HomeMy WebLinkAbout5237 RESOLUTION NO. 5 2 3 7
A RESOLUTION OF THE CITY COUNCIL OF THE
CITY OF AUBURN, WASHINGTON, APPROVING THE
2017-2022 TRANSPORTATION IMPROVEMENT
PROGRAM OF THE CITY OF AUBURN PURSUANT
-- TO CHAPTER 35.77 OF THE REVISED CODE OF
WASHINGTON (RCW)
WHEREAS; Section 35.77.010 RCW requires that the legislative body of
each City prepare and adopt a comprehensive Transportation Improvement
Program (TIP) for the ensuing six years, but only after conducting a public
hearing; and
WHEREAS, a public hearing to review the 2017-2022 Transportation
Improvement Program for the City of Auburn was held on June 20, 2016 at the
hour of 7:00 p.m. in the Council Chambers of the Auburn City Hall, pursuant to
notice published in the legal newspaper of the City of Auburn on June 09, 2016.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF AUBURN,
WASHINGTON, HEREBY RESOLVES as follows:
Section 1. The streets within the corporate limits of the City of Auburn to
be improved as a part of the City of Auburn 2017-2022 Transportation
Improvement Program, are identified on the document attached hereto, marked
as Exhibit "A," and incorporated herein by reference, with improvements to be as
described therein.
Section 2. That the City Engineer of the City of Auburn is hereby directed
to forward a certified copy of this Resolution to the Washington State Department
of Transportation for filing not more than thirty (30) days after the adoption of this
Resolution.
Section 3. That the Mayor is hereby authorized to implement such
administrative procedures as may be necessary to carry out the directions of this
legislation.
Resolution No. 5237
June 15, 2016
Page 1
Section 4. That this Resolution shall take effect and be in full force upon
passage and signatures hereon.
DATED this6 day of 9-A4A-4
.j , 2016
CITY OF AUBURN
NANCY BA US, OO iW
ATTEST:
Danielle E. Daskam, City Clerk
APP" • ED+S TO FORM:
94 ft--• 41(
.niel B. Heid; City 'ttorney
Resolution No. 5237
June 15, 2016
Page 2
Ho4, *
B�Ur = :N
��� O�ETHAN YOU �MAGINE.O
2017-2022
Transportation Improvement
Program
A_
• I,
r) (�- i=may` it \ i�
-ate .. 4,-_,,,�I r asi- .I ...., , tf ,„ �•,. _fi w
r . jam_ - rr= „41 , ' ,Ilk \ sr ,�ri
s _ /Y 1 i t , -.'L> mkt 5 .�!
f C
oma\
ams
Ai.215? i
Community Development and Public Works
Department
Transportation Section
Adopted June 20, 2016 by Resolution 5237
City of Auburn Transportation Improvement Program
AVM !!) agity IP° 49."
t 11111
THAN YOU
t‘O IMAGI Nt,O
Transportation Improvement'
Program
20172,022
Adopted by Auburn City Council
June 20, 2016
City of Auburn
25 West Main Street
Auburn, WA 98001
(253)-931-3010
www.auburnwa.gov
City of Auburn Transportation Improvement Program
41 mc 0010::_
Aj—Ta
;sae°
1111 Oft
in
7100.17,..aintle THAN YOU
SOS' MAGI NES
Cover Photos: Left: Auburn Way South Improvements, Right: D St SE Reconstruction
City of Auburn Transportation Improvement Program
iii
City of Auburn Transportation Improvement Program
iv
City of Auburn Transportation Improvement Program
Table of Contents
Executive Summary 1
Introduction 1
Projects & Financing Plan Summary 3
Financial Constraint & Fund Balance Summary 15
Auburn Way Corridor (TIP# 3) 17
I Street NE Corridor (TIP# 4) 18
M Street Underpass (TIP# 5) 19
S 272nd/277th Street (TIP# 6) 20
A St NW, Phase 2 (TIP# 8) --- 21
AWS, Hemlock to Academy (TIP# 9) 22
M Street NE (TIP# 11) 23
.................... ..
