HomeMy WebLinkAboutCP1202 RFP-FINAL.pdf
1
REQUEST FOR PROPOSALS (RFP)
AUBURN WAY SOUTH FLOODING
IMPROVEMENT PROJECT – PHASE II
Proposals Due: February 1, 2013
CITY OF AUBURN
REQUEST FOR PROPOSALS (RFP)
Project No. CP1202, AUBURN WAY SOUTH FLOODING IMPROVEMENT – PHASE II
Proposals Due: February 1, 2013
The City of Auburn (“City”) is soliciting Proposals from qualified consulting teams to provide
professional services for the design and construction assistance for the Auburn Way South Flooding
Improvement Project – Phase II, CP1202.
Six (6) copies of the Proposal Package must be submitted on or before 5:00 P.M. on February 1,
2013. Proposals can be mailed to the City of Auburn Public Works Department, 25 West Main St,
Auburn, WA 98001 or hand delivered to One East Main St, Auburn WA 98001, 2nd Floor Customer
Service Center. Proposals shall be sent in a sealed envelope and clearly marked: “Proposal –
CP1202, Auburn Way South Flooding Improvement – Phase II” in the lower left corner. Questions
regarding this solicitation should be directed to Robert Lee, Project Engineer, by email only at
rlee@auburnwa.gov .
For specific instructions on information to include in the Proposal, refer to the section below entitled
Proposal Elements. Evaluation of the Proposals and ultimate consultant selection is identified in the
section entitled Selection Process and Evaluation Criteria below. Although the use of sub consultants
is recognized as being necessary for a multidiscipline large scale project, the City’s preference is for
the lead consultant to have the majority of the work performed in-house. The lead consultant shall
have experience with at least one storm drainage system design on a collector street with a total
project cost of at least $1,500,000 within the last 5 years.
PROJECT DESCRIPTION
The intersection of Auburn Way South (AWS) near the State Route (SR) 18 underpass frequently
floods during large and/or intense rain events. The current low-slope, gravity storm drain adjacent to
the underpass provides limited capacity for upstream tributary flows. A combination of former trunk
line improvements and pump station installation has provided some relief, but has not alleviated all
the flooding at the depressed underpass. The downstream drainage system is also capacity-limited
causing a “recirculation” of the pumped discharge, thereby limiting its effectiveness during larger rain
events.
The Comprehensive Stormwater Drainage Plan (2009) identified a two phase project to reduce
stormwater flows to AWS at SR 18 by diverting upstream flows from the impacted area. The total 25-
year flow to be routed away from AWS has been estimated at 10 cfs. This flow would be directed by
gravity flow at AWS and 17th St. SE toward the existing stormwater infiltration ponds located at 17th
and A Streets SE, and 21st and D Streets SE. Final modeling will be conducted by the City’s on-call
modeling consultant to determine pipe size and slope.
Phase 1 was completed in 2009. This phase installed a diversion manhole at AWS and 17th St. SE to
route 3 cfs into a new 24-inch diameter storm drain flowing west along 17th St. SE, then south along
K St. SE, with eventual discharges into the 21st infiltration pond. The amount of the diversion for this
phase was limited to the available capacity in the existing K St. SE storm line.
2
Phase 2, this project, will intercept all remaining flow from the diversion manhole and route it to the
west. At the intersection of K St SE and 17th St. SE, a new flow control structure will be installed to
maintain the current flow to K St. SE. From this point west, approximately 3,100 LF of 24”-30” pipe
will be required to replace the existing lines in 17th St. SE. The existing pipes along 17th St. SE at the
intersections of J St. SE and B St. SE will be plugged, diverting all flows west and away from their
current connection to the AWS drainage system. Eliminating the discharge into these two pipes will
increase the flow in the 17th St. SE storm line by an additional 4.5 cfs. Inlet spacing along the project
shall be considered to meet current design standards. This project also includes deepening the
existing 17th and A Street SE infiltration pond to provide an additional 7 acre-feet of storage.
