HomeMy WebLinkAbout6280 Exhibit "B" Policy / Text Amendment 1-4Exhibit B
POLICY /TEXT• AMENDMENT #1
Auburn School District Updated 2009 -2015 Capital
Facilities Plan
Incorporate Auburn School District Updated 2009 -2015
Capital Facilities Plan as part of Auburn Comprehensive
Plan
(Adopted by the Auburn School District Board of Directors
May 2009)
Section
Table of Contents
Executive Summary Page 1
Section II Enrollment Projections Page 6
Section III Standard of Service Page 8
Section IV Inventory of Facilities Page 15
Section V Pupil Capacity Page 18
Section VI Capital Construction Plan Page 21
Section VII Impact Fees Page 24
Section VIII Appendices Page 28
Appendix A.1 - Student Enrollment Projections Page 29
Appendix A.2 - Capital Facilities Plan Projections Page 43
Appendix A.3 Student Generation Survey Page 48
Auburn School District No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
I. Executive Summary
This Six -Year Capital Facilities Plan (the "Plan ") has been prepared by the Auburn
School District (the "District ") as the District's principal planning document, in
compliance with the requirements of Washington's Growth Management Act and the
adopted ordinances of the counties and cities served by the District. This plan was
prepared using data available in the spring of 2009.
This Plan is consistent with prior long -term capital facilities plans adopted by the
District. However, this Plan is not intended to be the sole plan for all of the District's
needs. The District may prepare interim and periodic long -range Capital Facilities Plans
consistent with Board Policies and actions, taking into account a longer or a shorter time
period; other factors and trends in the use of facilities; and other needs of the District as
may be required. However, any such plan or plans will be consistent with this Six -Year
Capital Facilities Plan.
To enable the collection of impact fees in the unincorporated areas of King County and
within the City of Auburn and City of Kent; the King County Council, the City of
Auburn and the City of Kent will adopt this Plan by reference as part of each
jurisdiction's respective comprehensive plan. To enable the collection of impact fees in
the Cities of Algona and Pacific, these municipalities must also adopt this Plan and adopt
school impact fee ordinances.
Pursuant to the requirements of the Growth Management Act and the local ordinances,
the Plan will be updated on an annual basis, and any changes in the fee schedule(s)
adjusted accordingly.
The Plan establishes the District's "standard of service" in order to ascertain the
District's current and future capacity. While the State Superintendent of Public
Instruction establishes square footage guidelines for capacity, those guidelines do not
account for the local program needs of the District. The Growth Management Act and
the school impact fee ordinance authorize the District to define its standard of service
based on the District's specific needs. In general, the District's current standard provides
that class size for grades K -2 should not exceed 25 students; class size for grades 3 -4
should not exceed 27 students; class size for grade 5 should not exceed 30 students.
When averaged over the six elementary grades, this computes to 26.5 students per
classroom. Class size for grades 6 -12 should not exceed 30 students, with some subject
areas restricted to lesser numbers. (See Section III for more specific information.)
2
Auburn School District No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
EXECUTIVE SUMMARY
CAPITAL FACILITIES PLAN CHANGES FROM 2008 TO 2009
Listed below is a summary level outline of the changes from the 2008 Capital
Facilities Plan that are a part of the 2009 Plan. The changes are noted by Section
for ease of reference.
Section I
Executive Summary
A. Updated to reflect new information within the Plan.
B. Summary level list of changes from previous year.
Section II
Enrollment Projections
Updated projections. See Appendices A.1 & A.2.
Section III
Standard of Service
A. Increase of 2 early childhood classrooms at elementary level
B. Increase of 1 second grade TOSA program at elementary level
C. Reduction of 1 structured learning classroom at middle level
D. Increase of 2 structured learning classrooms at the high school level
Section IV
Inventory of Facilities
Updated to include portables at Lakeland Hills Elementary for Fall of 2009.
Updated to include Special Education Transition Facility for Fall of 2009.
Updated to include portables at Mt. Baker Middle School for Fall of 2009.
Section V
Pupil Capacity
Updated to include portables at Lakeland Hills Elementary for Fall of 2009.
Updated to include Special Education Transition Facility for Fall of 2009.
Updated to include portables at Mt. Baker Middle School for Fall of 2009.
4
Auburn School District No. 408
Capital Facilities Plan
2009 through 2015
Section II
Enrollment Projections
Auburn School District No. 408
Capital Facilities Plan
2009 through 2015
Section III
Standard of Service
Auburn School District No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
STANDARD OF SERVICE
SPECIAL EDUCATION RESOURCE ROOMS
The Auburn School District operates a resource room program at the elementary level for
special education students requiring instruction to address their specific disabilities. Seventeen standard
classrooms are required to house this program. The housing requirements for this program exceed
the SPI space guidelines by ten standard classrooms. The loss of capacity is expected as growth
in program is larger than the total elementary population.
Loss of Permanent Capacity 10 rooms @ 26.5 each =
Loss of Temporary Capacity 0 rooms @ 26.5 each =
Total Capacity Loss
(265)
0
(265)
NATIVE AMERICAN RESOURCE ROOM
The Auburn School District operates one resource room to support the education of Native American
students at the elementary level. One standard classroom. is fully dedicated to serve these students.
Loss of Permanent Capacity 1 room @ 26.5 each =
Loss of Temporary Capacity 0 rooms @ 26.5 each =
Total Capacity Loss
(27)
0
(27)
HEAD START
The Auburn School District operates a Head Start program for approximately 120 youngsters in six
sections of 1/2 day in length. The . program is housed at'three elementary schools and utilizes
three standard elementary classrooms and auxiliary office spaces. The housing requirements
for this program are not provided for in the SPI space guidelines.
Loss of Permanent Capacity 3 rooms @ 26.5 each =
Loss of Temporary Capacity 0 rooms @ 26.5 each =
Total Capacity Loss
(80)
0
(80)
EARLY CHILDHOOD SPECIAL EDUCATION
The Auburn School District operates a pre - school program for young children with disabilities below
age five. This program is housed at eight different elementary schools and currently uses eleven
standard classrooms. The housing requirements for this program are'not provided for in the SPI
space guidelines.
Loss of Permanent Capacity 11 rooms @ 26.5 each =
Loss of Temporary Capacity 0 rooms @ 26.5 each =
Total Capacity Loss
(292)
0
(292)
READING LABS
The Auburn School District operates a program for students needing remediation and additional
language arts instruction. These programs utilize non - standard classroom spaces if available in
each elementary school. Four elementary schools do not have non - standard rooms available, thus
they are housed in a standard classroom. The housing requirements for this program are not
provided for in the SPI space guidelines.
Loss of Permanent Capacity 4 rooms @ 26.5 each =
Loss of Temporary Capacity 0 rooms @ 26.5 each =
Total Capacity Loss
10
(106)
0
(106)
Exhibit B
POLICY/TEXT AMENDMENT #1
Auburn School District Updated 2009-2015 Capital
Facilities Plan
Incorporate Auburn School District Updated 2009-2015
Capital Facilities Plan as part of Auburn Comprehensive
Plan
(Adopted by the Auburn School District Board of Directors
May 2009)
AUBURN SCHOOL DISTRICT No. 408
915 Fourth Street NE
Auburn, Washington 98002
(253) 931 -4900
Serving Students in:
Unincorporated King County
City of Auburn
City of Algona
City of Kent
City of Pacific
BOARD of DIRECTORS
Janice Nelson
Ray Vefik
Carol Helgerson
Lisa Conners
Craig Schumaker
Dennis Kip Herren, Superintendent
AUBURN SCHOOL DISTRICT
"Avenue to Excellence"
Table of Contents
Section I Executive Summary Page 1
Section II Enrollment Projections Page 6
Section III Standard of Service Page 8
Section IV Inventory of Facilities Page 15
Section V Pupil Capacity Page 18
Section VI Capital•Construction Plan Page 21
Section VII Impact Fees Page 24
Section VIII Appendices Page 28
Appendix A.1 - Student Enrollment Projections Page 29
Appendix A.2 - Capital Facilities Plan Projections Page 43
Appendix A.3 Student Generation Survey Page 48
Auburn School District No. 408
Capital Facilities Plan
2009 through 2015
Section I
Executive Summary
Auburn School District No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
I. Executive Summary
This Six -Year Capital Facilities Plan (the "Plan ") has been prepared by the Auburn
School District (the "District ") as the District's principal planning document, in
compliance with the requirements of Washington's Growth Management Act and the
adopted ordinances of the counties and cities served by the District. This plan was
prepared using data available in the spring of 2009.
This Plan is consistent with prior long -term capital facilities plans adopted by the
District. However, this Plan is not intended to be the sole plan for all of the District's
needs. The District may prepare interim and periodic long -range Capital Facilities Plans
consistent with Board Policies and actions, taking into account a longer or a shorter time
period; other factors and trends in the use of facilities; and other needs of the District as
may be required. However, any such plan or plans will be consistent with this Six -Year
Capital Facilities Plan.
To enable the collection of impact fees in the unincorporated areas of King County and
within the City of Auburn and City of Kent; the King County Council, the City of
Auburn and the City of Kent will adopt this Plan by reference as part of each
jurisdiction's respective comprehensive plan. To enable the collection of impact fees in
the Cities of Algona and Pacific, these municipalities must also adopt this Plan and adopt
school impact fee ordinances.
Pursuant to the requirements of the Growth Management Act and the local ordinances,
the Plan will be updated on an annual basis, and any changes in the fee schedule(s)
adjusted accordingly.
The Plan establishes the District's "standard of service" in order to ascertain the
District's current and future capacity. While the State Superintendent of Public
Instruction establishes square footage guidelines for capacity, those guidelines do not
account for the local program needs of the District. The Growth Management Act and
the school impact fee ordinance authorize the District to define its standard of service
based on the District's specific needs. In general, the District's current standard provides
that class size for grades K -2 should not exceed 25 students; class size for grades 3 -4
should not exceed 27 students; class size for grade 5 should not exceed 30 students.
When averaged over the six elementary grades, this computes to 26.5 students per
classroom. Class size for grades 6 -12 should not exceed 30 students, with some subject
areas restricted to lesser numbers. (See Section III for more specific information.)
2
•£•d xipuaddd ut pautuluoo sr ulup sigZ •sluautdo[anap pagiluapt
.ioj uEds api.ti goua .toj siaqutnu uoipuraua2 luapnls lunlou loulstQ agl sane poq;aui stq.I.
•utalsXs um) luapnls sdoulsip ay wag ulup luapnls q tm 2uiddgtu aql alut2alui 01 puu
`•SIJ'Clump ao.tatd puu Aunoj 2ui)I wag ulup `aium1Jos 2utdduut slJpo asn oqi gltm
st Elup 01412utloal[oo Jo poglaW atu •S.tuaIC anti 2sul agl ut palorulsuoo sluaWdolanap
X[iutui- ilinua puE Apwtj apuis wag lot.tlstQ [oogos u.mgnd aga ut loogos puallu XIIEniou
oqm sluapnls ay 5uisn pa1E.taua2 uaaq aim! SJOIOE3 uoi1EJaua2 luapnls 041 •sliun
2utllamp A[tuiuj -il[nm puu Xltutuj aputs .ioj saaj loudutt loops pasodo.td aql glJoJ slas
IIA uotloas •luautdolanap puu glmoj2 2utouauadxa loulstQ u Xq pa.unout p drui [uosg
0141 jo autos 2utlaaw ut 1slsSE of saaJ lOEdutt Jo luautssassu agl JOJ apinoJd lua)I jo'i3
0141 put uzngnd Jo fit) aql `Aluno) Out)I / q paldopu saouuutp o as j loudU!I [oogoS au
'600Z goJCj,4 ut l0[[uq aql uo paou[d sum lugl ansst puoq u puu Xnal sluauzanoJdutt IEliduo
u 01 pal suo[lupuawwooaJ 0S31.11 •SJC0i U01 lxau agl .tano WOWS UOAOS JO lu311139E03.1
puu sat ;t[touJ 2uilsixa of sluawanotdutt IulidCO JoJ prwoq ay 01 suot1upuauwooa.t
aput.0 aalliutcuo3 01.1t.1002S E 800Z iogolop ut puu satlil(OJ lOUlsip [[CJo
matna.t antsuaga.tdutoO E palaldutoo loulsip au •SEOJC asap ui luautdolanap pamols sug
amlumop otuiouooa 041 'tOOZ ui sladolanap of plos sum lap SO.IOU gSi AtalututxoJddu
JO EOM Uu SUIT lua)I JO '2tD atu •Ilam SE 2O[.11SIQ aql IOEduti 1Egl luamdolanap
jo slaN00d .Jaglo a.IE atag,j, •loulsip aql Jo SE= 'cairn utngnd gl.Iou 0142 put `[[iH ua'I
ay 'gums puu[a)lu-j ay are pulsip [oogos all uo 2OUdun luuotitu2is anuq 11341 SE0.IE 00141
1OulsIQ loops umgnd aqa u[gl[m SEWS luaWdolanap aalut ay wag pa2E.taua2 act 02
°seamO ! uotlC[ndod luapnls paloaroid aql mu! 01 patinbat 0.113 satli[IOEJ mau au •glmoJ2
alupoWuzo00E 02 sans loogOS alnjnj Jo uoi1istnbou aql su [[am se `[oogoS kuluauza[a
mau E puu looIOS a[ppiut mau u jo uoi2OTUIsuoO aql sapnlout mid 041 'LOOZ 30 [tud 0142
ut 2utuado £reluawa[g uasgoouf .mgl•V puu 900Z Jo [[ud aql ut 2uivado kruluauia[g sll!H
pUEI031u1 Slim `•SOOZ itiuruga3 ut saalon ay iCq panotddu sloo4OS ,Ctuluauta[a mau oml Jo
uotlippu 0141 puu `.SOOZ .taquialdas ut pauado puu £OOZ i(.tuniga3 ui s.talon aql icq panotdde
loo4OS mau E JoJ papino.td snit' •satli[1OEJ 5utlsixa sdOulsIQ ay 01 uot1uziutapoW
pasodoid puu suogippu aql sassaippu IA Uogoas ui umogs uuld uotlorulsuoo IEliduO 0111
(uoiluuuoJUI
ogioads atom .10J A uoiaoas 33S) '8002 `i .tagolop Jo su £OL`17 I Sum sluapnls [unpiniput
Jo.tagwnu [unlou aqs •(ualIatapui)I,cuu [in3 sapnioui) £8'8i0`bi sum pouad autCS
sill .tOJ luaut[loiva Cg1 J,,) lua[untnbg awa 11nJ sua1agm £i7L`£ i SCAN i(ltOUduO 60-800Z
mOUlsiU 041 •sWooJssujO [uuo[lisuen 2utpn[oai sat1111OEJ Jo £C.toluanui 5upsixa all puu
a0tn.tas Jo ptupuuls St41 uo pasuq paluin0[EO Si louls[Q all ut s[oogOS amp iC1tOUdCO aqs
Auburn School District No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
EXECUTIVE SUMMARY
CAPITAL FACILITIES PLAN CHANGES FROM 2008 TO 2009
Listed below is a summary level outline of the changes from the 2008 Capital
Facilities Plan that are a part of the 2009 Plan. The changes are noted by Section
for ease of reference.
Section I
Executive Summary
A. Updated to reflect new information within the Plan.
B. Summary level list of changes from previous year.
Section II
Enrollment Projections
Updated projections. See Appendices A.1 & A.2.
Section III
Standard of Service
A. Increase of 2 early childhood classrooms at elementary level
B. Increase of 1 second grade TOSA program at elementary level
C. Reduction of 1 structured learning classroom at middle level
D. Increase of 2 structured learning classrooms at the high school level
Section IV
Inventory of Facilities
Updated to include portables at Lakeland Hills Elementary for Fall of 2009.
Updated to include Special Education Transition Facility for Fall of 2009.
Updated to include portables at Mt. Baker Middle School for Fall of 2009.
Section V
Pupil Capacity
Updated to include portables at Lakeland Hills Elementary for Fall of 2009.
Updated to include Special Education Transition Facility for Fall of 2009.
Updated to include portables at Mt. Baker Middle School for Fall of 2009.
4
Section VII
Impact Fees
Auburn School District No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
EXECUTIVE SUMMARY
CHANGES TO IMPACT FEE DATA ELEMENTS 2008 to 2009
DATA ELEMENTS
CPF
2008
CPF
2009
EXPLANATION
Student Generation Factors
Single Family
Elementary
0.3370
0.3200
Consistent with King County Ordinance 11621,
Student Generation Factors are calculated
Mid School
0.1450
0.1520
by the school district based on district
Sr. High
Multi - Family
0.1780
0.1580
records of average actual student generation
rates for new developments constructed
Elementary
0.0650
0.0790
over the last five years.
Mid School
0.0290
0.0340
Sr. High
0.0390
0.0420
School Construction Costs
Elementary $21,750,000
$21,750,000
Middle School $42,500,000
$42,500,000
Site Aquistion Costs
Cost per acre $272,387
$286,006
Updated estimates on land costs
Area Cost Allowance Boec $168.43
$168.79
Updated to projected SPI schedule.
Match % - State 59.32%
59.17%
Updated to current SPI schedule.
Match % - District 40.68%
40.83%
Computed
District Average AV
Single Family $290,617
$316,271
Updated from March 2009 King County
Dept of Assessments data.
Multi - Family $78,574
$85,729
Updated from March 2009 King County
Dept of Assessments data using weighted
average.
Debt Sery Tax Rate $1.79
$1.67
Current Fiscal Year
GO Bond Int Rate 5.11%
4.99%
Current Rate (Bond Buyers 20 Index 3 -09)
Section VIII
Appendices
Appendix A.1 - Updated enrollment projections from October 1, 2008
Appendix A.2 - Updated enrollment projections with anticipated buildout schedule.
Appendix A.3 - Student Generation Survey March 2009
5
Auburn School District No. 408
Capital Facilities Plan
2009 through 2015
Section II
Enrollment Projections
Auburn School District No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
ENROLLMENT PROJECTIONS
The Auburn School District uses a modified cohort survival model to project future enrollment for all
of the District's operations. Table 11.1 is an extract from the comprehensive projection model found in
Appendix A.2 titled "CAPITAL FACILITIES PLAN Enrollment Projections ". This Table shows the
anticipated enrollment for the next six years based on the previous 6 year history of the District under the
assumptions set forth in the comprehensive projections, Appendix A.1, and the projection for additional
students generated from new developments in the district as shown in Appendix A.2.
TABLE
11.1
ASD ENROLLMENT
PROJECTIONS (March 2009
Projected
GRADE
2008 -09
Actual
2009 -10
Projected
2010 -11
Projected
2011 -12
Projected
2012 -13
Projected
2013 -14
Projected
2014 -15
Projected
KDG
998
1024
1051
1082
1114
1142
1170
1
1015
1057
1084
1116
1149
1177
1205
2
1024
1044
1087
1118
1151
1179
1207
3
1048
1058
1078
1126
1159
1187
1216
4
1044
1092
1102
1128
1176
1205
1233
5
1069
1088
1136
1152
1178
1223
1252
K - 5
6198
6364
6538
6722
6926
7114
7283
6
1096
1095
1114
1168
1185
1208
1252
7
1034
1120
1119
1144
1199
1211
1234
8
1076
1065
1152
1157
1182
1233
1246
6 -8
3206
3280
3385
3469
3566
3652
3732
9
1256
1368
1361
1458
1469
1495
1549
10
1341
1218
1330
1329
1426
1431
1455
11 •
1350
1275
1151
1267
1265
1355
1358
12
1352
1326
1250
1130
1245
1237
1325
9 -12
5299
5187
5092
5184
5406
5517
5687
TOTALS
14703
14831
15016
15374
15898
16284
16701
GRADES K -12
Actual
Projected
Projected
Projected
Projected
Projected
Projected
K -5 w/K @ 1/2
5699
5851
6013
6181
6369
6543
6698
6 -8
3206
3280
3385
3469
3566
3652
3732
9 -12
5299
5187
5092
5184
5406
5517
5687
K -12 w/K @ 1/2
14204
14319
14490
14833
15341
15713
16117
Note: The distric is currently operating Full Day Kindergarten in nine schools and includes two state
funded Full Day Kindergarten at two additional elementary schools.
7
Auburn School District No. 408
Capital Facilities Plan
2009 through 2015
Section III
Standard of Service
Auburn School District No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
STANDARD OF SERVICE
The School Impact Fee Ordinances adopted by King County, the City of Auburn
and the City of Kent indicate that each school district must establish a "Standard of Service" in
order to ascertain the overall capacity to house its projected student population. The Superintendent
of Public Instruction establishes square footage "capacity" guidelines for computing state funding
support. The fundamental purpose of the SPI guidelines is to provide a vehicle to equitably
distribute state matching funds for school construction projects. By default these guidelines
have been used to benchmark the district's capacity to house its student population. The SPI
guidelines do not make adequate provision for local district program needs, facility configurations,
emerging educational reform, or the dynamics of each student's educational program. The Auburn
School District Standard of Service addresses those local considerations that require space in
excess of the SPI guidelines. The effect on the space requirements for both permanent and
relocatable facilities is shown below for each grade articulation pattern. Conditions that may
result in potential space needs are provided for information purposes without accompanying
computations.
OVERVIEW
The Auburn School District operates fourteen elementary schools housing 6,198 students in grades
K through 5. 665 of the 998 Kindergarten students attend 1/2 days throughout the year. Grades 1
through 5, plus 333 kindergartners, attend on a full day basis. When converted to a full time equivalence
the K -5 enrollment is 5,784. Four middle schools house 3,206 students in grades 6 through 8. The District
operates three comprehensive senior high schools and one alternative high school housing 5,299
students in grades 9 through 12. The District opened the fourth high school in the fall of 2005.
CLASS SIZE
The number of pupils per classroom determines the number of classrooms required to house the
student population. Class sizes are subject to collective bargaining. Changes to class size
agreements can have significant impact on available space.
The current pupil /teacher limit across all elementary programs is an average of 26.5 students per
teacher. Consistent with this staffing limit, room capacities are set at 26.5 students per room at grades
K - 5. At grades 6 - 12 the limit is set at 30 pupils.per room. The SPI space allocation for each grade
articulation level, less the computed reduction for the Auburn School District Standard of Service,
determines the District's capacity to house projected pupil populations. These reductions are shown
below by grade articulation level.
ELEMENTARY SCHOOLS
STRUCTURED LEARNING FOR DEVELOPMENTALLY DISABLED SPECIAL EDUCATION
The Auburn School District operates a structured learning program for students with moderate to severe
disabilities at the elementary school level which currently uses ten classrooms to provide for 105 students.
The housing requirements for this program are provided for in the SPI space guidelines. No loss of
capacity is expected unless population with disabilities grows at a disproportionate rate compared to
total elementary population.
ADAPTIVE BEHAVIOR
The Auburn School District operates an adaptive behavior program for students with behavior
disabilities at the elementary school level. The program uses two classrooms to provide for 20 students.
The housing requirements for this program exceed the SPI space allocations by two classrooms.
Loss of Permanent Capacity 2 rooms @ 26.5 each =
Loss of Temporary Capacity 0 rooms @ 26.5 each =
Total Capacity Loss
9
(53)
0
(53)
Auburn School District No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
STANDARD OF SERVICE
SPECIAL EDUCATION RESOURCE ROOMS
The Auburn School District operates a resource room program at the elementary level for
special education students requiring instruction to address their specific disabilities. Seventeen standard
classrooms are required to house this program. The housing requirements for this program exceed
the SPI space guidelines by ten standard classrooms. The loss of capacity is expected as growth
in program is larger than the total elementary population.
Loss of Permanent Capacity 10 rooms @ 26.5 each =
Loss of Temporary Capacity 0 rooms @ 26.5 each =
Total Capacity Loss
(265)
0
(265)
NATIVE AMERICAN RESOURCE ROOM
The Auburn School District operates one resource room to support the education of Native American
students at the elementary level. One standard classroom is fully dedicated to serve these students.
Loss of Permanent Capacity 1 room @ 26.5 each =
Loss of Temporary Capacity 0 rooms @ 26.5 each =
Total Capacity Loss
(27)
0
(27)
HEAD START
The Auburn School District operates a Head Start program for approximately 120 youngsters in six
sections of 1/2 day in length. The program is housed at three elementary schools and utilizes
three standard elementary classrooms and auxiliary office spaces. The housing requirements
for this program are not provided for in the SPI space guidelines.
Loss of Permanent Capacity 3 rooms @ 26.5 each =
Loss of Temporary Capacity 0 rooms @ 26.5 each =
Total Capacity Loss
(80)
0
(80)
EARLY CHILDHOOD SPECIAL EDUCATION
The Auburn School District operates a pre - school program for young children with disabilities below
age five. This program is housed at eight different elementary schools and currently uses eleven
standard classrooms. The housing requirements for this program are'not provided for in the SPI
space guidelines.
Loss of Permanent Capacity 11 rooms @ 26.5 each =
Loss of Temporary Capacity 0 rooms @ 26.5 each =
Total Capacity Loss
(292)
0
(292)
READING LABS
The Auburn School District operates a program for students needing remediation and additional
language arts instruction. These programs utilize non - standard classroom spaces if available in
each elementary school. Four elementary schools do not have non - standard rooms available, thus
they are housed in a standard classroom. The housing requirements for this program are not
provided for in the SPI space guidelines.
Loss of Permanent Capacity 4 rooms @ 26.5 each =
Loss of Temporary Capacity 0 rooms @ 26.5 each =
Total Capacity Loss
10
(106)
0
(106)
Auburn School District No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
STANDARD OF SERVICE
MUSIC ROOMS
The district elementary music programs require one acoustically modified classroom at each
elementary school for music instruction. The housing requirements are not provided for
in the SPI space guidelines.
Loss of Permanent Capacity 14 rooms @ 26.5 each =
Loss of Temporary Capacity 0 rooms @ 26.5 each =
Total Capacity Loss
(371)
0
(371)
ENGLISH AS A SECOND LANGUAGE PROGRAM
The Auburn School District operates a pullout program at the elementary school level for students
learning English as a second language. This program requires fourteen standard classrooms that are not
provided for in the SPI space guidelines.
Loss of Permanent Capacity 14 rooms @ 26.5 each =
Loss of Temporary Capacity 0 rooms @ 26.5 each =
Total Capacity Loss
(371)
0
(371)
SECOND GRADE TOSA PROGRAM
The Auburn School District provides a TOSA reading specialist program for eight highly impacted
elementary schools. This pullout model provides direct instruction to students who are not at grade
level and do not receive other services. This program requires eight standard classrooms that are
not provided for in the SPI space guidelines.
Loss of Permanent Capacity 8 rooms @ 26.5 each = (212)
Loss of Temporary Capacity 0 rooms @ 26.5 each = 0
Total Capacity Loss (212)
ELEMENTARY LEARNING SPECIALIST PROGRAM
The Auburn School District provides a learning specialist program to increase literacy skills for
first and second graders. This program model has been created from the 1 -728 funds and currently
has the specialist going into existing teacher classrooms, as well as pulling out students into
designated classrooms. The district is utilizing classrooms at all fourteen elementary schools.
Loss of Permanent Capacity 14 rooms @ 26.5 each =
Loss of Temporary Capacity 0 rooms @ 26.5 each =
Total Capacity Loss
(371)
0
(371)
FULL DAY KINDERGARTEN
The Auburn School District provides Full -Day Kindergarten programs to increase academic skills for
kindergarten students. This program model has been created from tuition, 1 -728 funds and currently
has two schools receiving state funding for 2008 -09 school year. The district is utilizing fourteen
classrooms at nine of the fourteen elementary schools. Housing requirements exceed the OSPI space
guidelines for this program by seven classrooms.
Loss of Permanent Capacity 7 rooms @ 26.5 each =
Loss of Temporary Capacity 0 rooms @ 26.5 each =
Total Capacity Loss
11
(186)
0
(186)
Auburn School District No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
STANDARD OF SERVICE
MIDDLE SCHOOLS
SPECIAL EDUCATION RESOURCE ROOMS
The Auburn School District operates a resource room program for each grade at the middle school level.
This is to accommodate special education students needing remedial instruction to address their specific
disabilities. Nine classrooms are required at the middle school level to provide for approximately 300 students.
The housing requirements for this program are not entirely provided for in the SPI space guidelines.
ADAPTIVE BEHAVIOR SPECIAL EDUCATION
The Auburn School District offers a self- contained program for students with moderate to severe behavior
diabilities. The program is housed at one of the middle schools and uses one classroom. The housing
requirements for this program are not provided for in the SPI space allocations.
STRUCTURED LEARNING CENTER AND DEVELOPMENTALLY DISABLED SPECIAL EDUCATION
The Auburn School District operates four structured learning classrooms at the middle school level for
students with moderate to severe disabilities and one developmentally disabled classroom for students with
profound disabilities. Two of the four classrooms for this program are provided for in the SPI space allocations.
Loss of Permanent Capacity 2 rooms @ 26.5 each =
Loss of Temporary Capacity 0 rooms @ 26.5 each =
Total Capacity Loss
(53)
0
(53)
MIDDLE SCHOOL COMPUTER LABS
The Auburn School District operates a minimum of one computer lab at each middle school. This program
utilizes a standard classroom per middle school. The housing requirements for this program
are not provided for in the SPI space guidelines.
Loss of Permanent Capacity 4 rooms @ 30 each = (120)
Loss of Temporary Capacity 0 rooms @ 30 each = 0
Total Capacity Loss (120)
ENGLISH AS A SECOND LANGUAGE
The Auburn School District operates a pullout program at the middle school level for students
learning English as a second language. This program requires four standard classrooms that are not
provided for in the SPI space guidelines.
Loss of Permanent Capacity 4 rooms @ 30 each = (120)
Loss of Temporary Capacity 0 rooms @ 30 each = 0
Total Capacity Loss (120)
ROOM UTILIZATION
The Auburn School District provides a comprehensive middle school program that includes
elective options in special interest areas. Facilities to accommodate special interest activities are
not amenable to standard classroom usage. The district averages 95% utilization of all available
teaching stations. SPI Report #3 dated 11/14/08 identifies 148 teaching stations available in the
mid -level facilities. The utilization pattern results in a loss of approximately 8 teaching stations.
Loss of Permanent Capacity 8 rooms @ 30 each =
Loss of Temporary Capacity 0 rooms @ 30 each =
Total Capacity Loss
12
(240)
0
(240)
Auburn School District No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
STANDARD OF SERVICE
SENIOR HIGH SCHOOLS
SENIOR HIGH COMPUTER LABS
The Auburn School District operates two computer labs at each of the senior high schools. This
program utilizes two standard classrooms at comprehensive high schools and one at West Auburn.
The housing requirements for this program are not provided for in the SPI space guidelines.
Loss of Permanent Capacity 7 rooms @ 30 each =
Loss of Temporary Capacity 0 rooms @ 30 each =
Total Capacity Loss
(210)
0
(210)
ENGLISH AS A SECOND LANGUAGE
The Auburn School District operates a pullout program at three comprehensive high schools for students
learning English as a second language. This program requires three standard classrooms that are not
provided for in the SPI space guidelines.
Loss of Permanent Capacity 3 rooms @ 30 each = (90)
Loss of Temporary Capacity 0 rooms @ 30 each = 0
Total Capacity Loss (90)
STRUCTURED LEARNING CENTER PROGRAM
The Auburn School District operates six structured learning center classrooms for 53 students with
moderate to severe disabilities. This program requires two standard classrooms that are not provided
for in the SPI space guidelines.
Loss of Permanent Capacity 2 rooms @ 30 each =
Loss of Temporary Capacity 0 rooms @ 30 each =
Total Capacity Loss
(60)
0
(60)
TRANSITION PROGRAM FOR 18 -21 YEAR OLD
The Auburn School District operates a transition program for 18 -21 year old students with moderate to severe
disabilities. Two classrooms are utilized for this program that connects students to the community and work.
The housing requirements for this program are not provided for in the SPI space guidelines.
Loss of Permanent Capacity 2 rooms @ 30 each =
Loss of Temporary Capacity 0 rooms @ 30 each =
Total Capacity Loss
(60)
0
(60)
SPECIAL EDUCATION RESOURCE ROOMS
The Auburn School District operates a resource room program at the senior high level for special
education students requiring instruction to address their specific learning disabilities. The current senior
high school program requires eleven classrooms to provide for approximately 370 students.
The SPI space guidelines provide for one of the eleven teaching stations.
Loss of Permanent Capacity 10 rooms @ 30 each =
Loss of Temporary Capacity 0 rooms @ 30 each =
Total Capacity Loss
13
(300)
0
(300)
Auburn School District No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
STANDARD OF SERVICE
PERFORMING ARTS CENTERS
Auburn High School includes 25,000 square feet used exclusively for a Performing Arts Center. The
SPI Inventory includes this space when computing unhoused student capacity. This space was
not intended for nor is it usable for classroom instruction. It was constructed to provide a
community center for the performing arts. Using SPI capacity guidelines, 25,000 square feet
computes to 208 unhoused students or 8.33 classrooms.
Loss of Permanent Capacity 8.33 rooms @ 30 each = (250)
ROOM UTILIZATION
The Auburn School District provides a comprehensive high school program that includes numerous
elective options in special interest areas. Facilities to accommodate special interest activities are
not amenable to standard classroom usage. The district averages 95% utilization of all available
teaching stations. SPI Report #3 dated 11/14/08 identifies 148 teaching stations available in the
senior high facilities. The utilization pattern results in a loss of approximately 10 teaching stations.
Loss of Permanent Capacity 10 rooms @ 30 each =
Loss of Temporary Capacity 0 rooms @ 30 each =
Total Capacity Loss
STANDARD OF SERVICE COMPUTED TOTALS
ELEMENTARY
Loss of Permanent Capacity = (2,332)
Loss of Temporary Capacity 0
Total Capacity Loss (2,332)
MIDDLE SCHOOL
Loss of Permanent Capacity = (533)
Loss of Temporary Capacity 0
Total Capacity Loss (533)
SENIOR HIGH
Loss of Permanent Capacity = (1,270)
Loss of Temporary Capacity 0
Total Capacity Loss (1,270)
TOTAL
Loss of Permanent Capacity = (4,135)
Loss of Temporary Capacity 0
Total Capacity Loss (4,135)
14
(300)
0
(300)
Auburn School District No. 408
Capital Facilities Plan
2009 through 2015
Section IV
Inventory of Facilities
Auburn School District No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
INVENTORY OF FACILITIES
Table IV.1 shows the current inventory of permanent district facilities and their OSPI rated capacities.
Table IV.2 shows the number and location of each portable unit by school. The district uses relocatable
facilities to:
1. provide interim housing in school attendance areas uniquely impacted by increasing school
populations that would otherwise require continual redistricting.
2. make space available for changing program requirements and offerings determined by unique student
needs, and
3. provide housing to cover district needs until permanent facilities can be financed and constructed.
Relocatable facilities are deemed to be interim, stop gap measures that often place undesirable stress on existing
physical plants. Core facilities (i.e. gymnasiums, restrooms, kitchens, labs, lockers, libraries, etc.) are not of
sufficient size or quantity to handle the increased school population served by adding relocatable classrooms.
Table Permanent Facilities
IV.1 @ OSPI Rated Capacity
(November 2008)
District School Facilities
Buildin '
. .
Acres
Address
Elementar Schools
Washin•ton Elementa
492
5.40
20 E Street Northeast, Auburn WA, 98002
Terminal Park Elementa
401
6.70
1101 D Street Southeast, Auburn WA, 98002
Dick Scobee Elementa
550
10.50
1031 14th Street Northeast, Auburn WA, 98002
Pioneer Elementa
415
8.30
2301 M Street Southeast, Auburn WA, 98002
Chinook Elementa
485
8.75
3502 Auburn Wa South, Auburn WA, 98092
Lea Hill Elementa
459
10.00
30908 124th Avenue Southeast, Auburn WA, 98092
Gildo Re Elementa
531
10.00
1005 37th Street Southeast, Auburn WA, 98002
Ever • reen Hei:hts Elem.