Grade-Separated Crossing of BNSF Yard (TIP# 12) 24
8th Street NE Widening (TIP# 15) _ 25
49th Street NE (TIP# 16) 26
46th PI S Realignment (TIP# 25) 27
Neighborhood Traffic Safety Program(TIP# 33) 28
124th Ave SE Corridor Improvements, Phase 2 (TIP#40) 29
R Street Bypass (TIP#41) 30
SE 320th Street Corridor Improvements (TIP# 42) 31
AWS (SR-164) Corridor Safety Improvements (TIP#43) 32
West Valley Highway Improvements (15th NW to W Main St) (TIP#49) 33
M St SE Storm Improvements (TIP# 58) 34
Auburn RGC Access Improvements (TIP# 59) 35
M Street SE Corridor (TIP# 60) 36
AWS Bypass (TIP# 61) 37
AWS Streetscape Improvements (TIP#62) 38
38
Lea Hill Rd Segment 1 (TIP# 64) 39
Lea Hill Rd Segment 2 (TIP# 65) 40
Lea Hill Rd Segment 3 (TIP# 66) 41
• West Valley Highway Improvements (SR-18 to 15th SW) (TIP# 72) 42
Stewart Road (Lake Tapps Parkway) (TIP# 73) ........................................ ........ 43
R St SE Corridor Extension (TIP# 74) 44
Intersection Signal & ITS Improvements 45
A St Traffic Signal Improvements (TIP# 2) .......... . ................................. . ........ 45
M Street SE/12th Street SE Traffic Signal (TIP# 14) 46
Harvey Rd NE/8th St NE Intersection Improvements (TIP# 17) 47
M St SE & 29th St SE Intersection Safety Improvements (TIP# 18) ........: ........ 48
Auburn Way North/1st Street NE Signal Improvements (TIP# 19) 49
R St SE & 21st St SE Intersection Safety Improvements (TIP# 20) 50
Main Street Signal Upgrades (TIP# 21) 51
Traffic Signal Improvements (TIP# 34) 52
C St SW & 15`h St SW Intersection (TIP# 38) 53
124th Ave SE & Se 320th St Intersection Improvements (TIP# 39) - 54
124th Ave SE & SE 284th St Intersection Safety (TIP#•45) 55
v
City IV-Auburn Transportation Improvement Program
ITS Dynamic Message Signs (TIP# 50) 56
Lake Tapps Parkway ITS Expansion (TIP# 51) 57
A St SE & Lakeland Hills Way Intersection (TIP# 52) 58
AWS/12th Street SE Intersection Improvements (TIP# 53) 59
29th St SE/R St SE Intersection Improvements (TIP# 63) 60
37th Street & A St SE Traffic Signal Safety Improvement (TIP# 68) 61
22nd Street NE & 1St NE Intersection (TIP# 69) 62
Non-Motorized & Transit Improvements 63
F St SE Non-Motorized Improvements (TIP#10) 63
Riverwalk Drive SE Non-Motorized Improvements (TIP# 23) 64
Academy Drive Multi-Use Trail (TIP# 24) 65
Metro Shuttle (TIP# 26) . .. .. . .. ...... .._ 66
Citywide Pedestrian Accessibility Program (TIP# 30) 67
Citywide Arterial Bicycle and Safety Improvements (TIP# 31) 68
Citywide ADA & Sidewalk Improvements (TIP# 32) 69
Downtown Transit Access Improvements (TIP#44) 70
Auburn Way South Sidewalk Improvements (TIP# 55) 71
Evergreen Heights Safe Routes to School Improvements (TIP# 56) 72
BNSF/A St SE Pedestrian Crossing (TIP# 67) 73
Preliminary Engineering & Miscellaneous Projects.::..::.::::::::::::.:.::...::...:: 75
A Street NW, Phase 1 (TIP# 1) 75
Mohawk Plastics Site Mitigation (TIP# 13) 76
A Street SE Safety Improvements Study (TIP# 27)... .. . . .. ........ 77
S 272"d/277th St - Monitoring (TIP# 29) 78
Kersey Way SE Corridor Study (TIP# 54) 79
Pavement Preservation Projects ... ...... ....... ...... . ..... 81
15"i St SW Reconstruction (TIP# 7) 81
Lake Tapps Parkway Preservation (TIP#22) 82
Annual Bridge Structure Preservation (TIP# 28) 83
Arterial Preservation Program (TIP# 35) 84
Arterial Crack Seal Program (TIP# 36) 85
Local Street Improvement Program (TIP# 37) 86
Auburn Way North Preservation Ph 2 (TIP# 46) 87
Auburn Way North Preservation Ph 3 (TIP# 47)...........................: .::: ::::::::::::::::::::.....v;.v :..:.: 88
A ST SE Preservation (TIP#48) 89
Arterial Bridge Deck Rehabilitation (TIP# 57) 90
Auburn Way North Preservation (TIP# 70) 91
15th St NW/NE Preservation (TIP# 71) 92
Project Summary Sheet Appendix A
2017-2022 TIP Project Map Appendix B
vi
City of Auburn Transportation Improvement Program
EXECUTIVE SUMMARY
The Transportation Improvement Program (TIP) is a 6-year plan for transportation
improvements that support the City of Auburns current and future growth. The TIP along with
the Comprehensive Transportation Plan (CTP) serve as source documents for the City of
Auburn Capital Facilities Plan which is a Comprehensive Plan element required by
Washington's Growth Management Act. The program may be revised at any time by a majority
of the City Council after a public hearing.
