HomeMy WebLinkAboutMatrixAIRPORT ADVISORY COMMITTEE PROJECT - GOAL MATRIX
#
PROJECT
LEAD
Est. COST
REVIEW
EST.
STATUS
DESCRIPTION
DATE
COMPL.
DATE
3
Hangar Rows 9 & 10
Steve Burke /AMG/
$200,000
5/16/2012
8/31/2012
Steve Burke putting appropriate documents together to
roof
Bob Jones
send out project for bid for summer completion.
7
Noise Complaints
AMG
0
5/16/2012
NA
No reports since last report
9
Airport Security
AMG
TBD
5/16/2012
TBD
Each association has been contacted informing them of
Update
the airports desire to have the airport control access.
11
Airport Master Plan
Coleman /AMG
TBD
5/16/2012
Feb 2014
3/16/2012, Draft RFQ was prepared by AMG in
Mid -Term Update
preparation for advertisement.
12
Occupancy Rates
AMG
-0-
5/16/2012
NA
• Row 9/10 38/40 (95 %) -1
• Row 2 Full (14) (100 %) no change
• Row 8 4/6 (67 %) no Change
• Rows 3 -7 52/85 (62 %) -3
• Storage Units 8/12 Full (67 %) -1
• Tie down 31/100 full (31 %) -2
13
General Airport
Board Only
TBD
5/16/2012
NA
Event to showcase Auburn Airport, e.g. WWI —II
Event
aircraft. Static display /food /sale vendors/ flights.
14
Fuel Dispenser
AMG
$10,000
5/16/2012
TBD
AMG contacted Dave Stocker of Epic Aviation and
Replacement
he is assisting in locating proper replacement
dispenser
15
Aircraft Accident
AMG
TBD
5/16/2012
6/30/2012
18 pages of document created with guidance from
Emergency Plan and
FAA Advisory Circular.
Recover Plan
16
Update Airport
Chris Anderson /RM
TBD
5/16/2012
7/31/2012
Time Line received from RM, Kickoff meeting held
Storm water
4/11/2012
"SWWPP" Plan
Last Revision Date: 3/18/2012
AIRPORT ADVISORY COMMITTEE PROJECT - GOAL MATRIX
18
West Side Trees
AMG
TBD
5/16/2012
8/31/2012
Trees on the west side of the airport in the wet land
DESCRIPTION
DATE
DATE
areas have grown to a height that penetrates the
2
Airport Rules and
AMG
0
9/20/2010
Runway Safety Area. These need to be cut
Regulations
down/removed. Contacted a tree removal to give
10
Aircraft Wash Rack
AMG
TBD
3/31/2012
ideas and pricing. Grant fiends might be available
7
MIA Appraisal
AMG
0
12/31/2010
from FAA or State for this project. Additional bid
1
Airport Storm
Reid
$50,000
4/20/2011
will be received by 4/30/2012.
1 /
#
PROJECT
LEAD
Est. COST
REVIEW
COMPL.
STATUS
DESCRIPTION
DATE
DATE
2
Airport Rules and
AMG
0
9/20/2010
Completed
Regulations
10
Aircraft Wash Rack
AMG
TBD
3/31/2012
Completed
7
MIA Appraisal
AMG
0
12/31/2010
Completed
1
Airport Storm
Reid
$50,000
4/20/2011
Completed
Water Design
Middleton /AMG
Update
4
Runway Lighting
Steve
$350,000
6/2/2011
Construction Completed.
Replacement
Burke /Reid
Middleton /AMG
5
Storm Water
Robert
0
4/8/2011
Project Completed
Retention Ponds
Lee /Storm
Water /Coleman
6
Airport Hangar
AMG
0
9/7/2011
Completed
Inspection
8
Drainage Mitigation
Tim Carlaw
Recent observation — no change since last report. No
standing water. Monitoring and will update as necessary
17
Repair of Storm
AMG
$25,000
11/11/2011
Completed
Water Catch Basins
Last Revision Date: 3/18/2012