456
8.09
5602 South 316th, Auburn WA, 98001
Al ,ac Elementa
494
10.60
310 Milwaukee Boulevard North, Pacific WA, 98047
Lake View Elementa
595
16.40
16401 Southeast 318th Street, Auburn WA, 98092
Hazelwood Elementa
578
12.67
11815 Southeast 304th Street, Auburn WA, 98092
Ilalko Elementa
585
12.00
301 Oravetz Place Southeast, Auburn WA, 98092
Lakeland Hills Elementa
594
12.00
1020 Evergreen Way SE, Auburn WA,98092
Arthur Jacobsen Elementa
614
10.00
29205 132'' Street SE, Auburn, WA 98092
ELEM CAPACITY
7249
Middle Schools
Cascade Middle School
836
17.30
1015 24th Street Northeast, Auburn WA, 98002
01 m.ic Middle School
898
17.40
1825 K Street Southeast, Auburn WA, 98002
Rainier Middle School
849
26.33
30620 116th Avenue Southeast, Auburn WA, 98092
Mt. Baker Middle School
845
30.88
620 37th Street Southeast, Auburn WA, 98002
MS CAPACITY
3,428
Senior Hi_h Schools
West Auburn Hi:h School
231
5.10 401 West Main Street, Auburn WA, 98001
Auburn Senior Hi:h
2,261
18.60
800 Fourth Street Northeast, Auburn WA, 98002
Auburn Riverside HS
1,388
33.00
501 Oravetz Road, Auburn WA, 98092
Auburn Mountainview HS
1,431
40.00
28900 124'h Ave SE, Auburn, WA 98092
SH CAPACITY
5,311
TOTAL CAPACITY 16,025
16
Auburn School District No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
INVENTORY OF FACILITIES
TABLE
IV.2
TEMPORARY /RELOCATABLE
FACILITIES INVENTORY
(March 2009)
2009 -10
Elementary Location
2008 -09
2009 -10
2010 -11
2011 -12
2012 -13
2013 -14
2014 -15
Washington
0
2
0
O N M M C!) N C D N N N ON Ct 0
0
0
0
Terminal Park
2
2
2
2
2
2
Dick Scobee
3
• 8
3
3
3
3
Pioneer
3
8
3
3
3
3
Chinook
5
13
5
5
5
5
Lea Hill
5
330
5
2
2
2
Gildo Rey
6
CO
6
6
6
6
Evergreen Heights
0
2
2
2
2
Alpac
2
2
2
2
2
Lake View
2
2
2
2
2
Hazelwood
0
0
0
0
0
Ilalko
2
2
2
2
2
Lakeland Hills Elementary
0
2
4
4
4
Arthur Jacobsen Elementary
0
0
0
0
0
TOTAL UNITS
30
32
34
33
33
33
33
TOTAL CAPACITY
795
848
901
875
875
875
875
Middle School Location
2008 -09
2009 -10
2010 -11
2011 -12
2012 -13
2013 -14
2014 -15
Cascade
0
0
0
2
2
2
2
Olympic
0
0
0
0
2
2
2
Rainier
5
5
5
• 8
8
8
8
Mt. Baker
6
8
8
8
8
8
8
TOTAL UNITS
11
13
13
18
20
20
20
TOTAL CAPACITY
330
390
390
540
600
600
600
Sr. High School Location
2008 -09
2009 -10
2010 -11
2011 -12
2012 -13
2013 -14
2014 -15
West Auburn
0
0
0
1
1
1
1
Auburn
12
12
12
12
12
12
12
Auburn Riverside
13
13
13
13
13
13
13
Auburn Mountainview
0
0
0
0
0
0
0
TOTAL UNITS
25
25
25
26
26
26
26
TOTAL CAPACITY
750
750
750
780
780
780
780
COMBINED TOTAL UNITS
66
70
72
77
79
79
79
COMBINED TOTAL CAPACITY
1,875
1,988
2,041
2,195
2,255
2,255
2,255
17
Auburn School District No. 408
Capital Facilities Plan
2009 through 2015
Section V
Pupil Capacity
1/
3/
Auburn School District No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
PUPIL CAPACITY
While the Auburn School District uses the SPI inventory of permanent facilities as the data from
which to determine space needs, the District's educational program requires more space than that
provided for under the formula. This additional square footage is converted to numbers of pupils in
Section III, Standard of Service. The District's capacity is adjusted to reflect the need for additional
space to house its programs. Changes in the capacity of the district recognize new unfunded
facilities. The combined effect of these adjustments is shown on Line B in Tables V.1 and V.2 below.
Table V.1 shows the Distict's capacity with relocatable units included and Table V.2 without these units.
Table V.1
Capacity
WITH relocatables
2008 -09 2009 -10
2010 -11
2011 -12
2012 -13
2013 -14
2014 -15
A. SPI Capacity 15,950 15,950
A.1 SPI Capacity -New Elem
A.2 SPI Capacity- New MS
B.
C.
D.
E.
Capacity Adjustments
Net Capacity
ASD Enrollment
ASD Surplus /Deficit
CAPACITY ADJUSTMENTS
Include Relocatable
2/ Exclude SOS (pg 14)
1/
3/
2/
(2,260) (2,147)
15,950
(2,094)
15,950
(1,940)
15,950
800
(1,880)
16,750
(1,880)
13,690 13,803
14,703 14,319
(1,013) (516)
1,875 1,988
(4,135) (4,135)
13,856
14,490
(634)
2,041
(4,135)
14,010
14,833
(823)
2,195
(4,135)
14,870
15,341
(471)
2,255
(4,135)
14,870
15,713
(843)
2,255
(4,135)
16,750
585
(1,880)
15,455
16,117
(662)
2,255
(4,131
Total Adjustments
(2,260) (2,147)
(2,094)
(1,940)
(1,880)
(1,880)
Table V.2
Capacity
WITHOUT relocatables
(1,8801
2008 -09 2009 -10
2010 -11
2011 -12
2012 -13
2013 -14
2014 -15
A.
A.1
A.2
B.
C.
D.
E.
CAPACITY
SPI Capacity
SPI Capacity -New Ele
SPI Capacity- New MS
15,950 15,950
m
Capacity Adjustments
Net Capacity
ASD Enrollment
ASD Surplus /Deficit
ADJUSTMENTS
Exclude SOS (pg 14)
(4,135) (4,135)
15,950
(4,135)
15,950
(4,135)
15,950
800
(4,135)
16,750
(4,135)
16,750
585
(4,135)
11,815 11,815
14,703 14,319
(2,888) (2,504)
(4,135) (4,135)
11,815
14,490
(2,675)
(4,135)
11,815
14,833
(3,018)
(4,135)
12,615
15,341
(2,726)
(4,135)
12,615
15,713
(3,098)
(4,135)
Total Adjustments
(4,135) (4,135)
(4,135)
(4,135)
(4,135)
(4,135)
13,200
16,117
(2,917)
(4,135)
(4,135)
if New facilities shown in 2012 -13 and 2014 -15 are not funded under the current Capital Facilities Plan.
2/ The Standard of Service represents 25.38% of SPI capacity. When new facilities are added the Standard
of Service computations are decreased to 23.35% of SPI capacity.
3/ Students beyond the capacity are accomodated in other spaces (commons, library, theater, shared teaching space).
19
Building
2008 -09
2009 -10
2010 -11
2011 -12
2012 -13
2013 -14
2014 -15
West Auburn
231
231
231
231
231
231
231
Auburn
2,261
2,261
2,261
2,261
2,261
2,261
2,261
Auburn Riverside
1,388
1,388
1,388
1,388
1,388
1,388
1,388
Auburn Mountainview
1,431
1,431
1,431
1,431
1,431
1,431
1,431
SH CAPACITY
5,311
5,311
5,311
5,311
5,311
5,311
5,311
PERMANENT FACILITIES
@ SPI Rated Capacity
(March 2009)
A.
Elementa
Schools
Auburn School District No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
PUPIL CAPACITY
Building
2008 -09
2009 -10
2010 -11
2011 -12
2012 -13
2013 -14
2014 -15
Washington
492
492
492
492
492
492
492
Terminal Park
401
401
401
401
401
401
401
Dick Scobee
550
550
550
550
550
550
550
Pioneer
415
415
415
415
415
415
415
Chinook
485
485
485
485
485
485
485
Lea Hill
459
459
459
459
459
459
459
Gildo Rey
531
531
531
531
531
531
531
Ever Heights
456
456
456
456
456
456
456
Alpac
494
494
494
494
494
494
494
Lake View
595
595
595
595
595
595
595
Hazelwood
578
578
578
578
578
578
578
Ilalko
585
585
585
585
585
585
585
Lakeland Hills
585
585
585
585
585
585
585
Arthur Jacobsen
585
585
585
585
585
585
585
Elementary #15
585
ELEM CAPACITY
7,211
7,211
7,211
7,211
7,211
7,211
7,796
B. Middle Schools
Building
2008 -09
2009 -10
2010 -11
2011 -12
2012 -13
2013 -14
2014 -15
Cascade
836
836
836
836
836
836
836
Olympic
898
898
898
898
898
898
898
Rainier
849
849
849
849
849
849
849
Mt. Baker
845
845
845
845
845
845
845
Middle School #5
0
0
0
0
800
800
800
MS CAPACITY
3,428
3,428
3,428
3,428
4,228
4,228
4,228
C. Senior His Schools
'COMBINED CAPACITY I 15,950 I 15,950 I 15,950 I 15,950 I 16,750 I 16,750 I 17,335 I
20
Auburn School District No. 408
Capital Facilities Plan
2009 through 2015
Section VI
Capital Construction Plan
Auburn School District No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
CAPITAL CONSTRUCTION PLAN
The formal process used by the Board to address current and future facility needs began in 1974
with the formation of a community wide citizens committee. The result of this committee's work
was published in the document titled 'Guidelines for Development.' In 1985 the Board formed a
second Ad Hoc citizens committee to pick up from the work of the first and address the needs of
the District for subsequent years. The work of this committee was published in the document
titled 'Directions for the Nineties.' In 1995 the Board commissioned a third Ad Hoc citizens
committee to make recommendations for improvements to the District's programs and physical
facilities. The committee recommendations are published in the document titled 'Education Into
The Twenty -First Century - - A Community Involved.'
The 1995 Ad Hoc committee recommended the District develop plans for the implementation,
funding, and deployment of technology throughout the District's programs. The 1996 Bond
proposition provided funding to enhance the capacity of each facility to accommodate
technological applications. The 1998 Capital Levy provided funding to further deploy
technology at a level sufficient to support program requirements in every classroom and
department. In 2005 a replacement technology levy was approved to continue to support
technology across all facets of the District's teaching, learning and operations.
In addition to the technology needs of the District the Ad Hoc committee recognized the District
must prepare for continued student enrollment growth. As stated in their report, "the District
must pursue an appropriate high school site as soon as possible." The Ad Hoc recommendation
included commentary that the financing should be timed to maintain consistent rates of
assessment.
A proposition was approved by the voters on April 28, 1998 that provided $8,000,000 over six
years to address some of the technology needs of the District; and $5,000,000 to provide funds to
acquire school sites.
During the 1997 -98 school year a Joint District Citizen's Ad Hoc Committee was appointed by
the Auburn and Dieringer School Boards to make recommendations on how best to serve the
school population from an area that includes a large development known as Lakeland South.
Lakeland South at that time was immediately adjacent to the southern boundary of the Auburn
School District. On June 16, 1998 the Ad Hoc Committee presented its recommendation at a
joint meeting of the Auburn and Dieringer Boards of Directors. On June 22, 1998 the Auburn
School Board adopted Resolution No. 933 authorizing the process to initiate the adjustment of
the boundaries of the District in accordance with the Ad Hoc Committee's recommendation. On
June 23, 1998 the Dieringer School Board adopted a companion Resolution No. 24 -97 -98
authorizing the process to initiate the adjustment of the boundaries in accordance with the Ad
Hoc Committee's recommendation. These actions resulted in the transfer of an area from
Dieringer to Auburn containing most of the Lakeland South development and certain other
undeveloped properties. Development in this area is progressing at an aggressive rate.
In April of 2002, the Board formed a fifth citizen's Ad Hoc committee to address the following
two items and make recommendations to the board in the Fall of 2002:
a. A review of the conclusion and recommendations of 1985 and 1995 Ad Hoc Committees
related to accommodating high school enrollment growth. This included the review of
possible financing plans for new facilities.
22
Auburn School District No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
CAPITAL CONSTRUCTION PLAN
b. Develop recommendations for accommodating high school enrollment growth for the
next 10 years if a new senior high school is not built.
This committee recommended the board place the high school on the ballot for the fifth time in
February 2003. The February election approved the new high school at 68.71% yes votes. The
school opened in the Fall of 2005.
In the Fall of 2003 the school board directed the administration to begin the planning and design
for Elementary #13 and Elementary #14. In the Fall of 2004, the Auburn School Board passed
Resolution No. 1054 to place two elementary schools on the ballot in February 2005. The voters
approved the ballot measure in February of 2005 at 64.72 %. Lakeland Hills Elementary
(Elementary #13) opened in the Fall of 2006. Arthur Jacobsen Elementary (Elementary #14) is
located in the Lea Hill area on a 10 acre site and opened in the Fall of 2007. These two
elementary schools were built to accommodate the housing growth in Lakeland Hills and Lea
Hill areas of the school district.
In the 2004 -05 school year, the Board convened a sixth Citizen's Ad Hoc committee to again
study and make recommendations about the future impacts in the District. One of the areas of
study was the need for New Facilities and Modernization. The committee made a number of
recommendations including school size, the need for a new middle school, and to begin a capital
improvements program to modernize or replace facilities based upon criterion.
During the 2005 -06 school year, a Joint District Citizen's Ad Hoc Committee was appointed by
the Auburn and Kent School Boards to make recommendations on how best to serve the school
population that will come from an area that includes a number of projected developments in the
north Auburn valley. On May 17, 2006 the Ad Hoc Committee presented its recommendation at
a joint meeting of the Auburn and Kent Boards of Directors. On June 14, 2006 the Kent School
Board adopted Resolution No. 1225 authorizing the process to initiate the adjustment of the
boundaries of the District in accordance with the Ad Hoc Committee's recommendation. On
June 26, 2006 the Auburn School Board adopted a companion Resolution No. 1073 authorizing
the process to initiate the adjustment of the boundaries in accordance with the Ad Hoc
Committee's recommendation. These actions resulted in the transfer of an area from the Kent
School District to the Auburn School District effective September 29, 2006.
In October of 2008, after two years of review and study, a Steering Committee made
recommendations to the school board regarding the capital improvements program to modernize
or replace facilities as recommended by the 2004 -05 Citizen's Ad Hoc Committee. These
recommendations, based on specific criteria, led to the school board placing a school
improvement bond and capital improvements levy on the ballot in March 2009. Voters did not
approve either measure that would have updated 24 facilities and replaced three aging schools.
This review also identified the need for a Special Education Transition Facility for students with
disabilities that are 18 to 21 years old. This facility is planned to be operational by the Fall of
2009 to address this growth need.
The District is projecting 1998 additional students within the six year period including the
Lakeland, Lea Hill, and north Auburn valley areas. This increase in student population will
23
1/
1/
1/
1/
Auburn School District No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
CAPITAL CONSTRUCTION PLAN
require the acquisition of new middle school and new elementary school sites and construction of
a middle school and elementary school during the six year window.
Based upon the District's capacity data and enrollment projections, as well as the student
generation data included in Appendix A.3, the District has determined that approximately eighty-
six percent of the capacity improvements are necessary to serve the students generated from new
development, with the remaining additional capacity required to address existing need.
The table below illustrates the current capital construction plan for the next six years. The exact
timelines are wholly dependent on the rate of growth in the school age population and passage of
bond issues and/or capital improvement levies.
2009 -15 Capital Construction Plan
March 2009
Project
Funded
Projected
Cost
Fund
Source
Project Timelines
08 -09 09 -10 10 -11 11 -12 12 -13 13 -14 14 -15
All Facilities -
Technology
Modernization
Yes
$12,000,000
2006
6 Year
Cap Levy
XX
XX
XX
XX
Portables
Yes
$1,200,000
Impact Fees
XX
XX
XX
XX
XX
XX
XX
Property Purchase
New Middle School
New Elementary
Yes
Yes
$9,000,000
$3,500,000
Impact
Fees
State Mat
XX
XX
XX
-----
XX
const
XX
XX
const
XX
open
Special Education
Transition Facilit
Yes
$750,000
Impact Fees
XX
XX
Middle School #5
No
$42,500,000
Bond
Impact Fee
XX
plan
Elementary #15
No
$21,750,000
Bond
Impact Fee
----
XX
plan
XX
const
XX
open
Multiple Facility
Im . rovements
No
$46,400,000
Capital Levy
XX
XX
XX
XX
XX
XX
Replacement of
three a : in schools
No
$239,000,000
Bond Issue
XX
XX
XX
XX
XX
XX
1/ These funds may be secured through local bond issues, sale of real property, impact fees, and state matching funds.
The District currently is not eligible for state assistance at the elementary school level for new construction. The district is eligible for
state matching funds for modernization.
24
Auburn School District No. 408
Capital Facilities Plan
2009 through 2015
Section VII
Impact Fees
IMPACT FEE COMPUTATION (Spring
Middle school site acquistion within 6 year period
Middle School #5 within 6 year period
Elementary #15 within 6 year period
I. SITE COST PER RESIDENCE
Auburn Sch ,strict No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
2009)
Formula: ((Acres x Cost per Acre) /Facility Size) x Student Factor
Site
Acrea
e
Cost/
Acre
Facility
Ca•aci
Student Generation Factor
Single Famil Multi Family
Cost/
Single Family
Cost/
Multi Family
Elem (K - 5)
12
$0
550
0.3200
0.0790
$0.00
$0.00
Middle Sch (6 - 8
25
$286,006
800
0.1520
0.0340
$1,358.53
$303.88
Sr High (9 - 12)
40
$0
1500
0.1580
0.0420
$0.00
$0.00
II. PERMANENT FACILITY CONSTRUCTION COST PER RESIDENCE
Formula: ((Facility Cost/Facility Size) x Student Factor) x (Permanent to Total Square Footage Percentage)
n
Famil
$1,358.53
303.88
Facility
Cost
Facility
Size
% Perm Sq Ft/
Total S• Ft
Student Generation Factor
Single Famil Multi Family
Cost/
Single Family
Cost/
Multi Family
Elem (K -5)
$21,750,000
550
0.9691
0.3200
0.0790
$12,263.82
$3,027.63
Mid Sch (6 - 8)
$42,500,000
800
0.9691
0.1520
0.0340
$7,825.67
$1,750.48
Sr High (9 - 12)
$0
1500
0.9691
0.1580
0.0420
$0.00
$0.00
III. TEMPORARY FACILITY CONSTRUCTION COST PER RESIDENCE
Formula: ((Facility Cost/Facility Size) x Student Factor) x (Temporary to Total Square Footage Ratio)
mil
$20,089.49
$4,778.11
Facility
Cost
Facility
Size •
% Temp Sq Ft/
Total S• Ft
Student Generation Factor
Single Famil Multi Famil
Cost/
Single Famil
Cost/
Multi Famil
Elem (K - 5)
$122,845
26.5
0.0309
0.3200
0.0790
$45.80
$11.31
Mid Sch (6 - 8)
$122,845
30
0.0309
0.1520
0.0340
$19.22
$4.30
Sr High (9 - 12)
$0
30
0.0309
0.1580
0.0420
$0.00
$0.00
IV. STATE MATCH CREDIT PER RESIDENCE
Formula: (Boeckh Index x SPI Foo age x District Match x Student Factor)
$65.02
15.61
Boeckh
Index
SPI
Foota
e
District
Match
Student Generation Factor
Single Famil Multi Family
Cost/
Single Family
Cost/
Multi Family
Elem (K - 5)
$168.79
90
59.17%
0.3200
0.0790
$2,876.34
$710.10
Mid Sch (6 - 8)
$168.79
108
59.17%
0.1520
0.0340
$1,639.52
$366.73
Sr High (9 - 12)
$168.79
130
59.17%
0.1580
0.0420
$2,051.39
$545.31
25
$6,567.25
$1,622.14
Auburn School District No. 408
CAPITAL FACILITIES PLAN
2009 through 2015
V. TAX CREDIT PER RESIDENCE
Formula: Expressed as the present value of an annuity
TC = PV(interest rate,discount period,average assd value x tax rate)
Ave Resid
Assd Value
Curr Dbt Sery
Tax Rate
Bnd Byrindx
Ann Int Rate
Numb of
Years
Tax Credit
Single Family
Tax Credit
Multi Family
Single Family $316,271 $1.67 4.99% 10
Multi Family $85,729 $1.67 4.99% 10
$4,080.39
$1,106.04
VI. DEVELOPER PROVIDED FACILITY CREDIT
Formula: (Value of Site or Facility /Number of dwelling units)
Value No. of Units
Facil Credit
Single Family $0.00
Multi Family
1
$0.00 1
$0.00
$0.00
FEE
RECAP
SUMMARY
PER UNIT IMPACT FEES
Single
Family
Site Costs
Permanent Facility Const Costs
Temporary Facility Costs
State Match Credit
Tax Credit
$1,358.53
$20,089.49
$65.02
($6,567.25)
($4,080.39)
FEE (No Discount) $10,865.40
FEE (50% Discount)
Facility Credit
Net Fee Obligation
$5,432.70
$0.00
$5,432.70
Multi
Family
$303.88
$4,778.11
$15.61
($1,622.14)
($1,106.04)
$2,369.42
$1,184.71
$0.00
$1,184.71
Auburn Sch. ,strict No. 408
CAPITAL FACILITIES PLAN
2009 throu • h 2015
IMPACT FEE ELEMENTS
SINGLE FAMILY
MULTI FAMILY
Elem
K -5
Mid Sch
6 -8
Sr High
9 -12
Elem
K -5
Mid Sch
6 -8
Sr High
9 -12
Student Factor
Single Family - Auburn actual count (3/08)
0.320
0.152
0.158
0.079
0.034
0.042
New Fac Capacity
ASD District Standards
550
800
1500
550
800
1500
New Facility Cost
Elementary Cost Estimates Feb 2008
$21,750,000
$42,500,000
$21,750,000
$42,500,000
$10,302,842
Middle School Cost Estimate Feb 2008
$259,416
5.00%
Middle School
2010
$286,006
Temp Rm Capacity
ASD District Standard of Service.
26.5
30
30
26.5
30
30
Grades K - 5 @ 26.5 and 6 - 12 @ 30.
Temp Facility Cost
Relocatables, including site work, set up, and furnishing
$122,845
$122,845
$122,845
$122,845
$122,845
$122,845
Site Acreage
ASD District Standard or SPI Minimum
12
25
40
12
25
40
Site Cost/Acre
See below
$286,006
$286,006
$286,006
$286,006
$286,006
$286,006
Perm Sq Footage
SPI Rpt #3 dated Nov 14, 2008
1,723,525
1,723,525
1,723,525
1,723,525
1,723,525
1,723,525
Temp Sq Footage
66 portables at 832 sq. ft. each
54,912
54,912
54,912
54,912
54,912
54,912
Total Sq Footage
Sum of Permanent and Temporary above
1,778,437
1,778,437
1,778,437
1,778,437
1,778,437
1,778,437
% - Perm Facilities
Permanent Sq. Footage divided by Total Sq. Footage
96.91%
96.91%
96.91%
96.91%
96.91%
96.91%
% - Temp Facilities
Temporary Sq. Footage divided by Total Sq. Footage
3.09%
3.09%
3.09%
3.09%
3.09%
3.09%
SPI Sq Ft/Student
From SPI Regulations
90
108
130
90
108
130
Boeckh Index
From SPI schedule for March 2009
$168.79
$168.79
$168.79
$168.79
$168.79
$168.79
Match % - State
From SPI Webpage March 2008
59.17%
59.17%
59.17%
59.17%
59.17%
59.17%
Match % - District
Computed
40.83%
40.83%
40.83%
40.83%
40.83%
40.83%
Dist Aver AV
King County Department of Assessments March 2009
$316,271
$316,271
$316,271
$85,729
$85,729
$85,729
(multi family weighted average)
Debt Sery Tax Rate
Current Fiscal Year
$1.67
$1.67
$1.67
$1.67
$1.67
$1.67
G. 0 Bond Int Rate
Current Rate - (Bond Buyer 20 Index March 2009)
4.99%
4.99%
4.99%
4.99%
4.99%
4.99%
Site Cost Pro "ections
Recent Property
Acquisitions
Acreage
Purchase
Year
Purchase
Price
Purchase
Cost/Acre
Adjusted
Present Day
Projected Annual
Inflation Factor
Sites
Required
Latest Date
of Acquisition
Projected
Cost/Acre
Lakeland
12.00
2002
$2,701,043
$225,087
$301,638
Labrador
35.00
2008
$7,601,799
$217,194
$217,194
Total
47.00
$10,302,842
$219,209
$259,416
5.00%
Middle School
2010
$286,006
27
Auburn School District No. 408
Capital Facilities Plan
2009 through 2015
Section VIII
Appendix
Appendix A.1 - Student Enrollment Projections
Appendix A.2 - CAPITAL FACILITIES PLAN Enrollment Projections
Appendix A.3 - Student Generation Survey
Appendix A.1 - Student Enrollment Projections
Auburn School District #408
Student Enrollment Projections
October 2008
Introduction
The projective techniques give some consideration to historical and current data as a basis for
forecasting the future. In addition, the `projector' must make certain assumptions about the operant
variables within the data being used. These assumptions are "judgmental" by definition. Forecasting
can be defined as the extrapolation or logical extension from history to the future, or from the known
to the unknown. The attached tabular data reviews the history of student enrollment, sets out some
quantitative assumptions, and provides projections based on these numerical factors.
The projection logic does not attempt to weigh the individual sociological, psychological, economic,
and political factors that are present in any demographic analysis and projection. The logic embraces
the assumptions that whatever these individual factors have been in the past are present today, and will
be in the future. It further moderates the impact of singular factors by averaging data over thirteen
years and six years respectively. The results provide a trend, which reflects a long (13 -year) and a short
(6 -year) base from which to extrapolate.
Two methods of estimating the number of kindergarten students have been used. The first uses the
average increase or decrease over the past 13 and 6 -year time frame and adds it to each succeeding
year. The second derives what the average percentage Auburn kindergartners have been of the live
births in King County for the past 5 years and uses this to project the subsequent four years.
The degree to which the actuals deviate from the projections can only be measured after the fact.
This deviation provides a point of departure to evaluate the effectiveness of the assumptions and logic
being used to calculate future projections. Monitoring deviation is critical to the viability and
credibility of the projections derived by these techniques.
Tables
Table 1 — Thirteen Year History of October 1 Enrollments — page 3
The data shown in this table is the baseline information used to project future enrollment. This data
shows the past record of enrollment in the district on October 1 of each year.
Table 2 — Historical Factors Used in Projections - page 4
This table shows the three basic factors derived from the data in Table 1. These factors have been
used in the subsequent projections. The three factors are:
1. Factor 1— Average Pupil Change Between Grade Levels
This factor is sometimes referred to as the "holding power" or "cohort survival." It is a
measure of the number of pupils gained or lost as they move from one grade level to the
next.
2. Factor 2 - Average Pupil Change by Grade Level
This factor is the average change at each grade level over the 13 or 6 -year period.
3. Factor 3 — Auburn School District Kindergarten Enrollment as a Function of King
County Live Births.
This factor calculates what percent each kindergarten class was of the King County live
births in the 5 previous years. From this information has been extrapolated the
kindergarten pupils expected for the next 4 years.
1
Table 3 — Projection Models — pages 5 -13
This set of tables utilizes the above mentioned variables and generates several projections. The
models are explained briefly below.
❑ Table 3.13 (pg 5) — shows a projection based on the 13 -year average gain in kindergarten
(Factor 2) and the 13 -year average change between grade levels (Factor 1). The data is
shown for the district as a whole.
❑ Table 3.6 (pg 5) — shows a projection using the same scheme as Table 3.13 except it
shortens the historical to only the most recent 6 years.
❑ Table 3.13A and 3.6A (pg 6) — uses the same factors above except Factor 3 is substituted
for Factor 2. The kindergarten rates are derived from the King County live births instead
of the average gain.
❑ Tables 3E.13, 3E.6, 3E.13A, 3E.6A (pg 7) — breaks out the K -5 grades from the district
projection. Summary level data is provided for percentage gain and pupil gain by grade
articulation.
❑ Tables 3MS.13, 3MS.6, 3MS.13A, 3MS.6A (pg 8) — breaks out the 6 -8 grades from the
district projection. Summary level data is provided for percentage gain and pupil gain by
grade articulation.
❑ Tables 3SH.13, 3SH.6, 3SH.13A, 3SH.6A (pg 9) — breaks out the 9 -12 grades from the
district projection. Summary level data is provided for percentage gain and pupil gain by
grade articulation.
❑ Table 4 (pg 10) — Collects the four projection models by grade group for ease of
comparison.
❑ Table 5 (pgs 11 -13) — shows how well each projection model performed when compared
with actual enrollments. Data is provided in both number and percent formats for the
past 13 years.
Summary.
Historically, average gain in students over the past 6 years is 1.53% annually that equates to 213
students. Over the past 13 years the average gain is 1.41% and equates to 189 students annually.
Using the cohort survival models that data below is a summary of the range of variation between the
four models. This data can be used for planning for future needs of the district.
The models show changes in the next six years:
• Elementary level shows increase ranging from 286 to 581. (page 7)
• Middle School level shows increase ranging from 170 to 256. (page 8)
• High School level shows decreases ranging from -38 to -112. (page 9)
The models show these changes looking forward thirteen years:
• Elementary level shows increase ranging from 490 to 1220. (page 7)
• Middle School level shows increase ranging from 300 to 599. (page 8)
• High School level shows increase ranging from 106 to 374. (page 9)
This data does not factor new developments that are currently under construction or in the planning
stages.
2
AUBURN SCHOOL DISTRICT STUDENT ENROLLMENT PROJECTIONS - October 2008
TABLE Thirteen Year History of October 1 Enrollments(Rev 10/08)
1
Actual
GRADE
96/97
97/98 98/99
99 -00
00 -01
01 -02
02 -03
03 -04
04 -05
05 -06
06 -07
07 -08
08 -09
KDG
963
978
854
849
912
846
905
922
892
955
941
996
998
1
998
1031
995
943
905
968
900
982
960
963
1012
995
1015
2
970
1014
1023
1015
914
949
961
909
992
963
1002
1019
1024
3
990
980
1009
1054
1031
966
940
996
918
1002
1031
997
1048
4
961
985
974
1012
1071
1077
973
947
1016
939
1049
1057
1044
5
917
958
982
983
1011
1108
1062
1018
957
1065
998
1078
1069
6
916
941
962
981
998
1028
1104
1111
1020
1004
1058
1007
1096
7
934
959
939
1015
979
1017
1021
1131
1124
1028
1014
1057
1034
8
949
911
959
974
1003
1004
1026
1052
1130
1137
1072
1033
1076
9
1061
1163
1156
1202
1222
1405
1441
1473
1461
1379
1372
1337
1256
10
1084
1012
1165
1132
1157
1073
1234
1249
1261
1383
1400
1368
1341
11
893
1026
1007
1036
1067
1090
927
1010
1055
1182
1322
1352
1350
12
805
811
917
855
865
930
933
902
886
1088
1147
1263
1352
TOTALS
12441
12769
12942
13051
13135
13461
13427
13702
13672
14088
14418
14559
14703
Percent of Gain
2.64% 1.35% 0.84% 0.64% 2.48% (0.25)%
2.05% (0.22)% 3.04% 2.34% 0.98% 0.99%
Pupil Gain
328 173 109 84 326 -34
275 -30 416 330 141 144
Average % Gain for 1st 6 years. 1.28%
Average % Gain for last 6 years 1.53%
Average Pupil Gain for 1st 6 years. 164
Average Pupil Gain for last 6 years 213
Average % Gain for 13 years. 1.41%
Average Pupil Gain for 13 years. 189
TABLE
1A Grade Group Combinations
KDG 963 978 854 849 912 846 905 922 892 955 941 996
K,1,2 2931 3023 2872 2807 2731 2763 2766 2813 2844 2881 2955 3010
K -5 5799 5946 5837 5856 5844 5914 5741 5774 5735 5887 6033 6142
K -6 6715 6887 6799 6837 6842 6942 6845 6885 6755 6891 7091 7149
1 -3 2958 3025 3027 3012 2850 2883 2801 2887 2870 2928 3045 3011
1 -5 4836 4968 4983 5007 4932 5068 4836 4852 4843 4932 5092 5146
1 -6 5752 5909 5945 5988 5930 6096 5940 5963 5863 5936 6150 6153
6 -8 2799 2811 2860 2970 2980 3049 3151 3294 3274 3169 3144 3097
7 -8 1883 1870 1898 1989 1982 2021 2047 2183 2254 2165 2086 2090
7 -9 2944 3033 3054 3191 3204 3426 3488 3656 3715 3544 3458 3427
9 -12 3843 4012 4245 4225 4311 4498 4535 4634 4663 5032 5241 5320
10 -12 2782 2849 3089 3023 3089 3093 3094 3161 3202 3653 3869 3983
998
3037
6198
7294
3087
5200
6296
3206
2110
3366
5299
4043
prj08- 09.xls Page 3 10/20/2008
AUBURN SCHOOL DISTRICT STUDENT F "''OLLMENT PROJECTIONS - October 2008
., c Factors Used in Projections
2
Factor Average Pupil Change Between Grade
1 Levels
13 YEAR BASE 6 YEAR BASE
K to 1
54.67 K to 1
47.80
1to2
11.08 1to2
17.60
2 to 3
20.08 2 to 3
22.20
3to4
19.17 3to4
32.20
4to5
19.00 4to5
31.80
5to6
14.42 5to6
13.80
6to7
________
15.67 6to7
11.40
7to8
13.25 7to8
18.80
8 to 9
301.42 8 to 9
276.20
9 to 10
(74.75) 9 to 10
(53.80)
10 to 11
(91.17) 10 to 11
(80.00)
11 to 12
(84.83) 11 to 12
(37.00)
total 218.00 total 301.00
Factor 1 is the average gain or loss of pupils as they
move from one grade level to the next. Factor 1 uses
the past (12) OR (5) years of changes.
Factor Average Pupil Change By Grade Level
2
13 YEAR BASE
AUBURN SCHOOL DISTRICT KINDERGARTEN ENROLLMENTS
AS FUNCTION OF KING COUNTY LIVE BIRTH RATES
6 YEAR BASE
K
2.92
K
15.20
1
1.42
1
6.60
2
4.50
2
23.00
3
4.83
3
10.40
4
6.92
4
19.40
5
12.67
5
10.20
6
15.00
6
(3.00)
7
8.33
7
(19.40)
8
10.58
8
4.80
9
16.25
9
(43.40)
10
21.42
10
18.40
11
38.08
11
68.00
12
45.58
12
90.00
Factor 2 is the average change in grade level size
from 94/95 OR 01/02.
prj08- 09.xls
Factor
3
AUBURN SCHOOL DISTRICT KINDERGARTEN ENROLLMENTS
AS FUNCTION OF KING COUNTY LIVE BIRTH RATES
CAL-
ENDAR
YEAR
TOTAL
LIVE
BIRTHS
2 /3rds
BIRTHS
1 /3rds
BIRTHS
YEAR
OF
ENROLL
ADJUSTED
LIVE
BIRTHS
KDG
ENROLL.
AUBURN KINDERGARTEN
ENROLLMENT AS A % OF
ADJUSTED LIVE BIRTHS
1971
16,436
10,957
5,479
77/78
14,625 578
3.952%
1972
13,719
9,146
4,573
78/79
13,539 598
4.417%
1973
13,449
8,966
4,483
79/80
13,478 618
4.585%
1974
13,493
8,995
4,498
80/81
13,524 600
4.436%
1975
13,540
9,027
4,513
81/82
13,687 588
4.296%
1976
13,761
9,174
4,587
82/83
14,375 698
4.856%
1977
14,682
9,788
4,894
83/84
14,958 666
4.452%
1978
15,096
10,064
5,032
84/85
16,048 726
4.524%
1979
16,524
11,016
5,508
85/86
16,708 792
4.740%
1980
16,800
11,200
5,600
86/87
17,000 829
4.876%
1981
17,100
11,400
5,700
87/88
18,241 769
4.216%
1982
18,811
12,541
6,270
88/89
18,626 817
4.386%
1983
18,533
12,355
6,178
89/90
18,827 871
4.626%
1984
18,974
12,649
6,325
90/91
19,510 858
4.398%
1985
19,778
13,185
6,593
91/92
19,893 909
4.569%
1986
19,951
13,301
6,650
92/93
21,852 920
4.210%
1987
22,803
15,202
7,601
93/94
21,624 930
4.301%
1988
21,034
14,023
7,011
94/95
24,062 927
3.853%
1989
25,576
17,051
8,525
95/96
26,358 954
3.619%
1990
26,749
17,833
8,916
96/97
24,116 963
3.993%
1991
22,799
15,199
7,600
97/98
20,973 978
4.663%
1992
20,060
13,373
6,687
98/99
21,573 854
3.959%
1993
22,330
14,887
7,443
99/00
22,129 849
3.837%
1994
22,029
14,686
7,343
00/01
24,013 912
3.798%
1995
25,005
16,670
8,335
01/02
22,717 846
3.724%
1996
21,573
14,382
7,191
02/03
21,622 905
4.186%
1997
21,646
14,431
7,215
03/04
22,023 922
4.186%
1998
22,212
14,808
7,404
04/05
22,075 892
4.041%
Last 5
1999
22,007
14,671
7,336
05/06
22,327 955
4.277%
year
2000
22,487
14,991
7,496
06/07
22,014 941
4.274%
Average
2001
21,778
14,519
7,259
07/08
21,835 996
4.562%
4.328%
2002
21,863
14,575
7,288
08/09
22,242
998
Actual
4.487%
2003
22,431
14,954
7,477
09/10
22,726
984
<-- Prjctd
Average
2004
22,874
15,249
7,625
10/11
22,745
984
<-- Prjctd
Average
2005
22,680
15,120
7,560
11/12
23,723
1027
<-- Prjctd
Average
2006
24,244
16,163
8,081
12/13
24,683
1068
<-- Prjctd
Average
2007
24,902
16,601
8,301
13/14
8,301 .