INTRODUCTION
Purpose
The purpose of the TIP is to identify priority transportation projects and assure that the city has
advanced plans as a guide in carrying out a coordinated transportation program. There are
always more projects than available revenues. Therefore, a primary objective of the TIP is to
integrate the two to produce a comprehensive, realistic program for the orderly development
and maintenance of our street system. Projects are required to be included in the TIP in order
to be eligible for state and federal grants. Grant funding for projects listed may not yet be
secured.
Statutory Requirements
Six Year Transportation Improvement Program - RCW 35.77.010 requires that each city
prepare and adopt a comprehensive transportation improvement program for the ensuing six
calendar years consistent with its CTP. This six-year TIP shall be filed with the Secretary of the
Washington State Department of Transportation (WSDOT) each year within 30 days of
adoption.
Projects of Regional Significance - RCW 35.77.010 also requires each city to specifically set
forth those projects and programs of regional significance for inclusion in the transportation
improvement program for that region. The 2017-2022 TIP includes three projects of regional
significance:
TIP Project Number Project Title
TIP# 6 S 272nd/277th Street Corridor
TIP# 9 AWS Corridor Imps (Hemlock to Academy)
TIP# 61 SR-18 to Auburn Way South (SR-164) Bypass
Executive Summary & Introduction 1
City of Auburn Transportation Improvement Program
Methodology
Annual updates of the TIP begins with developing a revenue forecast to provide a reasonable
estimate of funding available to accomplish the transportation improvement needs. Since the
desire to construct transportation improvements typically exceeds the available forecast
revenue, it is necessary to establish some method of prioritizing the needs.
Transportation needs are identified by examining the latest information concerning level of
service, safety and accident history, growth trends, traffic studies and the City's adopted CTP.
The likelihood of receiving federal or state grants for various improvements, community
interests and values are also considered. All of these factors yield a prioritized list of
transportation improvements.
Projects are placed into one of the following categories;
• Roadway Improvements,
• Intersection, Signal & Intelligent Transportation System Improvements,
• Non-Motorized & Transit Improvements,
• Preliminary Engineering & Miscellaneous Projects, and
• Roadway Preservation Projects.
Each project is identified as a Capacity or Non-capacity improvement and those that lay within
the limits of a defined Arterial LOS Corridor per with Table 2-2 of the City's CTP are identified
accordingly. Capacity projects from the 6-year plan are incorporated into the CTP as Group A
projects. Longer term capacity projects are listed in the CPT as Group B Projects.
Detailed project costs and funding sources are identified and provided for each project listed in
the proposed TIP. The prioritized list is then financially constrained in the first three years to
reflect the financial projections to yield the six-year Transportation Improvement Program. After
completing all reviews and compiling the document, staff makes final recommendations to the
Planning and Community Development Committee and City Council for approval.
