17 Project No: cp1920 Project Type:Non-Capacity Project Manager:Scott Nutter Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Fund Balance - - - - - Grants - Secured Federal - 497,990 2,010 - 500,000 Contributions 350,000 - - 350,000 REET 2 - 1,813,000 37,000 - 1,850,000 - 2,660,990 39,010 - 2,700,000 Capital Expenditures: Design - 112,294 - - 112,294 Construction - 2,548,696 39,010 - 2,587,706 Long-Term Debt Service - - - - - - 2,660,990 39,010 - 2,700,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Fund Balance - - - - - Grants - Secured Federal - - - - 2,010 Contributions - REET 2 - - - - 37,000 - - - - 39,010 Capital Expenditures: Design - - - - - Construction - - - - 39,010 Long-Term Debt Service - - - - - - - - - 39,010 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: The project will convert all City owned cobra-head street lights to LED. This phase of the project will convert all City owned cobra- head street lights to LED and add smart lighting control technology. Federal grant funding for this phase of the project was awarded in 2019. Future phases to upgrade other types of City street lights (such as decorative residential and downtown decorative lights) to LED will be considered as additional funding is available. Progress Summary: A detailed audit of all existing City owned lights and the design phase of the project have been completed. The construction phase of the project is programmed to begin during Spring 2020. REET funds shown in 2021 reflect anticipated carry forward of 2020 funds to complete project in 2021. Future Impact on Operating Budget: Annual savings in power usage is anticipated to be $130,000 per year. Additional maintenance savings will be realized in the reduction of materials for light replacement and is estimated to be $20,000 per year. City of Auburn Capital Facilities Plan 219 CAPITAL IMPROVEMENT FUND (328)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Neighborhood Traffic Safety Program TIP# R-1 Project No:cp1814, cp1907, cp2013, gcbd06 Project Type:Non-Capacity (Annual) Project Manager:Scott Nutter Activity: (Previous 2 Yrs.)2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Fund Balance - - - - - Grants - Unsecured (Fed,State,Local)- - - - - REET 2 76,198 10,000 10,000 10,000 96,198 Other - - - - - 76,198 10,000 10,000 10,000 96,198 Capital Expenditures: Design 76,198 1,000 1,000 1,000 78,198 Right of Way - - - - - Construction - 9,000 9,000 9,000 18,000 76,198 10,000 10,000 10,000 96,198 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Fund Balance - - - - - Grants - Unsecured (Fed,State,Local)- - - - - REET 2 10,000 50,000 50,000 50,000 180,000 Other - - - - - 10,000 50,000 50,000 50,000 180,000 Capital Expenditures: Design 1,000 5,000 5,000 5,000 18,000 Right of Way - - - - - Construction 9,000 45,000 45,000 45,000 162,000 10,000 50,000 50,000 50,000 180,000 Description: This program will implement low-cost traffic calming strategies, supported by engineering studies as necessary. Projects will be selected annually based on requests from residents, or police concerns, crash history, and available staff and financial resources. Progress Summary: Staffing constraints and limited resources make this program challenging to administer. Traffic calming strategies and approaches are being updated to be more sustainable, and adapted to the limited resources (staff and financial) available. REET funding has been reduced by $140k annually starting in 2021 from the approved amount shown in the previous CFP. Future Impact on Operating Budget: The traffic calming program will have no impact on the operating budget for street maintenance. Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Total Expenditures: City of Auburn Capital Facilities Plan 220 CAPITAL IMPROVEMENT FUND (328)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: City Wetland Mitigation Projects Project No:cp1315 Project Type:Non-Capacity Project Manager:Jeff Tate Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Fund Balance - - - - - Grants - Secured (Fed,State,Local)- - - - - Fund 124 Wetland Mitigation Account 6,969 5,000 36,600 5,000 48,569 REET - - - - - 6,969 5,000 36,600 5,000 48,569 Capital Expenditures: Design - 10,000 - 10,000 Monitoring 1,868 5,000 5,000 5,000 11,868 Construction 5,101 21,600 - 26,701 6,969 5,000 36,600 5,000 48,569 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Fund Balance - - - - - Grants - Secured (Fed,State,Local)- - - - - Fund 124 Wetland Mitigation Account 5,000 5,000 5,000 5,000 61,600 REET - - - - - 5,000 5,000 5,000 5,000 61,600 Capital Expenditures: Design - - - - 10,000 Monitoring 5,000 5,000 5,000 5,000 30,000 Construction - - - - 21,600 5,000 5,000 5,000 5,000 61,600 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: This project designs and constructs off-site wetland mitigation in the Auburn Environmental Park for