• preliminary
number of DOH
Source: Center for Health Statistics, Washington State Department of Health
Page 4 10/20/2008
AUBURN SCHOOL DISTRICT STUDENT ENROLLMENT PROJECTIONS - October 2008
TABLE DISTRICT PROJECTIONS
3.13 Based on 13 Year History
GRADE
ACTUAL
08/09
PROJ
09/10
PROJ
10/11
PROJ
11/12
PROJ
12/13
PROJ
13/14
PROJ
14/15
PROJ
15/16
PROJ
16/17
PROJ
17/18
PROJ
18/19
PROJ
19/20
PROJ
20/21
PROJ
21/22
KDG 998 1001 1004 1007 1010 1013 1016 1018 1021 1024 1027 1030 1033 1036
1 1015 1053 1056 1059 1061 1064 1067 1070 1073 1076 1079 1082 1085 1088
2 1024 1026 1064 1067 1070 1073 1075 1078 1081 1084 1087 1090 1093 1096
3 1048 1044 1046 1084 1087 1090 1093 1096 1098 1101 1104 1107 1110 1113
4 1044 1067 1063 1065 1103 1106 1109 1112 1115 1118 1121 1123 1126 1129
5 1069 1063 1086 1082 1084 1122 1125 1128 1131 1134 1137 1140 1142 1145
6 1096 1083 1077 1101 1097 1099 1136 1139 1142 1145 1148 1151 1154 1157
7 1034 1112 1099 1093 1116 1112 1114 1152 1155 1158 1161 1164 1167 1170
8 1076 1047 1125 1112 1106 1130 1126 1128 1165 1168 1171 1174 1177 1180
9 1256 1377 1349 1426 1414 1408 1431 1427 1429 1467 1470 1473 1476 1478
10 1341 1181 1303 1274 1352 1339 1333 1356 1352 1354 1392 1395 1398 1401
11 1350 1250 1090 1212 1183 1260 1248 1242 1265 1261 1263 1301 1304 1307
12 1352 1265 1165 1005 1127 1098 1176 1163 1157 1180 1176 1178 1216 1219
TOTALS 1 14703 1 14570 I 14527 I 14586 1 14809 I 14913 I 15048 1 15109 1 15185 I 15271 I 15336 I 15408 I 15480 15518
Percent of Gain (0.91)% (0.30)% 0.41% 1.52% 0.70% 0.91% 0.40% 0.51% 0.56% 0.43% 0.47% 0.47% 0.24%
Pupil Gain (133) (43) 60 222 104 136 61 76 85 65 72 73 38
TABLE DISTRICT PROJECTIONS
3.6 Based on 6 Year His ory
GRADE
ACTUAL
08/09
PROJ
09/10
PROJ
10/11
PROJ
11/12
PROJ
12/13
PROJ
13/14
PROJ
14/15
PROJ
15/16
PROJ
16/17
PROJ
17/18
PROJ
18/19
PROJ
19/20
PROJ
20/21
PROJ
21/22
KDG 998 1013 1028 1044 1059 1074 1089 1104 1120 1135 1150 1165 1180 1196
1 1015 1046 1061 1076 1091 1107 1122 1137 1152 1167 1183 1198 1213 1228
2 1024 1033 1063 1079 1094 1109 1124 1139 1155 1170 1185 1200 1215 1231
3 1048 1046 1055 1086 1101 1116 1131 1146 1162 1177 1192 1207 1222 1238
4 1044 1080 1078 1087 1118 1133 1148 1163 1179 1194 1209 1224 1239 1255
5 1069 1076 1112 1110 1119 1150 1165 1180 1195 1210 1226 1241 1256 1271
6 1096 1083 1090 1126 1124 1133 1163 1179 1194 1209 1224 1239 1255 1270
7 1034 1107 1094 1101 1137 1135 1144 1175 1190 1205 1220 1236 1251 1266
8 1076 1053 1126 1113 1120 1156 1154 1163 1194 1209 1224 1239 1254 1270
9 1256 1352 1329 1402 1389 1396 1432 1430 1439 1470 1485 1500 1515 1531
10 1341 1202 1298 1275 1349 1335 1342 1378 1377 1385 1416 1431 1446 1462
11 1350 1261 1122 1218 1195 1269 1255 1262 1298 1297 1305 1336 1351 1366
12 1352 1313 1224 1085 1181 1158 1232 1218 1225 1261 1260 1268 1299 1314
TOTALS I 14703 I 14665 I 14682 I 14802 I 15077 I 15270 I 15502 I 15676 I 15878 I 16089 I 16279 I 16485 I 16698 I 16896
Percent of Gain (0.26)% 0.11% 0.82% 1.86% 1.28% 1.52% 1.12% 1.29% 1.33% 1.18% 1.27% 1.29% 1.18%
Pupil Gain (38) 16 121 275 194 232 174 202 211 190 207 213 198
prj08- 09.xls Page 5 10/20/2008
AUBURN SCHOOL DISTRICT STUDENT E' "'OLLMENT PROJECTIONS - October 2008
'i. c DISTRICT PROJECTIONS
3.13A Based on Birth Rates & 13 Year History
GRADE
ACTUAL
08/09
PROJ
09/10
PROJ
10/11
PROJ
11/12
PROJ
12/13
PROJ
13/14
PROJ
14/15
PROJ
15/16
PROJ
16/17
PROJ
17/18
PROJ
18/19
PROJ
19/20
PROJ
20/21
PROJ
21/22
K 998 984 984 1027 1068
1 1015 1053 1038 1039 1081 1123
2 1024 1026 1064 1049 1050 1093 1134
3 1048 1044 1046 1084 1069 1070 1113 1154
4 1044 1067 1063 1065 1103 1089 1089 1132 1173
5 1069 1063 1086 1082 1084 1122 1108 1108 1151 1192
6 1096 1083 1077 1101 1097 1099 1136 1122 1123 1165 1207
7 1034 1112 1099 1093 1116 1112 1114 1152 1138 1139 1181 1222
8 1076 1047 1125 1112 1106 1130 1126 1128 1165 1151 1152 1194 1236
9 1256 1377 1349 1426 1414 1408 1431 1427 1429 1467 1452 1453 1496 1537
10 1341 1181 1303 1274 1352 1339 1333 1356 1352 1354 1392 1378 1378 1421
11 1350 1250 1090 1212 1183 1260 1248 1242 1265 1261 1263 1301 1286 1287
12 1352 1265 1165 1005 1127 1098 1176 1163 1157 1180 1176 1178 1216 1202
TOTALS 1 14703 1 14553 1 14490 1 14570 1 14851
Percent of Gain (1.02)% (0.43)% 0.55% 1.93%
Pupil Gain (150) (63) 80 281
I _I I I I I I I
TABLE DISTRICT PROJECTIONS
3.6A Based on Birth Rates & 6 Year History
GRADE
ACTUAL
08/09 _
PROJ
09/10 _
PROJ
10/11
PROJ
11/12
PROJ
12/13
PROJ
13/14
PROJ
14/15 _
PROJ
15/16
PROJ
16/17
PROJ
17/18
PROJ
18/19 _
PROJ
19/20
PROJ
20/21
PROJ
21/22
KDG 998 984 984 1027 1068
1 1015 1046 1031 1032 1075 1116
2 1024 1033 1063 1049 1050 1092 1134
3 1048 1046 1055 1086 1071 1072 1114 1156
4 1044 1080 1078 1087 1118 1103 1104 1147 1188
5 1069 1076 1112 1110 1119 1150 1135 1136 1178 1220
6 1096 1083 1090 1126 1124 1133 1163 1149 1150 1192 1234
7 1034 1107 1094 1101 1137 1135 1144 1175 1160 1161 1204 1245
8 1076 1053 1126 1113 1120 1156 1154 1163 1194 1179 1180 1222 1264
9 1256 1352 1329 1402 1389 1396 1432 1430 1439 1470 1455 1456 1499 1540
10 1341 1202 1298 1275 1349 1335 1342 1378 1377 1385 1416 1402 1402 1445
11 1350 1261 1122 1218 1195 1269 1255 1262 1298 1297 1305 1336 1322 1322
12 1352 1313 1224 1085 1181 1158 1232 1218 1225 1261 1260 1268 1299 1285
TOTALS 1 14703 1 14636 14608 1 14712 1 14996
Percent of Gain (0.46)% (0.19)% 0.71% 1.93%
Pupil Gain (67) (28) 104 284
1 1 1 1 1 1 1 1
prj08- 09.xls
Page 6 10/20/2008
AUBURN SCHOOL DISTRICT STUDENT ENROLLMENT PROJECTIONS - October 2008
TABLE K - 5 PROJECTIONS
3E.13 Based on 13 Year Histor
GRADE
ACTUAL
08/09
PROJ I PROJ
09/10 10/11
PROJ
11/12
PROJ
12/13
PROJ
13/14
PROJ I PROJ
14/15 15/16
PROJ
16/17
PROJ
17/18
PROJ
18/19
PROJ
19/20
PROJ
20/21
PROJ
21/22
KDG 998 1001 1004 007 1010 1013 1016 1018 11 1 1024 1027 1030 1033 1036
1 1015 1053 1056 1059 1061 1064 1067 1070 1073 1076 1079 1082 1085 1088
2 1024 1026 1064 1067 1070 1073 1075 1078 1081 1084 1087 1090 1093 1096
3 1048 1044 1046 1084 1087 1090 1093 1096 1098 1101 1104 1107 1110 1113
4 1044 1061 1063 1065 1103 1108 1109 1112 1115 1118 1121 , 1123 1128 1129
5 1069 1063 1086 1082 1084 1122 1125 1128 1131 1134 1137 1140 1142 1145
K -5 TOTS 6198 I 6254 I 6319 1 6363 T 6415 I 6467 I 6485 1 6502 I 6520 I 6537 1 6555 I 6572 I 6590 1 6607
Percent of Gair 0.90% 1.04% 0.71 % 0.81 % 0.81 /o 0.27% 0.27°/0 0.27% 0.2 % 0.27% 0.27°/0 0.27% 0.27%
Pupil Gain 56 65 45 51 52 18 18 17 18 18 17 18 18
TABLE K - 5 PROJECTIONS
3E.6 Based on 6 Year Histor.
GRADE
ACTUAL PROD PROJ
08/09 I 09/10 I 10/11
PROJ
11/12
PROJ
12/13
PR•J
13/14
PROJ I PROJ
14/15 15/16
PR•J
16/17
PROJ
17/18
PROJ
18/19
PROJ 1 PROJ
19/20 l 20/21
PROJ
21/22
KDG 998 1013 1028 044 TO- 9 10 4 1089 1104 120 ¶135 1150 1165 1180 1196
1 1015 1046 1061 1076 1091 1107 1122 1137 1152 1167 1183 1198 1213 1228
2 1024 1033 1063 1079 1094 1109 1124 1139 1155 1170 1185 1200 1215 1231
3 1048 1046 1055 1086 1101 1116 1131 1146 1162 1177 1192 1207 1222 1238
4 1044 1080 1078 1087 1118 1133 1148 1163 1179 1194 1209 1224 1239 1255
5 1069 1076 1112 1110 1119 1150 1165 1180 1195 1210 1226 1241 1256 1271
6 year 13 year I
286 409
K -5 TOT! 6198 I 6294 I 6398 1 6481 I 6581 1 6688 1 6779 I 6871 1 6962 1 7053 1 7144 1 7235 - 7327 1 7418
Percent of Gair 1.55% 1.66% 1.30% 1.55% 1.62% 1.36% 1.35% 1.33% 1.31% 1.29% 1.28% 1.26% 1.24%
Pupil Gain 96 104 83 100 107 91 91 91 91 91 91 91 91
6 year 13 year I
581 1220
TABLE K - 5 PROJECTIONS
3E.13A Based on Birth Rates & 13 Year Histor
GRADE
ACTUAL
08/09
PROJ
09/10
PROJ
10/11
PROJ
11/12
PROJ
12/13
PROJ
13/14
PROJ
14/15
PROJ
15/16
PROJ
16/17
PROJ
17/18
PROJ
18/19
PROJ
19/20
PROJ
20/21
PROJ
21/22
K 998 984 984 1027 1068
1 1015 1053 1038 1039 1081 1123
2 1024 1026 1064 • 1049 1050 1093 1134
3 1048 1044 1046 1084 1069 1070 1113 1154
4 1044 1081 1083 1065 1103 1089 1089 1132 1173
5 1069 1063 1086 1082 1084 1122 1108 1108 1151 1192
K-5 TOT I 6198 1 6237 1 6282 I 6347 1 6457 I j
Percent of Garr 0.62% 0.73% 1.03% 1.73%
Pupil Gain 39 45 65 110
TABLE K - 5 PROJECTIONS
3E.6A Based on Birth Rates & 6 Year Histor
GRADE
ACTUAL
08/09
PROJ
09/10
PROJ
10/11
PROJ
11/12
PROJ PROJ
12/13 13/14
PROJ
14/15
PROJ
15/16
PROJ
16/17
PROJ
17/18
PROJ
18/19
PROJ I PROJ
19/20 1 20/21
PROJ
21/22
KDG 998 984 984 1027 1068
1 1015 1046 1031 1032 1075 1116
2 1024 1033 1063 1049 1050 1092 1134
3 1048 1046 1055 1086 1071 1072 1114 1156
4 1044 1080 1078 1087 1118 1103 1104 1147 1188
5 1069 1076 1112 1110 1119 1150 1135 1136 1178 1220
K- 5 TOT I 6198 I 6264 I 6324 1 6391 1 6501 j 1 j ) 1 1
Percent of Gair 1.07% 0.96% 1.05% 1.72%
Pupil Gain 66 60 66 110
4 year
259
4 year I
303
prj08- 09.xls Page 7 10/20/2008
TABLE
MIDDLE SCHOOL PROJEC
TIONS
i
ACTUAL
PROJ
PROJ
PROJ
PROJ
PROJ
PROJ
PROJ
PROJ
PROJ
PROJ
PROJ
PROJ
PROJ
GRADE
08/09
09/10
10/11
11/12
12/13
13/14
14/15
15/16
16/17
17/18
18/19
19/20
20/21
21/22
6 1096
1083
1090
1126 1124
1133
1163
1179
1194
1209
1224
1239
1255
1270
7 1034
1107
1094
1101 1137
1135
1144
1175
1190
1205
1220
1236
1251
1266
8 1076
1053
1126
1113 1120
1156
1154
1163
1194
1209
1224
1239
1254
1270
6 -8 TOT 3206
3243
3310
3340 3381
3424
3462
3516
3577
3623
3669
3714
3760
3805
Percent of Gain
1.15%
2.07%
.90% 1.23%
1.27%
1.10%
1.58%
1.74%
1.27%
1.26%
1.24%
1.23%
1.21%
Pupil Gain
37
67
30 41
43
38
55
61
46
46
46
46
46
AUBURN SCHOOL DISTRICT STUDENT F "'OLLMENT PROJECTIONS - October 2008
TABLE
3MS.13
MIDDLE SCHOOL PROJECTIONS
Based on 13 Year History
GRADE
ACTUAL
08/09
PROJ
09/10
PROJ
10/11
PROJ
11/12
PROJ
12/13
PROJ
13/14
PROJ
14/15
PROJ
_ 15/16
PROJ
16/17
PROJ
17/18
PROJ
18/19
PROJ
19/20
PROJ
20/21
PROJ
21/22
6 1096 1083 1077 1101 1097 1099 1136 1139 1142 1145 1148 1151 1154 1157
7 1034 1112 1099 1093 1116 1112 1114 1152 1155 1158 1161 1164 1167 1170
8 1076 1047 1125 1112 1106 1130 1126 1128 1165 1168 1171 1174 1177 1180
6 -8 TOT I 3206 I 3242 I 3301 I 3306 I 3319 I 3341 I 3376 I 3419 I 3463 l 3471 I 3480 I 3489 I 3498 I 3506
Percent of Gain 1.13% 1.82% 0.14% 0.40% 0.64% 1.07% 1.26% 1.27% 0.25% 0.25% 0.25% 0.25% 0.25%
Pupil Gain 36 59 5 13 21 36 43
43
9
9
9
9
9
6 year 13 year
170 300
TABLE
MIDDLE SCHOOL PROJECTIONS
6 year
256
13 year I
599
_M
GRADE
ACTUAL
08/09
PROJ
09/10
PROJ
10/11
PROJ
11/12
PROJ
12/13
PROJ
13/14
PROJ
14/15
PROJ
15/16
PROJ
16/17
PROJ
17/18
PROJ
18/19
PROJ
19/20
PROJ
20/21
PROJ
21/22
6 1096
1083
1077
1101 1097
1099
1136
1122
1123
1165
1207
7 1034
1112
1099
1093 1116
1112
1114
1152
1138
1139
1181 1222
8 1076
1047
1125
1112 1106
1130
1126
1128
1165
1151
1152 1194 1236
6 -8 TOT 3206
3242
3301
3306 3319
3341
3376
3402
3426
3455
3539 - --
Percent of Gain
1.13%
1.82%
0.14% 0.40%
0.64%
1.07%
0.75%
0.71%
0.84%
2.45%
Pupil Gain
36
59
5 13
21
36
25
24
29
85
TABLE MIDDLE SCHOOL PROJECTIONS
6 year
170
10 year 1
333
_r..S
GRADE
ACTUAL
08/09
PROJ
09/10
PROJ
10/11
PROJ
11/12
PROJ
12/13
PROJ
13/14
PROJ
14/15
PROJ
15/16
PROJ
16/17
PROJ
17/18
PROJ
18/19
PROJ
19/20
PROJ
20/21
PROJ
21/22
6 1096
1083
1090
1126 1124
1133
1163
1149
1150
1192
1234
7 1034
1107
1094
1101 1137
1135
1144
1175
1160
1161
1204 1245
8 1076
1053
1126
1113 1120
1156
1154
1163
1194
1179
1180 1222 1264
6 -8 TOT 3206
3243
3310
3340 3381
3424
3462
3487
3504
3533
3617 -- _
Percent of Gain
1.15%
2.07%
0.90% 1.23%
1.27%
1.10%
0.72%
0.49%
0.82%
2.40%
Pupil Gain
37
67
30 41
43
38
25
17
29
85
prj08- 09.xls
6 year
256
10 year]
411
Page 8 10/20/2008
AUBURN SCHOOL DISTRICT STUDENT ENROLLMENT PROJECTIONS - October 2008
TABLE
3SH.13
SR. HIGH PROJECTIONS
Based on 13 Year History
GRADE
ACTUAL
08/09
PROJ
09/10
PROJ
10/11
PROJ
11/12
PROJ
12/13
PROJ
13/14
PROJ
14/15
PROJ
15/16
PROJ
16/17
PROJ
17/18
PROJ
18/19
PROJ
19/20
PROJ
20/21
PROJ
21/22
9 1256 1377 1349 1426 1414 1408 1431 1427 1429 1467 1470 1473 1476 1478
10 1341 1181 1303 1274 1352 1339 1333 1356 1352 1354 1392 1395 1398 1401
11 1350 1250 1090 1212 1183 1260 1248 1242 1265 1261 1263 1301 1304 1307
12 1352 1265 1165 1005 1127 1098 1176 1163 1157 1180 1176 1178 1216 1219
9 -12 TOT 5299 I 5074 I 4906 I 4917 I 5075 I 5105 I 5187 I 5188 I 5203 I 5262 I 5301 I 5347 I 5393 I 5405
6 year
(112)
Percent of Gain (4.25)% (3.30)% 0.22% 3.21% 0.60% 1.61% 0.01% 0.30% 1.13% 0.74% 0.86% 0.87% 0.22%
Pupil Gain (225) (167) 11 158 30 82 1 15 59 39 46 46 12
TABLE
3SH.6
SR. HIGH PROJECTIONS
Based on 6 Year His ory
GRADE
ACTUAL
08/09
PROJ
09/10
PROJ
10/11
PROJ
11/12
PROJ
12/13
PROJ
13/14
PROJ
14/15
PROJ
15/16
PROJ
16/17
PROJ
17/18
PROJ
18/19
PROJ
19/20
PROJ
20/21
PROJ
21/22
9 1256 1352 1329 1402 1389 1396 1432 1430 1439 1470 1485 1500 1515 1531
10 1341 1202 1298 1275 1349 1335 1342 1378 1377 1385 1416 1431 1446 1462
11 1350 1261 1122 1218 1195 1269 1255 1262 1298 1297 1305 1336 1351 1366
12 1352 1313 1224 1085 1181 1158 1232 1218 1225 1261 1260 1268 1299 1314
13 year I
106
9 -12 TOT 5299 I 5128 I 4974 I 4981 I 5114 I 5158 I 5261 I 5289 I 5339 I 5413 I 5466 I 5536 I 5612 I 5673
6 year
(38)
Percent of Gain (3.22)% (3.02)% 0.15% 2.67% 0.86% 2.00% 0.53% 0.94% 1.38% 0.98% 1.28% 1.38% 1.08%
Pupil Gain (171) (155) 8 133 44 103 28 50 74 53 70 76 61
TABLE
3SH.13A
SR. HIGH PROJECTIONS
Based on Birth Rates & 13 Year History
GRADE
ACTUAL
08/09
PROJ
09/10
PROJ
10/11
PROJ
11/12
PROJ
12/13
PROJ
13/14
PROJ
14/15
PROJ
15/16
PROJ
16/17
PROJ
17/18
PROJ
18/19
PROJ
19/20
PROJ
20/21
PROJ
21/22
9 1256 1377 1349 1426 1414 1408 1431 1427 1429 1467 1452 1453 1496 1537
10 1341 1181 1303 1274 1352 1339 1333 1356 1352 1354 1392 1378 1378 1421
11 1350 1250 1090 1212 1183 1260 1248 1242 1265 1261 1263 1301 1286 1287
12 1352 1265 1165 1005 1127 1098 1176 1163 1157 1180 1176 1178 1216 1202
9 -12 TOT I 5299 I 5074 I 4906 I 4917 I 5075 I 5105 I 5187 I 5188 I 5203 I 5262 I 5284 I 5310 I 5376 I 5447
Percent of Gain (4.25)% (3.30)% 0.22% 3.21% 0.60% 1.61% 0.01% 0.30% 1.13% 0.41% 0.50% 1.25% 1.31%
Pupil Gain (225) (167) 11 158 30 82 1 15 59 21 26 66 70
6 year
(112)
TABLE
3S1-1.6A
SR. HIGH PROJECTIONS
Based on Birth Rates & 6 Year History
GRADE
ACTUAL
08/09
PROJ
09/10
PROJ
10/11
PROJ
11/12
PROJ
12/13
PROJ
13/14
PROJ
14/15
PROJ
15/16
PROJ
16/17
PROJ
17/18
PROJ
18/19
PROJ
19/20
PROJ
20/21
PROJ
21/22
9 1256 1352 1329 1402 1389 1396 1432 1430 1439 1470 1455 1456 1499 1540
10 1341 1202 1298 1275 1349 1335 1342 1378 1377 1385 1416 1402 1402 1445
11 1350 1261 1122 1218 1195 1269 1255 1262 1298 1297 1305 1336 1322 1322
12 1352 1313 1224 1085 1181 1158 1232 1218 1225 1261 1260 1268 1299 1285
13 year I
374
13 year I
148
9 -12 TOT 5299 5128 4974 4981 5114 5158 5261 5289 5339 5413 5436 5462 5522 5592
Percent of Gain (3.22)% (3.02)% 0.15% 2.67% 0.86% 2.00% 0.53% 0.94% 1.38% 0.43% 0.48% 1.09% 1.27%
Pupil Gain (171) (155) 8 133 44 103 28 50 74 23 26 60 70
6 year
(38)
13 year
293
prj08- 09.xls Page 9 10/20/2008
AUBURN SCHOOL DISTRICT STUDENT E "QOLLMENT PROJECTIONS - October 2008
TABLE
4
PROJECTION COMPARISONS
BY GRADE GROUP
KINDERGARTEN
GRADE
ACTUAL
08/09
PROJ
09/10
PROJ
10/11
PROJ
11/12
PROJ
12/13
PROJ
13/14
PROJ
14/15
PROJ
15/16
PROJ
16/17
PROJ
17/18
PROJ
18/19 __
PROJ
19/20
PROJ
20/21
PROJ
21/22
E.13 998 1001 1004 1007 1010 1013 1016 1018 1021 1024 1027 1030 1033 1036
E.6 998 1013 1028 1044 1059 1074 1089 1104 1120 1135 1150 1165 1180 1196
E.13A 998 984 984 1027 1068
E.6A 998 984 984 1027 1068
6 year
17
91
GRD 1 -- GRD 5
GRADE
ACTUAL
08/09
PROJ
09/10
PROJ
10/11
PROJ
11/12
PROJ
12/13
PROJ
13/14 _
PROJ
14/15
PROJ
15/16
PROJ
16/17
PROJ
17/18
PROJ
18/19
PROJ
19/20
PROJ
20/21
PROJ
21/22
13 year
38
198
E.13 5200 5253 5315 5357 5405 5454 5469 5484 5498 5513 5527 5542 5557 5571
E.6 5200 5281 5370 5438 5523 5614 5690 5766 5842 5918 5994 6070 6146 6222
E.13A 5200 5253 5298 5320 5388
E.6A 5200 5281 5340 5364 5432
6 year
269
490
13 year
371
1022
GRD 6 -- GRD 8
GRADE
ACTUAL
08/09
PROJ
09/10
PROJ
10/11
PROJ
11/12
PROJ
12/13
PROJ
13/14 __
PROJ
14/15
PROJ
15/16
PROJ
16/17
PROJ
17/18
PROJ
18/19
PROJ
19/20
PROJ
20/21
PROJ
21/22
MS.13 3206 3242 3301 3306 3319 3341 3376 3419 3463 3471 3480 3489 3498 3506
MS.6 3206 3243 3310 3340 3381 3424 3462 3516 3577 3623 3669 3714 3760 3805
MS.13A 3206 3242 3301 3306 3319 3341 3376 3402 3426 3455 3539
MS.6A 3206 3243 3310 3340 3381 3424 3462 3487 3504 3533 3617
6 year
170
256
13 year
300
599
GRD 9 -- GRD 12
GRADE
ACTUAL
08/09
PROJ
09/10
PROJ
10/11
PROJ
11/12
PROJ
12/13
PROJ
13/14
PROJ
14/15
PROJ
15/16
PROJ
16/17
PROJ
17/18
PROJ
18/19
PROJ
19/20
PROJ
20/21
PROJ
21/22
SH.13 5299 5074 4906 4917 5075 5105 5187 5188 5203 5262 5301 5347 5393 5405
SH.6 5299 5128 4974 4981 5114 5158 5261 5289 5339 5413 5466 5536 5612 5673
SH.13A 5299 5074 4906 4917 5075 5105 5187 5188 5203 5262 5284 5310 5376 5447
SH.6A 5299 5128 4974 4981 5114 5158 5261 5289 5339 5413 5436 5462 5522 5592
6 year
(112)
(38)
(112)
(38)
13 year
106
374
148
293
DISTRICT TOTALS
GRADE
ACTUAL
08 /09
PROJ
09/10
PROJ
10/11
PROJ
11/12
PROJ
12/13
PROJ
13/14
PROJ
14/15
PROJ
15/16
PROJ
16/17
PROJ
17/18
PROJ
18/19
PROJ
19/20
PROJ
20/21
PROJ
21/22
3.13 14703 14570 14527 14586 14809 14913 15048 15109 15185 15271 15336 15408 15480 15518
3.6 14703 14665 14682 14802 15077 15270 15502 15676 15878 16089 16279 16485 16698 16896
3.13A 14703 14553 14490 14570 14851
3.6A 14703 14636 14608 14712 14996
6 year
345
799
13 year
815
2193
prj08- 09.xls
Page 10 10/20/2008
AUBURN SCHOOL DISTRICT STUDENT ENROLLMENT PROJECTIONS - October 2008
TABLE
5
PROJECTION COMPARISONS
BY GRADE GROUP
Total = October 1 Actual Count AND Projected Counts
Diff = Number Projection is under( -) or over Actual
= Percent Projection is under( -) or over Actual
Prj 3.13 - 13 YEAR HISTORY & Using Average Kdg Increase
Prj 3.6 - 6 YEAR HISTORY & Using Average Kdg Increase
Prj 3.13A 13 YEAR HISTORY & King Cty Birth Rates
Prj 3.6A - 6 YEAR HISTORY & King Cty Birth Rates
Grades
K - 5
Total
1996 -97
Diff
%
Total
1997 -98
Diff
%
Total
1998 -99
Diff
%
Total
1999 -00
Diff
%
2000 -01
Total Diff
2000 -01
Diff
ACTUAL
5799
xxx
xxx
5946
xxx
xxx
5837
xxx
xxx
5856
xxx
xxx
5844 xxx
xxx
Prj 3E.13
5843
44
0.76%
5928
(18)
(0.30)%
6049
212
(0.54)%
5778
(78)
3.15%
5811 (33)
(0.56)%
Prj 3E.6
5821
22
0.38%
5904
(42)
(0.71)%
6026
189
(0.96)%
5735
(121)
2.74%
5664 (180)
(3.08)%
Prj 3E.13A
5853
54
0.93%
5783
(163)
(2.74)%
5936
99
(2.64)%
5811
(45)
1.51%
5919 75
1.28%
Prj 3E.6A
5798
(1)
(0.02)%
'5768
(178)
(2.99)%
5917
80
(2.93)%
5785
(71)
1.15%
5895 51
0.87%
Grades
6 - 8
Total
1996 -97
Diff
%
Total
1997 -98
Diff
%
Total
1998 -99
Diff
%
Total
1999 -00
Diff
%
Total
2000 -01
Diff
%
ACTUAL
2799
xxx
xxx
2811
xxx
xxx
2860
xxx
xxx
2970
xxx
xxx
2980
xxx
xxx
Prj 3E.13
2875
76
2.72%
2820
9
0.32%
2910
50
(2.64)%
2927
(80)
(2.62)%
3023
43
1.44%
Prj 3E.6
2848
49
1.75%
2789
(22)
(0.78)%
2878
18
(2.70)%
2895
(75)
(2.46)%
3009
29
0.97%
Prj3E.13A
2875
76
2.72%
2820
9
0.32%
2910
50
(2.64)%
2927
(80)
(2.62)%
3023
43
1.44%
Prj 3E.6A
2848
49
1.75%
2789
(22)
(0.78)%
2878
18
(2.70)%
2895
(75)
(2.46)%
3009
29
0.97%
Grades
9 - 12
Total
1996 -97
Diff
%
Total
1997 -98
Diff
%
Total
1998 -99
Diff
%
Total
1999 -00
Diff
%
Total
2000 -01
Diff
%
ACTUAL
3843
xxx
xxx
4012
xxx
xxx
4245
xxx
xxx
4225
xxx
xxx
4311
xxx
xxx
Prj 3E.13
3768
(75)
(1.95)%
4092
80
1.99%
4110
(135)
2.74%
4301
76
(0.32)%
4369
58
1.35%
Prj 3E.6
3750
(93)
(2.42)%
4069
57
1.42%
4103
(142)
1.51%
4313
88
(1.49)%
4394
83
1.93%
Prj 3E.13A
3768
(75)
(1.95)%
3983
(29)
(0.72)%
4110
(135)
2.74%
4301
76
(0.32)%
4369
58
1.35%
Prj 3E.6A
3750
(93)
(2.42)%
3970
(42)
(1.05)%
4103
(142)
1.51%
4313
88
(1.49)%
4394
83
1.93%
All
Grades
Total
1996 -97
Diff
%
Total
1997 -98
Diff
%
Total
1998 -99
Diff
%
Total
1999 -00
Diff
%
Total
2000 -01
Diff
%
ACTUAL
12441
xxx
xxx
12769
xxx
xxx
12942
xxx
xxx
13051
xxx
xxx
13135
xxx
xxx
Prj 3E.13
12486
45
0.36%
12840
71
0.56%
13069
127
(0.30)%
13006
(45)
0.97%
13203
68
0.52%
Prj 3E.6
12419
(22)
(0.18)%
12762
(7)
(0.05)%
13007
65
(0.82)%
12943
(108)
0.50%
13067
(68)
(0.52)%
Prj 3E.13A
12496
55
0.44%
12586
(183)
(1.43)%
12956
14
(1.44)%
13039
(12)
0.10%
13311
176
1.34%
Prj 3E.6A
12396
(45)
(0.36)%
12527
(242)
(1.90)%
12898
(44)
(1.89)%
12993
(58)
(0.33)%
13298
163
1.24%
prj08- 09.xls
Page 11 10/20/2008
AUBURN SCHOOL DISTRICT STUDENT F "ROLLMENT PROJECTIONS - October 2008
TABLE
5
PROJECTION COMPARISONS
BY GRADE GROUP (Continued)
Total = October 1 Actual Count AND Projected Counts
Diff = Number Projection is under( -) or over Actual
= Percent Projection is under( -) or over Actual
Prj 3.13 - 13 YEAR HISTORY & Using Average Kdg Increase
Prj 3.6 - 6 YEAR HISTORY & Using Average Kdg Increase
Prj 3.13A 13 YEAR HISTORY & King Cty Birth Rates
Prj 3.6A - 6 YEAR HISTORY & King Cty Birth Rates
Grades
K - 5
Total
2001 -02
Diff
%
Total
2002 -03
Diff
%
Total
2003 -04
Diff
%
Total
2004 -05
Diff
%
2005 -06
Total Diff
%
ACTUAL
5914
xxx
xxx
5741
xxx
xxx
5774
xxx
xxx
5735
xxx
xxx
5887 xxx
xxx
Prj 3E.13
5827
(87)
(1.47)%
5723
(18)
(0.31)%
5655
(119)
(0.49)%
5761
26
0.45%
5750 (137)
(2.33)%
Prj 3E.6
5802
(112)
(1.89)%
5735
(6)
(0.10)%
5662
(112)
(0.34)%
5821
86
1.50%
5795 (92)
(1.56)%
Prj 3E.13A
5839
(75)
(1.27)%
5743
2
0.03%
5605
(169)
(1.24)%
5709
(26) .