2 Executive Summary & Introduction
City ofAuburn Transportation Improvement Program
Projects & Financing Plan Summary
TIP# Roadway Projects 2017 2018 2019 2020 2021 2022 Total
1 Auburn Way Corridor(4th St NE to 4th St SE)
Capital Costs - - - 818,700 3,000,000 - 3,818,700
Funding Sources:
Unrestricted Street Revenue - - - 110,000 600,000 - 710,000
Unsecured.Grant - - - 708,700 2,400,000 - 3,108,700
Traffic Impact Fees_ _ _ _ _ _ -_ _ _ - - - - _
4 I Street NE Corridor(45th St NE to S 277th St)
Capital Costs - - - 6,760,000 - - 6,760,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - - - - - -
Traffic Impact Fees - - - - - - -
Other(Development) - - - 6,760,000 - - 6,760,000
¢ "M Street Underpass 13rd St SE to 8th St SEI -
Capital Costs 130,080 129,500 128,920 128,350 128,000 127,500 772;350
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Secured State Grant - - - ., - - -
Traffic Impact Fees 130,080 129,500 128.920 128,350 128,000 127,500 772,350
Traffic Mitigation Fees - - - - - - -
PWTFL - - - - - - -
Other(Agencies) - - - - - -
6 S 272nd/277th Street Corridor
Capital Costs 200.000 - - - - - 200,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Secured Fed&State Grants - - - - - - -
Traffic Impact Fees - - - - - - -
Other(Development) - - - - - - -
Other(105 Fund) 200.000 - - - - - 200,000
' 8 A Stroot NW,Phase 2 '.
Capital Costs: - - - 3,000,000 - - 3,000,000
Funding Sources:
Unrestricted.Street Revenue - - - - - - -
Unsecured Grant - - - - - - -
Traffic Impact Fees - - - - - - -
Other(Development) - - - 3.000,000 - - 3,000,000 .
9 Auburn Way S(Hemlock to Academy)
Capital Costs: 100,000 - - 2,000.000 6,350,000 10,000,000 18,450,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - - 1,720,000 4,580,000 8,650,000 14,950,000
Traffic Impact Fees 50,000 - - 140,000 385,000 675,000 1,250,000
Other(MIT) 50.000 - - 140,000 1,385.000 675,000 2,250,000
" Z M Street NE(E MainSt to 4th-St NE[
CapitalCosts - 50,000 350,000 1,250,000 - - - 1,650,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - 280.000 1,000,000 - - - 1,280,000
Traffic Impact Fees .50,000 70,000 250.000. - - - 370,000
Projects & Financing Plan Summary 3
City of Auburn Transportation Improvement Program
TIP* Roadway Projects 2017 2018 2019 2020 2021 2022 Total
12 Grade-Separated Crossing of BNSF RaiNard
Capital Costs - - - - - 1,125,000 1,125,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - - - - - -
Traffic Impact Fees - - - - - -
Other(Development) - - - - - 1,125,000 1,125,000
15 8th Street NE Widening(Pike St to R St NEI
Capital Costs - - 450,000 1,000,000 - - 1,450,000
Funding Sourcos:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - 360,000 800,000 - - 1,160,000
Traffic Impact Fees - - 90.000 200,000 - - 290,000
16 49th Stroot NE(Auburn Way N to I St NEI
Capital Costs - - - 850,000 2,500,000 - 3,350,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - - - - - -
Traffic Impact Fees - - - - - - -
Other(Development) - - - 850,000 2,500,000 - 3,350,000
26 46th Place S Roalienmont
Capital Costs - - - - 825,000 - 825,000
Funding Sourcos:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - - - 575,000 - 575,000
Traffic Impact Fees - - - - 250,000 - 250,000
Other - - - - - - -
13 -Neighborhood Traffic Calming Improvements
Cipltal Coats 100,000 150,000 150,000 150,000 150,000 150.000 850,000
Funding Sources:
Cap.Imp.Fund Balance - - - - - - -
Unsecured Grant - - - - - - -
REET 2 100,000 150,000 150,000 150,000 150,000 150,000 850,000
_ _ Other - -- - - - - -
' 40 124th Avonuo SE Corridor Improvements(SE 312th to SE 318th(
Capital Costs - - 400,000 1,100,000 2,500,000 - 4,000,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - 300,000 880,000 2.000,000 - 3,180,000
Traffic Impact Fees - - 100,000 220,000 500.000 - 820.000
41 R Street Bypass
Capital Costs - - - - - 650,000 650,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - - - - - -
Traffic Impact Fees - - - - - 150,000 150,000
Other(Development) - - - - - 500,000 500,000
- 42 SE 320th Stroot Corridor Improvomonts 1116th-Avo SE to122nd AvoSEI - -
CapltalCoets - - - - 600,000 662.500 3,281,600 - 4,544,100
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - 480,000 530,000 2,953,440 - 3,963,440
Traffic Impact Fees - - 120,000 132,500 328,160 - 580,660
4 Projects & Financing Plan Summary
City of Auburn Transportation Improvement Program
TIP# Roadway Projects 2017 2018 2019 2020 2021 2022 Total
bA Auburn Way S(SR-164)Corridor Safety Improvements(Muckloshoot Plaza to Dogwood]
Capital Costs 20,000 - - - - - 20.000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Secured Federal Grant - - - - - - -
Traffic Impact Fees 20,000 - - - - - 20,000
Other(WSDOT) - - - - - - -
49 W Valley Highway Improvements(15th Street NW to W Main Stroet)
Capital Costs - - 100.000 600,000 3,000,000 - 3,700,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - - 480,000 2,400,000 - 2,880,000
Traffic Impact Fees - - 100,000 120,000 600,000 - 820,000
58 M ST.SE Storm Improymonts
Capital Costs 175,000 - - - - - 175,000
Funding Sources:
Unrestricted Street Revenue 125,000 - - - - - 125,000
Unsecured State Grant - - - - - - -
Other(Sidewalk Imp Funds) - - - - - - -
Other(105 Funds) 50,000 - - - - - 50,000
59 Regional Growth Center Access Improvements
Capital Costs - 500.000 580,000 3,900,000 - - 4,980,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - 400,000 464,000 3,120,000 - - 3,984,000
Traffic Impact Fees - 100.000 116,000 780,000 - - 996,000
Other - - - - - - - _ -
60 M Street SE Corridor(8th St SE to AWS(- -
CapitalCosts - - - 1.925,000 4,750,000 - 6,675,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - - 925,000 3,750,000 - 4,675,000
Traffic Impact Fees - - - 750,000 750.000 - 1,500,000
. Other(Development) _ _ _ - - - 250,000 250.000 - 500,000
61 Auburn.Way S'6ypass
Capital Costs - - - - 5,000,000 10,000,000 15,000,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - - - - - -
Traffic Impact Fees - - - - - - -
Other(WSDOT) - - - . 1,500,000 3,500,000 5,000,000
Other(Development) - - - - 3.500.000 6.500.000 10,000,000
' 62 Aubern Way S Strootscapo ImaroYements(SR-18 to M St SE)
Capital Costs - - - 1,950,000 2,800,000 - 4,750,000
Funding Sources:
Unrestricted.Street Revenue - - - 200,000 200,000 - 400,000
Unsecured Grant - - - 1,750,000 2,6.00,000 - 4,350,000
Traffic Impact Fees - - - - - - -
. Other _ - - - - -
64 'Loa Hill Road Segment 1 IR St NE to 105th PI SEj
Capital Casts 100.000 - - 2,450,000 10,000,000 - 12,550,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - 1,950,000 8,000,000 - 9,950,000
Traffic Impact Fees 100,000 - - 500,000 2.000,000 - 2,600,000
Projects & Financing Plan Summary 5
City of Auburn Transportation Improvement Program
TIP* Roadway Projects 2017 2018 2019 2020 2021 2022 Total
65 Lea Hill Road Segment 21105th PI SE to 112th Ave SEI
Capital Costs - - - - 3,500,000 8,500,000 12,000,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - - - 2,900,000 7,100.000 10,000,000
Traffic Impact Fees - - - - 600,000 1,400.000 2,000,000
66 Loa Hill Road Segment 31112th Ave SE to 124th Ave SEI
Capital Costs - - - - - 1,000,000 1,000,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - - - - 750,000 760,000
Traffic Impact Fees - - - - - 250.000 250,000
ZZ W Valley Highway Improvements(SR-18 to 15th St SWI
Capital Costs - 100,000 500,000 2,500.000 - - 3,100,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - 400,000 2,000,000 - - 2,400,000
Traffic Impact Fees - 100.000 100.000 500.000 - - 700,000
73 Stewart Road,Lake Tibbs Parkway Corridor
Capital Costs - 100,000 - - - - 100,000
Funding Sources:
Unrestricted Street Revenue - 66,000 - - - - 66,000
Unsecured Grant - - - - - - -
Traffic Impact Fees - - - - - - -
Traffic Mitigation Fees - 34,000 - - - - 34,000 .