participating development projects as approved through the City's development review process. Design, construction, monitoring, and maintenance of the mitigation is funded through wetland mitigation fees collected by the City. Progress Summary: Future Impact on Operating Budget: After construction, each wetland mitigation site will be monitored and maintained for a period of three to five years, depending on the specific requirements for the project. Funding for future year monitoring and maintenance is included in the development fees collected by the City, and is budgeted as part of the Capital Facilities Plan. Replacement plantings for Auburn Airport tree removal conducted in 2013. Design and construction of mitigation for other development sites deferred to 2021. Years 2019-2024 scheduled for site monitoring only. City of Auburn Capital Facilities Plan 221 CAPITAL IMPROVEMENT FUND (328)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Auburn Environmental Park Boardwalk - Phase 2 Project No:cp1611 Project Type:Non-Capacity Project Manager:Jeff Tate Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Fund Balance - - - - - Grants - Unsecured State - - - - - Grants - Local Unsecured - - - - - REET 2 - - - - - Other -TBD - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Fund Balance - - - - - Grants - Unsecured State - - - - - Grants - Local Unsecured - - - - - REET 2 75,000 - - - 75,000 Other -TBD - 800,000 - - 800,000 75,000 800,000 - - 875,000 Capital Expenditures: Design 75,000 - - - 75,000 Right of Way - - - - - Construction - 800,000 - - 800,000 75,000 800,000 - - 875,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: The Auburn Environmental Park (AEP) provides vegetated natural open space within an urbanized area. The AEP provides opportunities for local economic development, water quality improvement, storm water detention, flood control, fish and wildlife enhancement, visual resources, public education, and passive recreation, including walking trails and bird viewing amenities. In 2012, the City completed the construction of approximately 1,200 lineal feet of the first phase (Phase 1) of an elevated boardwalk trail in the Auburn Environmental Park (AEP). This trail extended from West Main Street through existing wetlands in the AEP terminating at the base of the Bird Viewing Tower constructed in 2009. As part of the construction of the elevated boardwalk, the City also installed interpretative signage, bench seating, limited new vehicle parking on Western Avenue and over two acres of wetland species of trees, plants and shrubs. Phase 2 of the elevated boardwalk trail would construct a combination of up to approximately 2,000 lineal feet of surface trail and elevated boardwalk trail from the current terminus at the Bird Viewing Tower to a connection with the Interurban Trail. The Phase 2 project will further previous and current Councils’ visions of the AEP providing passive recreation and environmental education opportunities for all Auburn citizens. Progress Summary: Design for this project is scheduled to start in fall of 2023. Future Impact on Operating Budget: Construction of the Phase 2 project is anticipated to incur approximately $10,000 in annual operating costs to the City’s operating budget. Operating costs are addressed in the Environmental Services portion of the Community Development and Public Works Department operating budget. City of Auburn Capital Facilities Plan 222 LOCAL REVITALIZATION FUND (330)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: City Downtown Public Parking Lot Reconfiguration Project No: cp1616 Project Type: Non-Capacity Project Manager: Ingrid Gaub Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Local Revitalization Fund 330 17,329 - 245,000 - 262,329 Grants- Secured (Fed,State,Local)- - - - - REET - - - - - Other -Contributions - - - - - 17,329 - 245,000 - 262,329 Capital Expenditures: Design - - - - Right of Way - - - - - Construction 17,329 - 245,000 - 262,329 17,329 - 245,000 - 262,329 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Local Revitalization Fund 330 - - - - 245,000 Grants- Secured (Fed,State,Local)- - - - - REET - - - - - Other -Contributions - - - - - - - - - 245,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 245,000 - - - - 245,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Reconfigure the City owned public parking lot between Safeway and Main Street to address pedestrian and vehicular circulation; remove existing landscaping to allow more flexibility in the parking lot redesign; explore whether more parking stalls can be added to the lot to aid in providing additional customer parking within Downtown Auburn; and resurface the parking lot. Progress Summary: Monies to improve the parking lot adjacent to Safeway and the B Street Plaza were used to create safety and aesthetic improvements to the plaza. New