(0.45)%
5750 (137)
(2.33)%
Prj 3E.6A
5831
(83)
(1.40)%
5776
35
0.61%
5631
(143)
(0.81)%
5756
21
0.37%
5784 (103)
(1.75)%
Grades
6 - 8
Total
2001 -02
Diff
%
Total
2002 -03
Diff
%
Total
2003 -04
Diff
%
Total
2004 -05
Diff
%
2005 -06
Total Diff
%
ACTUAL
3049
xxx
xxx
3151
xxx
xxx
3294
xxx
xxx
3274
xxx
xxx
3169 xxx
xxx
Prj 3E.13
3025
(24)
(0.79)%
3185
34
1.08%
3214
(80)
(8.86)%
3295
21
0.64%
3132 (37)
(1.17)%
Prj 3E.6
3011
(38)
(1.25)%
3192
41
1.30%
3216
(78)
(6.06)%
3311
37
1.13%
3137 (32)
(1.01)%
Prj 3E.13A
3025
(24)
(0.79)%
3185
34
1.08%
3214
(80)
(8.88)%
3295
21
0.64%
3132 (37)
(1.17)%
Prj 3E.6A
3011
(38)
(1.25)%
3192
41
1.30%
3216
(78)
(6.06)%
3311
37
1.13%
3137 (32)
(1.01)%
■
Grades
9 - 12
Total
2001 -02
Diff
%
Total
2002 -03
Diff
%
Total
2003 -04
Diff
%
2004 -05
Total Diff
%
2005 -06
Total Diff
%
ACTUAL
4498
xxx
xxx
4535
xxx
xxx
4634
xxx
xxx
4663 xxx
xxx
5032 xxx
xxx
Prj 3E.13
4455
(43)
(0.96)%
4577
42
0.93%
4630
(4)
5.90%
4783 120
2.57%
4898 (134)
(2.66)%
Prj 3E.6
4476
(22)
(0.49)%
4594
59
1.30%
4639
5
3.69%
4769 106
2.27%
4880 (152)
(3.02)%
Prj 3E.13A
4455
(43)
(0.96)%
4577
42
0.93%
4630
(4)
5.90%
4783 120
2.57%
4898 (134)
(2.66)%
Prj 3E.6A
4476
(22)
(0.49)%
4594
59
1.30%
4639
5
3.69%
4769 106
2.27%
4880 (152)
(3.02)%
All
Grades
Total
2001 -02
Diff
%
Total
2002 -03
Diff
%
Total
2003 -04
Diff
%
Total
2004 -05
Diff
%
Total
2005 -06
Diff
%
ACTUAL
13461
xxx
xxx
13427
xxx
xxx
13672
xxx
xxx
13672
xxx
xxx
14088
xxx
xxx
Prj 3E.13
13307
(154)
(1.14)%
13485
58
0.43%
13499
(173)
(1.27)%
13839
167
1.22%
13780
(308)
(2.19)%
Prj 3E.6
13289
(172)
(1.28)%
13521
94
0.70%
13542
(130)
(0.95)%
13901
229
1.67%
13812
(276)
(1.96)%
Prj 3E.13A
13319
(142)
(1.05)%
13505
78
0.58%
13447
(225)
(1.65)%
13787
115
0.84%
13780
(308)
(2.19)%
Prj 3E.6A
13318
(143)
(1.06)%
13562
135
1.01%
13510
(162)
(1.18)%
13836
164
1.20%
13801
(287)
(2.04)%
prj08- 09.xls
Page 12 10/20/2008
AUBURN SCHOOL DISTRICT STUDENT ENROLLMENT PROJECTIONS - October 2008
TABLE
5
PROJECTION COMPARISONS
BY GRADE GROUP (Continued)
Total = October 1 Actual Count AND Projected Counts
Diff = Number Projection is under( -) or over Actual
% = Percent Projection is under( -) or over Actual
Prj 3.13 - 13 YEAR HISTORY & Using Average Kdg Increase
Prj 3.6 - 6 YEAR HISTORY & Using Average Kdg Increase
Prj 3.13A 13 YEAR HISTORY & King Cty Birth Rates
Prj 3.6A - 6 YEAR HISTORY & King Cty Birth Rates
Grades
K - 5
Total
2006 -07
Diff
%
Total
2007 -08
Diff
%
Total
2008 -09
Diff
%
Average
Diff
Average
ok
ACTUAL
6033
xxx
xxx
6142
xxx
xxx
6198
xxx
xxx
xxx
xxx
Prj 3E.13
5871
(162)
(2.69)%
6085
(57)
(0.93)%
6179
(19)
(0.31)%
(22)
(0.22)%
Prj 3E.6
5921
(112)
(1.86)%
6138
(4)
(0.07)%
6237
39
0.63%
(26)
(0.27)%
Prj 3E.13A
5869
(164)
(2.72)%
6059
(83)
(1.35)%
6129
(69)
(1.11)%
(41)
(0.72)%
Prj 3E.6A
5912
(121)
(2.01)%
6094
(48)
(0.78)%
6172
(26)
(0.42)%
(36)
(0.62)%
Grades
6 - 8
Total
2006 -07
Diff
%
Total
2007 -08
Diff
%
Total
2008 -09
Diff
%
Average
Diff
Average
ok
ACTUAL
3144
xxx
xxx
3097
xxx
xxx
3206
xxx
xxx
xxx
xxx
Prj 3E.13
3131
(13)
(0.41)%
3107
10
0.32%
3179
(27)
(0.84)%
(0)
(0.80)%
Prj 3E.6
3146
2
0.06%
3116
19
0.61%
3195
(11)
(0.34)%
(5)
(0.68)%
Prj 3E.13A
3131
(13)
(0.41)%
3107
10
0.32%
3179
(27)
(0.84)%
(0)
(0.80)%
Prj 3E.6A
3146
2
0.06%
3116
19
0.61%
3195
(11)
(0.34)%
(5)
(0.68)%
Grades
9 - 12
Total
2006 -07
Diff
%
Total
2007 -08
Diff
%
Total
2008 -09
Diff
%
Average
Diff
Average
%
ACTUAL
5241
xxx
xxx
5320
xxx
xxx
5299
xxx
xxx
xxx
xxx
Prj 3E.13
5085
(156)
(2.98)%
5190
(130)
(2.44)%
5129
(170)
(3.21)%
(24)
0.30%
Prj 3E.6
5086
(155)
(2.96)%
5192
(128)
(2.41)%
5155
(144)
(2.72)%
(22)
(0.03)%
Prj 3E.13A
5085
(156)
(2.98)%
5190
(130)
(2.44)%
5129
(170)
(3.21)%
(33)
0.09%
Prj 3E.6A
5086
(155)
(2.96)%
5192
(128)
(2.41)%
5155
(144)
(2.72)%
(29)
(0.22)%
All
Grades
Total
2006 -07
Diff
%
Total
2007 -08
Diff
%
Total
2008 -09
Diff
%
Average
Diff
Average
ok
ACTUAL
14418
xxx
xxx
14559
xxx
xxx
14703
xxx
xxx
xxx
xxx
Prj 3E.13
14087
(331)
(2.30)%
14382
(177)
(1.22)%
14487
(216)
(1.47)%
(41)
(0.27)%
Prj 3E.6
14153
(265)
(1.84)%
14446
(113)
(0.78)%
14587
(116)
(0.79)%
(48)
(0.34)%
Prj 3E.13A
14085
(333)
(2.31)%
14356
(203)
(1.39)%
14437
(266)
(1.81)%
(69)
(0.59)%
Prj 3E.6A
14144
(274)
(1.90)%
14402
(157)
(1.08)%
14522
(181)
(1.23)%
(66)
(0.59)%
prj08- 09.xls
Historical Data is grouped by
K - 5, 6 -8, 9 -12 articulation
pattern.
Articulation pattern has no
numeric impact on efficacy
of projection models.
Page 13 10/20/2008
Appendix A.2 - CAPITAL FACILITIES PLAN
Enrollment Projections
Buildout Data for Enrollment Projections -March 2009
BASE DATA - BUILDOUT SCHEDULE
ASSUMPTIONS:
1 Uses Build Out Estimates received from developers.
2 Student Generation Factor are updated Auburn data for 2009 as allowed per King County Ordinance
3 Takes area labeled Lakeland East slated for 2007 and divides across 2010 -12
4 Takes area labeled Kersey Project slated for 2005 and divides across 20010 -15
5 Takes area labeled Bridges (Kent Impoundment) and projects across 2009 -2014
6 Includes known developments in N. Auburn, Lea Hill and Non - Lakeland developments (see Development Growth)
Student Generation Factors
2009 Auburn
Factors
Single
Family
Multi -
Family
Elementary
Middle School
Senior High
Total
0.3200
0.1520
0.1580
0.0790
0.0340
0.0420
0.6300 0.1550
Table
1
Auburn School Distr
Development
2009
2010
2011
2012
2013
2014
2015
Total
Lakeland Single Family Units
Lea Hill Area
Other Single Family Units
Total Single Family Units
Projected Pupils:
110 120 120 120
70 85 100 125 160 155
60 50 150 150 145 140 51
470
695
746
240
255
370 I 395
305
295 I 51
1911
Elementary Pupils K -5
77
82
118
126
98
94
16
612
Mid School Pupils 6 -8
36
39
56
60
46
45
8
290 -
Sr. High Pupils 9 -12
38
40
58
62
48
47
8
302 .
Total K -12
151
161
233
249
192
186
32
1204
Lakeland Multi Family Units
Other Multi Family Units
Total Multi Family Units
Projected Pupils:
13
83
0
48
0
32
0
0
0
0
0
0
0
0
13
163
96
48
32
0
0
0 0
176
Elementary Pupils
K -5 8 4 3 0 0 0 0 44
Mid School Pupils 6 -8 3 2 1
0 0 0 1,9
Sr. High Pupils 9 -12 4 2 1
Total K -12 15 7 5
0 0 0 25
0 0 0 80
Total Housing Units
336
303
402
395
305
295
51 I 2087
Elementary Pupils K -5
84
85
121
126
98
94
16
" 625
Mid School Pupils 6 -8
40
40
57
60
46
45
8
296
Sr. High Pupils 9 -12
42
42
60
62
48
47
8
309
Total K -12
166
168
238
249
192
186
32
1231
Cumulative Projection
Elementary - Grades K -5
Mid School - Grades 6 - 8
Senior High - Grades 9 - 12
Total
2008 -09
2009 -10
2010 -11
2011 -12
2012 -13
2013 -14
2014 -15
84
40
42
170
80
84
291
137
144
417
198
206
515
244
255
609
289
301
625
296
309
166
334
572
821
1013
1199
1231
Buildouts Nlarch 09 + ND3.6 ave projections
4Y
Buildout Data for Enrollrr- it Projections -March 2009
TABLE
2
New Projects - Annual New Pupils Added & Distributed
by Grade Level
Grade
03 -04
04 -05
05 -06
06 -07
6 Year
Percent of average
6yr Ave
ok
KDG
922
892
955
941
1012
1002
1031
1049
998
1058
1014
1072
1372
1400
1322
1147
996
995
1019
997
1057
1078
1007
1057
1033
1337
1368
1352
1263
GRADE
Average
Pupils by Grade
2008 -09
2009 -10
2010 -11
2011 -12
2012 -13
2013 -14
2014 -15
2015 -16
992
Enroll.
& Level
6.94%
3
996
918
1002
998.67
7.04%
4
KDG
951
6.70%
998
11
22
38
55
68
80
82
1
988
6.96%
1015
12
23
40
57
71
83
86
2
985
6.94% 42.01%
1024
12
23
40
57
70
83
85
3
999
7.04%
1048
12
24
40
58
71
84
87
4
1009
7.11%
1044
12
24
41
58
72
85
88
5
1031
7.26%
1069
12
24
42
60
74
87
89
6
1049
7.39%
1096
12
25
42
61
75
89
91
7
1065
7.50% 22.53%
1034
12
25
43
62
76
90
92
8
1083
7.63%
1076
13
26
44
63
77
92
94
9
1380
9.72%
1256
16
32
56
80
99
117
120
10
1334
9.40% 35.46%
1341
16
31
54
77
95
113
116
11
1212
8.54%
1350
14
29
49
70
87
102
105
12
1106
7.80%
1352
13
26
45
64
79
93
96
Totals
14190
100.00% Total
14703
166
334
572
821
1013
1199
1231
TABLE
3
6 year Historical Data
Average Enrollment and Percentage Distributed by Grade Level
Grade
03 -04
04 -05
05 -06
06 -07
07 -08
08 -09
6yr Ave
ok
KDG
922
892
955
941
1012
1002
1031
1049
998
1058
1014
1072
1372
1400
1322
1147
996
995
1019
997
1057
1078
1007
1057
1033
1337
1368
1352
1263
998
1015
1024
1048
1044
1069
1096
1034
1076
1256
1341
1350
1352
950.67
6.70%
1
982
960
963
987.83
6.96%
2
909
992
963
984.83
6.94%
3
996
918
1002
998.67
7.04%
4
947
1016
939
1008.67
7.11%
5
1018
957
1065
1030.83
7.26%
6
1111
1020
1004
1049.33
7.39%
7
1131
1124
1028
1064.67
7.50%
8
1052
1130
1137
1083.33
7.63%
9
1473
1461
1379
1379.67
9.72%
10
1249
1261
1383
1333.67
9.40%
11
1010
1055
1182
1211,83
8.54%
12
902
886
1088
1106.33
7.80%
Totals
13702
13672
14088
14418
14559
14703
14190.33
100.00%
% of change
change +1-
- 0.22%
3.04%
2.34%
0.98%
0.99%
-30
416
330
141
144
Buildouts March 09 + ND3.6 ave projections
45
Buildout Data for Enrollment Projections -March 2009
TABLE 4
ND 3.13
New Projects - Pupil
by Grade Level
Projection Cumulative
Updated March 2009
Uses a 'cohort survival'
model assuming 100% of
previous year new
enrollees move to the next
grade level.
Kindergarten calculates
previous years number plus
current generation based on
% of total enrollment. Other
use 100% cohort survival.
GRADE
2008 -09
Actual
2009 -10
Projected
2010 -11
Projected
2011 -12
Projected
2012 -13
Projected
2013 -14
Projected
2014 -15
Projected
2015 -16
Projected
KDG
1
2
3
4
5
K -5
6
7
8
GR 6 -8
9
10
11
12
998
1015
1024
1048
1044
1069
1012
1064
1038
1056
1079
1075
1026
1079
1087
1070
1087
1110
1045
1098
1106
1124
1106
1124
1065
1119
1127
1145
1161
1144
1080
1135
1143
1161
1178
1196
1096
1151
1159
1177
1194
1212
1101
1156
1164
1182
1199
1217
6198
6324 1 6459 I 6604 I 6760 I 6893 1 6988 1 7019
1096
1034
1076
1096
1124
1060
1102
1124
1150
1143
1136
1156
1157
1178
1169
1174
1188
1207
1225
1204
1217
1230
1244
1222
3206
3280 1 3377 1 3435 1 3504 I 3569 1 3647 1 3696
1256
1341
1350
1352
1394
1197
1264
1278
1381
1334
1119
1191
1482
1328
1260
1050
1494
1429
1253
1191
1506
1434
1347
1177
1547
1446
1350
1269
1547
1472
1347
1259
GR 9 -12
Total
5299
5133
5025
5120
5366
5464
5612
5625
14703
14736
14861
15159
15630
15926
16247
16340
% of change
change +/-
0.22%
0.85%
2.00%
3.11%
1.89%
2.02%
0.57%
33
125
298
471
296
321
93
TABLE 5
ND 3.6
New Projects - Pupil
by Grade Level
Projection Cumulative
Updated March 2009
Uses a 'cohort survival'
model assuming 100% of
previous year new
enrollees move to the next
grade level.
Kindergarten calculates
previous years number plus
current generation based on
% of total enrollment. Other
use 100% cohort survival.
GRADE
2008 -09
Actual
2009 -10
Projected
2010 -11
Projected
2011 -12
Projected
2012 -13
Projected
2013 -14
Projected
2014 -15
Projected
2015 -16
Projected
2016 -17
Projected
2017 -18
Projected
KDG
1
2
3
4
5
K -5
6
7
8
GR 6 -8
9
10
11
12
GR 9 -12
998
1015
1024
1048
1044
1069
1024
1057
1044
1058
1092
1088
1051
1084
1087
1078
1102
1136
1082
1116
1118
1126
1128
1152
1114
1149
1151
1159
1176
1178
1142
1177
1179
1187
1205
1223
1170
1205
1207
1216
1233
1252
1187
1223
1225
1233
1251
1269
6198
6364 I 6538 I 6722 1 6926 I 7114 7283 I 7388
1096
1034
1076
1095
1120
1065
1114
1119
1152
1168
1144
1157
1185
1199
1182
1208
1211
1233
1252
1234
1246
1270
1267
1257
3206
3280 1 3385 1 3469 I 3566 I 3652 I 3732 1 3794
1256
1341
1350
1352
1368
1218
1275
1326
1361
1330
1151
1250
1458
1329
1267
1130
1469
1426
1265
1245
1495
1431
1355
1237
1549
1455
1358
1325
1550
1494
1367
1314
1200
1237
1239
1247
1265
1284
7472
1284
1282
1271
3837
1568
1511
1383
1329
1214
1251
1253
1261
1279
1298
7556
1299
1296
1285
3880
1585
1528
1399
1344
5299
5187
5092
5184
5406
5517
5687
5726
5791
5857
Total
14703
14831
15016
15374
15898
16284
16701
16907
17099
17293
of change
change +/-
Buildouts March 09 + ND3.6 ave projections
0.87%
1.24%
128
18
-.v
2.39%
3.40%
2.43%
2.57%
1.23%
1.14%
1.14%
359
523 386
418
206
192
Buildout Data for Enrollrr' 't Projections -March 2009
TABLE 6
ND3.13A
New Developments - Pupil Projection Cumulative
by Grade Level Updated March 2009
2.02% 1.14%
Uses a 'cohort survival'
model assuming 100% of
previous year new
enrollees move to the next
grade level.
Kindergarten calculates
birth rate average plus
current generation based on
% of total enrollment. Other
use 100% cohort survival.
GRADE
2008 -09
Actual
2009 -10
Projected
2010 -11
Projected
2011 -12
Projected
2012 -13
Projected
2013 -14
Projected
2014 -15
Projected
2015 -16
Projected
KDG
1
2
3
4
5
6
7
8
9
10
11
12
998
1015
1024
1048
1044
1069
995 1007 1065 1123
1064 1062 1079 1139 1193
1038 1087 1089 1107 1163 1217
1056 1070 1124 1127 1142 1197 1241
1079 1087 1106 1161 1161 1175 1219
1075 1110 1124 1144 1196 1195 1198
6198
6306 I 6422 I 6587 I 6802 I 5854 I 4784 I 3658
1096
1034
1076
1096 1102 1143 1157 1174 1225 1213
1124 1124 1136 1178 1188 1204 1244
1060 1150 1156 1169 1207 1217 1222
3206
3280 I 3377 I 3435 I 3504 I 3569 I 3647 I 3679
1256
1341
1350
1352
1394 1381 1482 1494 1506 1547 1547
1197 1334 1328 1429 1434 1446 1472
1264 1119 1260 1253 1347 1350 1347
•1278 1191 1050 1191 1177 1269 1259
5299
5133
5025
5120
5366
5464 I 5612 I 5625
Total
14703
14719
14824
15142
15672
% of change
change +/-
0.11%
0.72%
2.14%
3.50%
16
105
318
530
TABLE 7
ND 3.6A
New Projects - Pupil Projection Cumulative
by Grade Level Updated March 2009
Uses a 'cohort survival'
model assuming 100% of
previous year new
enrollees move to the next
grade level.
Kindergarten calculates
birth rate average plus
current generation based on
of total enrollment. Other
use 100% cohort survival.
Based on 6 year history
GRADE
2008 -09
Actual
2009 -10
Projected
2010 -11
Projected
2011 -12
Projected
2012 -13
Projected
2013 -14
Projected
2014 -15
Projected
2015 -16
Projected
KDG
1
2
3
4
5
6
7
8
9
10
11
12
998
1015
1024
1048
1044
1069
995 1007 1065 1123
1057 1055 1072 1132 1187
1044 1087 1089 1107 1162 1217
1058 1078 1126 1129 1143 1199 1243
1092 1102 1128 1176 1175 1189 1234
1088 1136 1152 1178 1223 1222 1225
6198
6334 I 6465 I 6631 I 6845
I
1096
1034
1076
1095 1114 1168 1185 1208 1252 1240
1120 1119 1144 1199 1211 1234 1267
1065 1152 1157 1182 1233 1246 1257
3206
3280 I 3385 1 3469 I 3566 I 3652 I 3732 I 3764
1256
1341
1350
1352
1368 1361 1458 1469 1495 1549 1550
1218 1330 1329 1426 1431 1455 1494
1275 1151 1267 1265 1355 1358 1367
1326 1250 1130 1245 1237 1325 1314
5299
5187
5092
5184
5406
5517 I 5687 1 5726
Total
14703
14802
14942
15284
15817
% of change
change +/-
0.67%
0.95%
2.29%
3.49%
99
141
342
533
Buildouts March 09 + ND3.6 ave projections 47
Auburn S-'-ool District
Development Growtt, e 1/1/03 March, 2009
SINGLE FAMILY
Development Name
ni s
Parcels
urren
Occupancy
o =e
Occupied
Alder Meadows
30
30
0
As•en Meadows
21
21
0
Auburn Place
14
14
0
Bifrost Gate
52
52
0
Cambrid. a Pointe
26
23
3
Canterber Crossin•
20
20
0
C stal Court
13
13
0
Dawson Hills
6
6
0
Hazel Park
15
15
0
Kelli Meadows
8
8
0
Kin • sle Meadows
56
56
0
Lakeland: Montiano
104
104
0
Lakeland: The Reserve
80
80
0
Lakeland: Tuscan
76
76
0
Lakeland: Verona South
400
400
0
Lakeland: Verona North
181
181
0
LeeAnn Meadows
23
23
0
Little Fields
8
8
0
Marchini Meadows
IMEWECHEMIIII
Pacific Meadows
83
83
0
6
6
0
44
44
0
Pacific View
34
34
0
River Park Estates
18
18
0
River Rim
11
11
0
Sera Monte
33
33
0
Valle View Estates
8
8
0
Vinta•e Hills, Division 6
61
61
0
Vinta•e Hills, Division 7
20
20
0
Washin•ton National, Div 1
42
42
0
Totals
Elem
Middle
HS
Total
Student Generation Factors
em
IMIIIMILM
o a
4
4
4
12
0.133
0.133
0.133
0.400
11
9
6
26
0.524
0.429
0.286
1.238
5
3
3
11
0.357
0.214
0.214
0.786
32
14
21
67
0.615
0.269
0.404
1.288
9
3
0
12
0.391
0.130
0.000
0.522
7
0
4
11
0.350
0.000
0.200
0.550
5
6
5
16
0.385
0.462
0.385
1.231
4
2
3
9
0.667
0.333
0.500
1.500
26
18
11
55
1.733
1.200
0.733
3.667
2
1
2
5
0.250
0.125
0.250
0.625
25
19
18
62
0.446
0.339
0.321
1.107
19
5
7
31
0.183
0.048
0.067
0.298
19
7
7
33
0.238
0.088
0.088
0.413
35
15
10
60
0.461
0.197
0.132
0.789
79
35
31
145
0.198
0.088
0.078
0.363
41
16
19
76
0.227
0.088
0.105
0.420
9
3
6
18
0.391
0.130
0.261
0.783
1
2
3
6
0.125
0.250
0.375
0.750
31
9
21
61
0.373
0.108
0.253
0.735
4
2
2
8
0.667
0.333
0.333
1.333
19
12
11
42
0.432
0.273
0.250
0.955
5
4
3
12
0.147
0.118
0.088
0.353
5
0
2
7
0.278
0.000
0.111
0.389
5
3
2
10
0.455
0.273
0.182
0.909
8
2
0
10
0.242
0.061
0.000
0.303
4
1
1
6
0.500
0.125
0.125
0.750
36
21
19
76
0.590
0.344
0.311
1.246
18
6
6
30
0.900
0.300
0.300
1.500
9
4
8
21
0.214
0.095
0.190
0.500
477
226
235
938
0.320
0.152
0.158
0.630
49
SINGLE FAMILY
Auburn School District
Development Growth since 1/1/03 March, 2009
2009 Currently Under Constr
Development Name
Units/
Parcels
Current
Occupancy
To Be
Occupied
Beaver Meadows
60
12
48
Cambridge Pointe
26
23
3
Lakeland: Pinnacle Estates
76
32
44
Lakeland: Vista Heights
125
89
36
Riversointe
118
71
47
Trail Run
169
64
105
283
2009 and up Under Construct
Development Name
Units/
Parcels
Current
Occupancy
To Be
Occupied
Alicia Glenn
31
0
31
Anderson Acres
14
0
14
Backbone Ridge
7
0
7
Brandon Meadows
55
0
55
Brandon Place
78
0
78
Bridges
386
0
386
Bridle Estates
18
0
18
Cam -West
99
0
99
Carrington Pointe
24
0
24
Dal'it Dhaliwal Plat
8
0
8
Estes Park
31
0
31
Hargreet Kan.
8
0
8
Hazel Hei. hts
22
0
22
Hazel View
20
0
20
Kendall Ridge
106
0
106
Kerse 3 Pro'ect
373
0
373
Lakeland: East Phase 1
130
0
130
Lakeland: East Phase 2/3
340
0
340
Lawson Place
14
0
14
Megan's Meadows
9
0
9
Mountain View Estates
29
0
29
New Hose Lutheran Plat
8
0
8
Sgencer Place
13
0
13
Sti. g Plat
29
0
29
Vintage Place
25
0
25
Willow Place
18
0
18
YatE 3t 16 0 1'
1911 2194
Elem
Middle
HS
Total
Student Generation Factors
Elem
Middle
HS
Total
0
2
0
2
15
7
8
30
9
3
0
12
1
0
0
2
6
4
4
14
14
7
7
28
17
4
4
25
12
5
6
23
12
8
11
31
15
7
7
30
3
4
0
7
34
16
17
66
6
91
43
45
178
50
Student Generation Factors
Elem
Middle
HS
Total
10
5
5
20
4
2
2
9
2
1
1
4
18
8
9
35
25
12
12
49
124
59
61
243
6
3
3
11
32
15
16
62
8
4
4
15
3
1
1
5
10
5
5
20
3
1
1
5
7
3
3
14
6
3
3
13
34
16
17
67
119
57
59
235
42
20
21
82
109
52
54
214
4
2
2
9
3
1
1
6
9
4
5
18
3
1
1
5
4
2
2
8
9
4
5
18
8
4
4
16
6
3
3
11
5
2
10
702
333
3-..., 1381
Auburn S'ool District
Development .vth since 1/1/03
March, 2009
MULTI FAMILY
Development Name
Units/
Parcels
Current
Occupancy
To Be
Occupied
Butte Estates
29
29
0
Cox/Woodward TH
8
8
0
Lakeland: Cain i
168
168
0
Lakeland: Carrara
170
170
0
Lakeland: Palermo Pots
362
362
0
Lakeland: Siena
101
101
0
Lakeland: Sorano
79
79
0
Pasa Fino II
19
19
0
Seasons at Lea Hill Villa•e
332
332
0
0.059
1268
1268
0
2009 and be
and
Development Name
Units/
Parcels
Current
Occupancy
To Be
Occupied
Lakeland: Madera
70
57
13
Pacific Ave Du.lexes
12
8
4
Trail Run Townhomes
115
36
79
"D" Street Plat
32
0
32
Sundallen Condos
48
0
48
0.625
277
101
176
51
Elem
Middle
HS
Total
Student Generation Factors
Elem
Middle
HS
Total
8
6
4
18
0.276
0.207
0.138
0.621
1
3
1
5
0.125
0.375
0.125
0.625
4
2
1
7
0.024
0.012
0.006
0.042
5
1
4
10
0.029
0.006
0.024
0.059
19
7
20
46
0.052
0.019
0.055
0.127
5
0
1
6
0.050
0.000
0.010
0.059
1
1
1
3
0.013
0.013
0.013
0.038
2
1
1
4
0.105
0.053
0.053
0.211
55
22
20
97
0.166
0.066
0.060
0.292
100
43
53
196
0.079
0.034
0.042
0.155
Elem
Middle
HS
Total
Student Generation Factors
Elem
Middle
HS
Total
0
0
1
1
1
0
1
2
1
1
1
3
0
0
0
1
1
2
0
3
6
3
3
12
3
1
1
5
4
2
2
7
14
6
7
27
POLICY /TEXT AMENDMENT #2
Kent School District Updated 2009 -2010 to 2014 -2015
Capital Facilities Plan
Incorporate Kent School District Updated 2009 -2010 to
2014 -2015 Capital Facilities Plan as part of Auburn
Comprehensive Plan
(Adopted by the Kent School District Board of Directors
June 2009)
2009 - 2010 ° 2014 a 2015
New'Panther.Lake Elementary'School open in Fall 2009
Kent School-District No. 415 provides educationa[service to
Residents of "Unincorporated King County
and Residents of the Cities of
Kent, Covington, Auburn, Renton
Black Diamond, Map[e'1la!ley, and Sea(ac, Washington
April 2009
Kent School District No. 415
12033 SE 256th Street
Kent, Washington 98030 -6643
(253) 373 -7295
SIX - YEAR CAPITAL FACILITIES PLAN
2009 - 2010 - 2014 - 2015
KENT
scHoa
DISTRICT
BOARD of DIRECTORS
Jim Berrios
Bill Boyce
Sandra Collins
Chris Davies
Debbie Straus
ADMINISTRATION
Barbara Grohe, Ph.D. — Superintendent
Fred H. High — Assistant Superintendent for Business Services
Merri Rieger, Ed.D. — Assistant Superintendent, Learning & School Improvement
Larry Miner — Assistant Superintendent for Human Resources
John Knutson — Executive Director of Finance
Janis Bechtel — Executive Director, School Improvement 7 — 12
Jeanette Ristau — Executive Director, School Improvement K — 6
David Staight — Executive Director, School Improvement K — 6
Becky Hanks — Executive Director, Community Connections
Charles Lind — Executive Director, Labor Relations & Legal Services
Laura Madeo — Executive Director of Instructional Services
Thuan Nguyen — Chief Information Officer
Kent School District Six -Year Capital Facilities Plan April 2009
KENT
SCHOOL
DISTRICT
SIX - YEAR CAPITAL FACILITIES PLAN
2009 -2010 — 2014 -2015
April 2009
For information on the Plan, please call the
Finance & Planning Department at (253) 373 -7295
Capital Facilities Plan
Contributing Staff
Gwenn Escher - Derdowski
Forecast & Planning Administrator
Fred Long, Supervisor of Facilities & Construction
Karla Wilkerson, Facilities Department
Don Walkup, Supervisor of Transportation Department
Kathy Fosjord, Transportation Manager
Maps by Jana Tucker, Printing Services
Kent School District Six -Year Capital Facilities Plan April 2009
Six-Year Capital Facilities Ilan
7abk of Contents
Section Page Number
I Executive Summary 2.
I I Six -Year Enrollment Projection & History 4
I I I District Standard of Service 9
I V Inventory, Capacity & Maps of Existing Schools 12
✓ Six -Year Planning and Construction Plan 15
V I Relocatable Classrooms 18
✓ I I Projected Classroom Capacity 19
✓ III Finance Plan, Cost Basis and Impact Fee Schedules 24
I X Summary of Changes to Previous Plan 31
X Appendixes 32
Kent School District Six -Year Capital Facilities Plan April 2009
I Executive Summary
This Six -Year Capital Facilities Plan (the "Plan ") has been prepared by the Kent
School District (the "District ") as the organization's facilities planning document,
in compliance with the requirements of Washington's Growth Management Act,
King County Code K.C.C. 21A.43 and Cities of Kent, Covington, Auburn, Renton,
Black Diamond, Maple Valley, and SeaTac. This annual plan update was
prepared using data available in the spring of 2009 for the 2008 -2009 school
year.
This Plan is consistent with prior Tong -term capital facilities plans adopted by the
Kent School District. This Plan is not intended to be the sole planning document
for all of the District's needs. The District may prepare interim and periodic Long
Range Capital Facilities Plans consistent with Board Policies, taking into account
a longer or shorter time period, other factors and trends in the use of facilities,
and other needs of the District as may be required.
Prior Capital Facilities Plans of the Kent School District have been adopted by
Metropolitan King County Council and Cities of Kent, Covington, Auburn and
Renton and included in the Capital Facilities Plan element of the Comprehensive
Plans of each jurisdiction. The first ordinance implementing impact fees for the
unincorporated areas was effective September 15, 1993.
In order for impact fees to be collected in the unincorporated areas of Kent
School District, the Metropolitan King County Council must adopt this Plan and a
fee - implementing ordinance for the District. For impact fees to be collected in the
incorporated portions of the District, the cities of Kent, Covington, Auburn and
Renton must also adopt this Plan and their own school impact fee ordinances.
This Plan has also been submitted to cities of Black Diamond, Maple Valley, and
SeaTac.
This Capital Facilities Plan establishes a standard of service in order to ascertain
current and future capacity. While the State Superintendent of Public Instruction
establishes square footage guidelines for capacity, those guidelines do not
account for local program needs in the District. The Growth Management Act,
King County and City codes and ordinances authorize the District to make
adjustments to the standard of service based on specific needs for students of
the District.
This Plan includes the standard of service as established by Kent School District.
Program capacity is based on an average capacity and updated to reflect
changes to special programs served in each building. Relocatables in the
capacity calculation use the same standard of service as the permanent
facilities.
(continued)
Kent School District Six -Year Capital Facilities Plan April 2009 Page 2
I Executive Summary (continued)
The capacity of each school in the District is calculated based on the District
standard of service and the existing inventory, which includes some relocatable
classrooms. The District's program capacity of permanent facilities reflects
program changes and the reduction of class size to meet the requirements of
Student Achievement Initiative 728. Relocatables provide additional transitional
capacity until permanent facilities are completed.
Kent School District is the fourth largest district in the state. Enrollment is
electronically reported monthly to the Office of the Superintendent of Public
Instruction (OSPI) on Form P -223. Although funding apportionment is based on
Annual Average Full Time Equivalent (AAFTE), Enrollment on October 1 is a
widely recognized "snapshot in time" that is used to report the District's
enrollment for the year.
P -223 Headcount for October 1, 2008 was 26,831. P -223 FTE (Full Time
Equivalent) enrollment was 25,827.82. (FTE reports Kindergarten at .5 and excludes
Early Childhood Education [ECE] and college -only Running Start students.) The actual
number of individual students per the October 2008 full head count was 27,579.
(Full Headcount reports all enrolled students at 1.0 including Kindergarten, ECE and
college -only Running Start students.)
The District's standard of service, enrollment history and projections, and use of
transitional facilities are reviewed in detail in various sections of this Plan. The
District plans to continue to satisfy concurrency requirements through the
transitional use of relocatables.
A financing plan is included in Section VIII which demonstrates the District's
ability to implement this Plan. Pursuant to the requirements of the Growth
Management Act, this Plan will be updated annually with changes in the fee
schedules adjusted accordingly.
Kent School District Six -Year Capital Facilities Plan April 2009 Page 3
11 Six - Year Enrollment Projection
For capital facilities planning, growth projections are based on cohort survival and
student yield from documented residential construction projected over the next six years.
(See Table 2) The student generation factor, as defined on the next page, is the basis for
the growth projections from new developments.
King County births and the District's relational percentage average were used to
determine the number of kindergartners entering the system. (See Table 1) 8.48% of
22,874 King County live births in 2004 is projected for 1,940 students expected in
Kindergarten for October 1, 2009. Together with proportional growth from new
construction, 8.48% of King County births is equivalent to the number of students
projected to enter kindergarten in the district for the next six -year period. (See Table 2)
State Funded Full Day-Kindergarten ( "FDK ") programs required a revision to the
methodology for projecting Kindergarten at 1.0 FTE for qualifying schools.
Schools with half -day Kindergarten programs and the optional Tuition -based
FDK are projected at .50 FTE. (See Table 2A)
Early Childhood Education students (sometimes identified as "Preschool Special
Education [SE] or handicapped students ") are forecast and reported separately.
Capacity is reserved to serve the ECE programs at seven elementary schools.
The first grade population is traditionally 7 - 8% larger than the kindergarten population
due to growth and transfers to the District from private kindergartens. Cohort survival
method uses historical enrollment data to forecast the number of students projected for
the following year.
Near term projections assume some growth from new developments to be offset by
current local economic conditions. With notable exceptions, the expectation is that
enrollment increases will occur District -wide in the long term. District projections are
based on historical growth patterns combined with continuing development of projects in
the pipeline dependent on market/growth conditions.
The District will continue to track new development activity to determine impact to
schools and monitor conditions to reflect adjustments in this assumption. The six -year
enrollment projection anticipates moderate enrollment growth from new development
currently in some phase of planning or construction in the district.
Information on new residential developments and the completion of these proposed
developments in all jurisdictions may be considered in the District's future analysis of
growth projections.
Within practical limits, the District has kept abreast of proposed developments. The
Kent School District serves seven permitting jurisdictions: unincorporated King County,
the cities of Kent, Covington, and Auburn and smaller portions of the cities of Renton,
SeaTac, and Maple Valley. The west Lake Sawyer area of Kent School District is in the
city of Black Diamond.
Kent School District Six -Year Capital Facilities Plan
(Continued)
April 2009 Page 4
I I Six - Year Enrollment Projection (Continued)
STUDENT GENERATION FACTOR
"Student Factor" is defined by King County code as "the number derived by a
school district to describe how many students of each grade span are expected
to be generated by a dwelling unit" based on district records of average actual
student generated rates for developments completed within the last five years.
Following these guidelines, the student generation rate for Kent School District is
as follows:
Single Family Elementary .445
Middle School .118
Senior High .245
Total
.808
Multi - Family Elementary .296
Middle School .075
Senior High .111
Total .482
The student generation factor is based on a survey of 1,878 single family
dwelling units and 1,283 multi - family dwelling units with no adjustment for
occupancy rates. Please refer to Appendix E on Page 36 of the Capital Facilities
Plan for details of the Student Generation Factor survey.
The actual number of students in those residential developments was
determined using the District's Education Logistics (EDULOG) Transportation
System.
Kent School District Six -Year Capital Facilities Plan
April 2009 Page 5
KENT SCHOOL DISTRICT No. 415
OCTOBER P 223 F T E (Full Time Equivalent) ENROLLMENT HISTORY 1
LB = Live Births LB in 1985 LB In 1906 LB in 1987 LB in 1988 LB In 1889 LB In 1890 L8 in 1991 LB in 1992 LB In 1993 L8 in 1994 LB in 1995 LB in 1998 LB In 1997 LB In 1998
LB in 1999
L8 In 2000 LB in 2001
LB in 2002
LB in 2003
riora- aw- .....M rrnirec us, sysrrErw.ar•_••- •_1- ,•••-.• -- -m..A. a:.iawVan,rz`s:,.,c3.3.114 1x.,1 wrvn2.icyxw.g.`... --"7GarraCmnrnV.+r:8sie itR:rA.trSXVISZ-aulintae
ahm3K.Z easi677.EM ARVIM,vileuemma:i aw s Pra li.e14aaa- vurnz..arara.......0r._
October FTE Enrollment 1990
'"R.C3r,.
