The City of Auburn Fee Schedule authorizes Utility Connection Fees. The intent of this handout
is to provide an informative summary of selected sections of the Fee Schedule. This document
is intended to aid in understanding Utility Connection Fees, and is not intended to replace or
supersede any portion of the Fee Schedule or the Auburn City Code. Also included in this
handout are the monthly rates as of January 1, 2013. These rates are for reference only and
are subject to change.
What are Utility Connection Fees?
Utility Connection Fees are fees on development used to pay for its proportionate share
of the capital costs and installation of the City's utility infrastructure. The City of Auburn
collects Utility Connection fees for the Water, Sanitary Sewer, and Storm Drainage
Utilities. The following pages of this handout contain the fee schedules for the different
utility connection fees.
• Utility Connection Fees are charged for new construction and/or when upgrading an
existing service.
When Are Utility Connection Fees paid?
• The City usually collects Utility Connection Fees at the time a building permit is issued.
If a change in the service does not require a building permit, Utility Connection Fees will
then be collected at the issuance of the associated permit. In cases where a facility
extension is included in the building process, the permit will not be issued until after the
new extension has been accepted by the City.
What do Utility Connection Fees consist of?
Utility Connection fees may consist of several different fees.
• The Permit Fee includes administrative costs and inspection time and the cost of
material (in the case of a water meter for example).
The System Development Charge is a charge imposed on new customers, or existing
customers revising the use of their property, in recognition of the previous investment of
the City and it's customers in the utility system.
A Utility Payback Fee is an assessment recorded against the property. This fee was
established to reimburse developers that installed utility infrastructure that benefits other
parcels. Parcel(s) that benefit from said utilities must pay their pro-rata share prior to
connection to the utility.
The Charge in Lieu of Assessment is another type of fee, which is charged to property
not previously assessed for utility lines abutting their property.
Property located outside the city limits installing utility lines may also be charged a
County Right-of-Way Permit Fee. This fee is for a permit to dig within the county right-
of-way and will be obtained by the City.
STORM SEWER CONNECTION CHARGES
Connection fees are comprised of a Permit Fee and the System Development Charge as
foll ows:
STORM PERMIT FEE
Permit Level** Permit Fee
Level 1 $210.00
Level2 $400.00
Level 3 Base Fee + the Cumulative Additional Fees as indicated be low:
• Base Fee= $1,440.00 for up to 10,000 SF of disturbed
area
• Cumulative Additional Fee #1 = Base Fee+ $400.00 for
10,001 SF up to 43,560 SF (1 Acre) of disturbed area
• Cumulative Additional Fee #2 = Cumulative Additional
Fee #1 + $100.00 per Acre for each additional disturbed
Acre over 1 Acre
**Permit levels are determined as follows:
Level 1 permits are for all projects that
• are not located in a Critical Area and
• add or replace less than 2,000 square feet of impervious surface area;
and/or
• disturb less than 7,000 square feet of land.
Level 2 permits are for all projects that:
• add or replace 2,000 to 4,999 square feet of impervious surface area; or
• disturb 7,000 square feet or more of land.
Level 3 permits are for all projects that:
• add 5,000 square feet or more of impervious surface area, or
• convert % acres or more of native vegetation to lawn/landscaped area,
or
• convert 2.5 acres or more of native vegetation to pasture, or the new
plus replaced impervious surface area is 5,000 square feet or more and
the value of improvements exceeds 50% of the assessed value of
existing improvements.
SYSTEM DEVELOPMENT CHARGE (SOC)
Type System Development Charge
(SOC)
Single Family Residence & $1,162.00 per Parcel
Duplexes (on Individual Parcels)
Other Parcels $1,162.00 per ESU**
Sample 1: Single Family Residence Parcel that adds or replaces less than 2,000 SF and
disturbs less than 7,000 SF of land (level 1 permit).
Permit Fee
soc
Total***
$ 210
$11162
$1,372
Sample 2: Commercial\lndustrial Parcel
Total of 55,000 SF parcel (30,000 SF Building and 20,000 SF Parking Lot, and 5,000 SF
landscaping), therefore, there is 55,000 SF of disturbed area and 50,000 SF of new impervious
area:
Permit base fee
Add. 1
$ 1,440.00
$ 400.00 (Based on up to 43,560 SF of disturbed area)
Add. 2 $ 26.26 (Based on remaining 11 ,440 SF of disturbed area)
Total Permit Fee$
SDC***
1,866.26
$22,346.15
Total**** $2{212.41
Notes:
*
**
***
****
Based on one single-family residence or one duplex per parcel. More than one unit per
parcel will be charged at the Other Parcel rate.
E.S.U. -Equivalent Service Unit -A configuration of development of impervious
surfaces estimated to contribute an amount of runoff to the City's storm drainage system
which is approximately equal to that created by the average single family residential
parcel. One E.S.U. is equal to 2,600 square feet of impervious surface or any portion
thereof.
When calculating the total SOC a credit will be applied for the existing impervious area.
(Total SOC minus calculated SDC for existing impervious area using the definition of
impervious surface as given in ACC 13.41.01 0)
Check to see if any charges in lieu of assessment or payback charges are applicable.
ALL CONNECTION FEES AND SYSTEM DEVELOPMENT CHARGES ARE SUBJECT TO
CHANGE.