catenary lighting and planters were added to the plaza as a short- to medium-term improvement. The lighting increases safety and the planters were added to delineate walking paths and create visual interest. Completion of design and construction is delayed until the Heritage Building is addressed. Future Impact on Operating Budget: None anticipated as the City already maintains the parking lot. City of Auburn Capital Facilities Plan 223 CAPITAL IMPROVEMENT FUND (328)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Capital Projects Fund Project Title: Local Revitalization Project No: Project Type: Project Manager: Description: Activity: (Previous 2 Yrs.)2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Fund Balance - - - - Grants - Secured (Fed,State,Local)- - - - - REET 2 457,909 220,600 225,000 223,700 903,509 457,909 220,600 225,000 223,700 903,509 Capital Expenditures: Design - - - - - Construction - - - - - Long-Term Debt Service 457,909 220,600 225,000 223,700 903,509 457,909 220,600 225,000 223,700 903,509 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Fund Balance - - - - - Grants - - - - - REET 2 222,000 219,800 222,300 219,200 1,332,000 222,000 219,800 222,300 219,200 1,332,000 Capital Expenditures: Design - - - - - Construction - - - - - Long-Term Debt Service 222,000 219,800 222,300 219,200 1,332,000 222,000 219,800 222,300 219,200 1,332,000 To pay debt service costs on 2010 General Obligation bonds issued for the Downtown Promenade improvements. Progress Summary: Future Impact on Operating Budget: N/A Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 224 TABLE CI-3 Impact on Future Operating Budgets COMMUNITY IMPROVEMENTS Project:2022 2023 2024 2025 2026 2027 Total 1 104th Ave. Park Development 12,500$ 12,500$ 12,500$ 12,500$ 12,500$ 12,500$ 75,000$ 2 AEP Boardwalk -Phase 2 - - - 10,000 10,000 10,000 30,000 3 City Street Light LED Retrofit (150,000) (150,000) (150,000) (150,000) (150,000) (150,000) (900,000) Total (137,500)$ (137,500)$ (137,500)$ (127,500)$ (127,500)$ (127,500)$ (795,000)$ City of Auburn Capital Facilities Plan 225 AIRPORT Current Facilities The City of Auburn operates the Auburn Municipal Airport, providing hangar and tie-down facilities/leasing space for aircraft-related businesses. As of 2017, there were approximately 142,000 take-offs and landings (aircraft operations) at the airport annually. Table A-1 “Facilities Inventory” lists the facilities with current capacity and location. The Airport Master Plan was completed in May 2015 for the period 2012 through 2032. Level of Service (LOS) The Auburn Municipal Airport Master Plan provides a maximum runway capacity (LOS standard) of 231,000 aircraft operations annually; one take-off or landing equals one aircraft operation. This LOS is recognized by the Federal Aviation Administration (FAA). The FAA requires the airport to have the capital facilities capacity (i.e., runways, taxiways, holding areas, terminal, hangars, water/sewer system, etc.) necessary to accommodate 100% of aircraft operations during any one year. By 2022, the Airport Master Plan forecasts the number of operations to be 198,623 – well below the capacity of the airport runway. Capital Facilities Projects and Financing The City’s Airport facilities include ten non-capacity projects totaling $16,491,360. These include the Runway/Taxiway Rehab, RSA grading & Precision Approach Path Indicator (PAPI) project, hangar facility construction project, open T-hangar upgrades, and Airport office/middle ramp reconfigure project. Table A-2 shows the proposed financing plan followed by individual worksheets showing the project detail. Impact on Future Operating Budgets As Table A-3 shows, operating budget impacts of $12,000 are forecasted for Airport facilities during the six years 2022 – 2027. TABLE A-1 Facilities Inventory Airport FACILITY # of Aircraft # of Feet LOCATION Existing Inventory: Hangars (Public)145 2143 E Street NE Hangars (Private)103 2143 E Street NE Tiedowns 153 2143 E Street NE Runway 3,841 2143 E Street NE Total Existing Inventory 401 3,841 Proposed Capacity Projects: Private Hangar Development 23 - 2143 E Street NE Total Proposed Capacity Projects 23 - 2026 Projected Inventory Total 424 3,841 CAPACITY City of Auburn Capital Facilities Plan 226 TABLE A-2 CAPITAL FACILITIES PLAN PROJECTS AND FINANCING AIRPORT 2021 2022 2023 2024 2025 2026 Total Capacity Projects: None - Page Non-Capacity Projects: 228 Annual Repair and Maintenance of Airport Facilities Capital Costs 100,000 150,000 500,000 100,000 200,000 238,800 1,288,800 Funding Sources: Airport Fund 100,000 150,000 500,000 100,000 200,000 238,800 1,288,800 Grants - - - - - - - 229 Jet A Fueling Facility Capital Costs - 50,000 350,000 - - - 400,000 Funding Sources: Airport Fund - 25,000 175,000 - - - 200,000 Other Agencies - 25,000 175,000 - - - 200,000 Grants - - - - - - - 230 