1991 1992 1993 1994
1995 1996 1997
1998
1999 2000 2001
2002 2003
2004 2005 2006 2007 2008
.K ....Z.3..A.d e.t/
iRM:irWi1,.'.....01.3k V•.SY',IV3. -S, .....RA
•SSP(aKA_lT'Jf.9.:W14...t.,yg{ dip]
a:J,Y+G9f1+ "a.dE341mssa QtnnIal av
- 1..-GS,..91.71,4C7.4.
T..Y1serrA 111i N .1,17.74Ol,:fC+;A.C....eraTASR, KW% Mi...
King County Live Births 2 19,825 19.999 20,449 21,289 22.541 23,104 23,002 23,188 22,355 22,010 21,817 21,573 21,646 22,212 22,007 22,487 21,778 21,863 22,431
Increase! Decrease 851 174 450 840 1,252 563 -102 186 -833 -345 -193 -244 73 566 - 205 480 -709 85 568
Kindergarten / Birth % 2 8.88% 9.49% 9.40% 9.07% 8.47% 8.54% 8.44% 8.38% 8.27% 8.56% 8.25% 8.41% 8.06% 8.05% 8.33% 8.41% 8.22% 8.29% 8.48%
Kindergartent 2 3 880 949 962 965 955 987 971 972 925 942 900 907 873 894 917 943 895 906 768
State Funded Full Day Kindergarten 1-2.3
365
Grade 1 1,852 1,945 2,029 2,017 1,967 1,975 2,152 2,085 2.064 1,989 2,069 1,936 1,922 1,851 1,954 1938 2003 1873 1920
Grade 2 1,773 1,944 1,998 2,048 1,937 2,011 1,979 2.194 2,095 2,078 2,015 2,067 1,936 1,965 1,935 1981 1998 2045 1916
Grade 3 1,824 1.866 1,950 1,972 1,965 1,959 2,025 2,058 2,208 2,111 2,098 2,040 2,055 1,975 2,020 1962 2026 2033 2081
Grade 4 1,793 1,916 1,900 1,939 1,942 2,012 1,966 2,064 2,045 2,222 2,086 2,166 2,068 2.072 2,057 2024 2015 2049 2060
Grade 5 1,702 1,865 1,911 1,907 1,899 1,924 1,988 2,023 2,108 2,037 2,251 2,109 2,149 2,067 2,102 2090 2051 2020 2044
Grade 6 1,629 1,733 1,885 1,951 1,915 1,895 1,924 2,036 2,045 2,119 2,056 2,253 2,151 2,205 2,139 2164 2101 2098 2081
Grade 7 1,624 1,720 1,812 1,915 1,946 1,925 1,899 1,982 2,063 2,081 2,208 2,127 2.380 2,209 2,243 2200 2205 2130 2117
Grade 8 1,545 1,628 1,724 1,799 1,882 1,941 1,927 1,936 1,970 2,015 2,033 2,154 2,079 2,351 2,221 2293 2254 2184 2143
Grade 9 - Junior High 1,483 1,612 1,689 1,716 1,800 1,894 1,963 1,931 1,925 2,102 2,208 2,246 2,404
Grade 9 - Senior High 2,309 2,705 2767 2772 2560 2573
Grade 10 1,468 1,480 1,663 1,698 1,690 1,765 1,851 1,977 1,953 2,045 2,113 2,064 2,039 2,207 2,124 2173 2212 2474 2245
Grade 11 1,360 1,400 1,409 1,537 1,529 1,606 1,681 1,797 1,849 1,782 1,770 1,835 1,823 1,787 1,907 1799 1881 1882 1966
Grade 12 1,202 1,255 1,290 1,340 1.368 1,430 1,465 1,507 1,632 1,537 1,432 1,440 1,475 1,466 1,446 1475 1451 1491 1549
Total Enrollment 4
20,135 21,312 22,222 22,803 22,794 23,323 23,792 24,560 24,882 25,060 25,238 25,344 25,354 25,358 25.770 25,809 25,864 25,745 25,828
Yearly FTE Increase 916 1,178 909 582 -10 529 469 768 322 178 178 106 9 4 412 39 55 -119 83
Cumulative Increase 916 2,094 3,003 3,585 3,575 4,104 4,574 5,341 5,663 5,841 6,019 6.126 6,135 6,140 6,552 6,591 6.646 6,527 6,610
1 FTE enrollment counts have been rounded to the nearest whole number. Most Kindergarten students are reported at .5 FTE although most elementary schools now provide some fut day Kindergarten programs.
2 This number indicates actual births In King County 5 years prior to enrollment year as updated by King Co Health Dept. KSD percentage based on actual Kindergarten enrollment 5 years later.
3 Starting in 2008, Kindergarten students are reported at 1.0 (same as headcount) at 5 schools which qualified for Full Day Kindergarten (FDK) funded through State Apportionment See Table 2A for FD Kindergarten detail.
For Full Day Kindergarten at other schools, the second half of the day Is funding by grants or tuition and the students are still reported at .5 FTE on the P -223 Enrollment Report which generates state apportionment funding.
4 Enrollment reported to the state on Form P -223 generates basic education funding and excludes Early Childhood Education ("ECE' & 'sr or Birth to 2 Preschool Special Education) and college-only Running Start students.
October 2008 P -223 Headcount = 26,831 & Full Headcount = 27,579. Full Headcount Includes Kindergarten, Early Childhood Education & college -only Running Start students at 1.0 Headcount.
Kent School District Six -Year Capital Facilities Plan
Table 1
April 2009 Page 6
KENT SCHOOL DISTRICT No. 415
SIX - YEAR F T E ENROLLMENT PROJECTION
State Funded FDK at 14 schools L8 in 2003 LB in 2004 LB In 2005
LB in 2006 LB in 2007
LB est 08
LB est 09
October
2008 2009 2010 2011 2012 2013 2014
.rl s': ,r� _ `..l :S: :RAi�; � .ia: \QT .iD.Iw ... '. fY: }ii '?S `Ni�...: .•ii.VC•∎ ::i0Y?4,3,V.Z1'alrya_'�T:rA 1• "1 C:� t L.
'Sy '$�r a..�:a 4f1 -�1 "1 iV:i"1'..ti �•u'k•',l.a .l
King County Live Births' 22,431
22,874 22,680 24,244 24,899 25,000 25,100 '
Increase / Decrease 568 443 -194 1,564 655 101
100
Kindergarten / Birth % 2 8.48% 8.48% 8.48% 8.48% 8.48% 8.48% 8.48%
213 Kindergarten FTE @ .5 768 479 471 537 565 569 573
2(3 FD Kindergarten @ 1.0 365 982 982 982 982 982 982
Grade 1 1,920 2,021 2,081 2,054 2,183 2,232 2,230
Grade 2 1,916 1,961 2,083 2,145 2,117 2,249 2,299
Grade 3 2,081 1,971 1,989 2,122 2,184 2,156 2,289
Grade 4 2,060 2,073 2,001 2,029 2,163 2,226 2,198
Grade 5 2,044 2,065 2,085. 2,023 2,051 2,185 2,248
Grade 6 2,081 2,091 2,110 2,140 2,077 2,106 2,242
Grade 7
Grade 8
Grade 9
Grade 10
Grade 11
Grade 12
2,117 2,096 2,111 2,130 2,160 2,097 2,426
2,143 2,131 2,129 2,144 2,163 2,193 2,130
2,573 2,497 2,507 2,505 2,522 2,544 2,579
2,245 2,249 2,210 2,219 2,227 2,232 2,251
1,966 1,841 1,889 1,857 1,864 1,871 1,875
1,549 1,661 1,662 1,705 1,676 1,683 1,689
Total FTE Enrollment 25,828 26,118 26,310 26,592 26,934 27,325 27,711
Note: 2 / 314
Yearly Increase 83 290 192 282 342 391 386
Yearly Increase /Decrease % 0.32% 1.12% 0.74% 1.07% 1.29% 1.45% 1.41%
Cumulative Increase 83 373 565 847 1,189 1,580 1;966
1 Kindergarten enrollment projection is based on KSD percentage of live births in King County five years previous.
2 Kindergarten FTE projection is calculated by using the District's previous year percentage of King County births
5 years earlier compared to actual kindergarten enrollment in the previous year. (Excludes ECE - Early Childhood Education)
3 Kindergarten projection is at 1.0 FTE for 14 schools qualifying for Grant & State Apportionment Funded Full Day Kindergarten (FDK)
Schools with 1/2 Day Kindergarten and Optional Tuition -based Full Day Kindergarten programs are projected at .5 FTE.
4 Oct. 2008 P223 FTE is 25,828 & Headcount is 26,831. Full student count with ECE Preschool & Running Start = 27,579.
•
'Full Time Equivalent (FTE)
25,828 126,118
26,310
26,592
I 26,934 I
27,325
1 27,711 tr;
•
1 Kindergarten enrollment projection is based on KSD percentage of live births in King County five years previous.
2 Kindergarten FTE projection is calculated by using the District's previous year percentage of King County births
5 years earlier compared to actual kindergarten enrollment in the previous year. (Excludes ECE - Early Childhood Education)
3 Kindergarten projection is at 1.0 FTE for 14 schools qualifying for Grant & State Apportionment Funded Full Day Kindergarten (FDK)
Schools with 1/2 Day Kindergarten and Optional Tuition -based Full Day Kindergarten programs are projected at .5 FTE.
4 Oct. 2008 P223 FTE is 25,828 & Headcount is 26,831. Full student count with ECE Preschool & Running Start = 27,579.
•
G R O W T H
... .. ... _ ,... .
PROJECTIONS
•
- Ad-ustments for current economic factors
.
For facilities planning purposes, this six -year enrollment projection anticipates moderate enrollment
growth from new development currently in some phase of planning or construction in the district.
Kent School District Six -Year Capital Facilities Plan Table 2
April 2009 Page 7
KENT SCHOOL IISTRICT No. 415
CAPACITY of ELEMENTARY SCHOOLS & KINDERGARTEN PROJECTIONS for October 2009
2008 -2009
Program
ELEMENTARY SCHOOL ABR
Capacity
Carriage Crest Elementary
Cedar Valley Elementary
Covington Elementary
Crestwood Elementary
East Hill Elementary
Emerald Park
Fairwood Elementary
George T. Daniel Elementary
Gtenridge Elementary
Grass Lake Elementary
Horizon Elementary
Jenkins Creek Elementary
CC
CV
CO
CW
EH
EP
FW
DE
GR
GL
HE
JC
Kent Elementary KE
Lake Youngs Elementary LY
Martin Sortun Elementary MS
Meadow Ridge Elementary MR
Meridian Elementary ME
Millennium Elementary ML
Neely- O'Brien Elementary NO
Panther Lake Elementary PL
Park Orchard Elementary PO
Pine Tree Elementary PT
Ridgewood Elementary RW
Sawyer Woods Elementary SW
Scenic Hill Elementary SH
Soos Creek Elementary SC
Springbrook Elementary SB
Sunrise Elementary SR
452
402
498
456
464
504
408
450
456
452
504
398
464
524
474
464
524
498
440
396
480
522
504
504
464
408
398
504
Elementary TOTAL 13,012
28 Elementary Schools 2
Note 1: KAI = Kindergarten Academic Intervention at ML & PT: FDK Program for qualified Kindergarten students & 1/2 Day Kindergarten for remainder of Kindergarten students.
Note 2: 12 schools have State Funded FDK projected at 1.0 FTE - 2 schools have KAI FDK @.1.0 & 1/2 Day K @ .5 - 14 have Optional Tuition -based &/or 1/2 Day Kindergarten all projected at .5 FTE.
1.0 FTE
Forecast
for
1.0 Funded
State
Apportionment
FDK
1.0 FTE
Forecast
for
1.0 Funded
I - 728
FDK
1.0 FTE .5 FTE
Forecast Forecast
for for
1.0 Funded 0.50 Funded
Title I Kindergarten
1 KAI FDK 1/2 Day
.5 FTE
Forecast
for
0.50 Funded
Optional
Tuition -Based
1/2 Day (& FDK)
.5 FTE
Forecast
for
0.50 Funded
Basic Ed
1/2 Day K Only
Oct -09
Projected
Kindergarten
Students
FTE
Elem
Schl
Abry
Code
@ 1.0
@ .50
58
-
34
37
36
58
34
37
36
CC
CV
CO
CW
98
71
30
34
98
71
30
34
EH
EP
FW
DE
50
32
19
33
50
32
19
33
GR
GL
HE
JC
79
96
83
22
79
96
83
22
KE
LY
MS
MR
31
40
102
82
31
25
ME
ML
NO
PL
102
82
40 25
20 16
71
71
20
16
36
35
PO
PT
RW
SW
36
35
76
56
23
36
76
56
23
36
SH
SC
SB
SR
380 542 60 41 292 146 982 479
x 2
■
6
6
2
9
5
958
1940
HdCnt
Kent School District Six -Year Capital Facilijies-Plan
Table 2 A
April 2009 Page 8
III Current Kent School District "Standard of Service"
In order to determine the capacity of facilities in a school district, King County
Code 21A.06 references a "standard of service" that each school district must
establish in order to ascertain its overall capacity. The standard of service
identifies the program year, the class size, the number of classrooms, students
and programs of special need, and other factors determined by the district which
would best serve the student population.
This Plan includes the standard of service as established by Kent School District.
The District has identified schools with significant special needs programs as
"impact" schools and the standard of service targets a lower class size at those
facilities. Relocatables included in the capacity calculation use the same
standard of service as the permanent facilities. (See Appendix A, B & C)
The standard of service defined herein may continue to change in the future.
Kent School District is continuing a long -term strategic planning process
combined with review of changes to capacity and standard of service
adjustments to meet the requirements of Student Achievement Initiative 728.
This process will affect various aspects of the District's "standard of service" and
future changes will be reflected in future capital facilities plans. Because the
funding for Initiative 728 is incremental, implementation of the Initiative is also
incremental and may result in changes to school capacity.
Current Standards of Service for Elementary Students
Class size for Kindergarten is planned for an average of 22 students.
Class size for grades 1 - 4 is planned for an average of 23 students.
Class size for grades 5 - 6 is planned for an average of 29 students.
Program capacity for general education elementary classrooms is calculated at
an average of 24 students per classroom because of fluctuations between
primary and intermediate grade levels (i.e. third /fourth or fourth /fifth grade split
classes, etc.). Most elementary schools provide full day kindergarten programs
(FDK or KAI — Full Day Kindergarten or Kindergarten Academic Intervention) with
the second half of the day funded by grants or tuition.
Students have scheduled time in a computer lab. Students may also be provided
music instruction and physical education in a separate classroom or facility.
Special Education for students with disabilities may be provided in a self -
contained classroom with a capacity of 10 -15 depending on the program.
Kent School District Six -Year Capital Facilities Plan April 2009
(continued)
Page 9
I I I Current Kent School District "Standard of Service" (continued)
Identified students will also be provided other educational opportunities in
classrooms for programs such as those designated as follows:
English Language Learners (E L L)
Self- contained Special Education Support Center Programs (SC)
Integrated Programs & Resource Rooms (for special remedial assistance)
Early Childhood Education (ECE) (3 -4 yr. old students with disabilities)
School Adjustment (SA) Program for severely behavior - disordered students
Speech & Language Therapy & Programs for Hearing Impaired students
Adaptive Support Center for Mild, Moderate & Severe Disabilities (ASC -DD)
Occupational & Physical Therapy Programs (OT /PT)
Developmental Kindergarten in SC Programs
Kindergarten Academic Intervention Program (KAI -Full Day Kindergarten)
Education for Disadvantaged Students (Title I) — Federal Program
Learning Assisted Programs (LAP) — State Program
District Remediation Programs
Education for Highly Capable Students (formerly "Gifted" Program)
Some of the above special programs require specialized classroom space, as
well as music and physical education classrooms, computer labs, etc.; thus, the
permanent capacity of some of the buildings housing these programs is reduced.
Some students, for example, leave their regular classroom for a short period of
time to receive instruction in these special programs and "pull -out" space must
be allocated to serve these programs. Some newer buildings have been
constructed to accommodate most of these programs; some older buildings have
been modified, and in some circumstances, these modifications reduce the
classroom capacity of the buildings. When programs change, program capacity
is updated to reflect the change in program and capacity.
Current Standards of Service for Secondary Students
The standards of service outlined below reflect only those programs and
educational opportunities provided to secondary students which directly affect
the capacity of the school buildings. Reductions have been made in 7th and 10th
grade English classes for Initiative 728. These standards are subject to change
pending annual updates based on staff and public review for changes funded by
Student Achievement Initiative 728.
Class size for grades 7 - 8 is planned for an average of 29 students.
Class size for 7th & 10th grade English class is planned for an average of 25
students.
Class size for grades 9 - 12 is planned for an average of 31 students.
Special Education for students with disabilities may be provided in a self -
contained classroom with a capacity of 10 -15 depending on the program. (contd.)
Kent School District Six -Year Capital Facilities Plan
April 2009 Page 10
III Current Kent School District "Standard of Service" (continued)
Identified secondary students will also be provided other educational
opportunities in classrooms for programs designated as follows:
Computer, Multi -media & Technology Labs & Programs — (Nova Net - Advanced Academics)
Technology Academy programs at Kent - Meridian High School & Mill Creek Middle School
Science Programs & Labs — Biology, Chemistry, Physics, Oceanography, Astronomy,
Meteorology, Marine Biology, General Science, etc.
English Language Learners (E L L)
Integrated Programs & Resource Rooms (for special remedial assistance)
Basic Skills Programs
Transition Outreach Program (TOP) for 18 -21 year old Special Education students
Child Development Preschool and Daycare Programs
Music Programs — Band, Orchestra, Chorus, Jazz Band, etc.
Art Programs — Painting, Design, Drawing, Ceramics, Pottery, Photography, etc.
Theater Arts — Drama, Stage Tech, etc.
Journalism and Yearbook Classes
Highly Capable (Honors or Gifted) and Advanced Placement Programs
International Baccalaureate ( "I B ") Program
Kent Phoenix Academy — Performance Learning Center, Gateway, Virtual High School &
Kent Success program with evening classes designed for credit retrieval
Traffic Safety Education
JROTC - Junior Reserve Officers Training Corps
Variety of Career & Technical Education Programs (CTE- Vocational Education)
Family & Consumer Science — Culinary Arts, Sewing, Careers w /Children /Educ., etc.
Health & Human Services — Sports Medicine, Sign Language, Cosmetology, etc.
Business Education — Word Processing, Accounting, Business Law & Math, DECA,
FBLA (Future Business Leaders), Sales & Marketing, Economics, Web Design
Technical & Industry — Woodworking, Cabinet Making, Building Trades, Metals,
Automotive & Manufacturing Technology, Welding, Machine Shop, Drafting, Drawing,
CAD (Computer -aided Design), Electronics, Engineering & Design, Aviation, etc.
Graphic & Commercial Arts, Media, Photography, Theater & Stage, Ag & Horticulture
Many of these programs and others require specialized classroom space which
can reduce the permanent capacity of the school buildings. In addition,
alternative home school assistance, choice and transition programs are provided
for students in grades 3 - 12 at Kent Mountain View Academy.
Space or Classroom Utilization
As a result of scheduling conflicts for student programs, the need for specialized
rooms for certain programs, and the need for teachers to have a work space
during their planning periods, it is not possible to achieve 100% utilization of
regular teaching stations at secondary schools. Based on the analysis of actual
utilization of classrooms, the District has determined that the standard utilization
rate is 85% for secondary schools. Program capacity at elementary schools
reflects 100% utilization at the elementary level with adjustments for pull -out
programs served in relocatables. In the future, the District will continue dose
analysis of actual utilization.
Kent School District Six -Year Capital Facilities Plan
April 2009 Page 11
I V Inventory and Capacity of Existing Schools
Currently, the District has permanent program capacity to house 27,321 students
and transitional (relocatable) capacity to house 1,552. This capacity is based on
the District's Standard of Service as set forth in Section III. Included in this Plan
is an inventory of the District's schools by type, address and current capacity.
(See Table 3 on Page 13)
The ratio between permanent capacity and transitional capacity has changed
from 96 - 4% to 97 - 3% since the previous Plan.
The program capacity is periodically updated for changes in programs, additional
classrooms and new schools. Program capacity has been updated in this Plan to
reflect program changes and new capacity for building additions at the high
schools.
Program capacity also reflects adjustments for the Student Achievement
Initiative 728 reduction in class size. The class size reduction received voter
approval in the Educational Programs and Operations Levy as well as through
funding for Student Achievement Initiative 728. The District will conduct annual
public review and update class size recommendations in accordance with the
requirements and incremental funding of Student Achievement Initiative 728.
Kent Mountain View Academy (formerly Kent Learning Center and Grandview
Elementary) serves Grades 3 — 12 with transition, choice and home school
assistance programs. It is located in the former Grandview School in the western
part of the District in the city of SeaTac. This school was originally designed as
an elementary school and is included in the elementary capacity for this Plan.
Kent Phoenix Academy is a non - traditional high school which opened in Fall
2007 in the renovated site and building that formerly served Sequoia Middle
School. KPA has four special programs including the Performance Learning
Center, Gateway, Virtual High School and Kent Success. Kent Success replaced
the former Night Academy at Kent - Meridian High School and provides afternoon
and evening classes for credit retrieval.
Calculation of Elementary, Middle School and Senior High School capacities are
set forth in Appendices A, B and C. A map of existing schools is included on
Page 14.
Kent School District Six -Year Capital Facilities Plan
April 2009 Page 12
KENT SCHOOL DISTRICT No. 415
INVENTORY and CAPACITY of EXISTING SCHOOLS
Year
SCHOOL Opened ABR ADDRESS
2008 -2009
Program
Capacity 1
Carriage Crest Elementary
Cedar Valley Elementary
Covington Elementary
Crestwood Elementary
1990 CC 18235 - 140th Avenue SE, Renton 98058
1971 CV 26500 Timbertane Way SE, Covington 98042
1961 CO 17070 SE Wax Road, Covington 98042
1980 CW 25225 - 180th Avenue SE, Covington 98042
452
402
498
456
East Hill Elementary
Emerald Park
Fairwood Elementary
George T. Daniel Elementary
1953 EH 9825 S 240th Street, Kent 98031
1999 EP 11800 SE 216th Street, Kent 98031
1969 FW 16600 - 148th Avenue SE, Renton 98058
1992 DE 11310 SE 248th Street, Kent 98030
464
504
408
450
Glenridge Elementary 1996 GR 19405 - 120th Avenue SE, Renton 98058 456
Grass Lake Elementary 1971 GL 28700 - 191st Place SE, Kent 98042 452
Horizon Elementary 1990 HE 27641 - 144th Avenue SE, Kent 98042 504
Jenkins Creek Elementary 1987 JC 26915 - 186th Avenue SE, Covington 98042 398
Kent Elementary .1999 KE 24700 - 64th Avenue South, Kent 98032 464
Lake Youngs Elementary 1965 LY 19660 - 142nd Avenue SE, Kent 98042 524
Martin Sortun Elementary 1987 MS 12711 SE 248th Street, Kent 98030 474
Meadow Ridge Elementary 1994 MR 27710 - 108th Avenue SE, Kent 98030 464
Meridian Elementary 1939 ME 25621 - 140th Avenue SE, Kent 98042 524
Millennium Elementary 2000 ML 11919 SE 270th Street, Kent 98030 498
Neely -O 'Brien Elementary 1990 NO 6300 South 236th Street, Kent 98032 440
Panther Lake Elementary 1938 PL 20831 -108th Avenue SE, Kent 98031 396
Park Orchard Elementary 1963 PO 11010 SE 232nd Street, Kent 98031 480
Pine Tree Elementary 1967 PT 27825 - 118th Avenue SE, Kent 98030 522
Ridgewood Elementary 1987 RW 18030 - 162nd Place SE, Renton 98058 504
Sawyer Woods Elementary 1994 SW 31135 - 228th Ave SE, Black Diamond 98010 504
Scenic Hill Elementary 1960 SH 26025 Woodland Way South. Kent 98030 464
Soos Creek Elementary 1971 SC 12651 SE 218th Place, Kent 98031 408
Springbrook Elementary 1969 SB 20035 - 100th Avenue SE, Kent 98031 398
Sunrise Elementary 1992 SR 22300 - 132nd Avenue SE, Kent 98042 504
Elementary TOTAL
Cedar Heights Middle School 1993 CH 19640 SE 272 Street, Covington 98042 923
Mattson Middle School 1981 MA 16400 SE 251st Street, Covington 98042 804
Meeker Middle School 1970 MK 12600 SE 192nd Street, Renton 98058 890
Meridian Middle School 1958 MM 23480 - 120th Avenue SE, Kent 98031 790
Mill Creek MS (former Kent Jr Hi) 2 2005 / 1952 MC 620 North Central Avenue, Kent 98032 828
Northwood Middle School 1996 NW 17007 SE 184th Street. Renton 98058 972
Middle School TOTAL 5,207
Kent - Meridian Senior High School
Kentlake Senior High School
Kentridge Senior High School
Kentwood Senior High School
Senior High TOTAL
Kent Mountain View Academy 3
1951 KM 10020 SE 256th Street, Kent 98030
1997 KL 21401 SE 300th Street, Kent 98042
1968 KR 12430 SE 208th Street, Kent 98031
1981 KW 25800 - 164th Avenue SE, Covington 98042
1965 MV /LC 22420 Military Road, Des Moines 98198
Kent Phoenix Academy 4 1966 PH 11000 SE 2641h Street, Kent 98030
DISTRICT TOTAL
1,772
2,157
2,270
2,137
LEM
I
27,321
Changes to capacity reflect program changes and new building additions at high schools.
2 Mill Creek Middle School and Technology Academy replaced renovated Kent Junior High in 2005.
S Kent Mountain View Academy serves grades 3 -12. The school was formerly known as Kent Learning Center & Grandview Elementary.
` Kent Phoenix Academy is a non - traditional high school which opened in Fall 2007 in the former Sequoia MS building.
Kent School District Six -Year Capital Facilities Plan
Table 3
April 2009 Page 13
Kent School District Six -Year Capital Facilities Plan
>
N
0
co
ca
co
co
W
0 0
SE Petrovltsk
S 212th St
• Kent
Mountain View
Academy
Neely O'Brien
Elementary •
%,, Kent
Elementary
m I es Rd
0
VJ
`4r
m
0
c
U
Springbrook
Elementary
•
Panther Lake
Elementary
East Hill
Elementary
•MiIl Creek •
MidICI a School
Kent - Meridian
High School•
Scenic Hill • T,
Elementary <
L
0
W
y
Q
L
0
Carriage Crest
Elementary •
• Meeker
• Middle Sc
Glenridge
Elementary
Kentridge
High School
• SE 208th St
'airwood
ementary
•
hool
Lake
•Youngs
Elementar
Emerald Park
Elementary
•
Soos Creek•
Elementary
/Park Orchard
Elementary
• Meridian
•Middle School
fl\J
*Sunrise
Elementary
SE 240th St
Daniel
• Elementary
Martin •
Sortun
Elementary
•
Administration
• Center
Kent Phoenix
Academy
•
Millennium
Elementary
Meadow gage
Elemen ary •
•
Pine Tree
Elementary
SE 256th St
• Meridian
Elementary
Ridgewood
Elementary
•
1•vI
Northwood
Middle School
Lake
Desire
Kent School District No. 415
Serving residents of
Unincorporated King County
City of Kent
City of Renton
City of Auburn
City of Sea Tac
City of Covington
City of Maple Valley
City of Black Diamond
Lake
Youngs
SE 240th St
N
0
>
Mattson
Middle Scho
•
•
• Kentwood
High School
sI
Crestwood
Elementary
Lake
Meridian
Horizon •
Elementary
N
0
'0
c
N
155
Cedar Valley
Elementary
•
Jenkins
Creek • Cedar Heights
Elementary • Middle School
Kent - Kangley Road
• Covington
Elementary
Grass Lake
•
Elementary
SE Govin9ton- SawYerR ,
28 Elementary Schools
6 Middle Schools
4 Senior High Schools
Kent Mountain View Academy (Grades 3 -12)
Kent Phoenix Academy (9 -12)
Lake
Morton
SE 272nd St
Lake
Sawyer
Kentlake•
High School
Sawyer Woods.
Elementary
V Six -Year Planning and Construction Plan
At the time of preparation of this Plan in spring of 2009, the following projects are
completed or in the planning phase in Kent School District:
• Construction is in progress for additional classroom capacity at Kent - Meridian High
School and has recently been completed at Kentlake High School.
• Sequoia Middle School was renovated and reconfigured to provide capacity for
approximately 350 high school students at the non - traditional high school, Kent Phoenix
Academy in 2007 -08.
• Kent Junior High was renovated and renamed Mill Creek Middle School. Mill Creek MS
also serves the Kent Technology Academy program for students in Grades 7 - 8. The
construction of Phase I I of the renovation of Mill Creek MS is in progress.
• In February 2006, voters approved construction funding for replacement of Panther Lake
Elementary School and a future Elementary School to accommodate new growth. A new
site was acquired and construction is in progress for replacement of Panther Lake
Elementary. The new Panther Lake will open to replace the current school in Fall 2009.
• Planning is in progress for a replacement school for Covington Elementary School.
• Enrollment projections reflect future need for additional capacity at the elementary school
level. Future facility and site needs are reflected in this Plan.
• Some funding is secured for purchase of additional portables and some funding may be
provided by impact fees as needed. Sites are based on need for additional capacity.
As a critical component of capital facilities planning, county and city planners and
decision - makers are encouraged to consider safe walking conditions for all
students when reviewing applications and design plans for new roads and
developments. This should include sidewalks for pedestrian safety as well as bus
pull -outs and turn - arounds for school buses.
Included in this Plan is an inventory of potential projects and sites identified by the
District which are potentially acceptable site alternatives in the future. (See Table 4 on Page 16
& Site map on Page 17)
Voter approved bond issues have included funding for the purchase of sites for some of
these and future schools, and the sites acquired to date are included in this Plan. Some
funding is secured for purchase of additional sites but some may be funded with impact
fees as needed. Not all undeveloped properties meet current school construction
requirements and some property may be traded or sold to meet future facility needs.
2006 voter approval of $106M bond issue for capital improvement included the
construction funding for a new elementary school, replacement of Panther Lake
Elementary, and classroom additions to high schools. Some impact fees will also be
applied to those projects. Student Achievement Initiative 728 funds are being utilized to
reduce class size and provide extended learning opportunities. Based on community
input at public hearings, the Board will continue annual review of standard of service and
those decisions will be reflected in the each update of the Capital Facilities Plan.
Kent School District Six -Year Capital Facilities Plan
April 2009 Page 15
KENT SCHOOL DISTRICT No. 415
Site Acquisitions and Projects Planned to Provide Additional Capacity
SCHOOL / FACILITY / SITE
LOCATION 1 Type
Status
# on
Map
ELEMENTARY
, ' i.,_ _ .ti } ;. . +t 'r is
Projected
Projected
% for
Completion
Program
new
Date
Capacity
Growth
Approximate Approximate
(Numbers assigned to future schools may not correlate with number of existing schools.)
13 Replacement for Panther Lake Elementary (F) SE 216th Street & 102nd Ave SE
PL Elementary Site (F) SE 216th Street & 102nd Ave SE
Panther Lake Elementary - Replaced in 2009 SE 208 Street & 108th Ave SE
5 Replacement for Covington Elementary (U) SE 256th Street & 154th Ave SE
Covington Elem - Replacement planned for 2011 17070 SE Wax Road, Covington
Elementary # 31 (Actual #29) (F) To be determined 2
Site for Elementary # 31 (Unfunded) To be determined 2
MIDDLE SCHOOL
Mill Creek Middle School
Phase II of Renovation
Sequoia Middle School
SENIOR HIGH
New Non - traditional High School
Kent Phoenix Academy (Funded)
Classroom additions at Kentlake High School (F)
Classroom additions at Kent- Meridian HS (F)
TEMPORARY FACILITIES
Relocatables
SUPPORT FACILITIES
Bus Facility (Unfunded)
# on
Map
3 OTHER SITES ACQUIRED
4 Covington area North (Near Mattson MS)
7 Covington area South (Scarsella)
5 Covington area West (Halteson- Wikstrom)
3 Ham Lake area (Pollard)
8 SE of Lake Morton area (West property)
2 Shady Lk area (Sowers, Blaine, Drahota, Paroline)
1 So. King Co. Activity Center (Nike site)
12 South Central site (Plemmons- Yeh -Wms)
Replacement
Site
Replacement
Replacement
Replacement
New
Site
Construction Fall 2009 500 21%
2009 21%
Planning 2009 -396
Planning 2011 600 20%
Planning 2011 -498
Planning 2012 -13 600 100%
Planning 2012 -13 100%
620 N. Central Avenue, Kent Renovation construction 2009 828 NIA
In progress
Renovation & Reconfiguration Renovation Planning 2007 - 771 NIA
for Kent Phoenix Academy
Former Sequoia Middle School
11000 SE 264th Street, Kent
21401 SE 300th Street, Kent
10020 SE 256th Street, Kent
For placement as needed
Renovation
Additions
Additions
New
Near Kent - Meridian High School New
SE 251 & 164 SE, Covington 98042
SE 290 & 156 SE, Kent 98042
SE 256 & 154 SE, Covington 98042
16820 SE 240, Kent 98042
SE 332 & 204 SE, Kent 98042
17426 SE 192 Street, Renton 98058
SE 167 & 170 SE, Renton 98058
SE 286th Street & 124th Ave. SE, Kent
Utilized
Utilized
In progress
2007 -08
2008
2009
Planning 2008+
Planning TBD 2
350 100%
171 100%
79 100%
Additional
Capacity
24.31 each 100%
N/A
Type
Land Use
Jurisdiction
Elementary
Elementary
Elementary
Elementary
Secondary
Elementary
TBD 2
TBD 2
City of Covington
King County
City of Covington
King County
King County
King County
King County
King County
Notes:
' Unfunded facility needs will be reviewed in the future.
2 TBD - To be determined - Some sites are acquired but placement, timing and /or configuration have not been determined.
3 Numbers correspond to sites on Site Bank Map on Page 17. Other site locations are parcels identified in Table 7 on Page 27.
Kent School District Six -Year Capital Facilities Plan Table 4
April 2009 Page 16
Kent School District Six -Year Capital Facilities Plan
h
0
c
SE 192nd St
SE Petrovitsky Rd
108th Ave SE
Springbrook
Elementary
S 212th St
Kent
Mountain View
Academy
m
Neely O'Brien
Elementary.
Iley Highway
Kent
Elementary.
c
0
U
w
0
t
orriage Cres
Elementary.
Meeker
• Middle School
Glenridge
Elementary
Fairwood
Elementary
0
Ridgewood
Elementary
•
Northwood
Middle School
•
Lake
Desire
Lake Youngs
• Elementary
Kentridge
High School
• SE 208th St
/anther Lot
Elementary
Panther Loke
Replocement
Emerald Park
Elementary
• Soos'Creek
Elementary
(I) Xark Orchard
Elementary
•
East Hill
Elementary
•Mal Creek •
addle School Daniel•
Kent- Elementary
Meridian
High
School
•
132nd Ave SE
• Meridian
Middle School
SE 240th St
w
N
Scenic Hill," m
Elementary
t
0
SE 288th Street
Martin
Sortun
Elementary
• Sunrise
Elementary
SE 256th St
Lake Youngs
SE 240th St
Kent School District No. 415
Site Bank
M
Property Acquisitions
Mattson
Middle Scho .restwood
Elementary
Administration
Center
Kent • oenix
Academy Millennium
Elementary
Meadow Ridge rw
.Elementary m
•Pine Tree Q
Elementary a
c
• Meridian
Elementary
Lake Meridian
-Kentwood
High School
6
Cedar Valley
Elementary
•
Jenkins
Creek.
Elementary
Pipe Lake
Cedar Heights
• Middle School
SE 272 nd St
Horizon •
Elementary
Kent - Kangley Road
• Covington
stoA Elementary
Grass Lake
0 Elementary
Bi0o4 S. Covington - sawyer
O4
•
SE 304th Street
Lake
Morton
Kentlake •
High School
Sawyer Woods
Elementary •
0
SE 336th St
Lake
Sawyer
V I Relocatable Classrooms
For the purpose of clarification, the term "portables" and the more descriptively
accurate term, "relocatables" are used interchangeably in this Plan. The Plan
also references use of portables or relocatables as interim or transitional
capacity /facilities.