SANITARY SEWER CONNECTION CHARGES
Connection fees are comprised of a Permit Fee and the System Development Charge as
follows:
Permit Fee System Development Type Existing Sewer New Service Line Charge (SOC)
Stub Required
Single Family Parcel $88.00 $155.00 $850.00 Per Parcel
Other Parcels $88.00 $155.00 $850.00 Per RCE*
Sample 1: (This is strictly an example and not the set fee for this type of connection)
Single-family residential , side sewer stub present:
Permit Fee
soc .
Total**
$ 88
$ 850
$ 938
Sample 2: Commercial building with one side sewer connection and 1.5 RCE's* worth of
plumbing fixtures:
Permit Fee
soc
Total**
Notes:
$ 88
$ 1,275
$ 1,363
* Residential Customer Equivalent, Calculated using Metro Non-Residential Sewer Use
Certificate.
** Check to see if any Assessment Charges are Applicable.
ALL CONNECTION FEES AND SYSTEM DEVELOPMENT CHARGES ARE SUBJECT TO
CHANGE.
King County Capacity Charge:
Sanitary sewer connections made after January 1, 2013, will be required to pay a King County
Capital Improvements fee. The residential fee is $53.50 per month for 15 years and is billed
every six months by King County. Non-residential fees are determined by use. First payment is
due six months after the date of connection. No capacity charge is required for repairs or
replacement of existing sewer connections.
Questions should be addressed to King County: (206) 296-1450
WATER SERVICE CONNECTION CHARGES
Water Service Installation Permit Fee System
Meter Size Existing Water Water Service & Meter Box Development
(In Inches) Service & Meter Installed by City** Charge
Box* Paved Street Unpaved Street (SOC)
%"or less $212.00 $2,175.00 $1 ,170.00 $2,424.00
1" $280.00 $2,380.00 $1,475.00 $4,048.00
1-W' $450.00 $3,210.00 $2,305.00 $8,072.00
2" $560.00 $3,488.00 $2,588.00 $12,920.00
3" (Actual Cost) (Actual Cost) (Actual Cost) $24,240.00
4" (Actual Cost) (Actual Cost) (Actual Cost) $40,408.00
6" (Actual Cost) (Actual Cost) (Actual Cost) $80,792.00
8" (Actual Cost) (Actual Cost) (Actual Cost) $129,280.00
10" (Actual Cost) (Actual Cost) (Actual Cost) $135,971.00
* Installation of a water meter done by the City and the service either already exists or has
been installed by the developer.
** Installation of the entire water service is done by the City.
Sample 1: Single-family residence 3/4" meter water service and meter box required:
Permit Fee $ 2,175.00
soc $ 2.424.00
Total* $ 4,599.00
Sample 2: Commercial warehouse with a 1-Y2" domestic meter, a 1" irrigation meter and
fireline. Water Services and meter boxes installed by the contractor.
1-W' Domestic Permit
1" Irrigation Permit
SOC (for domestic)
SOC (for irrigation)
Fireline Connection Permit
Total*
Notes:
$ 450.00
$ 280.00
$ 8,072.00
$ 4,048.00
$ 335.00
$ 13,187.00
*Check to see if any charges in lieu of assessment or payback charges are applicable.
ALL CONNECTION FEES AND SYSTEM DEVELOPMENT CHARGES ARE SUBJECT TO
CHANGE.
MONTHLY RATES
STORM
Customer Classes Base Rate ESU Rate
per Month per Month
Single Family Residential $17.41 N/A
Non-Single Family (NSF) $10.83 $13.85/ESU
NSF w/Detention $10.83 $11 .13/ESU
NSF w/Retention $10.83 $6.88/ESU
NSF w!Water Quality Treatment $10.83 $8.32/ESU
NSF w/Detention and Water Quality Treatment $10.83 $6.29/ESU
NSF w/Retention and Water Quality Treatment $10.83 $3.94/ESU
The monthly charge for non-single family parcels shall be based upon the following formula:
BASE RATE+ (TNESU x ESU RATE)= Monthly Storm Charge
TNESU =Total number of equivalent service units contained on the parcel
All rates effective as of January 1, 2013.
SANITARY SEWER
Customer Classes Monthly Rate*
Single Family Residential Inside City Limits $21 .02
Single Family Residential Outside City Limits $31 .53
Non-Single Family Inside City Limits
Rate for first 750 cubic feet of water used $21 .02
Rate for each additional 100 cubic feet $2.12
Non-Single Family Outside City Limits
Rate for first 750 cubic feet of water used $31 .53
Rate for each additional 100 cubic feet $3.18
All rates effective as of January 1, 2013. *Does not include King County service charge.
WATER
Customer Classes Base Rate Quantity Charge per
per Month 100 cubic feet (ccf)
$2.61 0-7ccf
Single Family Residential $13.17 $3.20 7.01 -15 ccf
$3.63 > 15 ccf
Multi-Family Residential $39.25 $2.74
Commercial $39.25 $3.12
Manufacturing/Industrial $39.25 $2.54
Schools $39.25 $2.96
City Accounts $39.25 $3.63
Irrigation Only $13.24 $3.63
All rates effective as of January 1, 2013. For Customers outside the City limits, all charges will