AWOS, Beacon & Emergency Generator Capital Costs - - - 111,110 1,050,000 - 1,161,110 Funding Sources: Airport Fund - - - 5,555 52,500 - 58,055 Grants - - - 105,555 997,500 - 1,103,055 231 Annual Airport Pavement Maintenance Capital Costs 25,000 50,000 - 50,000 50,000 100,000 275,000 Funding Sources: Airport Fund 25,000 50,000 - 50,000 50,000 100,000 275,000 Grants - - - - - - - 232 Hangar Facility Construction Capital Costs 2,750,000 - - - - - 2,750,000 Funding Sources: Airport Fund - - - - - - - Bond Proceeds 2,750,000 - - - - - 2,750,000 233 Open T-Hangar Upgrades Capital Costs - 1,060,900 - - - - 1,060,900 Funding Sources: Airport Fund - - - - - - - Bond Proceeds - 1,060,900 - - - - 1,060,900 234 Runway/Taxiway Rehab, RSA Grading & PAPI project Capital Costs - 444,440 3,111,110 - - - 3,555,550 Funding Sources: Airport Fund - 22,220 155,555 - - - 177,775 Grants - 422,220 2,955,555 - - - 3,377,775 235 Property Access to Airport Capital Costs - - - - 50,000 - 50,000 Funding Sources: Airport Fund - - - - 50,000 - 50,000 Grants - - - - - - - City of Auburn Capital Facilities Plan 227 TABLE A-2 (continued) 2021 2022 2023 2024 2025 2026 Total Non-Capacity Projects: 236 Precision Instrument Approach Capital Costs - 25,000 25,000 - - - 50,000 Funding Sources: Airport Fund - 25,000 25,000 - - - 50,000 Other Agencies - - - - - - - 237 Airport Office / Middle Ramp Reconfigure Capital Costs - - 75,000 75,000 5,750,000 - 5,900,000 Funding Sources: Airport Fund - - 7,500 7,500 575,000 - 590,000 Other Agencies - - 67,500 67,500 5,175,000 - 5,310,000 SUMMARY: CAPITAL COSTS Capacity Projects - - - - - - - Non-Capacity Projects 2,875,000 1,780,340 4,061,110 336,110 7,100,000 338,800 16,491,360 Total Costs 2,875,000 1,780,340 4,061,110 336,110 7,100,000 338,800 16,491,360 FUNDING SOURCES: Airport Fund 125,000 272,220 863,055 163,055 927,500 338,800 2,689,630 Other Agencies - 25,000 242,500 67,500 5,175,000 - 5,510,000 Bond Proceeds 2,750,000 1,060,900 - - - - 3,810,900 Grants (Fed,State,Local)- 422,220 2,955,555 105,555 997,500 - 13,601,730 Total Funding 2,875,000 1,780,340 4,061,110 336,110 7,100,000 338,800 16,491,360 City of Auburn Capital Facilities Plan 228 AIRPORT FUND (465)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Annual Repair and Maintenance of Airport Facilities Project No:apbd05, cp1931 Project Type:Non-Capacity Project Manager:TBD Description: Activity: (Previous 2 Years)2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Airport Revenue 9,211 190,789 100,000 150,000 300,000 Grants (Fed,State,Local)- - - - - Other - - - - - 9,211 190,789 100,000 150,000 300,000 Capital Expenditures: Design - 20,000 20,000 25,000 40,000 Right of Way - - - - - Construction 9,211 170,789 80,000 125,000 260,000 9,211 190,789 100,000 150,000 300,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Airport Revenue 500,000 100,000 200,000 238,800 1,288,800 Grants (Fed,State,Local)- - - - - Other - - - - - 500,000 100,000 200,000 238,800 1,288,800 Capital Expenditures: Design 100,000 20,000 40,000 45,000 250,000 Right of Way - - - - - Construction 400,000 80,000 160,000 193,800 1,038,800 500,000 100,000 200,000 238,800 1,288,800 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: Due to the current conditions of the Facilities at the Airport, this program provides for necessary maintenance and repair work such as slab sealing, roof replacement, hangar beam replacement, painting, electrical repairs, etc. for buildings identified in the 2018 Facility Condition Assessment as being in "Fair" to "Good" condition. Repair and maintenance of these facilities will help prolong the service life of these buildings. Progress Summary: Program began in 2017. In 2018, a Facilities Condition Assessment was completed. Future Impact on Operating Budget: This project will decrease the need for more costly repairs and maintenance on older buildings. City of Auburn Capital Facilities Plan 229 AIRPORT FUND (465)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Jet A Fueling Facility Project No:apbd04 Project Type:Non-Capacity Project Manager:Ingrid Gaub Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Airport Revenue - - - 25,000 Other Agencies - - - 25,000 - State Grant -Unsecured - - - - - - - - 50,000 - Capital Expenditures: Design - - - 50,000 - Right of Way - - - - - Construction - - - - - - - - 50,000 - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Airport Revenue 175,000 - - - 200,000 Other Agencies 175,000 - - - 200,000 State Grant -Unsecured - - - - - 350,000 - - - 400,000 Capital Expenditures: Design - - - - 50,000 Right of Way - - - - - Construction 350,000 - - - 350,000 350,000 - - - 400,000 Construct any necessary site improvements to accommodate a temporary 2,000 gallon fueling truck for Jet A fuel on site in 2018. Design and Construct a permanent 12,000 gallon Fuel Tank for Jet A service at Airport in 2022 and 2023 