Currently, the District utilizes 128 relocatables to house students in excess of
permanent capacity, for program purposes at school locations, and several for
storage or other purposes. (See Appendices A B C D)
Based on enrollment projections, implementation of additional full day
kindergarten programs, program capacity and the need for additional permanent
capacity, the District anticipates the need to purchase some additional
relocatables during the next six -year period. The continually escalating cost of
moving relocatables will increasingly limit the choice between building new
relocatables on site and relocating older ones.
During the time period covered by this Plan, the District does not anticipate that
all of the District's relocatables will be replaced by permanent facilities. During
the useful life of some of the relocatables, the school -age population may decline
in some communities and increase in others, and these relocatables provide the
flexibility to accommodate the immediate needs of the community.
Portables, or relocatables, may be used as interim or transitional facilities:
1. To prevent overbuilding or overcrowding of permanent school
facilities.
2. To cover the gap between the time of demand for increased
capacity and completion of permanent school facilities to meet
that demand.
3. To meet unique program requirements.
Relocatables currently in use are continually evaluated resulting in some being
improved and some replaced. Quality concerns will be among those addressed
by the next Community Facilities Planning Committee for review of capital
facilities needs for the next bond issue.
The Plan projects that the District will use relocatables to accommodate interim
housing needs for the next six years and beyond. The use of relocatables, their
impacts on permanent facilities, life cycle and operational costs, and the
interrelationship between relocatables, emerging technologies and educational .
restructuring will continue to be examined.
Kent School District Six -Year Capital Facilities Plan April 2009 Page 18
V I I Projected Six Year Classroom Capacity
As stated in Section 1 V, the program capacity study is periodically updated for
changes in special programs and reflects class size fluctuations in Grades K - 4.
As shown in the Inventory and Capacity chart in Table 3 on Page 13, the
program capacity is also reflected in the capacity and enrollment comparison
charts.. (See Tables 5 & 5 A -B -C on pages 20 - 23)
Enrollment is electronically reported to OSPI on Form P -223 on a monthly basis
and funding apportionment is based on Annual Average FTE (AAFTE). The first
school day of October is widely recognized as the enrollment "snapshot in time"
to report enrollment for the year.
Full Time Equivalent (FTE) student enrollment for October 2008 was 25,827.82.
Kindergarten students are reported at .5 although many schools provide full day
kindergarten ( "FDK ") with alternative funding for the second half of the day.
State - funded Full Day Kindergarten programs will report and project some
Kindergarten students at 1.00 FTE at qualifying FDK schools. P -223 FTE
excludes Early Childhood Education (preschool) students and College -only
Running Start students. (See Tables 5 & 5 A -B-C on pages 20 - 23)
In October there were 679 students in 11th and 12th grade participating in the
Running Start program at 10 -20 different colleges and receiving credits toward
both high school and college graduation. 334 of these students attended classes
only at the college ( "college- only ") and are excluded from FTE and headcount for
capacity and enrollment comparisons.
Kent School District continues to be the fourth largest district in the state of
Washington. P -223 Headcount for October 2008 Was 26,831 with kindergarten
students counted at 1.0 and excluding ECE and college -only Running Start
students. A full headcount of all students enrolled in October 2008 totals 27,579
which includes ECE and college -only Running Start students.
Based on the enrollment forecasts, current inventory and capacity, current
standard of service, relocatable capacity, and future planned additional
classroom space, the District anticipates having sufficient capacity to house
students over the next six years. (See Table 5 and Tables 5A -B -C on Pages 20 - 23)
This does not mean that some schools will not experience overcrowding. There
may be significant need for additional portables and/or new schools to
accommodate growth within the District and class size reduction mandated
under Student Achievement Initiative 728. Some schools, by design, may be
opened with relocatables on site. Boundary changes, limited and costly
movement of relocatables, zoning changes, market conditions, and educational
restructuring will all play a major role in addressing overcrowding and
underutilization of facilities in different parts of the District.
Kent School District Six -Year Capital Facilities Plan
April 2009 Page 19
KENT SCHOOL DISTRICT No. 415
PROJECTED ENROLLMENT and CAPACITY
TOTAL DISTRICT
,.3evaszrzi 24,12 :, +;4saar;.riri+evoaf,/�nMPAYD,
7111)6 0 173 :erli^acrZraartZo4.,:.r >seVAMADZ .IMCWIZ ssAValeae: WEitaL
2elt srssia n.:5;214: 0•-a
SCHOOL YEAR
2008 -2009
2009 -2010
2010 -2011
2011 -2012
2012 -2013
2013 -2014
2014 -2015
'.
Actual
P R 0 J E C T E D
1 3S :x1Ca.E'MMIMa4{,EfA.KasmlXarTP, OOLL.'T702'..fn2%.1AL +(.314!DNS,n:SCAINZWItlY,s.
2=45. E c.- . -Mdar+ B+ <^' " ";tv:. ^ATiM'a¢narrn .s.�eaJfsn6:x^.M r;G`4F
Permanent Program Capacity 1
CChanges to Permanent Capacity 1 I
27,150 27,321 27,504 27,504 27,606 28,206 28,206
Classroom additions at Kentlake HS (F) 171
Classroom additions at Kent - Meridian HS (F) 79
Mill Creek MS Renovation - No new Capacity 2
Replacement schools with projected increase in capacity
Panther Lake Elementary 3 (Funded)
To Replace current school capacity
500
-396
Covington Elementary 3 (Unfunded) 600
To Replace current school capacity -498
New Elementary # 3i (Funded)
600
Permanent Program Capacity Subtotal' 27,321 27,504 27,504 27,606 28,206 28,206 28,206
(Interim Relocatable Capacity
Elementary Relocatable Capacity Required
0 120 288 408 96 480 840
Middle School Relocalable Capacity Required 4 0 0 0 0 0 0 0
Senior High Relocatable Capacity Required
Total Relocatable Capacity Required 1 8.6
0 0 0 0 0 0 0
0 120 288 408 96 480 840
TOTAL CAPACITY 1
27,321
27,624
27,792
28,014
28,302
28,686
29,046
TOTAL FTE ENROLLMENT/ PROJECTION 5
25,828
26,118
26,310
26,592
26,934
27,325
27,711
DISTRICT AVAILABLE CAPACITY
1,493 1,506 1,482 1,422 1,368 1,361 1,335
1 Capacity is based on standard of service for programs provided and updated periodically to reflect program changes.
2 Phase I I of renovation continues for Mill Creek Middle School & Kent Technology Academy. (No new capacity added.)
3 Replacement schools for Panther Lake & Covington Elementary will be built on new sites with increased capacity.
a In Fall 2004, 9th grade moved to the high schools which increased capacity available at Middle School 7 - 8 grade levels.
5 FTE = Full Time Equivalent Enrollment/Projections (i.e. 1/2 day Kindergarten student = .5 & Full Day Kindergarten student = 1.0 FTE).
6 2008 -2009 total classroom relocatable capacity is 1,552.
Kent School District Six -Year Capital Facilities Plan
Table 5
April 2009 Page 20
KENT SCHOOL DISTRICT No. 415
PROJECTED ENROLLMENT and CAPACITY
SENIOR HIGH - Grades 9 -12
tOa faart=EU.iksatatifia ;.51KIX. r an;'4ncV:=Urge?ai-
MILFa°.iaja
70s1�./M74,1Wfa
o r r ` s ,-= , ,•
u, awue
�axc
SCHOOL YEAR
2008-2009
2009 -2010
2010 -2011
2011 -2012
2012 -2013
2013 -2014
2014 -2015
Actual
P R 0 J E C T E D
„ K.. �,.... m.,_.... nA, �,,.,.:+9.,e- ,2s,,.,�,,r�a-�:. ..�. - �n�sac:2-s¢rr•.�a��;i3ssa�
n,.r sac., aoe�caeair� ,v`. aM1CLSZVV..l,.:S;i3ffs,M .t,fY eY.F�.lst7irvli-
Senior High Permanent Capacity'
Includes Kent Phoenix Academy 2
Changes to High School Capacity
8,515 8,686 8,765 8,765 8,765 8,765 8,765
Classroom additions at Kentlake HS (F) 171
Classroom additions at Kent - Meridian HS 79
and KM Technology Academy 3 (F)
Subtotal 8,686 8,765 8,765 8,765 8,765 8,765 8,765
Relocatable Capacity Required 1
0
0
0
0
0
0
0
TOTAL CAPACITY 1
8,686 8,765 8,765 8,765 8,765 8,765 8;765
FTE ENROLLMENT / PROJECTION a
8,333 8,248 8,268 8,286 8,289 8,330 8,394
SURPLUS (DEFICIT) CAPACITY
Number of Relocatables Required
353 517 497 479 476 435 371
0
0
0
0
0
No Classroom Relocatables required at this time. Some Relocatables used for classroom and program purposes.
0
0
' Capacity is based on standard of service for programs provided and updated periodically to reflect program changes.
2 Sequoia Middle School was renovated and reconfigured as a new non - traditional high school, and re- opened in Fall 2007
as Kent Phoenix Academy serving grades 9 - 12 with four special programs.
3 KM added a new high school Technology Academy program in 2007 serving students in grades 9 - 10 in 2008 -09.
FTE = Approximate Full Time Equivalent Enrollment or projections, excluding College -only Running Start students.
Kent School District Six -Year Capital Facilities Plan Table 5 A
April 2009 Page 21
KENT SCHOOL DISTRICT No. 415
PROJECTED ENROLLMENT and CAPACITY
MIDDLE SCHOOL - Grades 7 - 8
iiS !Ci.x,, mint ".3`.3L'1zrAgn trw.,70Y.,ustrarkyL'finntirinc .i,J.^.L::;...curiS''
SCHOOL YEAR
my4i3usTRA.75Xv"i.mo.14
2008 -2009
?e
37346 z r sha -4.. `+�Ta
"n•• . S3,0g.•.'Ii:3:.✓in"rawr,z.14-
2013 -2014
2014 -2015
2009 -2010
2010 -2011
2011
-2012
2012 -2013
Actual
P R 0 J
E C T E D
Middle School Permanent Capacity 1
Changes to Middle School Capacity
4 Mill Creek MS & Kent Technology Academy
are open during Phase 2 of Renovation
(No new capacity added in renovation)
5,207 5,207 5,207 5,207 5,207 5,207 5,207
Subtotal 5,207 5,207 5,207 5,207 5,207 5,207 5,207
Relocatable Capacity Required 1
0
0
0
0
0
0
0
TOTAL CAPACITY 1 & 3
5,207 5,207 5,207 5,207 5,207 5,207 5,207
. F ENROLLMENT / PROJECTION 2
TE
4,260 4,227 4,240 4,274 4,323 4,290 4,256
SURPLUS (DEFICIT) CAPACITY 5
947 980 967 933 884 917 951
No Classroom Relocatables required at middle schools at this time. Some Relocatables used for classroom and program purposes.
Capacity is based on standard of service for programs provided and updated periodically to reflect program changes.
2 FTE = Approximate Full Time Equivalent Enrollment or Projections
3 Grade level reconfiguration - All 9th grade students moved to the high schools in Fall 2004.
4 Mill Creek Middle School & Technology Academy - Kent Junior High was renovated and re- opened in
Fall 2005 with a Technology Academy serving 7th & 8th grade students from all service areas.
Phase I I of Mill Creek renovation continues in 2008 -09 and the school is open during construction.
5 Middle School capacity meets concurrency requirements and no impact fees are collected for middle schools.
Kent School District Six -Year Capital Facilities Plan
Table 5 B
April 2009 Page 22
KENT SCHOOL DISTRICT No. 415
PROJECTED ENROLLMENT and CAPACITY
ELEMENTARY - Grades K - 6
tEAkmcu;coswarrorwavown? rs,tcoavvsiS_'4'arueeh,xtT'.
gnau.,,maseumbR
£C2 ""
-xs • • �Tsma,4asc
7..:Si1]Aarstriifii"'sta
SLi18w ieo.f.z.: i.26-
_TuP3?5i wtiP
SCHOOL YEAR
2008 -2009
2009 -2010
2010 -2011
2011 -2012
2012 -2013
2013 -2014
2014 -2015
Actual
P R 0 J E C T E D
W '"° 3ll423NR IZ_ CA RI CL i1.771X'.IAC'ti-.C+I.tS2.51th
:TZ N58e''Si*.4uA
'OURN= LW lYT.a :4W5....9XNaLC_ rSSS.i1Mna_ 'd^a 1C=3
Elementary Permanent Capacity 1
13,012 13,428 13,532 13,532 13,634 14,234 14,234
Kent Mountain View Academy 2 416
Changes to Elementary Capacity
Replacement schools with projected increase in capacity
Panther Lake Elementary 4 (Funded)
Replaces current school capacity
500
-396
Covington Elementary 4 (Unfunded) 600
Replaces current Covington Elem. capacity -498
New Elementary # 31 (Funded) 5
600
Subtotal 13,428 13,532 13,532 13,634 14,234 14,234 14234
Relocatable Capacity Required 1
0 120 288 408 96 480 840
TOTAL CAPACITY 2
13,428 13,652 13,820 14,042 14,330 14,714 15,074
FTE ENROLLMENT / PROJECTION 3
13,235 13,643 13,802 14,032 14,322 14,705 15,061
SURPLUS (DEFICIT) CAPACITY
193 9 18 10 8
9 13
Number of Relocatables Required
0
5
13
17
4
35 Classroom Relocatables required in 2014 -15. Some additional Relocatables used for program purposes.
20
35
Capacity is based on standard of service for programs provided and is updated periodically to reflect program changes.
2 Kent Mountain View Academy is a special program at the former Grandview School serving students in Grades 3 - 12.
The school building (formerly Kent Learning Center & Grandview Elem.) was designed as an elementary school.
s FTE = Approximate Full Time Equivalent Enrollment or Projections (Kindergarten @ .5 or 1.0 & excluding ECE)
Kindergarten projection is at .5 FTE for Half Day Kindergarten programs or optional Tuition -based Full Day Kindergarten.
Kindergarten projection is at 1.0 FTE for Full Day Kindergarten programs funded by state apportionment or grants.
4
Replacement schools for Panther Lake & Covington Elementary will be built on new sites with increased capacity.
5 Site selection and construction timing for Elementary #31 is pending review of location and capacity needs.
Kent School District Six -Year Capital Facilities Plan Table 5 C
Apnl 2009 Page 23
VIII Finance Plan
The finance plan shown on Table 6 demonstrates how the Kent School District
plans to finance improvements for the years 2009 - 2010 through 2014 - 2015.
The financing components include secured and unsecured funding and impact
fees. The plan is based on voter approval of future bond issues, collection of
impact fees under the State Growth Management Act and voluntary mitigation
fees paid pursuant to State Environmental Policy Act.
Voters approved a $69.5 million bond issue for Capital Construction and
Improvements in February 2002. The bond issue partially funded building
additions at three high schools which coincided with moving 9th grade students
from junior high to senior high schools in September 2004. The District received
some District Equalization funds (formerly known as "state matching funds ") and
has utilized impact fees for the senior high additions.
In February 2006, voters approved a $106 million bond issue for replacement of
Panther Lake Elementary School with increased capacity, as well as construction
of a new elementary school to accommodate growth. The new Panther Lake
Elementary School is under construction and will be open in Fall 2009.
The bond issue also funded Phase II of the renovation for Mill Creek Middle
School and renovation of Sequoia Middle School for reconfiguration as a new
non - traditional high school. Kent Phoenix Academy opened at the former
Sequoia Middle School site in September 2007.
2006 construction funding approval also provided for some additional classrooms
to be constructed at Kentlake and Kent - Meridian High Schools. Some impact
fees will be utilized for the new construction that will increase capacity.
Enrollment projections reflect future need for additional capacity at the
elementary level and unfunded facility needs will be reviewed in the future.
Some funding is secured for additional portables and some will be funded from
impact fees.
For the Six -Year Finance Plan, costs of future schools are based on estimates
from Kent School District Facilities Department. Please see pages 26 -27 for a
summary of the cost basis.
Kent School District Six -Year Capital Facilities Plan
April 2009 Page 24
KENT SCHOOL DISTRICT No. 415
SIX-YEAR FINANCE PLAN
-., ',_,'.. ,-',Y.--,•,4-,-.1:-7-:' - '..,4,-..., '4, :1,,,, ;,. ,-,.. -1- ;4-: ;-, 4,0' -r.3.$,,4"fr•,',7.i..;':--...e.',■.;•-_-r ',r, ".1;gp,:?!;:z:::,N:'- ':',;,..e"',,,,,ce,,== ,./i-1::;,1;:t,'s ' 'r,_:=7,.',.::,, C-1-z,z6n.,,z, .r..-.:.$%Pf.-:-,r,7,,, ':):k.s.'i,'‘...:4
, ,.:-,-;;;-... ,...... ,: .-",
,,,, ,,.,- -_ T.,' tr:.,'X,',...:.-:;-1.,:".%:..."-1: 's• ' ' T " . ', ' t'-"Zi.:‘,,tWZ: :9
.i..--r-::, ":— ,"'
'''''' '-'■''''.;s- --,'-':;:.'in..; - .;Z:,...,.'.:.L: -!..--._:' 0 '...-.:-.. .';'.'.. .)'' . ' ,-,-‘,..r.e•re..,571.,'■;.. Secured
Unsecured
State 2 or Local 3
Impact
Fees
SCHOOL FACILITIES
* 2009
2010
2011 . 2012
2013
2014 TOTAL
-,:,
Local & State
--.: ,■-■ .:."_::'''''..t ':_°;.fg:-.-V-7,' :::::';',..;:t.:Pati?''f'i:Vat.'15`;';;;35.3-1"‘''t:::'■--e" '...?; tei147-„W2:t1:7%:::,.Aqe-rg,7-&;Z;z5f.A3',IT`:;'Wkt;,t44;;;:V:Vili.24-.k.r:oag:4-AY.;:2*.3'Zt.:..liti,14C:e3-,:nV.,t4i. aCt7141. ;11;:lagiiier;P.
PERMANENT FACILITIES
$5,700,000
$2,500,000
$26,700,000
$4,485,013
$28,900,000
$30,320,000
$2,500,000
5246,860 $259,200
2 relocatables 2 relocatables
::...
,.t.
-.,. 55,700,000 $1,700,000 $4,000,000
..;- $1,000,000 51,500,000
$2,500,000
;...
1-
=.' $26,700,000 $21,093,000 $5,607,000
.‘;
i= $4,485,013 53,543,160 $941,853
A,
,,. U8,900,000 $1,850,000 $21,270,000 $5,780,000
$30,320,000 514,000,000 55,600,000 510,720,000
•t,
.3- 52,500,000 $2,500,000
''
4 •
•.--,
5506,060 579,000 $427,060
1.1
'-
'..
....
..
Addition to Kentlake HS 1- 2
Addition to Kent-Meridian HS 1-2
Panther Lake Elem Replacement 1
3
Panther Lake Elementary Site
Covington Elementary Replacement 1
Elementary # 31 1-2-3
Elementary Site 3
F
F
F
F
U
F
U
TEMPORARY FACILITIES
Additional Relocatables 3 4
F
U
OTHER
N/A
Totals
539.385,013 5246,860 $29,159,200 532,820,000. $0 $0 $101,611,073 $43,265,160 $26,870,000 $31,475,913
* F = Funded U = Unfunded
1 Based on estimates of actual or future construction
2 The District anticipates receiving some state
3 Facility needs are pending review. Some of
4 Cost of Relocatables based on current cost
5 Fees in this column are based on amount of
costs from Facilities Department. (See Page 25 for Cost Basis Summary)
matching funds for these projects.
these projects may be funded with impact fees.
and adjusted for Inflation for future years.
fees collected to date and estimated fees on future units.
Kent Scht.
trict Six-Year Capital Facilities Plan
Tab
April 2009 F 5
V III Finance Plan - Cost Basis Summary
For impact fee calculations, construction costs are based on cost of the last
elementary school, adjusted for inflation, and projected cost of the next
elementary school.
Elementary School
Cost
Projected Cost
Millennium Elementary #30
Opened in 2000
$12,182,768
Cost of Panther Lake Elementary
Replacement (To open in 2009)
$26,700,000
Projected cost - Covington Elementary
Replacement (Projected to open in 2011)
$28,900,000
Projected cost of Elementary #31 in 2012
$30,320,000
Average cost of Covington Elem.
replacement & Elementary #31
$29,610,000
Construction cost of the additions to two high schools:
Senior High School Additions
Projected Cost
Total
2008 Addition to Kentlake High School
$5,700,000
2009 Addition to Kent - Meridian HS
$2,500,000
Construction cost of new HS capacity
$8,200,000
Site Acquisition Cost
The site acquisition cost is based on an average cost of sites purchased or built
on within the last ten years. Please see Table 7 on page 27 for a list of site
acquisition costs and averages.
District Adjustment
The impact fee calculations on pages 29 and 30 include a "District Adjustment"
which is equal to the amount of increase that the impact fee formulas drive out
for this year and adjusted for increase in the Consumer Price Index.
Kent School District Six -Year Capital Facilities Ran
April 2009 Page 26
KENT SCHOOL DISTRICT No. 415
Site Acquisitions & Costs
Average of Sites Purchased or Built on within last 10 Years
Type &
# on Map School / Site
Elementary
13 / Urban Panther Lake Elementary Replacement Site
5 / Urban Elementary Site (Halleson & Wikstrom)
Year Open /
Purchased
Location
Acreage
Cost
Avg cost/acre
Total Average Cost / Acre
2008 102xx SE 216, Kent 98031 9.40 $4,485,013 $477,129
2004 15435 SE 256 St, Covington 98042 10.00 $1,093,910 $109,391
Elementary Site Subtotal 19.40 $5,578,923
Middle School
Urban Northwood Middle School 1996 17007 SE 184 St, Renton 98058 24.42 $655,138 $26,828
10 / Urban Mill Creek MS (Kent JH) / McMillan St. assemblage 2002 411 -432 McMillan St., Kent 98032 1.23 $844,866 $686,883
12 / Urban So Central Site - Unincorp KC (Plemmons, Yeh, Wms) 1999 E of 124 SE btw 286 -288 PI (UKC) 39.36 $1,936,020 $49,188
Middle School Site Subtotal 65.01 $3,436,024
Senior High
11 / Urban K -M High School Addition (Kent 6 & Britt Smith) 2002 & 2003 10002 SE 256th Street 6.31 $3,310,000 $524,564
Senior High Kentlake High School (Kombol Morris) 1997 21401 SE 300 St, Kent 98042 40.00 $537,534 $13,438
6 / Urban Kentwood Sr Hi Addition (Sandhu) 1998 16807 SE 256th Street 3.83 $302,117 $78,882
Senior High Site Subtotal 50.14 $4,149,651
Note: All rural sites were purchased prior to adoption of Urban Growth Area.
Numbers correspond to locations on Site Bank & Acquisitions Map on Page 17.
Properties purchased prior to 1996
1 So. King County Activity Center (Nike site) purchased prior to 1996.
4 / Urban Site - Covington area North (So of Mattson MS) 1984
3 / Rural Site - Ham Lake east (Pollard) 1992
7 / Rural Site - South of Covington (Scarsella) 1993
8 / Rural Site - SE of Lake Morton area (West) 1993
2 / Urban Site - Shady Lake (Sowers- Blaine- Drahota- Paroline) 1995
9 Old Kent Elementary replaced and currently leased out.
Kent Scho. .strict Six -Year Capital Facilities Plan
Tat..
$287,573
Elem site average
$52,854
Middle Schl Site Avg.
$82,761
Sr HI Site Average
Total Acreage & Cost
134.55 $13,164,598
Total Average Cost / Acre
$97,842
April 2009 age 27
KENT SCHOOL DISTRICT
FACTORS FOR ESTIMATED IMPACT FEE CALCULATIONS
Student Generation Factors - Single Family Student Generation Factors - Multi - Family
Elementary (Grades K - 6) 0.445 Elementary 0.296
Middle School (Grades 7 - 8) 0.118 Middle School 0.075
Senior High (Grades 9 - 12) 0.245 Senior High 0.111
Total 0.808 Total 0.482
Projected Increased Student Capacity OSPI - Square Footage per Student
Elementary 600 Elementary 90
Middle School 900 Middle School 117
Senior High 250 Senior High 130
Special Education 144
Required Site Acreage per Facility
Elementary (required) 11 Average Site Cost / Acre
Middle School (required) 21 Elementary
Senior High (required) 32 Middle School
Senior High
$287,573
$0
$0
New Facility Construction Cost
Elementary * $29,610,000 Temporary Facility Capacity & Cost
Middle School $0 Elementary @ 24
Senior High * $8,200,000 Middle School @ 29
* See cost basis on Pg. 26 Senior High @ 31
$123,430
$0
$0
Temporary Facility Square Footage State Equalization Credit (iormehy "State Match•)
Elementary 73,748 Current District Equalization Percentage
Middle School 18,544
Senior High 22,960
Total 3% 115,252 Area Cost Allowance ACA - Cost/Sq. Ft.
Area Cost Allowance (Effective July 08) $168.79
55.78%
Permanent Facility Square Footage
Elementary 1,475,936
Middle School 660,904
Senior High 1,121,963
Total 97% 3,258,803
District Average Assessed Value
Single Family Residence $348,876
Total Facilities Square Footage District Average Assessed Value
Elementary 1,549,684 Multi - Family Residence $121,557
Middle School 679,448 Apartments 71% Condos 29%
Senior High 1,144,923
Total 3,374,055 Capital Levy Tax Rate /$1,000
Current / $1.000 Tax Rate (1.73255) $1.73
Developer Provided Sites / Facilities
Value 0 General Obligation Bond Interest Rate
Dwelling Units 0 Current Bond Interest Rate 4.96%
Kent School District Six -Year Capital Facilities Plan
April 2009 Page 28
KENT SCHOOL DISTRICT
IMPACT FEE CALCULATION for SINGLE FAMILY RESIDENCE
Site Acquisition Cost per Single Family Residence
Formula: ((Acres x Cost per Acre) / Facility Capacity) x Student Generation Factor
IRequired Site Acreage I Average Site Cost/Acre I Facility Capacity 1 Student Factor I
A 1 (Elementary)
A 2 (Middle School)
A 3 (Senior High)
11
21
32
$287,573
$0
$0
600
1,065
1,000
0.445
0.118
0.245
0.808
A
Permanent Facility Construction Cost per Single Family Residence
Formula: ((Facility Cost / Facility Capacity) x Student Factor) x (Permanent/Total Square Footage Ratio)
Construction Cost I Facility Capacity r Student Factor I Footage Ratio I
$2,346.12
$0
$0
$2,346.12
B 1 (Elementary)
B 2 (Middle School)
B 3 (Senior High)
$29,610,000
$0
$8,200,000
600
900
250
0.445
0.118
0.245
0.808
0.97
0.97
0.97
B
Temporary Facility Cost per Single Family Residence
Formula: ((Facility Cost / Facility Capacity) x Student Factor) x (Temporary / Total Square Footage Ratio)
Facility Cost I Facility Capacity I Student Factor 1 Footage Ratio I
$21,301.93
$0
$7,794.92
$29,096.85
C 1 (Elementary)
C 2 (Middle School)
C 3 (Senior High)
$123,430
$0
$0
24
29
31
0.445
0.118
0.245
0.808
District Equalization Credit per Single Family Residence (formerly "State Match ")
Formula: Area Cost Allowance x SPI Square Feet per student x District Equalization % x Student Factor
IArea Cost Allowance I SPI Sq. Ft. / Student I Equalization % I Student Factor I
0.03
0.03
0.03
C
$68.66
$0
$0
$68.66
D 1 (Elementary)
D 2 (Middle School)
D 3 (Senior High)
$168.79
$168.79
$168.79
90
117
130
Tax Credit per Single Family Residence
Average SF Residential Assessed Value
Current Capital Levy Rate / $1,000
Current Bond Interest Rate
Years Amortized (10 Years)
Developer Provided Facility Credit
Fee Recap
A = Site Acquisition per SF Residence
B = Permanent Facility Cost per Residence
C = Temporary Facility Cost per Residence
Subtotal $31,511.62
D = State Match Credit per Residence
TC = Tax Credit per Residence
Subtotal $11,445.12
0.5578
0
0.5578
0.445 $3,770.75
0.118 $0
0.245 $2,998.71
D $6,769.46
$348,876
$1.73
4.96%
10 TC b $4,675.66
Facility / Site Value I Dwelling Units
0
$2,346.12
$29,096.85
$68.66
$6,769.46
$4,675.66
0
Total Unfunded Need $20,066.50
50% Developer Fee Obligation
FC = Facility Credit (if applicable)
District Adjustment (See Page 26 tor explanation)
Net Fee Obligation per Single Family Residence
Kent School District Six -Year Capital Facilities Plan
FC b 0
$10,033
0
($4,639)
$5,394
April 2009 Page 29
KENT SCHOOL DISTRICT
IMPACT FEE CALCULATION for MULTI - FAMILY RESIDENCE
Site Acquisition Cost per Multi- Family Residence Unit
Formula: ((Acres x Cost per Acre) / Facility Capacity) x Student Generation Factor
A 1 (Elementary)
A 2 (Middle School)
A 3 (Senior High)
Required Site Acreage I Average Site Cost/Acre 1 Facility Capacity 1 Student Factor
11
21
32
$287,573
$0
$0
500
1,065
1,000
0.296
0.075
0.111
0.482
A -0
Permanent Facility Construction Cost per Multi - Family Residence Unit
Formula: ((Facility Cost / Facility Capacity) x Student Factor) x (Permanent / Total Square Footage Ratio)
IConstruction Cost I Facility Capacity I Student Factor I Footage Ratio I
B 1 (Elementary)
B 2 (Middle School)
B 3 (Senior High)
$1,872.68
50
50
$1,872.68
$29,610,000
50
$8,200,000
600
900
250
0.296
0.075
0.111
0.482
0.97
0.97
0.97
B b
Temporary Facility Cost per Multi - Family Residence Unit
Formula: ((Facility Cost / Facility Capacity) x Student Factor) x (Temporary / Total Square Footage Ratio)
C 1 (Elementary)
C 2 (Middle School)
C 3 (Senior High)
514,169.37
$0
53,531.58
$17,700.95
Facility Cost I Facility Capacity I Student Factor I Footage Ratio I
5123,430
$0
$0
24
29
31
0.296
0.075
0.111
0.482
District Equalization Credit per Multl- Family Residence (formerly "State Match ")
Formula: Area Cost Allowance x SPI Square Feet per student x District Equalization % x Student Factor
IArea Cost Allowance I SPI Sq. Ft. / Student 1 Equalization % I Student Factor 1
0.03
0.03
0.03
C
D 1 (Elementary)
D 2 (Middle School)
D 3 (Senior High)
Tax Credit per Multi
$45.67
50
50
$45.67
$168.79
$168.79
5168.79
90
117
130
- Family Residence Unit
Average MF Residential Assessed Value
Current Capital Levy Rate / $1,000
Current Bond Interest Rate
Years Amortized (10 Years)
Developer Provided Facility Credit
Fee Recap
A = Site Acquisition per Multi- Family Unit
B = Permanent Facility Cost per MF Unit
C = Temporary Facility Cost per MF Unit
Subtotal
D = State Match Credit per MF Unit
TC = Tax Credit per MF Unit
Subtotal
0.5578
0
0.5578
0.296 $2,508.18
0.075 50
0.111 51,358.60
D K' $3,866.78
$121,557
51.73
4.96%
10 TC b $1,363.29
I Facility / Site Value I Dwelling Units I
0
$1,872.68
$17,700.95
$45.67
53,866.78
$1,363.29
Total Unfunded Need
50% Developer Fee Obligation
FC = Facility Credit (if applicable)
District Adjustment (See Page 28 for explanation)
Net Fee Obligation per Multi- Family Residence Unit
Kent School District Six -Year Capital Facilities Plan
0
519,619.29
$5,230.07
$14,389.22
FC b
$7,195
0
(53,873)
$3,322
April 2009 Page 30
0
IX Summary of Changes to April 2008 Capital Facilities Plan
The Capital Facilities Plan (the "Plan ") is updated annually based on previous
Plans in effect since 1993. The primary changes from the April 2008 Plan are
summarized here.
Projects in progress include replacement and expansion of Panther Lake and
Covington Elementary schools, a future new elementary school, classroom
additions at high schools to accommodate new growth, renovation for Kent
Phoenix Academy and Phase II of the renovation at Mill Creek Middle School.
Changes to capacity continue to reflect fluctuations in class size as well as
program changes. Reduction in class size and extended learning opportunities
for Student Achievement Initiative 728 are reflected in this update. Changes in
relocatables or transitional capacity reflect use, purchase, sale, surplus and /or
movement between facilities. Permanent and temporary facility ratio has
changed from 96 — 4% to 97 — 3 %.
The student enrollment forecast is updated annually. Six -year Kindergarten
projections were modified to meet the requirements for State Funded Full Day
Kindergarten programs.
The district expects to receive some state equalization (formerly "matching ")
funds for projects in this Plan and tax credit factors are updated annually.
Biennieal update of student generation rates was reported last year. Unfunded
site and facility needs will be reviewed in the future.
Changes to Impact Fee Calculation Factors include:
ITEM
Grade/Type
FROM
TO
Comments
Student Generation Factor
Single Family (SF)
Student Generation Factor
Multi- Family (MF)
District Equalization Ratios (former State Match)
Area Cost Allowance (former Boeckh Index)
Average Assessed Valuation (AV)
AV - Average of Condominiums & Apts.
Debt Service Capital Levy Rate / $1000
General Obligation Bond Interest Rate
Impact Fee - Single Family
Impact Fee - Multi- Family
Elem 0.445 0.445 No Change — Update in 2010
MS 0.118 0.118
SH 0.245 0.245
Total 0.808 0.808 No Change — Biennial Update
Elem
MS
SH
Total
SF
MF
SF
MF
0.296
0.075
0.111
0.296
0.075
0.111
0.482
57.06%
$168.79
$316,091
$102,465
$1.73
5.11%
$5,304
$3,266
No Change — Update in 2010
0.482 No Change — Biennial Update
Per OSPI Website
Per OSPI Website
Per Puget Sound ESD
Per Puget Sound ESD
55.78%
$168.79
$348,876
$121,557
$1.73
4.96%
$5,394
$3,322
Per King Co. Assessor Report
Market Rate
Change to fee + $90
Change to fee + $56
Kent School District Six -Year Capital Facilities Plan
April 2009 Page 31
X
Appendixes
Appendix A: Calculations of Capacities for Elementary Schools
Appendix B: Calculations of Capacities for Middle Schools
Appendix C: Calculations of Capacities for Senior High Schools
Appendix D: Use of Relocatables
Appendix E: Student Generation Factor Survey
Kent School District Six -Year Capital Facilities Plan April 2009 Page 32
0:E0E-
KENT SCHOOL DISTRICT No. 415
STANDARD of SERVICE - PROGRAM CAPACITY • INVENTORY of RELOCATABLES - FTE and HEADCOUNT ENROLLMENT
K S D
ELEMENTARY
SCHOOL
Number of
Std/I-ligh Cap
2SE / IP
2 Special
• 2008-2009
Program
Classroom
. . .
Relocatable
, „ , ,
10/1/2008
, ., - , -,.
10/1/2008
r. • ,
F
Std or High Cap
Capacity
ELL
Program
Program
Use
Use
Capacity
4
P223 FTE
P223 Hdcount
D
Classrooms
at 24 average '
CR
Cepaci
Capacity 2
Relocatables
Relocatables
at 24 average '
Enrollment
Enrollment
K
8
•
al
Carriage Crest
Cedar Valley
Covington
Crestwood
East Hill
Emerald Park
Fairwood
George T. Daniel Bern
Glenridge
Grass Lake
Horizon
Jenkins Creek
Kent Elem.