L R St SE Corridor Extengion
Capital Costs - - - - 2,000,000 8.000,000 10,000,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - - - - - -
Traffic Impact Fees - - - - - - -
Other(Development) - - - .. 2,000,000 8.000.000 10,000,000
Subtotal,Roadway Projects:
Capital Costs 875,080 1,329,500 4,158,920 29,794,550 49,784,600 39,552,500 125,495,150
Funding Sources
Unrestricted Street Revenue 125,000 66,000 - 310,000 800,000 - 1,301,000
Grants - 680,000 3,004,000 14.863,700 32,158,440 16,500.000 67,206,140
Traffic Impact Fees 350,080 399,500 '1,004,920 3,470,850 5,541,160 2,602,500 13,369,010
Traffic Mitigation Fees - 34,000 - - - - 34,000
REET 2 100,000 150,000 150,000 150,000 150,000 150,000 850,000
Other(WSDOT) - - - - 1,500,000 3.500,000 5,000,000
Other(Development) - - - 10.860,000 8,250,000 16,125,000 35,235,000
Other(Muckleshool Tribe) 50,000 - - 140,000 1,385,000 675,000 2,250,000
Other(Arterial Presery.Fund) 250.000 - - - - - 250,000
Total Funding 875,080 1,329,500 4,158,920 29,794,550 49,784,600 39,552,500 125,495,150
6 Projects & Financing Plan Summary
City ofAuburn Transportation Improvement Program
TIP# Intersection,Signal&ITS Protects 2017 2018 2019 2020 2021 2022 Total
2 A Street Traffic Signal Improvements
Capital Costs - - 125,000 900,000 - - 1,025,000
Funding Sources:
Unrestricted Street Revenue - - 125,000 250,000 - - 375.000
Unsecured Grant - - - 650,000 - - 650,000
Traffic Impact Fees - - - - - - -
Other(REET2). - - - - - - -
' 14 M Street SEA 12th"Street SE Traffic Signal. -
Capital Costs - - - 625,000 - .- 625,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - - 500.000 - - 600,000
Trac Impact Fees - - - - -
ffi - -
Other(Development) - - - 125.000 - - 125,000
3 Harvey Road&8th Street NE Intersection Improvements
Capital Costs 85,383 85,200 84.800 84,400 84,400 84.200 508,383
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - - - - - -
Traffic Impact Fees 85.383 85.200 84.800 84.400 84,400 84200 508;383
18 M Street SE&29th Street SE Intersection Improvements
Capital Costs - - - 400,000 - - 400,000
Funding Sources:
Unrestricted Street Revenue - - - 100,000 - - 100,000
Unsecured Grant - - - 300,000 - - 300,000
Traffic Impact Fees - - - - - - -
Other - - - - -
19 Auburn Way N&1st Street NE Signal Improvements
Capital Costs - 50,000 550,000 - - - 600,000
Funding Sources:
Unrestricted Street Revenue - 50,000 125,000 - - - 175,000
Unsecured Grant - - 425,000 - - - 425,000
Traffic Impact Fees - - - - - - -
18 .R Street SE 8'21st Street SE Intorsectlori Improvements - - - - - - - - . -_
Capital Costs - - - 800,000 - - 800,000
Funding Sources:
Unrestricted Street Revenue - - - 100,000 - - 100,000
Secured State Grant - - - 700,000 - - 700,000
Traffic Impact Fees - - - - - - -
Traffic Mitigation Fees - - - - - - - .
21 Downtown Traffic Signal Uonrado
Capital Costs 20,000 - - - - - 20,000
Funding Sources:
Unrestricted Street Revenue 20,000 - - - - - 20,000
Unsecured Grant - - - - - - -
Traffic Impact Fees - - - - - - -
Traffic Mitigation Fees - - - - - - -
34 Traffic Signal Improvements
Capital Costs 175.000 175,000 200,000 200.000 200.000 200,000 1,150,000
Funding Sources: . .