after the runway extension is complete and demand for Jet A fuel is established. The funding will be split 50% between the airport and a private party. Progress Summary: Due to the delay on the completion of the Runway, this project has been moved to 2022. Future Impact on Operating Budget: None Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 230 AIRPORT FUND (465)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: AWOS, Beacon & Emergency Generator Project No:cpxxxx Project Type:Non-Capacity Project Manager:Ingrid Gaub Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Airport Revenue - - - - - Federal - Non-Primary Entitlements - - - - - Federal- Unsecured - - - - - State Grant -Unsecured - - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Airport Revenue - 5,555 52,500 - 58,055 Federal - Non-Primary Entitlements - 100,000 200,000 - 300,000 Federal- Unsecured - - 745,000 - 745,000 State Grant -Unsecured - 5,555 52,500 - 58,055 - 111,110 1,050,000 - 1,161,110 Capital Expenditures: Design - 111,110 225,000 - 336,110 Right of Way - - - - - Construction - - 825,000 - 825,000 - 111,110 1,050,000 - 1,161,110 Grants / Other Sources:Federal Aviation Administration and Washington State Department of Transportation Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: This project will fund the environmental, design and construction of an Automated Weather Observation System (AWOS), Beacon and emergency generator. This will be funded at 90% by the FAA Progress Summary: After discussion with the FAA this project was expanded to include beacon and emergency generator expenses. Future Impact on Operating Budget: $2,000 annually for on-going maintenance and repair City of Auburn Capital Facilities Plan 231 AIRPORT FUND (465)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Annual Airport Pavement Maintenance Project No:apbd12 Project Type: Non-Capacity Project Manager: Tim Mensonides Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Airport Revenue - 25,000 25,000 50,000 25,000 Grants (Fed,State,Local)- - - - - Other - - - - - - 25,000 25,000 50,000 25,000 Capital Expenditures: Design - 2,000 2,000 5,000 4,000 Right of Way - - - - - Construction - 23,000 23,000 45,000 46,000 - 25,000 25,000 50,000 50,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Airport Revenue - 50,000 50,000 100,000 275,000 Grants (Fed,State,Local)- - - - - Other - - - - - - 50,000 50,000 100,000 275,000 Capital Expenditures: Design - 5,000 5,000 10,000 27,000 Right of Way - - - - - Construction - 45,000 45,000 90,000 248,000 - 50,000 50,000 100,000 275,000 Grants / Other Sources: This project will complete pavement maintenance and preservation activities for the Airport Runway, Taxiways and other paved surfaces at the Auburn Airport to maintain the facilities in adequate operational conditions Progress Summary: Future Impact on Operating Budget: None Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 232 AIRPORT FUND (465)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Hangar Facility Construction Project No:apbd10, cp1932 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Airport Revenue - 50,000 - - 50,000 Bond Revenue - - 2,750,000 - 2,750,000 Grants (Fed,State,Local)- - - - - Other (Public/Private Partnership)- - - - - - 50,000 2,750,000 - 2,800,000 Capital Expenditures: Design - 50,000 250,000 - 300,000 Right of Way - - - - - Construction - - 2,500,000 - 2,500,000 - 50,000 2,750,000 - 2,800,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Airport Revenue - - - - - Bond Revenue - - - - 2,750,000 Grants (Fed,State,Local)- - - - - Other (Public/Private Partnership)- - - - - - - - - 2,750,000 Capital Expenditures: Design - - - - 250,000 Right of Way - - - - - Construction - - - 2,500,000 - - - - 2,750,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: There is significant demand for hangar space in the Puget Sound region. The airport currently has a hangar wait list with over 90 names on it. This project would construct a new row of T hangars on the Airport's southeast tie down ramp. Progress Summary: Working with our consultant on the type of hangar facilities needed at the Airport and a refined estimated cost. Future Impact on Operating Budget: Utilization of 3.8 million dollar bond issued in 2021 to fund construction. In 2022 hangar revenues increase $204,000 annually. City of Auburn Capital Facilities Plan 233 AIRPORT FUND (465)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Open T-Hangar Upgrades Project No:apbd14 Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Airport Revenue - - - - - Bond Revenue - - - 1,060,900 - Grants (Fed,State,Local)- - - - - Other (Public/Private Partnership)- - - - - - - - 1,060,900 - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - 1,060,900 - - - - 1,060,900 - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Airport Revenue - - - - - Bond Revenue - - - - 1,060,900 Grants (Fed,State,Local)- - - - - Other (Public/Private Partnership)- - - - - - - - - 1,060,900 Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - 1,060,900 - - - - 1,060,900 Due to the current conditions of the hangar facilities at the Airport, this program will replace or upgrade hangar facilities as they reach the end of their service life. A Facility Condition Assessment was completed in 2018. In 2019 an in depth analysis of the hangars' structure and roofing was conducted with a recommendation to not replace but upgrade the structures. The demand on the airport is greater for closed hangars vs open units. This project will convert 2 open rows to closed hangars and increase airport revenues at approximately $100,000 annually. This will allow for 2 open rows to remain on the airport and provide greater hangar options for airport tenants. Progress Summary: Future Impact on Operating Budget: Utilization of 3.8 million dollar bond issued in 2021 to fund construction. In 2023 hangar revenues increase $100,000 annually. Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 234 AIRPORT FUND (465)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Runway/Taxiway Rehab, RSA Grading & PAPI project Project No:apbd13 Project Type: Non-Capacity Project Manager: Tim Mensonides Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Airport Revenue - - - 22,220 Federal -Non Primary Entitlement - - - 400,000 Grants unsecured -Federal - - - - - Grants unsecured - State - - - 22,220 - - - - 444,440 - Capital Expenditures: Design - - - 444,440 - Right of Way - - - - - Construction - - - - - - - - 444,440 - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Airport Revenue 155,555 - - - 177,775 Federal -Non Primary Entitlement 200,000 - - - 600,000 Grants unsecured -Federal 2,600,000 - - - 2,600,000 Grants unsecured - State 155,555 - - - 177,775 3,111,110 - - - 3,555,550 Capital Expenditures: Design 466,600 - - - 911,040 Right of Way - - - - - Construction 2,644,510 - - - 2,644,510 3,111,110 - - - 3,555,550 Grants / Other Sources: Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: This project will complete a Fog seal of on the Airport Taxiways to extend the life of the pavement and complete rehabilitation of the Runway to prolong the useful life of the Runway. This project will also complete necessary improvements to the property purchased from the Park and Ride to be in compliance with the FAA requirements for the Runway Safety Area. In addition the project will install Precision Approach Path Indicator (PAPI) for Runway to replace aging Visual Approach Slope Indicator (VASI) system. Progress Summary: After discussion with the FAA this project combined the Runway/Taxiway Rehab, the RSA Grading and the PAPI project into one project as part of the 2021 -2026 Capital Facilities Plan. Future Impact on Operating Budget: $2,000 annually for PAPI on-going maintenance and repair City of Auburn Capital Facilities Plan 235 AIRPORT FUND (465)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Property Access to Airport Project No:cpxxx Project Type:Non-Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Airport Revenue - - - - - Grants (Fed,State,Local)- - - - - Other (Public/Private Partnership)- - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Airport Revenue - - 50,000 - 50,000 Grants (Fed,State,Local)- - - - - Other (Public/Private Partnership)- - - - - - - 50,000 - 50,000 Capital Expenditures: Design - - 50,000 - 50,000 Right of Way - - - - - Construction - - - - - - - 50,000 - 50,000 Enter into a through the fence agreement for access to the Airport. Progress Summary: Future Impact on Operating Budget: None Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 236 AIRPORT FUND (465)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Precision Instrument Approach Project No:apbd15 Project Type:Non -Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Airport Revenue - - - 25,000 - Bond Revenue - - - - - Grants (Fed,State,Local)- - - - - Other (Public/Private Partnership)- - - - - - - - 25,000 - Capital Expenditures: Design - - - 25,000 - Right of Way - - - - - Construction - - - - - - - - 25,000 - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Airport Revenue 25,000 - - - 50,000 Bond Revenue - - - - - Grants (Fed,State,Local)- - - - - Other (Public/Private Partnership)- - - - 25,000 - - - 50,000 Capital Expenditures: Design 25,000 - - - 50,000 Right of Way - - - - - Construction - - - - - 25,000 - - - 50,000 Approval process with the FAA to improve the airport's instrument approach. Progress Summary: Future Impact on Operating Budget: None Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 237 AIRPORT FUND (465)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Airport Office / Middle Ramp Reconfigure Project No:cpxxx Project Type:Non -Capacity Project