Lake Youngs
Martin Sortun
Meadow Ridge
Meridian Elementary
Millennium Elementary
Neely-O'Brien
Panther Lake
Park Orchard
Pine Tree
Ridgewood
Sawyer Woods
Scenic Hill
Soos Creek
SprIngbrook
Sunrise
Kent Mtn. View Academy MV
IElementary TOTAL 3
CC
CV/e
CO/e
CW
EH
EP
FW/s
DE
GR
GL/h
HE
JC
KE/eh
LY/h
MS
MR/e
MEM
ML
NO
PL
PO
FT/h
RW/h
SW
SH
SC/e
SB
SR/h
18
16
20
19
17
21
17
18
19
18
21
15
17
21
19
17
21
20
16
15
18
21
21
21
17
17
15
21
14
432
384
480
456
408
504
408
432
456
432
504
360
408
504
456
408
504
480
384
360
432
504
504
504
408
408
360
504
358
5
8
5
2
7
2
3
5
4
4
2
7
8
7
3
6
3
3
5
3
7
4
1
2
6
4
5
2
3
20
18
18
0
58
0
0
18
0
20
0
38
56
20
18
56
20
18
56
36
48
18
0
0
56
0
38
0
60
452
402
498
456
464
504
408
450
456
452
504
398
464
524
474
464
524
498
440
396
480
522
504
504
464
408
398
504
416
1
2
1
4
3
2
3
1
2
1
3
3
2
0
0
3
0
5
7
2
3
1
0
3
3
2
3
0
0
0
0
1
3
0
0
0
0
0
0
1
2
0
1
4
2
0
5
0
0
0
2
0
0
0
0
0
0
0
0
24
72
0
0
0
0
0
0
24
48
0
24
96
48
0
120
0
0
0
48
0
24
0
0
0
0
445.38
326.50
518.50
474.50
527.00
465.50
406.17
502.11
428.20
420.53
501.36
362.09
541.00
497.07
485.50
445.04
493.03
530.50
850.15
482.50
467.03
460.00
494.08
465.66
502.00
374.50
371.03
529.50
68.65
480
358
557
510
576
498
442
503
457
440
536
388
541
520
532
447
522
576
709
517
468
484
531
501
502
397
401
565
73
530 12,740 122 688
13,428
61 22 528
Elementary classroom capacity is based on average of 24: 18-22 in K-3, 23 in Grade 4 &
2 Kent School District Standard of Service reserves some rooms for pull-out programs. ie.
3 Elementary schools have 100% space utilization rate. 4 Elementary FTE reports Kind @
5 FDK = Full Day Kindergarten T = Tuition-based I =1-728 Funded Schoolwide K = KAI
Kent Schc ict Slx-Year Capital Facilities Plan
13,235.08 14,027
29 in Grades 5-6. Includes adjustments for class size reduction or program changes.
20 Total = 17 Standard + 1 Computer Lab + 1 Music + 1 Integrated Program classroom.
.5 FDK @ 1.0 - P223 Headcount reports Kindergarten @ 1.0. Excludes ECE preschoolers.
Title I Funded A = State Apportionment Funded H = Half Day Kindergarten only
APPE' A
T
T
1
T
T
A
T
H
A
H
A
T
K
K
A
K
T
A
T
T
0
April 2009 Pf
KENT SCHOOL DISTRICT No. 415
STANDARD of SERVICE - PROGRAM CAPACITY - INVENTORY of RELOCATABLES - FTE and HEADCOUNT ENROLLMENT
# of
Standard
SE / IP
Special Ed
Spec
Special 1
2008 -2009
Program
Classroom
Relocatable
10/1/2008
10/1/2008
Std
Capacity 2
ELL
ELL
Prgm
Program
Program
Use
Use
Capacity
P223 FTE 3
Headcount 3
Clsrms
at 25 -29
Cis
Capacity
Clsrms
Capacity
Capacity 2
Relocatables
Relocatables
at 29 ea.
Enrollment
Enrollment
Cedar Heights Middle School CH 32 782 9 93 2 48 923
Mattson Middle. School MA 24 585 6 59 7 160 804
Meeker Middle Schoot MK 33 807 4 59 1 24 890
Meridian Middle School MJ 26 631 5 64 4 95 790
Mill Creek Middle School MC 30 729 5 51 2 48 828
Northwood Middle School NW 33 807 4 46 5 119 972
Kent Mountain View Academy (Grades 3 - 12) Middle School Grade 7 - 8 Enrollment
Middle School TOTAL
O 2
6 0
O 0 0
3 6 174
O 4 116
O 0 0
145
0
745.09 747
667.00 670
652.11 655
714.20 716
762.00 762
662.60 663
56.20 57
178 4,341 33 372 21 494 5,207
9
12 435
4,259.20 4,270
APPENDIX B
# of
Standard
SE / I
Special Ed
Spec
Special 1
2008 -2009
Program
Classroom
Relocatable
10/1 /2008
10/1 /2008
Std
Capacity
ELL
ELL
Prgm
Program
Program
Use
Use
Capacity
P223 FTE 3
Headcount 3
Clsrms
at 25-31
Cls
Capacity
Clsrms
Capacity
Capacity 2
Relocatables
Relocatables
at 31 ea.
Enrollment
Enrollment
CO
Kent - Meridlan Senior High KM 53 1,376 8 110 12 286 1,772
Kentlake Senior High KL 58 1,508 12 145 14 333 1,986
Kentridge Senior High KR 69 1,766 11 123 16 381 2,270
Kentwood Senior High KW 65 1,692 5 51 17 394 2,137
Kent Mountain View Academy (Grades 3 - 12) Senior High Grade 9 -12 Enrollment See Elem
Kent Phoenix Academy PH 350
Regional Justice Center RJ N/A N/A
1
0 5
0 4 124
5
155
155
4
5 155
1,778.20 1,813
1,798.20 1,833
2,192.60 2,237
2,097.37 2,171
154.57 157
279.60 290
33.00 33
Senior High TOTAL
245 6,342 36 429 59 1,394 8,515
5
19 589
8,333.54 8,534
APPENDIX C
DISTRICT TOTAL
953
23,423
191
1,489
80
1,888 1 27,150
75
53
1,552
Excludes Running Start &
Early Childhood Ed students
25,827.82
26,831
' Special Pr og ram capacity includes classrooms requiring specialized use such as Special Education, Career & Technical Education Programs, Computer Labs, etc.
2 Secondary school capacity is adjusted for 85% utilization rate and 1 -728 class slze reduction in 7th & 10th grade English classes. 9th grade moved to HS in 2004.
3 Enrollment Is reported on FTE & Headcount basis. P223 Headcount excludes ECE & College -only Running Start students. Full headcount including ECE & RS = 27,579.
Some totals may be slightly different due to rounding.
Kent School District Six -Year Capital Facilities Plan
Total of Appendices A B & C
April 2009 Page 34
KENT SCHOOL DISTRICT No. 415
USE of RELOCATABLES
lea911sxrs.'+timavi eeNItICr•reuagetisM tNCaax2,',3EX oraCadSrlEarzst 41026 .'r.T4l3R_ F— ufaar
itZ WaXStrsursaraw+nMIC:
7CPAas VASMIZT rLrru:Otis^OMEW.�.GQa.2xsah.,v
meaahafirsl
School Year
2008 - 2009 2009 -2010 2010 -2011 2011 -2012
2012 -2013
2013 -2014
2014 -2015
Relocatable Use 1
No. of
Student
No. of
Student
No. of
Student
No. of
Student
No. of
Student
No. of
Student
No. of
Student
Relocatables
Capacity
Relocatables
Capacity
Relocatabies
Capacity
Relocatables
Capacity
Relocatables
Capacity
Relocatabies
Capacity
Relocatables
Capacity
mes0 mr.:�Sau :t: NM'TL'lars rzt.,,:4.4.1: sur4 Jec.,?.'^....w4
1$3..� s:e_ne+4r ._f n.anr,e:-tx.
n'T.. 977 .— xn:J.^.':�
.tier..1/4w■nuo.o 73.M3- r4..LFySt:eu -raHI
i te..g. ..t
1.. ..samr..
•s/ /04c.en
e.".3C_^'.4 -• 0. 1ttcw�CF.wrove,.
- =3,- --
7-.KaW:w
Relocatables for classroom use
53 53 53
53
53
53
53
Relocatables for program use
(ie. Computer labs, music, etc.)
75 75 75
75
75
75
75
Elementary Capacity Required @ 24 2
0 0 5 120 13
312 17
408
4
96
20
480
35 840
Middle School Capacity Required @ 29 3
0 0 0 0 0
0 0
0
0
0
0
0
0 0
Senior High Capacity Required @ 31
0 0 0 0 0
0 0
0
0
0
0
0
0 0
# of Relocatables Utilized 4
128 128 128
128
128
128
128
Classroom Relocatable /Capacity Required
0 0 5 120 13
312 17
408
4
96
20
480
35 840
Plan for Allocation of Required Classroom
Relocatable Facilities included in Finance Plan:
Elementary 112 0 5 13
17
4
20.
35
Middle School 3 0 0 0
0
o
0
0
Senior High 4
0
0
0
0
0
0
0
Total
0
5
13
17
4
20
35
Use of additional relocatables for classrooms or special programs is based on need and fluctuations of enrollment at each school.
2 Full Day Kindergarten will Increase the need for relocatables at the elementary level until permanent capacity can be provided.
3 Grade Level Reconfiguration - In 2004. 9th grade students moved to high schools creating sufficient permanent capacity at middle schools.
4 Although relocatables are utilized for a wide variety of purposes, new construction and boundary adjustments are timed to minimize the requirement for relocatables.
Kent Schc Ict Six -Year Capital Facilities Plan
APPET D
April 2009 35
KENT SCHOOL v1STRICT No. 415
Student Generation Factor Survey
Edulog
a
Single Family Developments
Elementary
Area
Total
Units
Students
Students
Total
Elem
Student Generation Factor
HS
Total
Elem
MS
HS
Total
Elem
MS
HS
78
Crofton Hills / Savana / The Reserve / Stonefield - Covington
CO
351
.360
169
62
129
1.026
0.481
0.177
0.368
187
Eastland Meadows - Kent
SC
13
21
9
2
10
1.615
0.692
0.154
0.769
399
Fem Crest East - Kent
SR
171
132
86
20
26
0.772
0.503
0.117
0.152
400
Fem Crest West - Kent
SR
130
79
47
10
22
0.608
0.362
0.077
0.169
228
Kentlake Highlands - Kent
SW
97
87
47
13
27
0.897
0.485
0.134
0.278
389
Parke Meadows & North Parke Meadows - Covington
CW
106
117
70
15
32
1.104
0.660
0.142
0.302
410
Rhododendron Estates - Kent
ML
16
37
24
6
7
2.313
1.500
0.375
0.436
419
Southridge - Eagle Crest - Park View - Kent
HE
219
164
99
24
41
0.749
0.452
0.110
0.187
420
Tamarack Ridge - Covington
CW
134
78
40
12
26
0.582
0.299
0.090
0.194
179
The Parks - Renton
RW
172
153
71
21
61
0.890
0.413
0.122
0.355
337
The Parks at Riverview - Kent
NO
148
38
20
9
9
0.257
0.135
0.061
0.061
416
Trovitsky Park - Renton
RW
167
124
81
11
32
0.743
0.485
0.066
0.192
417
Wood Creek - Covington
CW
154
128
73
16
39
0.831
0.474
0.104
0.253
Total
1,878
1,518
836
221
461
0.808
• 0.445
0.118
0.245
Edulog
#
Multi- Family Developments
Elementary
Area
Total
Units
Students
Student Generation Factor
Total
Elem
MS
HS
Total
Elem
MS
HS
418
Adagio Apartments - Covington
CO
200
61 28 12 21
0.305 0.140 0.060 0.105
412
Alderbrook Apartments - Kent
EH
207
118 78 18 22
0.570 0.377 0.087 0.106
158
Brentwood Townhomes - Kent
SH
81
51 25 14 12
0.630 0.309 0.173 0.148
146
Fairwood Pond Apartments - Renton
FW
194
33 21 -7 5
0.170 0,108 0.036 0.026
414
Park Place Apartments - Kent
SH
51
88 62 9 17
1.725 1.216 0.176 0.333
102
Rock Creek Landing - Kent
PL
211
77 41 14 22
0.365 0.194 0.066 0.104
413
Silver Springs Apartments - Kent
PL
251
163 108 21 34
0.649 0.430 0.084 0.135
192
Sunrise at Benson Condos - Kent
GR
88
27 17 1 9
0.307 0.193 0.011 0.102
Total
1,283
618
380
96
142
0.482 0.296 0.075 0.111
Kent School District Six -Year Capital Facilities Plan
APPENDIX E
April 2009 Page 36
POLICY /TEXT AMENDMENT #3
Dieringer School District Updated 2009 -2014 Capital
Facilities Plan
Incorporate Dieringer School District Updated 2009 -2014
Capital Facilities Plan as part of Auburn Comprehensive
Plan
(Adopted by the Dieringer School District Board of
Directors April 2008)
Dieringer School District
Capital Facilities Plan
2010 -2015
DIERINGER SCHOOL DISTRICT NO. 343
1320 -178th Avenue East
Sumner, Washington 98390
(253) 862 -2537
BOARD OF DIRECTORS
Jim Barfoot
Pete George
Corey Pawlak
James Premo
John McKenna
Dr. Judy Neumeier- Martinson, Superintendent
• Dieringer
• Educating every child for
• Confidence today and
Contribution tomorrow
An Overview
Established in 1890, Dieringer School District consolidated with Lake Tapps School
District in 1936. The District's three schools, Lake Tapps Elementary School, Dieringer
Heights Elementary School and North Tapps Middle School, provide K through 8th
grade education, and serve as hubs for community activities as well. Dieringer School
District #343 is located in unincorporated Pierce County, bounded on the east by the
White River, on the west by the Stuck River, on the north by the city of Aubum, and on
the south by the cities of Bonney Lake and Sumner. The District surrounds the northern
two - thirds of Lake Tapps and covers approximately 5.5 square miles.
The current student enrollment is approximately 1,265 students in grades kindergarten
through eight. Students in grades first through third are housed at Lake Tapps
Elementary, constructed in 2005 as a replacement project. Dieringer Heights Elementary
opened in the fall of 2000 and is home to students in kindergarten, fourth and fifth grade.
An addition was just completed this year: Originally constructed in 1992 and added on
to in 1998, North Tapps Middle School houses students in grades sixth - eighth. An
Addition to the Middle School will be completed in late 2009, that will add an auxiliary
gym, health and fitness classroom and four science classrooms. The district supports an
additional 522 high school students who may select to attend any public high school. The
majority chose to attend Auburn Riverside and Sumner High Schools.
The district has a long standing history of providing high quality education for all our
students. Our goal is for our students to gain the skills that will allow them to become
successful, confident, contributing members of society. Dieringer is composed of
students who come to school well prepared and eager to learn. Parents are concerned with
student success and provide outstanding support for their children and the Dieringer
School District. The PTA and many volunteers contribute countless hours and resources
to our schools and students. The community supports the schools through the passage of
funding issues to support bus acquisition, student access to current technology, and the
construction of school facilities.
DIERJNGER SCHOOL DISTRICT D. 343
Capital Facilities Plan Update, 2009
Current Facilities Inventory of Public Schools
NAME
CAPACITY LOCATION
Lake Tapps Elementary 396 1320 -178th Ave E., Lake Tapps
Dieringer Heights Elementary 547 21727- 34th St. E., Lake Tapps
North Tapps Middle School 405 20029- 12th St., E., LaIce Tapps
High School 0
TOTAL 1,348
DIERINGER
DISTRICT
SCHOOL
NO, :343
.e Dieringer School District is located in an area that cone to experience growth.
_ nis growth can be noted by reviewing the following indicat,.,:. enrollment trend data,
proposed housing development, the increase in the assessed valuation of the real
property, and the mitigation impact fees received for new construction.
The District continues to experience slow, steady growth in student enrollment. This has
mirrored the Pierce County and Puget Sound Educational Service District (PSESD)
enrollment growth over the same period. A review of proposed construction within the
borders of the Dieringer School District indicates that the growth trend can be expected to
continue over the next four years and beyond. This growth trend will be slowed by the
current economic conditions, but will pick up in 2010 and beyond. There are 672 single .
family residents slated for construction within the next four years. Multi - family projects,
will contribute an additional 371 residential units during that time. These projects,
together with individual lots and general in- migration, are anticipated to generate an
additional 526 students in kindergarten through eighth grade.
Information from Pierce County Planning & Land Services indicates that there is space
and zoning for approximately 1,200 additional housing lots in the western portion of the
district. This creates a potential for 576 additional students, kindergarten through eighth
grade, that are not included in the above numbers.
To partially address this growth, the District passed a 2006 bond issue to construct an
additional five classrooms at Dieringer Heights Elementary. That addition is completed
and will be fully occupied in 2009. The bond issue also provided for the addition of an
auxiliary gym, health and fitness classroom, and four science rooms at North Tapps
Middle School; these projects have been delayed due to an extended permitting process
and are anticipated to be completed by December, 2009. Future anticipated growth will
create the need to acquire an additional school site and construct an additional school to
house the growing student enrollment.
1 V Lc, LL LEW, .11.1.1. V11111L+11 L 111E+1<+CLON
April, 2009
Proposed Housing Units for Approved Developments:
Single Family- 672 x .48 generation factor = 323 students K -8 grade
Multi - family — 371 x .1149 generation factor = 43 students K -8 grade
(Calculated based on Auburn SD 2005 Generation Factor)
Proposed Housing Units from Individual Lots and In- migration:
160 students K -8 grade
Enrollment Impact:
526 students K -8
Estimated 105 students a year over the period 2010 -2015
Potential five year enrollment increase = 41.51% (based on 1,267 enrollment 4-09)
Increase per grade level = 58 students
Approximately 175 students per school
TI.. £ ML. TI%.MI.L6.1 •■V V JJJI.UI
- Notice of application 1/24/01
- 28 Single Family Lots
- 1600 -2000 block of 16th St. @ the 17500 -17800 block of Sumner -Tapps Hwy.
- 3 lots sold; 3 houses completed /1 under construction
#2 Rainier Plateau (10)
- Notice of application 10/13/00
-10 Single Family Lots
- End of34`hSt.
- Site work underway; home construction 2008 (no change)
#3 Grandview Ridge II and III (9)
- Off Sumner -Tapps Hwy. across from Driftwood and Deer Island Dr.
- Grandview Ridge Notice of Application 1/13/99
- 50 Single Family Lots; completed
- III (9 lots) no date (no change)
#4 Northlake (154)
-north of Lake Tapps Elementary
- Preliminary Plat 7/23/02
-197 Single Family Lots
-43 homes completed/under construction; new starts will continue
#5 The Estates (139)
- Notice of application 8/27/04
-234 single family Lots
-South of road terminus from Lakeland Hills Hwy.
-56 homes completed; Division II 39 homes completed/7 foundations
#6 Tapps Meadow (Van Der Hoek) (11)
- Notice of application 9/13/04
-11 large lots
- across from Snag Island
-site work complete (no change)
#'7 Country Creek Estates (8)
-9 Single Family Lots -off 15`h near Edwards Road
- one (1) house nearing completion
1#8 Forest Canyon Estates (121)
-121 Single Family Lots —off Forest Canyon Rd.
- completion 2010 (no change)
#11 Carter Estates (16)
-16 Single Family Lots — Lake Tapps Parkway and 179th
-16 homes (no construction)
#12 Charlotte Avenue (6)
-6 Single Family Lots — Lalce Tapps Parkway and 176th
-6 homes (no construction)
#13 8th Street Development (324)
-324 Multi- family units; north of Sumner Meadows
- Sumner City limits
-324 units; site work; possible construction 2009
#14 Lakeland 8 (68)
-68 Single Family lots- north of Lake Tapps Parkway
-68 homes; site work (construction not scheduled)
#15 Auburn Annexation (100)
-100 Single Family Lots
Total Single Family Units to be built - 672
Total Multiple Family Units to be built - 371
2/09
ie Dieringer School District houses children in elemental hools serving students
iundergarten through fifth grade and a middle school that ,.,_,uses grades six through
eighth. High school- students, grades nine through twelve, attend adjacent high schools,
primarily in the Auburn School-District.
Dieringer School District follows a traditional school calendar beginning in early
September and completing in mid June. The daily school schedules begin between 7:49
and 8:45 a.m. and end between "2:17 and 3:15 p.m.
The Dieringer School District standard of service is based on class size and program
decisions adopted by the Dieringer School District Board of Directors. Due to the
passage of Initiative 728 and in keeping with the district philosophy regarding class size,
the targeted number of students per classroom kindergarten through third grade is 22,
fourth through fifth grade 25 and. sixth through eighth grade 27. These class sizes have
an impact on facilities and the permanent capacity of each school reflects these class
sizes.
In the District, rooms designated and assigned for special use are not counted as capacity
classrooms. At the elementary level, students are provided music instruction, physical
education and art instruction in separate, _non-capacity classrooms. Computer labs are
provided at each school as non-capacity spaces. Special education' and remedial
programs are provided as pullout programs and do not provide capacity. At the middle
school level, instruction is organized around a six period day; classrooms are calculated
as providing 5/6 capacity to accommodate teacher planning time in the instructional
space.
DrERINGER SCHOOL DISTRICT NO. 343
Capital Facilities Plan Update, 2009
Dieringer School District Service Standards
Public School Facilities
(Square Feet Per Student)
Elementary School 120
Middle School 189
Junior High NA
High School NA
Dieringer School District Individual Capacity Projects (2010 -2015)
NAME CAPACITY
Elementary School No. 3 400
North Tapps Middle School
Science Labs, Auxiliary Gym, Health and
Fitness Classroom Addition
162
High School NA
DIERINUER SCHOOL DISTRICT No. 343
Capital Facilities Plan Update, April 2009
CFP Projects and Financing Plan
Sources and Uses of Funds
(x $1,000)
Sources of Funds
Existing Revenue:
Bond Proceeds, Reserve
New Revenue:
Bonds, Levies, Fees, State Matching
Funds, Dedications, Mitigation Payments
$ 1,960
$1 9,775
TOTAL SOURCES $21,735
Uses of Funds
Elementary School No. 3 ($19,775)
North Tapps Middle School ($1,560)
Science Labs, Auxiliary Gym, Health
And Fitness Classroom
Non - Capacity Projects:
Technology Upgrades & Road Improvements J102
TOTAL USES ($21,735)
BALANCE 0
Permanent Capacity Projects
DIERINGER SCHOOL DISTRICT NO. 343
FINANCE PLAN
April, 2009
Unsecured Source of Funds Secured Source of Funds
Estimated Estimated Estimated Bond & State Impact
Cost Bond Amt. State Match Interest _ Match Fees
Elementary School No. 3 19,775,000 19,775,000 0
N T Middle School Additions 1,560,000 0 0 1,000,000 0 560,000
Total Capacity Projects 21,335,000 19,775,000 0 1,000,000 0 560,000
Non - Capacity Projects
Technology Improvements 200,000 0 0 200,000 0 0
Road Improvements 200,000 0 0 200,000 0 0
Total Non - Capacity Projects 400,000 0 0 400,000 0 0
TOTAL PROJECTS 21,735,000 19,775,000 0 1,400,000 0 560,000
DIERINGER SCHOOL DISTRICT NO. 343
PERMANENT CAPACITY PROJECTS
MASTER - SCHEDULE
April, 2009'
Name Current 6 - Year Total
Capacity Capacity Capacity 2009 -2010 2011 2012 2013 2014 2015
Lake Tapps Elementary 396 396
(LTES Replacement)
Dieringer Heights Elem. 431
DHES Classroom Addit. 116
547
Elementary School No. 3
431
116
547
400 400
North Tapps MS 405 405
NTMS Additions
(ScienceIRms) 108 108
(Auxilliary Gym) 54 54
TOTALS 1348 562 1910
X
X
X
Time Period
DIERINGER SCHOOL DISTRICT NO. 343
Capital Facilities Plan Update, 2009
Capital Facilities Requirements to 2015
Student Student Net Reserve Total Cost
Population Capacity Or (Deficiency) (Cost/Student
X
Net Deficiency)
2009 Actual 1265 1348 83
2010 -2015 Growth 526
562 36
Dieringer School District Cost Per Student
(2009 Dollars)
Elementary Middle Junior High High
Schools Schools Schools Schools
$28,115 $39,848 NA NA
.. .. . .
Student
Stud!
Facility
Cost/
Facility
Factor
Factor
Cost/
Cost/
Acreage
Acre
Capacity
SFR
MFR
SFR
MFR
Elemento 12.00
$25a000 400
0.322 0.069 $2,412
$515
TO7AL $Z412
$515
School Construction Cost:
. Rid ' aCIlity '
Student
Student
., .
Factor
Factor
Cost/
Cost/
Cost
Capacity
SFR
MFR
SFR
MFR
Elementa No. 3
$19,775,000
400
0.322
0.069
$15,919
$3,411
TOTAL
$23,154
$5,522
((Facility Cost/Facill Ca •acl )xStudent Generation
Factor)x(Temporary/Total Square Feet
Student
Student
Cost/
Cost/
Total Sq.F
Cost
Size
SFR
MFR
Elementa
•
0.322
0.069
•
TOTAL
50
$0
State Matching Credit:
Boeckh Index X SPI S•uare Footage X District Match % X Student Factor
Student
Student
Boeckh
SPI
District
Factor
Factor
Cost/
Cost/
Index
Footage
Match %
SFR
MFR
SFR
MFR
Elementa
TOTAL
$0
50
Tax Payment Credit:
SFR
MFR
Averate Assessed Value (est.) 2008
• $587,405 5364,872
Capital Bond Interest Rate 4/09
.'
4.65% ' 4.65%
Net Present Value of Average Dwelling
$4,613,880
52,865,954
Property Tax Levy
Rate
2009
•
51.9630 , 51.9630
Present Value of Revenue Stream
59,057
55,626
Site Ac•uistIon Costs
52412.00
5515.00
Permanent FacIll Cost
$23,154.43
$5,521.56
State Match Credit
50.00
50.00
Tax Payment Credit
(59,057,05)
(55,625.87)
POLICY /TEXT AMENDMENT #4
Federal Way School District Updated 2010 Capital
Facilities Plan
Incorporate Federal Way School District Updated 2010
Capital Facilities Plan as part of Auburn Comprehensive
Plan
(Adopted by the Federal Way School District Board of
Directors May 2009)
FEDERAL WAY PUBLIC SCHOOLS
2010
CAPITAL FACILITIES PLAN
BOARD OF EDUCATION
Suzanne Smith, President
Tony Moore, Vice President
Ed Barney, Director
Amye Bronson - Doherty, Director
Angela Griffin, Director
SUPERINTENDENT
Thomas R. Murphy
Prepared by: Sally D. McLean
Tanya Nascimento
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
TABLE OF CONTENTS
TABLE OF CONTENTS 1
INTRODUCTION 2 -3
SECTION 1 THE CAPITAL FACILITIES PLAN
Introduction 4
Inventory of Educational Facilities 5
Inventory of Non - Instructional Facilities 6
Needs Forecast - Existing Facilities 7
Needs Forecast - New Facilities 8
Six Year Finance Plan 9
SECTION 2 MAPS OF DISTRICT BOUNDARIES
Introduction 11
Map - Elementary Boundaries 12
Map - Middle School Boundaries 13
Map - High School Boundaries 14
SECTION 3 SUPPORT DOCUMENTATION
Introduction 15
Building Capacities 16 -17
Portable Locations 18 -19
Student Forecast 20 -22
Capacity Summaries 23 -27
King County Impact Fee Calculations 28 -30
SECTION 4 SUMMARY OF CHANGES FROM THE 2009 31 -33
PLAN
1
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
INTRODUCTION
In response to the requirements of the State of Washington Growth Management Act
(SHB)2929 (1990) and ESHB 1025 (1991)), and under the School Impact Fee
Ordinances of King County Code 21A, City of Federal Way Ordinance No. 95 -249
effective December 21, 1995 as amended, City of Kent Ordinance No.3260 effective
March 1996, and the City of Auburn Ordinance No. 5078 effective 1998, Federal Way
Public Schools has updated its 2010 Capital Facilities Plan as of May 2009.
This Plan is scheduled for adoption by King County, the City of Kent, City of Federal
Way and the City of Auburn and is incorporated in the Comprehensive Plans of each
jurisdiction by reference. This plan is also included in the Facilities Plan element of the
Comprehensive Plans of each jurisdiction. To date, the City of Des Moines has not
adopted a school impact fee ordinance. The City of Des Moines collects school impact
fees as part of the SEPA process.
The Growth Management Act requires the County to designate Urban Growth areas
within which urban growth can be encouraged. The Growth Management Planning
Council adopted and recommended to the King County Council four Urban Growth Area
Line Maps with designations for urban centers. A designation was made within the
Federal Way planning area, which encompasses Federal Way Public Schools boundaries.
King County will encourage and actively support the development of Urban Centers to
meet the region's need for housing, jobs, services, culture, and recreation. This Plan's
estimated population growth is prepared with this underlying assumption.
This Capital Facilities Plan will be used as documentation for any jurisdiction, which
requires its use to meet the needs of the Growth Management Act. This plan is not
intended to be the sole planning tool for all of the District needs. The District may
prepare interim plans consistent with Board policies or management need.
The District has prepared a multi -phase plan for the renovation and construction of
Federal Way Schools and support buildings. The Board authorized presenting the $149
million bond on May 15, 2007. The bond, passed at 63.93 %, will replace four
elementary schools, Lakeland, Panther Lake, Sunnycrest and Valhalla and one middle
school, Lakota.
Plans to replace Federal Way High School and Decatur High School and to increase
capacity by approximately 400 students at each school are planned in later phases.
Federal Way High School was built in 1938. It has been added onto at least 10 times and
currently has an almost maze -like layout. Based on an annual 4% increase in
construction cost, the estimated cost to rebuild Federal Way High School is $122 million.
Estimated construction costs will be re- calculated prior to the next bond election. None
of the cost to replace Federal Way or Decatur High School is included in the Impact Fee
calculation in this Plan.
2
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
The non - instructional projects included in the plan will consolidate support services
operations at a single location. The current Transportation and Maintenance facility
cannot continue to meet the District needs in the future. Nutrition services and other
administrative functions will also relocate to this centralized location.
In September 2007 Woodmont Elementary School began a K -8 program by adding a 6th
grade and progressively adding a grade level each year. In March 2008, the Board
approved a second K -8 program at Nautilus Elementary School. Nautilus began the
2008/09 school year with K -6`h grade. As the program grows there will be more data
available about the unique facility needs for this grade configuration.
The District opened a new school in September 2008. The Technology Access
Foundation (TAF) Academy will provide a small school setting for 6th through 12th grade
students. This academy is funded through a unique public /private partnership between
the Technology Access Foundation and Federal Way Public Schools. The focus of the
school is Science, Technology, Engineering and Math (STEM). The TAF Academy
opened in September of 2008 with students in grades 6, 7 and 9. In the 2009/10 school
year TAF Academy added 8th and 10`h grade. Grades 11 and 12 will be added in
successive years with a target population of about 350.
The District continues to study school boundaries as new housing and fluctuating
populations impact specific schools. Some shifts in boundaries may be required in the
coming year.
3
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
SECTION 1 - THE CAPITAL FACILITIES PLAN
The State Growth Management Act requires that several pieces of information be
gathered to determine the facilities available and needed to meet the needs of a growing
community.
This section provides information about current facilities, existing facility needs, and
expected future facility requirements for Federal Way Public Schools. A Financial Plan
that shows expected funding for any new construction, portables and modernization listed
follows this.
4
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
INVENTORY OF EDUCATIONAL FACILITIES
ELEMENTARY SCHOOLS
Adelaide
Brigadoon
Camelot
Enterprise
Green Gables
Lake Dolloff
Lake Grove
Lakeland
Mark Twain
Meredith Hill
Mirror Lake
Nautilus (K -8)
Olympic View
Panther Lake
Rainier View
Sherwood Forest
Silver Lake
Star Lake
Sunnycrest
Twin Lakes
Valhalla
Wildwood
Woodmont (K -8)
MIDDLE SCHOOLS
Federal Way Public Academy (6 -10)
Illahee
Kilo
Lakota
Sacajawea
Saghalie
Sequoyah
Totem
TAF Academy (6 -12)
HIGH SCHOOLS
Decatur
Federal Way
Thomas Jefferson
Todd Beamer
Career Academy at Truman
ALTERNATIVE SCHOOLS
Merit School
Internet Academy
1635 SW 304th Street
3601 SW 336th Street
4041 S 298th Street
35101 5th Avenue SW
32607 47th Avenue SW
4200 S 308th Street
303 SW 308th Street
35827 32nd Avenue S
2450 S Star Lake Road
5830 S 300th Street
625 S 314th Street
1000 S 289th Street
2626 SW 327th Street
34424 1st Avenue S
3015 S 368th Street
34600 12th Avenue SW
1310 SW 325th Place
4014 S 270th Street
24629 42nd Avenue S
4400 SW 320th Street
27847 42nd Avenue S
2405 S 300th Street
26454 16th Avenue S.
34620 9th Avenue S
36001 1st Avenue S
4400 S 308th Street
1415 SW 314th Street
1101 S Dash Point Road
33914 19th Avenue SW
3450 S 360th ST
26630 40th Ave S
26630 40th Ave S
2800 SW 320th Street
30611 16th Avenue S
4248 S 288th Street
35999 16th Ave S
31455 28th Ave S
36001 1St Ave S
31455 28th Ave S
5
Federal Way
Federal Way
Auburn
Federal Way
Federal Way
Auburn
Federal Way
Auburn
Federal Way
Auburn
Federal Way
Federal Way
Federal Way
Federal Way
Federal Way
Federal Way
Federal Way
Kent
Kent
Federal Way
Auburn
Federal Way
Des Moines
Federal Way
Federal Way
Auburn
Federal Way
Federal Way
Federal Way
Auburn
Kent
Kent
Federal Way
Federal Way
Auburn
Federal Way
Federal Way
98023
98023
98001
98023
98023
98001
98023
98001
98003
98001
98003
98003
98023
98003
98003
98023
98023
98032
98032
98023
98001
98003
98198
98003
98003
98001
98023
98003
98023
98001
98032
98032
98023
98003
98001
98003
98003
Federal Way 98003
Federal Way 98003
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
CURRENT INVENTORY NON - INSTRUCTIONAL FACILITIES
Developed Property
Administrative Building
MOT Site
Central Kitchen
Federal Way Memorial Field
Leased Space
Community Resource Center
Available Office Space
Undeveloped Property
31405 18th Avenue S
1066 S 320th Street
1344 S 308th Street
1300 S 308th Street
1813 S Commons
32020 lst Ave S
Federal Way
Federal Way
Federal Way
Federal Way
98003
98003
98003
98003
Federal Way 98003
Federal Way 98003
Site # 1
Location
75 SW 360th Street & 3rd Avenue SW — 9.2 Acres
65 S 351st Street & 52nd Avenue S — 8.8 Acres
60 E of 10th Avenue SW - SW 334th & SW 335`h Streets - 10.04 Acres
N of SW 320th and east of 45`h PL SW — 23.45 Acres
1 S 344th Street & 46th Avenue S - 17.47 Acres
82 l s` Way S and S 342 "d St — Minimal acreage
96 S 308th St and 14th Ave S — .36 Acres
81 S 332nd St and 9th Ave S — 20 Acres
Notes:
Not all undeveloped properties are large enough to meet school construction
requirements. Properties may be traded or sold depending on what locations are needed
to house students in the District.
6
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
NEEDS FORECAST - EXISTING FACILITIES
EXISTING FACILITY
FUTURE NEEDS
ANTICIPATED SOURCE OF
FUNDS
Purchase and Relocate
Portables
Interim Capacity
Anticipated source of funds is
Im.act Fees.
Elementary Schools:
Lakeland, Panther Lake,
Sunnycrest and Valhalla
Replace Existing Buildings
Increase capacity at Lakeland,
Panther Lake, Sunnycrest and
Valhalla b a total of 200 seats
Voter approved bonds.
Lakota Middle School
Rep lace Existin Buildin:
Voter a s .roved bonds
Federal Way High School
Replace Existing Building,
Increase Ca. aci
Future bond authorization
Decatur High School
Replace Existing Building,
Increase Ca . acit
Future bond authorization.
The District is also planning the replacement of some non - instructional facilities. The
District has purchased 20 acres (Site #81) for construction of consolidated facilities for
support services functions. Transportation, Nutrition Services, Maintenance and other
non - instructional functions will be housed at this centralized location.
As part of the multi -phase plan, the District intends to increase capacity for high school
students with expansion at the Decatur High School site. Increased capacity at Federal
Way High and at Decatur High in later phases supplant the need for construction of a
fifth comprehensive high school.
7
I LOCATION I ANTICIPATED SOURCE I
OF FUNDS
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
NEEDS FORECAST - ADDITIONAL FACILITIES
i
NEW FACILITY
No current plans for additional facilities.
8
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
Secured Funding
Projected Revenue
Actual and Planned Expenditures
Six Year Finance Plan
Sources
Imsact Fees (1)
$69,875
Land Sale Funds 2)
$143,642
Bond Funds (3)
$81,545,134
State Match (4)
$4,598,259)
TOTAL
$77,160,392
Sources
State Match 5)
$20,000,000
Bond or Le Funds 6)
$67,000,000
Land Fund Sales 7)
$10,000,000
Im.act Fees (8)
$1,800,000
TOTAL
$98,800,000
otal Secured Funding and Projected Revenue
$175,960,392
NEW SCHOOLS
Current and
Budget
2010
MODERNIZATION AND EXPANSION
Valhalla Elementary
Prior Years
2009/10
2010/11
2011
2011/12 0
2012
2013
2014
2015
Total
Total Cost
2012/13
2013/14
2014/15
2015/16
2010 -2015
Panther Lake Elementary
Lakeland Elementary
$18,500,000
$17,500,000
Sunnycrest Elementary
Lakota Middle School
$7,570,000
$9,930,000
$7,570,000
$9,930,000
TEMPORARY FACILITIES
$15,361,250
$15,038,750
$3,600,000
SO
$0
$9,930,000
$9,930,000
$18,638,750
$18,500,000
$17,500,000
$17,500,000
$17,500,000
$34,000,000
Portables (9)
TOTAL
$200,000
$66,501,250
$200,000
$200,000
$200,000
$35,098,750
$3,800,000
$200,000
$200,000
$0
$0
$0
NOTES:
I. These fees are currently being held in a King County, City of Federal Way and City of Kent impact fee account, and will be
available for use by the District for system improvements. This is year end balance on 12/31/08.