Cap. Imp.Fund Balance - - - - - - -
Unsecured Grant - - - - - - -
REET2 175,000 175,000 200.000 200,000 200,000 200.000 1,150,000
Projects & Financing Plan Summary 7
City of Auburn Transportation Improvement Program
TIPe Intersection,Signal BITS Projects 2017 2018 2019 2020 2021 2022 Total
38 C Street SW&15th Street SW Intersection Improvments
Capital Costs - - - 200,000 1.000.000 - 1,200,000
Funding Sources:
Unrestricted Streel Revenue - - - - - - -
Unsecured Grant - - - - 800.000 - 800,000
_Traffic Impact Fees - - - 200.000 200.000 - 400,000
12 124th Avenue SE&SE 320th Street Intersection Improvements
Capital Costs - - - 350,000 1,600,000 - 1,950,000
Funding Sources:
Unrestricted Street Revenue - - - 175,000 150,000 - 325,000
Unsecured Grant - - - - 1,200.000 - 1,200,000
Traffic Impact Fees - - - - - - -
Other(GRC) - - - 175,000 250,000 - 425,000
45 124th Avenue SE&SE 284th Street Intersection Safety Improvements
Capital Costs - - 100,000 600,000 - - 700,000
Funding Sdurces:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - - 450,000 - - 450,000
_
Traffic Impact Fees - - 100,000 150.000 - - 250,000
60 ITSDynamicMessage Signs
Capital Costs 100,000 150,000 150,000 150,000 150,000 - 700,000
Funding Sources:
Unrestricted.Street Revenue 100,000 30,000 30,000 30,000 30,000 - 220,000 I
Unsecured Grant - 120,000 120,000 120,000 120,000 - 480,000
Traffic Impact Fees - - - - - - -
Olher/MIT) - - - - - - .
51 Lake Tapes Parkway ITS Expansion
Capital Costs 900,000 - - - - - 900,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Secured Federal Grant - - - - - -
Unsecured Grant711,000 - - - - - 711,000
Traffic Impact Fees 189,000 - - - - - 189,000
62 A Street SE&Lakeland Hills Way SE Intersection Safety&Capacity Improvements
Capital Costs 25,000 - - - - - 25,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - - - - - -
Traffic Impact Fees 25,000 - - - - 25,000
63 Auburn Way S&12th Street Intersection Improvements
Capital Costs 150,000 - - - - - 150,000
Funding Sources:
Unrestricted Streel Revenue 150,000 - - - - - 150,000
Unsecured Grant - - - - - - -
Traffic Impact Fees - - - - - - -
8 Projects & Financing Plan Summary
City of Auburn Transportation Improvement Program
TIPA.Intanssction,Signal&ITS Projects 2017 2018 . .2019 2020 2021 2022 Total
63 29th Stroot SE'S.R Street SE Intersection Improvements
Capital Costs - - 100,000 1,800,000 - - 1,900,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - - 1,300,000 - - 1,300,000 '
Traffic impact Fees - - 100,000 500,000 - - 600,000
g 37th Street SE S.A Street SE Traffic Signal Safety Improvement
Capital Costs 183,965 - - - - - 183,965
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Secured Federal Grant 183,965 - - - - - 183,965
Traffic Impact Fees - - - - - - -
Arterial Preserv.Fund(105) - - - - - - -
69 72nd Street NES.I St NE Intersection
Capital Costs - 1,175,000 - - - - 1,175,000
Funding Sources:
Unrestricted Street Revenue - - - - - .. -
Secured Slate Grant - - - - - -
Unsecured Grant - 940,000 - - - - 940,000
Traffic Impact Fees - 235,000 - - - - 235,000
Subtotal.Intersection,Signal&ITS Prolects:
Capital Costs 1,639,348 1,635,200 1,309,800 6,109,400 3,034,400 284,200 14,012,348
Funding Sources:
Unrestricted Street Revenue 270,000 80,000 280,000 655,000 180,000 - 1,465,000
Grants 894,965 1,060.000 545,000 4,020,000 2.120,000 - 8,639,965
Traffic Impact Fees 299,383 320,200 284,800 934,400 284,400 84,200 2,207,383
Traffic Mitigation Fees - - - - - - -
REET 2 175,000 175.000 200,000 200,000 200,000 200,000 1,150,000
Arterial Preserv.Fund(105) - - - - - - -
Other(Development) - - - 125,000 - - 125,000
Other(Green River College) - - - 175,000 250 ,000 - 425,000
Other(MIT) - - - - - - -
Total Funding 1,639,348 1,635,200 1,309,800 6,109,400 3,034,400 284,200 14,012,348
Projects & Financing Plan Summary 9
,
City of Auburn Transportation Improvement Program
TIP: Non-Motorized&Transit Projects 2017 2018 2019 2020 2021 2022 Total
10 F Street SE Non-Motorized Improvements
Capital Costs 40,000 2,502,000 - - - - 2,542,000
Funding Sources:
Unrestricted Street Revenue - 150,000 - - - - 150,000
Secured Grant 40,000 - - - - - 40,000
Traffic Impact Fees - 190,000 - - - - 190,000
Unsecured Grant - 2,162,000 - - - - 2,162,000
23 Riverwalk Drive SE Non-Motorized Improvements
Capltal Costs - 250.000 1.500.000 - - - 1,750,000
Funding Sources:
Unrestricted Street Revenue - 125,000 125,000 - - - 250,000
Unsecured Grant - - 1,250,000 - - - 1,250,000
Traffic Impact Fees - - - - - - -
- Other(MIT) - 125.000. 125,000 - - _ .250,000.