Manager:TBD Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Airport Revenue - - - - - Bond Revenue - - - - - Grants (Fed,State,Local)- - - - - Other (Public/Private Partnership)- - - - - - - - - - Capital Expenditures: Design - - - - - Right of Way - - - - - Construction - - - - - - - - - - Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Airport Revenue 7,500 7,500 575,000 - 590,000 Bond Revenue - - - - Grants (Fed,State,Local)- - - - - Other (Public/Private Partnership)67,500 67,500 5,175,000 - 5,310,000 75,000 75,000 5,750,000 - 5,900,000 Capital Expenditures: Design 75,000 75,000 - - 150,000 Right of Way - - - - - Construction - 5,750,000 - 5,750,000 75,000 75,000 5,750,000 - 5,900,000 This project will reconfigure the Airport office and parking lot area to allow for additional development of an Airport based aviation business /restaurant. 10/90% split with the airport and private party. Progress Summary: Future Impact on Operating Budget: None Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: City of Auburn Capital Facilities Plan 238 TABLE A-3 Impact on Future Operating Budgets AIRPORT Project:2022 2023 2024 2025 2026 2027 Total 1 Automated Weather Observation System, Beacon & Emergency Generator -$ -$ -$ -$ 2,000$ 2,000$ 4,000$ 2 Precision Approach Path Indicator (PAPI) for Runway - - 2,000 2,000 2,000 2,000 8,000 Total -$ -$ 2,000$ 2,000$ 4,000$ 4,000$ 12,000$ City of Auburn Capital Facilities Plan 239 CEMETERY Current Facilities The City owns two cemeteries. The Mountain View Cemetery is a fully developed facility (60 acres and five buildings) that provides burial services and related merchandise for the community. The Pioneer Cemetery is a historic cemetery that is no longer used for burial purposes. Table C-1 “Facilities Inventory” lists the facilities along with their current capacity and location. Level of Service (LOS) The current LOS of 33 burial plots/niches and cremation in ground plots per 1,000 population is based on the existing inventory divided by the estimated 2021 citywide population of 83,005. The proposed LOS of 33 burial and plots/niches and cremation in ground plots per 1,000 population is based on the projected inventory divided by the 2026-projected citywide population of 87,239. Capital Facilities Projects and Financing The City’s Mountain View Cemetery facilities includes one capital projects costing $395,000 to build a new mausoleum. Table C-2 shows the proposed financing plan followed by the worksheet showing the project detail. Impact on Future Operating Budgets There are no operating budget impacts forecast for the cemetery during the six years 2022 – 2027. TABLE C-1 Facilities Inventory Cemetery CAPACITY FACILITY # of Plots/Niches LOCATION Existing Inventory: Mountain View Cemetery 2,771 2020 Mountain View Dr. Pioneer Cemetery - 8th & Auburn Way No. Total Existing Inventory 2,771 Proposed Capacity Projects: New Development - Burial Plots 96 Total Proposed Capacity Projects 96 2025 Projected Inventory Total 2,867 City of Auburn Capital Facilities Plan 240 TABLE C-2 CAPITAL FACILITIES PLAN PROJECTS AND FINANCING CEMETERY 2021 2022 2023 2024 2025 2026 Total Page Capacity Projects: 241 Mausoleum Building Capital Costs 40,000 - 355,000 - - - 395,000 Funding Sources: Cemetery Fund 40,000 - 355,000 - - - 395,000 Cemetery Endowed Care - - - - - - - SUMMARY: CAPITAL COSTS Capacity Projects 40,000 - 355,000 - - - 395,000 Non-Capacity Projects - - - - - - - Total Costs 40,000 - 355,000 - - - 395,000 FUNDING SOURCES: Cemetery Fund 40,000 - 355,000 - - - 395,000 Cemetery Endowed Care - - - - - - - Total Funding 40,000 - 355,000 - - - 395,000 City of Auburn Capital Facilities Plan 241 CEMETERY FUND (466)Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Enterprise Funds Project Title: Mausoleum Building Project No:cp1831 Project Type:Capacity Project Manager:Craig Hudson Description: Activity: 2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Unrestricted Cemetery Revenue 2,250 10,000 40,000 - 52,250 Bond Proceeds - - - - - Cemetery Endowed Care - - - - - 2,250 10,000 40,000 - 52,250 Capital Expenditures: Design 2,250 10,000 40,000 - 52,250 Right of Way - - - - - Construction - - - - - 2,250 10,000 40,000 - 52,250 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Unrestricted Cemetery Revenue 355,000 - - - 395,000 Bond Proceeds - - - - - Cemetery Endowed Care - - - - - 355,000 - - - 395,000 Capital Expenditures: Design - - - - 40,000 Right of Way - - - - - Construction 355,000 - - - 355,000 355,000 - - - 395,000 Total Expenditures: Total Funding Sources: Total Expenditures: Forecasted Project Cost: Total Funding Sources: This project will design and construct a 72 crypt and 48 niche mausoleum for above ground internment option. The public has expressed desire to have this option available as the current mausoleum is at capacity. Progress Summary: Project design is planned to be completed in 