2. These funds come from various sales of land and are set aside for estimated expenditures. This is year end balance on 12/31/08.
3. This is the 12/31/08 balance of bond funds. This figure includes interest earnings.
4. In anticipation of State Match Funds for Valhalla, Panther Lake, Lakeland, and Sunncrest Elementaries and Lakota Middle School, work on specific building upgrades is occurring.
This is a year end balance on 12/31/08.
5. This is anticipated State Match for projects attached to future bond issues. This is based on July 1, 2006 State Match indices. State Match funds are being used for high priority repairs, upgrades
and system improvements to existing buildings. These improvements include HVAC, and other structural improvements are not related to capacity increase.
6. These are anticipated bond funds. Voters have approved a bond for $149m, $45m of this bond is for non school construction. As of 12/31/08, $82m has been sold.
7. Projected sale of surplus properties.
8. These are projected fees based upon known residential developments in the District over the next six years. This figure assumes $25,000 per month for the next six years.
This figure has been adjusted to reflect the current economy.
9. These fees represent the cost of purchasing and installing new portables. The portable expenditure in future years may replace existing portables that are not functional.
These may not increase capacity and are not included in the capacity summary.
$800,000
$39,298,750
$800,000
$105,800,000
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
SECTION 2 - MAPS OF DISTRICT BOUNDARIES
Federal Way Public Schools has twenty-one elementary schools (grades K -5), two
schools with a K -8 grade configuration, seven middle school schools (grades 6 -8), four
high schools (grades 9 -12) and three small secondary schools. The Federal Way Public
Academy serves students in grades 6 -10. The TAF Academy serves students in grades 6-
12 who reside in the Totem Middle School service area. The Career Academy at Truman
High School serves students in grades 9 -12. The Internet Academy serves grades K -12.
The following maps show the service area boundaries for each school, by school type.
(Career Academy at Truman High School, Merit School, Internet Academy and Federal
Way Public Academy serve students from throughout the District). The identified
boundaries are reviewed annually. Any change in grade configuration or adoption of
programs that affect school populations may necessitate a change in school service areas.
The Growth Management Act requires that a jurisdiction evaluate if the public facility
infrastructure is in place to handle new housing developments. In the case of most public
facilities, new development has its major impact on the facilities immediately adjacent to
that development. School District are different. If the District does not have permanent
facilities available, interim measures must be taken until new facilities can be built or
until boundaries can be adjusted to match the population changes to the surrounding
facilities.
Adjusting boundaries requires careful consideration by the District and is not taken
lightly. It is recognized that there is a potential impact on students who are required to
change schools. Boundary adjustments impact the whole district, not just one school.
It is important to realize that a single housing development does not require the
construction of a complete school facility. School districts are required to project growth
throughout the district and build or adjust boundaries based on growth throughout the
district, not just around a single development.
11
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
ELEMENTARY SCHOOL BOUNDARIES
❑ Elementary Schools
1 Adelaide
2 Brigadoon
3 Camelot
4 Enterprise
5 Green Gables
6 Lake Dolloff
7 Lake Grove
8 Lakeland
9 Mark Twain
10 Meredith Hill
11 Mirror Lake
12 Nautilus
13 Olympic View
14 Panther Lake
15 Rainier View
16 Sherwood Forest
17 Silver Lake
18 Star Lake
19 Sunnycrest
20 Twin Lakes
21 Valhalla
22 Wildwood
23 Woodmont
Middle Schools
36 Federal Way Public Academy
30 Illahee
31 Kilo
32 Lakota
33 Sacajawea
34 Saghalie
37 Sequoyah
35 Totem
High Schools
40 Decatur
41 Federal Way
421 Thomas Jefferson
45 Todd Beamer
49 Career Academy at
Truman
Administrative
Building
Undeveloped Property
ti
l
I III
N�al�IIIN�I•�1m1
uu ul
III= 1111
au"
11
N?
�N
1
asi
7.
pm. mg
(LI
_
II
�,T � NQ�IIHII
id walsi IlNlnl
- 1 111 '
" s.IIINI Nlll,
uuNIfl111N
IIII M
AN
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
MIDDLE SCHOOL BOUNDARIES
❑ Elementary Schools
1 Adelaide
2 Brigadoon
3 Camelot
4 Enterprise
5 Green Gables
6 Lake Dolloff
7 Lake Grove
8 Lakeland
9 Mark Twain
10 Meredith Hill
11 Mirror Lake
12 Nautilus
13 Olympic View
14 Panther Lake
15 Rainier View
16 Sherwood Forest
17 Silver Lake
18 Star Lake
19 Sunnycrest
20 Twin Lakes
21 Valhalla
22 Wildwood
23 Woodmont
Middle Schools
36 Federal Way Public Academy
30 Illahee
31 Kilo
32 Lakota
33 Sacajawea
34 Saghalie
37 Sequoyah
35 Totem
High Schools
40 Decatur
41 Federal Way
421 Thomas Jefferson
45 Todd Beamer
49 Career Academy at
Truman
n Administrative Building
MOT Site
Undeveloped Property
N
WPM
I■
�1N11
■.RIKIQII
r ,
Im mo
aim IUlfh+IIIIr
I MINILi
IMR III
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
HIGH SCHOOL BOUNDARIES
El Elementary Schools
1 Adelaide
2 Brigadoon
3 Camelot
4 Enterprise
5 Green Gables
6 Lake Dolloff
7 Lake Grove
8 Lakeland
9 Mark Twain
10 Meredith Hill
11 Mirror Lake
12 Nautilus
13 Olympic View
14 Panther Lake
15 Rainier View
16 Sherwood Forest
17 Silver Lake
18 Star Lake
' 9 Sunnycrest
10 Twin Lakes
21 Valhalla
22 Wildwood
23 Woodmont
iffi
Middle Schools
36 Federal Way Public Academy
30 Illahee
31 Kilo
32 Lakota 1 45, 1 S-
33 Sacajawea —" _Al ' 4k,
34 Saghalie I M
g 1:1111 �I ,u
37 Sequoyah uu tiri :,'�;iull II"
35 Totem � ;° III ti if
® High Schools
40 Decatur
41 Federal Way
421 Thomas Jefferson
45 Todd Beamer
49 Career Academy at
Truman
0 Administrative Building
MOT Site
Undeveloped Property
J�
Naga 1.7.1
W l � r
—
rr
MIN
DAL
1
1r
IFS
1r
2
■
r�V
.• 1111
lid1•!
■IMM E
4
r
tT
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
SECTION 3 - SUPPORT DOCUMENTATION
Building Capacities - The Education Program
Portable Locations
Student Forecast — 2010 through 2016
Capacity Summaries
King County Impact Fees - Single and Multi - Family Units
15
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
Building Capacities
This Capital Facilities Plan establishes the District's "standard of service" in order to
ascertain the District's current and future capacity. The Superintendent of Public
Instruction establishes square footage guidelines for capacity, but these guidelines do not
take into consideration the education program needs.
In general, the District's current target class size provides that the average class size for a
standard classroom for grades K through 2 should be 20 students. In grades 3 -5 the target
is 25 students. For grades 6 to 12 the target class size is 26 students. Classrooms for
students with Individualized Education Program (Special Education) needs are calculated
at 12 seats per classroom.
Using the OSPI square footage calculation as a base line, the District has calculated a
program capacity for all schools. A recent Study & Survey was the basis for changes to
the OSPI building report. The following list clarifies the adjustments to the OSPI
calculation.
Music Rooms:
Each elementary school requires a standard classroom for music instruction.
All Day Kindergarten:
Every elementary school operates at least one all day Kindergarten program. These all
day Kindergarten program require additional capacity because the standard classroom is
available for one all day session rather than two half day sessions. The District will
operate 52 sections of all day Kindergarten in 2009/10
Special Education Resource Rooms:
Each elementary and middle school requires the use of a standard classroom(s) for
special education students requiring instruction to address specific disabilities
English as a Second Language Programs:
Each elementary, middle school and high school requires the use of a standard classroom
for students learning English as a second language.
Middle School Computer Labs:
Each middle school has computer labs.
High School Career Development and Learning Center (Resource) Room:
Each high school provides special education resource room and career development
classrooms for students requiring instruction to address specific disabilities.
16
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
BUILDING PROGRAM CAPACITIES
ELEMENTARY BUILDING
PROGRAM CAPACITY
School Name Headcount
Adelaide
372
Brigadoon
327
Camelot
269
Ente rise
458
Green Gables
437
Lake Dolloff
433
Lake Grove
323
Lakeland
392
Mark Twain
327
Meredith Hill
453
Mirror Lake
325
1 auti us
211
Olympic View
328
Panther Lake
383
Rainier View
432
Sherwood Forest
423
Silver Lake
390
Star Lake
361
Sunnycrest
369
Twin Lakes
297
Valhalla
449
Wildwood
317
Woodmont
350
2009 TOTAL
8,571
Elementary Average
1 373
Notes:
MIDDLE SCHOOL BUILDING
PROGRAM CAPACITY
School Name Headcount FTE
Illahee
855
864
Kilo
827
835
Lakota
766
774
Sacajawea
700
707
Saghalie
829
837
Se•uoyah
589
595
Totem
714
721
Federal Way Public Academy
209
211
Technology Access Foundation Academy **
2009 TOTAL
5,489
5,544
*Middle School Average
754 1 762
HIGH SCHOOL BUILDING
PROGRAM CAPACITY
School Name Headcount FTE
Decatur
1239
1,37
Federal Way
1482
1,51.
Thomas Jefferson
1339
1,432
Todd Beamer
1134
1,213
Career Academy at Truman
130
139
Federal Way Public Academy
109
117
Technology Access Foundation Academy **
2009 TOTAL
5,433
5,811
*High School Average
1 1,299 1 1,389
* Federal Way Public Academy and Career Academy at Truman High School
are non - boundary schools. These schools are not used in the calculated averages.
** Technology Access Foundation Academy is housed entirely in portables
on the Totem Middle School site.
17
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
Portable Locations
The Washington State Constitution requires the State to provide each student a basic
education. It is not an efficient use of District resources to build a school with a capacity
for 500 students due to lack of space for 25 students when enrollment fluctuates
throughout the year and from year to year.
Portables are used as temporary facilities or interim measures to house students when
increasing population impacts a school attendance area. Portables may also be required
to house students when new or changing programs require additional capacity. They also
provide temporary housing for students until permanent facilities can be financed and
constructed. When permanent facilities become available, the portable(s) is either used
for other purposes such as storage or child care programs, or moved to another school for
an interim classroom. Some portables may not be fit to move due to age or physical
condition. In these cases, the District may choose to buy new portables and surplus these
unfit portables. It is the practice and philosophy of Federal Way Public Schools that
portables are not acceptable as permanent facilities.
The following page provides a list of the location of the portable facilities, used for
temporary educational facilities by Federal Way Public Schools.
18
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
PORTABLE LOCATIONS
PORTABLES LOCATED
AT ELEMENTARY SCHOOLS
PORTABLES LOCATED
AT MIDDLE SCHOOLS
INSTRUCTIONAL
NON
INSTRUCTIONAL
Adelaide
2
1
Brigadoon
7
1
Camelot
1
Ente T rise
2
1
Green Gables
4
1
Lake Dolloff
1
1
Lake Grove
1
1
Lakeland
2
Mark Twain
3
1
Meredith Hill
3
4
Mirror Lake
4
Nautilus
1
Olympic View
2
Panther Lake
Rainier View
1
1
Sherwood Forest
4
Silver Lake
2
2
Star Lake
3
1
Sunnycrest
2
Twin Lakes
2
1
Valhalla
Wildwood
4
1
Woodmont
3
TOTAL
43
11
PORTABLES LOCATED
AT MIDDLE SCHOOLS
19
PORTABLES LOCATED
AT HIGH SCHOOLS
INSTRUCTIONAL
NON
INSTRUCTIONAL
Illahee
9
3
Kilo
7
1
Lakota
4
Sacajawea
4
1
Saghalie
4
Sequoyah
1
2
Totem
Merit
2
TAF Academy
6
1
28
4
19
PORTABLES LOCATED
AT HIGH SCHOOLS
PORTABLES LOCATED
AT SUPPORT FACILITIES
MOT
INSTRUCTIONAL
NON
INSTRUCTIONAL
Decatur
9
6
Federal Way
2
1
Thomas Jefferson
10
Todd Beamer
8
1
TAF Academy
8
TOTAL
37
2
PORTABLES LOCATED
AT SUPPORT FACILITIES
MOT
1
TDC
5
TOTAL
6
HEAD START PORTABLES AT DISTRICT SITES
Sherwood Forest
1
Total
1
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
Student Forecast
Student enrollment projections are a basic component of budget development.
Enrollment projections influence many of the financial estimates that go into budget
preparation. The majority of staffing requirements are derived directly from the
forecasted number of students. Allocations for instructional supplies and materials are
also made on the basis of projected enrollment. Other expenditures and certain revenue
projections are directly related to enrollment projections.
Enrollment projections are completed annually in the Business Services Department.
Projections must be detailed at various levels, district total, school - building totals, grade
level and program level to include vocational and special education students.
The basis of projections has been cohort survival analysis. Cohort survival is the analysis
of a group that has a common statistical value (grade level) as it progresses through time.
In a stable population the cohort would be 1.00 for all grades. This analysis uses
historical information to develop averages and project the averages forward. This
method does not trace individual students; it is concerned with aggregate numbers in each
grade level. The district has used this method with varying years of history and weighted
factors to study several projections. Because transfers in and out of the school system are
common, student migration is factored into the analysis as it increases or decreases
survival rates. Entry grades (kindergarten) are a unique problem in cohort analysis. The
district collects information on birth rates within the district's census tracts, and treats
these statistics as a cohort for kindergarten enrollment in the appropriate years.
The Federal Way School District is using various statistical methods for projecting
student enrollments. The resultant forecasted enrollments are evaluated below.
The first method is a statistical cohort analysis that produces ten distinct forecasts. These
are forecast of enrollment for one year. The projections vary depending on the number of
years of historical information and how they are weighted.
A second method is a projection using an enrollment projection software package that
allows the user to project independently at school or grade level and to aggregate these
projections for the district level. The Enrollment MasterTM software provides statistical
methods including trend line, standard grade progression (cohort) and combinations of
these methods. This software produces a five -year projection of school enrollment.
In December 2006, the District contracted a demographer to develop projections for the
Federal Way School District. The report was complete in January 2007. The model used
to forecast next year's enrollment uses cohort survival rates to measure grade to grade
growth, assumes market share losses to private schools (consistent with county-wide
average), assumes growth from new housing or losses due to net losses from migration.
This forecast was provided as a range of three projections. The long -range forecast
provided with this report used a model with cohort survival rates and growth rates based
on projected changes in the 5 -19 age group for King County. Most of the methods used
for long range enrollment reporting assume that enrollment is a constant percent of
20
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
something else (e.g. population) or that enrollment will mirror some projected trend for
the school -age population over time. The report included 5 different calculations to
provide a range of possible projections for the District to the year 2015. This model
produces a projection that is between 23,000 and 24,000 when applied to the low,
medium and high range modes. This provides a reasonable range for long -range planning
and is consistent with estimates from various models.
Long -range projections that establish the need for facilities are a modification of the
cohort survival method. The cohort method of analysis becomes less reliable the farther
out the projections are made. The Federal Way School District long -range projections
are studied annually. The study includes information from the jurisdictional
demographers as they project future housing and population in the region. The long -range
projections used by Federal Way Public Schools reflect a similar age trend in student
populations as the projections published by the Office of Financial Management for the
State of Washington.
Near term projections assume some growth from new housing, which is offset by current
local economic conditions. Current economic conditions do appear to be affecting
enrollment. This is reflected in the District's projections. The District tracks new
development from five permitting jurisdictions. Long range planning assumes a student
yield from proposed new housing consistent with historical growth patterns.
Growth Management requires jurisdictions to plan for a minimum of twenty years. The
Federal Way School District is a partner in this planning with the various jurisdictions
comprising the school district geography. These projections create a vision of the school
district community in the future.
21
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
Full Time Equivalent Enrollment History and Projections
Simplified FTE (K Headcount = .5 FTE; Middle School FTE =.99 Headcount; High School FTE = .935Headcount)
Calendar Yr
School Year
Elementary
Middle School
Senior High
October Headcount
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
* 2003 -04
2004 -05
2005 -06
2006 -07
2007 -08
2008 -09
B2009 -10
P2010 -11
P2011 -12
P2012 -13
P2013 -14
P2014 -15
P2015 -16
* New Configuration
9,127
9,164
9,105
9,022
8,912
8,865
8,793
8,838
8,894
8,988
9,091
9,175
9,253
Elementary K -5
5,524
5,473
5,309
5,261
5,167
5,155
5,076
5,077
5,042
4,995
4,969
5,012
5,086
Middle School 6 -8
6,408
6,515
6,770
6,754
6,637
6,456
6,325
6,167
6,129
6,109
6,111
6,066
6,022
High School 9 -12
22,000
21,000 -
20,000 -
19,000 -
18,000
17,000
16,000
15,000
Enrollment History and Six Year Forecast
Total K -12 Percent
FTE Change
21,059
21,152 0.4%
21,184 0.2%
21,037 -0.7%
20,716 -1.5%
20,476 -1.2%
20,194 -1.4%
20,082 -0.6%
20,065 -0.1%
20,092 0.1%
20,171 0.4%
20,253 0.4%
20,361 0.5%
0FTE
x00 �0� �00
0 s
, X00'
T3.0
O, 00
b0
School Year
°O'O °O, •°O
i J
7 'cD �UD
-0 -0
a0v �o
.), ,s
22
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
Capacity Summaries
All Grades, Elementary, Middle School, and High Schools
The Capacity Summaries combine Building Capacity information and the Student
Forecast information. The result demonstrates the requirements for new or remodeled
facilities and why there is a need for the District to use temporary facilities or interim
measures.
The information is organized in spreadsheet format, with a page summarizing the entire
District, and then evaluating capacity vs. number of students at elementary, middle
school, and high school levels individually.
The notes at the bottom of each spreadsheet provide information about what facilities are
in place each year.
23
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
CAPACITY SUMMARY - ALL GRADES
CAPACITY
20,194
Budget
- - Projected - -
Calendar Year
2010
2011
2012
2013
2014
2015
2016
School Year
2009/10
2010/11
2011/12
2012/13
2013/14
2014/15
2015/16
BUILDING PROGRAM
HEADCOUNT CAP ACITY
19,493
19,926
19,493
19,926
19,493
19,926
19,593
20,026
19,593
19,593
19,593
20,026
_
FTE CAPACITY
20,026
20,026
Add or subtract changes to capacity
Increase Capacity, Lakeland, Panther Lake
. Sunnycrest and Valhalla
. 100
100
-
Adjusted Program Headcount Capacity
19,593
19,493
19,593
19,593
19,593
19,593
19,593
Adjusted Program FTE Capacity
20,026
19,926
20,026
20,026
20,026
20,026
20,026
ENROLLMENT
Basic FTE Enrollment
20,194
20,082
20,065
20,092
20,171
20,253
20,361
Internet Academy Enrollment (AAFTE)
(315)
(315)
(315)
(315)
(315)
(315)
• (315)
Basic FTE Enrollment without Internet Academy
19,879
19,767
19,750
19,777
19,856
19,938
20,046
SURPLUS OR (UNHOUSED)
PROGRAM FTE CAPACITY
147
159
276
249
170
88
(20)
• RELOCATABLE CAPACITY
Current Portable Capacity
2,700
2,700
2;700
2,700
2,700
2,700
2,700
Deduct Portable Capacity
(125) ,
_
Add New Portable Capacity
125
Adjusted Portable Capacity
2,700
2,700
2,700
2,700
2,700
2,700
2,700
SURPLUS OR (UNHOUSED)
PROGRAM AND RELOCATABLE
CAPACITY
2,847
2,859
2,976
2,949
2,870
2,788
2,680
24
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
CAPACITY SUMMARY - ELEMENTARY SCHOOLS
CAPACITY
8,793
Budget
- - Projected - -
Calendar Year
2010
2011
2012
2013
2014
2015
2016
School Year
2009/10
2010/11
2011/12
2012/13
2013/14
2014/15
2015/16
BUILDING PROGRAM
HEAD COUNT CAPACITY
FTE CAPACITY
8,571
8,571
8,571
8,571
8,571
8,571
8,671
8,671
8,671
8,671
8,671
8,671
8,671
8,671
1. Increase Capacity Lakeland
and Sunn crest
100
Adjusted Program Headcount Capacity
8,571
8,571
8,671
8,671
8,671
8,671
8,671
Adjusted Program FTE Capacity
8,571
8,571
8,671
8,671
8,671
8,671
8,671
ENROLLMENT
Basic FTE Enrollment
8,793
8,838
8,894
8,988
9,091
9,175
9,253
2. Internet Academy (AAFTE)
(36)
(36)
(36)
(36)
(36)
(36)
(36)
Basic FTE Enrollment without Internet Academy
8,757
8,802
8,858
8,952
9,055
9,139
9,217
SURPLUS OR (UNHOUSED)
PROGRAM CAPACITY
(186)
(231)
(187)
(281)
(384)
(468)
(546)
RELOCATABLE CAPACITY 3.
Current Portable Capacity
1,075
1,075
1,075
1,075
1,075
1,075
1,075
Adjusted Portable Capacity
1,075
1,075
1,075
1,075
1,075
1,075
1,075
SURPLUS OR (UNHOUSED)
PROGRAM AND RELOCATABLE
CAPACITY
889
844
888
794
691
607
529
NOTES:
1. Increase Capacity at Lakeland, Panther Lake, Sunnycrest and Valhalla
2. Internet Academy students are included in projections but do not require full time use of school facilities.
3. Relocatable Capacity is based on the number of portables available and other administrative techniques which
can be used to temporarily house students until permanent facilities are available. This is a calculated number only.
The actual number of portables that will be used will be based on actual student population needs.
The District may begin to pull portables from the instructional inventory. Age and condition of the portables
will determine feasibility for continued instructional use.
25
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
CAPACITY SUMMARY - MIDDLE SCHOOLS
CAPACITY
5,076
Budget
- - Projected - -
Calendar Year
2010
2011
2012
2013
2014
2015
2016
School Year
2009/10
2010/11
2011/12
2012/13
2013/14
2014/15
2015/16
BUILDING PROGRAM
HEADCOUNT CAPACITY
FTE CAPACITY
5,489
5,544
5,489
5,544
5,489
5,544
5,489
5,544
5,489
5,544
5,489
5,544
5,489
5,544
Add or subtract changes in capacity
Adjusted Program Headcount Capacity
5,489
5,489
5,489
5,489
5,489
5,489
5,489
Adjusted Program FTE Capacity
5,544
5,544
5,544
5,544
5,544
5,544
5,544
ENROLLMENT
Basic FTE Enrollment
5,076
5,077
5,042
4,995
4,969
5,012
5,086
1. Internet Academy (AAFTE)
(74)
(74)
(74)
(74)
(74)
(74)
(74)
Basic FTE Enrollment without Internet Academy
5,002
5,003
4,968
4,921
4,895
4,938
5,012
SURPLUS OR (UNHOUSED)
PROGRAM CAPACITY
542
541
576
623
649
606
532
RELOCATABLE CAPACITY 2.
Current Portable Capacity
Add /Subtract portable capacity
Add new portable capacity Sequoyah
Subtract portable capacity from Totem
Adjusted Portable Capacity
825
25
(125)
725
725
725
725
725
725
725
725
725
725
725
725
725
SURPLUS OR (UNHOUSED)
P ROGRAM AND RELOCATABLE
CAPACITY
1,267
1,266
1,301
1,348
1,374
1,331
-
1,257
NOTES:
I. Internet Academy students are included in projections but do not require full time use of school facilities.
2. Relocatable Capacity is based on the number of portables available and other administrative techniques which
can be used to temporarily house students until permanent facilities are available. This is a calculated number only.
The actual number of portables that will be used will be based on actual student population needs.
The District may begin to pull portables from the instructional inventory. Age and condition of the portables
will determine feasibility for continued instructional use.
26
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
CAPACITY SUMMARY - HIGH SCHOOLS
CAPACITY
6,325
Budget
- - Projected - -
Calendar Year
2010
2011
2012
2013
2014
2015
2016
School Year
2009/10
2010/11
2011/12
2012/13
2013/14
2014/15
2015/16
BUILDING PROGRAM
HEADCOUNT CAPACITY
FTE CAPACITY
5,433
5,811
5,433
5,811
5,433
5,811
5,433
5,811
5,433
5,811
5,433
5,811
5,433
5,811
Add or subtract changes in capacity
900
900
900
Adjusted Program Headcount Capacity
5,433
5,433
5,433
5,433
5,433
5,433
5,433
Adjusted Program FTE Capacity
5,811
5,811
5,811
5,811
5,811
5,811
5,811
ENROLLMENT
Basic FTE Enrollment
6,325
6,167
6,129
6,109
6,111
6,066
6,022
1. Internet Academy (AAFTE)
(205)
(205)
(205)
(205)
(205)
(205)
(205)
Basic Ed without Internet Academy
6,120
5,962
5,924
5,904
5,906
5,861
5,817
SURPLUS OR ( UNHOUSED)
PROGRAM CAPACITY
(309)
(151)
(113)
(93)
(95)
(50)
(6)
RELOCATABLE CAPACITY 2.
Current Portable Capacity
800
900
900
900
900
900
900
Add /Subtract portable capacity
Add portable capacity at TAF Academy
100
Adjusted Portable Capacity
900
900
900
900
900
900
900
SURPLUS OR (UNHOUSED)
PROGRAM AND RELOCATABLE
3. CAPACITY
591
749
787
807
805
_
850
894
NOTES:
1. Internet Academy students are included in projections but do not require full time use of school facilities.
2. Relocatable Capacity is based on the number of portables available and other administrative techniques which
can be used to temporarily house students until permanent facilities are available. This is a calculated number only.
The actual number of portables that will be used will be based on actual student population needs.
The District may begin to pull portables from the instructional inventory. Age and condition of the portables
will determine feasibility for continued instructional use.
3. Capacity for unhoused students will be accommodated with traveling teachers and
no planning time in some classrooms. Puget Sound Early College will house approximately
60 of the unhoused students.
27
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
King County, the City of Federal Way, and the City of Kent Impact Fee Calculations
Single and Multi- Family Residences
Each jurisdiction that imposes school impact fees requires that developers pay these fees
to help cover a share of the impact of new housing developments on school facilities.
To determine an equitable fee throughout unincorporated King County, a formula was
established. This formula can be found in King County Code 21A and was substantially
adopted by the City of Federal Way and Kent. The formula requires the District to
establish a "Student Generation Factor" which estimates how many students will be
added to a school district by each new single or multi - family unit and to gather some
standard construction costs, which are unique to that district.
- STUDENT GENERATION FACTOR ANALYSIS
Federal Way Public Schools student generation factor was determined separately for
single - family units and multi - family units. The factors used in the 2010 Capital Facilities
Plan were derived using actual generation factors from single - family units that were
constructed in the last five (5) years.
- IMPACT FEE CALCULATION
Following the calculations for the student generation factor is a copy of the Impact Fee
Calculation for single family and multi - family units based on King County Code 21A and
the Growth Management Act.
➢ Temporary Facility Cost is the average cost of a portable purchased within the last 12
months.
Plan Year 2010 Plan Year 2009
Single Family Units
Multi - Family Units
$3,832 $4,017
$2,114 $1,733
28
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
STUDENT GENERATION
NEW CONSTRUCTION IN PRIOR 5 YEARS
Single Family Student Generation
Student Generation rate is based on totals.
Multi - Family Student Generation
Number of
Single Family
Dwellings
Number of
Multi - Family
Dwellings
Number of
Elementary
Students
Number of
Middle School
Students
Number of
High School
Students
Elementary
Student
Factor
Middle School
Student
Factor
High School
Student
Factor
Total
Student
Factor
DEVELOPMENT
09 Lakota Crest
41
0
3
7
2
0.0732
0.1707
0.0488
0.2927
09 Tuscan
18
0
9
2
1
0.5000
0.1111
0.0556
0.6667
08 Northlake Ride IV
90
0
30
9
15
0.3333
0.1000
0.1667
0.6000
08 Collin. tree Park
42
0
19
5
2
0.4524
0.1190
0.0476
0.6190
07 Colella Estates
81
0
31
13
22
0.3827
0.1605
0.2716
0.8148
07 Woodbrook
169
0
36
25
39
0.2130
0.1479
0.2308
0.5917
06 Devonshire
29
0
15
6
17
0.5172
0.2069
0.5862
1.3103
06 Orchid Lane
50
0
25
11
13
0.5000
0.2200
0.2600
0.9800
05 Danville Station
80
0
36
18
22
0.4500
0.2250
0.2750
0.9500
(05) Northlake Ridge I, II AND III
241
0
75
43
54
0.3112
0.1784
0.2241
0.7137
Total
841
0
279
139
187
Student Generation* 0.3317 0.1653 0.2224 0.7194
Student Generation rate is based on totals.
Multi - Family Student Generation
Elementa
Middle School
High School
Total
Auburn
0.079
0.034
0.042
0.155
Issa• uah
0.102
0.049
0.052
0.203
Kent
0.296
0.075
0.111
0.482
Lake Washington
0.132
0.049
0.031
0.212
Average 0.152 0.052 0.059 0.263
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
'hoot Site Acquisition Cost:
Facility
Acreage
Elementary
Middle School
High School
Cost /
Acre
IMPACT FEE
Facility
Capacity
Student
Factor
SFR
Student
Factor
MFR
Cost/
SFR
Cost/
MFR
School Construction Cost:
% Perm Fac./
Total S. Ft
Elementary
Middle School
High School
Facility
Cost
Facility
Capacity
Student
Factor
SFR
Student
Factor
MFR
Cost/
SFR
Cost/
MFR
95.62%
$9,100,000
200
0.3317
0.1520
$0
$0
4.38%
$193,607
25
0.1653
0.0520
$0
$0
$168.79
0.2224
0.0590
$0
$0
TOTAL
SO
$0
School Construction Cost:
% Perm Fac./
Total S. Ft
Elementary
Middle School
High School
Facility
Cost
Facility
Capacity
Student
Factor
SFR
Student
Factor
MFR
Cost/
SFR
Cost/
MFR
95.62%
$9,100,000
200
0.3317
0.1 520
$14,431
$6,613
4.38%
$193,607
25
0.1653
0.0520
SO
SO
$168.79
0.2224
0.0590
$0
$0
TOTAL
$14,431
- $6,613
Temporary Facility Cost:
% Temp Fac.
Total S• Ft
Elementary
Middle School
High School
Facility
Cost
Facility
Size
Student
Factor
SFR
Student
Factor
MFR
Cost/
SFR
Cost/
MFR
State Matching Credit Calculation:
Area Cost
Allowance /S. Ft
Elementary
Middle School
High School
Sq. Ft.
Student
State
Match
Student
Factor
SFR
Student
Factor
MFR
Cost/
SFR
Cost/
MFR
$168.79
90
61.09%
0.3317
0.1520
$3,078
$1,411
4.38%
$193,607
25
0.1653
0.0520
$56
$18
$168.79
0.2224
0.0590
$0
$0
TOTAL
$56
$18
State Matching Credit Calculation:
Area Cost
Allowance /S. Ft
Elementary
Middle School
High School
Sq. Ft.
Student
State
Match
Student
Factor
SFR
Student
Factor
MFR
Cost/
SFR
Cost/
MFR
$168.79
90
61.09%
0.3317
0.1520
$3,078
$1,411
$168.79
$1.48
$1.48
0.1653
0.0520
. $0
$0
$168.79
0.2224
0.0590
$0
$0
Total
$3,078
$1,411
Tax Payment Credit Calculation
Average Assessed Value (March 2009)
Capital Bond Interest Rate (March 2009)
Net Present Value of Average Dwelling
Years Amortized
Property Tax Levy Rate
Present Value of Revenue Stream
Mitigation Fee Summary
Site Acquisition Cost
Permanent Facility Cost
Temporary Facility Cost
State Match Credit
Tax Payment Credit
Sub -Total
50% Local Share
Single Family Multi- Family
Residences Residences
$ - $
$ 14,431 $ 6,613
$ 56 $ 18
$ (3,078) S. (1,411)
$ (3,745) $ (992)
SFR
MFR
$326,409
$86,497
4.96%
4.96%
$2,525,346
$669,206
10
10
$1.48
$1.48
$3,745
$992
$ 7,664 $ 4,228
$ 3,832 $
2,114
(Impact Fee
$ 3,832 $ 2,1141
30
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
SECTION 4
SUMMARY OF CHANGES FROM THE 2009 CAPITAL FACILITIES PLAN
The 2010 Capital Facilities Plan is an updated document, based on the 2009 Capital
Facilities Plan. The changes between the 2009 Plan and the 2010 Plan are listed below.
SECTION I - THE CAPITAL FACILITIES PLAN
SIX -YEAR FINANCE PLAN
The Six Year Finance Plan has been rolled forward to reflect 2010/2016
SECTION III - SUPPORT DOCUMENTATION
CAPACITY
Elementary capacity includes space for All Day Kindergarten programs at every
elementary school. Changes to the Building Program Capacities calculation are found on
page 17.
PORTABLES
The list of portables reflects the movement of portables between facilities or new
portables purchased. Portable Locations can be found on page 19.
STUDENT FORECAST
The Student Forecast now covers 2010 through 2016 Enrollment history and projections
are found on page 22.
CAPACITY SUMMARY
The changes in the Capacity Summary are a reflection of the changes in the capacities
and student forecast. New schools and increased capacity at current buildings are shown
as increases to capacity. Capacity Summaries are found on pages 24 -27.
IMPACT FEE CALCULATION - KING COUNTY CODE 21A
The Impact Fee Calculations have changed due to changes in several factors. The
adjustment made in the Impact Fee Calculation, causing a change in the Impact Fee
between the 2009 Capital Facilities Plan and the 2010 Capital Facilities Plan can be
found on page 32 and 33.
31
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
IMPACT FEE CALCULATION CHANGES FROM 2009 TO 2010
STUDENT GENERATION FACTORS
Student Generation factors are based on rates for new developments constructed over a
period of not more than five years prior to the date of the fee calculation. The changes in
student Generation factors between the 2009 Capital Facilities Plan and the 2010 Capital
Facilities Plan are due to developments that were deleted or added based upon the age of
the developments and the year placed in the survey. The Student Generation worksheet
is found on page 29.
SCHOOL CONSTRUCTION COSTS
The anticipated cost for replacing Lakeland, Panther Lake, Sunnycrest and Valhalla is
$70,000,000. The replacement will add 50 new seats to the school capacity at each
building. The total capacity at these four elementary schools is currently 1505. Adding
200 additional seats will increase the capacity by 13 %.
Total Cost .13 X $70,000,000 = $9,100,000
The District will use the above formula created as a base from the 2008 Capital Facilities
Plan for the 2010 Capital Facilities Plan. The capacity of the four elementary schools
may vary from year to year as programs are added or changed and construction cost may
increase over time. For instance, for each new all day Kindergarten program, the
building capacity will effectively be reduced by 20 headcount and the Board authorized
an increase in construction cost of $1m for Valhalla. These changes would increase the
construction cost. The District is using the base formula established in the 2008 plan in
the Impact Fee calculation.
32
FEDERAL WAY PUBLIC SCHOOLS 2010 CAPITAL FACILITIES PLAN
IMPACT FEE CALCULATION CHANGES FROM 2009 TO 2010
IMPACT FEE
Item
From /To Comment
Percent of Permanent Facilities 96.81% to 95.62% Report #3 OSPI
Percent Temporary Facilities 3.19% to 4.38% Updated portable inventory
Average Cost of Portable $168,307 to $193,607 Updated average of portables
Classroom purchased and placed in 2009
Area Cost Allowance $168.79 to $168.79 No change from the prior year.
State Match 61.84% to 61.09% Change effective July 2008
Average Assessed Value SFR — Per Puget Sound Educational
$297,242 to $326,409 Service District (ESD 121)
MFR —
$68,998 to $86,497
Capital Bond Interest Rate 5.11% to 4.96% Market Rate
Property Tax Levy Rate
$1.49 to $1.48 King County Treasury Division
Single Family Student Yield
Elementary .3285 to .3317
Middle School .1631 to .1653
High School .2446 to .2224
Multi- Family Student Yield
Elementary .1222 to .1520
Middle School .0621 to .0520
High School .0942 to .0590
33
Updated Housing Inventory
Updated Housing Inventory