King County Wastewater currently has plans to construct a 27” trunk sanitary sewer line along 17th
Street between K Street SE and C Street SW and it is anticipated that this will be under construction
in 2013. King County has submitted final plans approved by the City through the Development
process. The design of the City’s project must be coordinated with the King County project to
accommodate both systems in the same corridor.
Additional information for this project can be found on the City’s website at
http://www.auburnwa.gov/business/public_works/capital_projects_information.asp.
SCOPE OF WORK
The Scope of Work will include, at a minimum, the following elements:
1. General
Project Management
2. Preliminary Design –
Perform a geotechnical evaluation of the existing stormwater infiltration pond at 17th St
SE and A St SE.
3. Detailed Design
General. The Consultant will prepare plans, specifications, and cost estimates at the
30%, 60%, and 90% Design, and Final Construction Documents Levels.
4. Optional: Engineering Services During Construction may include:
Bid period assistance
Preparation of addendums
Shop drawings and submittal review
Preparation of change orders
Preparation of Record drawings
PROPOSAL ELEMENTS
Each proposal is limited to ten (10) double-sided pages (or 20 single sided pages), (excluding cover
and dividers) (minimum font size 10, Arial), and should address the following items relative to the
design and construction of storm drainage facilities and other project elements:
1. The Project Team, including sub-consultants, and expertise and experience with similar
projects. Include the following information:
Project name
Location and Project Costs
A brief description of the project
The firm’s role in the project
Project Team member roles in the project
A project reference and contact phone number
2. The identity and qualifications of the proposed Project Team members, including any sub-
consultants proposed, for the design effort and their availability.
3. The Project Team’s approach to the project.
4. The Project Team’s anticipated Project Schedule.
3
5. The firm’s process/procedures for providing quality assurance/quality control through out the
life of the project.
As a supplement to the above, you may include two (2) bound copies of general firm/team
information and Project Team member resumes.
SELECTION PROCESS AND EVALUATION CRITERIA
A committee of City personnel will evaluate and rate the proposals to these criteria, weighted as
indicated:
1. Project Team Experience with similar projects. (25%)
2. Approach to the Project. (25%)
3. Quality Assurance / Quality Control Plan. (20%)
4. Qualifications of the proposed Project Team (20%)
5. Schedule (10%)
Following the evaluation of the Proposals, the City will interview up to three (3) of the
prospective consultants. Those firms selected for interview will have the opportunity to present
their past experience in environmental evaluation and permitting, roadway and storm drainage
design, property acquisition, and overall project approach.
SELECTION SCHEDULE
The City’s proposed schedule for consultant selection, subject to change, is as follows:
1. Issue Request for Proposals January, 8 2013, January 15, 2013
2. Deadline for Submittal of Proposals February 1, 2013 @ 5:00 p.m.
3. Selection of Firm February 22, 2013
4. Complete Contract Negotiations March 15, 2013
5. Execution of Agreement March 29, 2013
TERMS AND CONDITIONS
The City of Auburn reserves the right to reject any and all Proposals and to waive irregularities and
informalities in the submittal and evaluation process. This solicitation for Consultant Services does
not obligate the City of Auburn to pay any costs incurred by respondents in the preparation and
submission of a Proposal. This solicitation does not obligate the City of Auburn to accept or contract
for any expressed or implied services. Furthermore, the City of Auburn reserves the right to award
the contract to the next most qualified Consultant if the selected Consultant does not execute a
contract within thirty (30) days after the award of the proposal.
Persons with disabilities may request this information be prepared and supplied in alternative forms by
calling 253-931-4013.
The City of Auburn does not discriminate on the grounds of race, color, religion, national origin, sex,
sexual orientation, age or handicap in consideration for a project award.
Dates of publication in the Seattle Daily Journal of Commerce, January 8, 2013 and January 15,
2013.
Dates of publication in the Seattle Times, January 8, 2013 and January 15, 2013.