2021 and construction to begin in 2023. Future Impact on Operating Budget: City of Auburn Capital Facilities Plan 242 City of Auburn Capital Facilities Plan 243 FIRE PROTECTION Current Facilities The Valley Regional Fire Authority provides fire protection and rescue services to a 40-square mile area which includes the City of Auburn, the City of Algona, the City of Pacific and King County Fire Protection District 31. The Valley Regional Fire Authority operates out of five stations, which are manned 24 hours per day. The North Station #31 also serves as the department headquarters and includes a hose and training tower. Each station is assigned fire apparatus (Engines and Aid Vehicles). Table F–1 “Facilities Inventory” lists the facilities along with their current capacity and location. Level of Service (LOS) The current LOS of 0.20 fire apparatus per 1,000 population is based on the existing inventory (17 fire apparatus) divided by the 2021 citywide population estimate of 83,005. The proposed LOS of 0.21 fire apparatus per 1,000 is based on the 2026-planned inventory (18 fire apparatus) divided by the 2026-projected citywide population of 87,239. Capital Facilities Projects and Financing The Valley Regional Fire Authority includes one capital project at a cost of $1,625,000 for fire apparatus enhancements and improvements. Table F-2 shows the proposed financing plan followed by an individual worksheet showing the project detail. Impact on Future Operating Budgets There are no operating budget impacts forecasted for fire protection during the six years 2022 – 2027. City of Auburn Capital Facilities Plan 244 TABLE F-1 Facilities Inventory Valley Regional Fire Authority FACILITY Fire Apparatus Aid Vehicles LOCATION Existing Inventory: Stations: North Station #31 1101 'D' Street NE, Auburn First Line 2 1 Reserve - 1 South Station #32 1951 'R' Street SE, Auburn First Line 1 1 Reserve 1 1 Lakeland Station #33 500 182nd Ave E, Auburn First Line 1 - Reserve 1 - Lea Hill Station #34 31290 124th Ave SE, Auburn First Line 1 - Brush Truck 1 - Reserve 1 - GSA Station #35 2815 C St SW, Auburn Reserve 1 1 Pacific Station #38 133 3rd Ave SE, Pacific First Line 1 - Reserve 1 - Total Existing Inventory 12 5 Proposed Inventory Additions: First Line 1 - Total Proposed Capacity Projects 1 - 2025 Projected Inventory Total 13 5 CAPACITY City of Auburn Capital Facilities Plan 245 TABLE F-2 CAPITAL FACILITIES PLAN PROJECTS AND FINANCING VALLEY REGIONAL FIRE AUTHORITY 2021 2022 2023 2024 2025 2026 Total Capacity Projects: Fire Station Facility Relocation, Enhancements & Improvements Capital Costs 75,000 1,250,000 75,000 75,000 75,000 75,000 1,625,000 Funding Sources: Grants - - - - - - - Other Proceeds (VRFA)- 750,000 - - - - 750,000 Impact/Mitigation Fees 75,000 500,000 75,000 75,000 75,000 75,000 875,000 SUMMARY: CAPITAL COSTS Capacity Projects - - - - - - - Non-Capacity Projects 75,000 1,250,000 75,000 75,000 75,000 75,000 1,625,000 Total Costs 75,000 1,250,000 75,000 75,000 75,000 75,000 1,625,000 FUNDING SOURCES: Grants (Fed,State,Local)- 750,000 - - - - 750,000 Impact/Mitigation Fees 75,000 500,000 75,000 75,000 75,000 75,000 875,000 Total Funding 75,000 1,250,000 75,000 75,000 75,000 75,000 1,625,000 City of Auburn Capital Facilities Plan 246 Valley Regional Fire Authority Capital Facilities Plan Six Year Capital Facilities Plan, 2021-2026 Project Title: Fire Station Facility Relocation, Enhancements & Improvements Project No:cpxxxx Project Type:Capacity Project Manager:Mark Horaski Description: Activity: (Previous 2 Yrs.)2020 YE 2021 Year End Funding Sources:Prior to 2020 Estimate 2021 Budget 2022 Budget Project Total Grants - - - - - Other Proceeds (VRFA)- - - 750,000 - Impact/Mitigation Fees 50,000 75,000 75,000 500,000 200,000 50,000 75,000 75,000 1,250,000 200,000 Capital Expenditures: Design - - - - - Right of Way - - - - - Aerial Apparatus Acquisition 50,000 75,000 75,000 1,250,000 200,000 50,000 75,000 75,000 1,250,000 200,000 Total 2023 2024 2025 2026 2021-2026 Funding Sources: Grants - - - - - Other Proceeds (VRFA)- - - - - Impact/Mitigation Fees 75,000 75,000 75,000 75,000 875,000 75,000 75,000 75,000 75,000 875,000 Capital Expenditures:- Design - - - - - Right of Way - - - - - Aerial Apparatus Acquisition 75,000 75,000 75,000 75,000 1,625,000 75,000 75,000 75,000 75,000 1,625,000 Facility Improvement projects are identified and prioritized annually and are subject to delay to accommodate emergency repairs. The Valley Regional Fire Authority includes one project for apparatus enhancements and improvements. Progress Summary: Fire mitigation and impact fees will be transferred to the Valley Regional Fire Authority to pay for apparatus enhancements and improvements. Future Impact on Operating Budget: Total Funding Sources: Total Expenditures: Total Expenditures: Total Funding Sources: Forecasted Project Cost: None