HomeMy WebLinkAboutMatrixAIRPORT ADVISORY COMMITTEE PROJECT - GOAL MATRIX # PROJECT LEAD Est. COST REVIEW EST. STATUS DESCRIPTION DATE COMPL. DATE 3 Hangar Rows 9 & Steve $200,000 3/21/2012 TBD Steve has changed and moved up bid schedule to secure 10 roof Burke /AMG /Robert contractor. Revised schedule sent out 11/2011. Jones 7 Noise Complaints AMG 0 2/15/2012 One helicopter noise compliant over Covington area 9 Airport Security AMG TBD 2/15/2012 TBD Discussed with City Legal Department on converting the Update access gates controlled by Condo Associations to City control. Steve Gross reviewing documents from lease agreements and development agreements to verify the language used (if any) regarding access gates (both auto and personnel). 10 Aircraft Wash Rack Tim Carlaw /Chris TBD 2/15/2012 TBD Investigating converting a closed hangar into wash area. Anderson /AMG One bid came in at $30,000.00. Discussed with numerous City staff on idea and received input from City staff. Steve Burke to come out to review the idea and give input and ideas. 11 Airport Master Plan Coleman /AMG TBD 3/21/2012 TBD Contact made with FAA and State to begin process for Mid -Term Update beginning the process in June 2012. Grant money available for the process (95% FAA 2.5% State) 12 Occupancy Rates AMG -0- 2/15/2012 NA • Row 9/10 36/40 (90 %) no change • Row 2 Full (14) (100 %) no change • Row 8 5/6 (6) (83 %) no change • Rows 3 -7 56/85 (66 %) down 1 • Storage Units 9/12 Full (75 %) down 1 • Tie down 35/100 full (35 %) down 1 13 General Airport Board Only TBD 3/21/2012 NA Event to showcase Auburn Airport, e.g. WWI —II Event aircraft. Static display /food /sale vendors/ flights. 14 Fuel Dispenser AMG $10,000 2/15/2012 3/31/2011 Order placed for fuel dispenser. Lead time is 60 to Replacement 90 days. Discussed installation with AirBP and asked for their assistance on -site when installed and Last Revision Date: 1/13/2012 AIRPORT ADVISORY COMMITTEE PROJECT - GOAL MATRIX COMPLETED # PROJECT LEAD Est. COST REVIEW COMPL. prior to switch over. There will be one day that fuel DESCRIPTION DATE DATE will not be available. Will post at gates when that 2 Airport Rules and AMG 0 10/20/2010 9/20/2010 date is schedule and issue NOTAM. 15 Aircraft Accident AMG TBD 2/15/2012 3/31/2012 Add to the Airport Security plan an Aircraft 7 Emergency Plan AMG 0 10/20/2010 12/31/2010 Recovery Plan. Contacted Jeff at AvTech to be part and Recover Plan of the process. AvTec is located on the airport and 1 Airport Storm Reid $50,000 4/20/2011 is an accident recovery company for aircraft. Will Water Design Middleton /AMG also ask AFS shop to participate. Additionally the Update plan will include RVFA and include training with 4 Runway Lighting Steve $350,000 7/20/2011 6/2/2011 them (annually). 16 Update Airport Tim Carlaw /Chris TBD 2/15/2012 3/31/2012 Mr. Anderson and Tim Carlaw will work the Reid Storm water Anderson /RM Middleton and update the plan for the industrial 5 "SWWPP" Plan Robert 0 4/8/2011 permit at the airport. Documents given to Anderson Retention Ponds Lee /Storm and RM. Contract with RM is in place to update the SWWPP and scope of work. COMPLETED # PROJECT LEAD Est. COST REVIEW COMPL. STATUS DESCRIPTION DATE DATE 2 Airport Rules and AMG 0 10/20/2010 9/20/2010 Second committee review (finance) for council approval on Regulations 9/20/2010 7 MIA Appraisal AMG 0 10/20/2010 12/31/2010 MAI appraisal for raw and improved land leases at the Auburn Airport for implementation 1/1/2011 1 Airport Storm Reid $50,000 4/20/2011 Completed Water Design Middleton /AMG Update 4 Runway Lighting Steve $350,000 7/20/2011 6/2/2011 Construction Completed. Waiting on Punch List and FAA Replacement Burke /Reid inspection. Middleton /AMG 5 Storm Water Robert 0 4/8/2011 Project Completed Retention Ponds Lee /Storm Last Revision Date: 1/13/2012 AIRPORT ADVISORY COMMITTEE PROJECT - GOAL MATRIX Last Revision Date: 1/13/2012 Water /Coleman 6 Airport Hangar AMG 0 9/7/2011 Completed Inspection 8 Drainage Mitigation Tim Carlaw TBD TBD TBD Recent observation — no change since last report. No standing water. Monitoring and will update as necessary 17 Repair of storm AMG $25,000 11/11/2011 The most deteriorated catch basins to be identified and Water Catch Basins repaired as required. Twenty (22) catch basin were repaired at cost of $23,794.35 (Note: 2 failing catch basins were repaired at the AFS shop which AFS Shop is paying for). Last Revision Date: 1/13/2012