24 Academy Drive Multi-Use Trail
Capital Casts - - - 425,000 425.000 - 850,000
Funding Sources:.
Unrestricted Street Revenue - - - 42.500 42.500 - 85,000
Unsecured Grant - - - 382,500 382.500 - 765,000
Traffic Impact Fees - - - - - - -
26 METRO Shuttle: Lakeland Hills Shuttle
Capital Costs 260.000 260,000 280,000 280,000 280,000 280,000 1,640,000
Funding Sources:
Unrestricted Street Revenue 260,000 260,000 280.000 280,000 280,000 280,000 1,640,000
Unsecured Grant - - - - - - -
Traffic Impact Fees - - - - - - -
30 Citywide Pedestrian Accessibility and Safety Program
Capital Costs 100,000 100,000 100,000 100,000 100,000 100,000 600,000
Funding Sources:
Unrestricted Street Revenue 100,000 100,000 100,000 100,000 100,000 100,000 600,000
Unsecured Grant - - - - - - -
Traffic Impact Fees - - - - - - -
31 Citywide Arterial Bicycle and Safety Improvements - -
Capital Costs - - 100,000 - 100,000 - 100,000 300,000
Funding Sources:
Unrestricted Street Revenue - 100,000 - 100,000 - 100,000 300,000
Unsecured Grant - - - - - - -
Traffic Impact Fees - - - - - - -
32 Citywide ADA&Sidewalk Improvements Program
Capital Costs 200,000 200,000 200.000 200.000 200.000 200,000 1,200,000
Funding Sources:
Cap.Imp.Fund Balance - - - - - - -
Unsecured Grant - - - - - - -
REET2 200.000 200,000 200,000 200,000 200,000 200.000 1,200,000
I0 Projects & Financing Plan Summary
City of Auburn Transportation Improvement Program
TIP: Non-Motorized&Transit Projects 2017 2018 2019 2020 2021 2022 Total
a Downtown Transit Center Access Improvements
Capital Costs - - 250,000 - - - 250,000
Funding Sources:
Unrestricted Street Revenue - - 50.000 - - - 60,000
Unsecured Grant - - 200,000 - - - 200,00D
- Traffic Impact Fees _ _ - _ - - -. - - - ._.
55 Auburn Way South Sidewalk Improvements
Capital Costs - 260,000 1,190,000 - - - 1,450,000
Funding Sources:
Unrestricted Street Revenue - 52,000 238,000 - - - 290,000
Unsecured Grant - 208,000 952,000 - - - 1,160,000
Traffic Impact Fees - - - - - - -
Other(MIT) - - - - - - -
56 Evergreen Heights Safe Routes to School Improvements
Capital Costs 300,000 410,000 2,270,000 - - - 2,980,000 .
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant 200.000 300,000 1,420,000 - - - 1,920,000
Traffic Impact Fees 50.000 57,000 400,033 - - - 507,033
Other(Auburn Sch.District) 50,000 53,000 327,443 - - - 430,443
Other(Development) - - 122,524 - - - 122,624
67 BNSF/A St SE Peedestrian Crossing Improvements
Capital Costs - - - - 650,000 4,900,000 6,550,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - - - 400,000 3,500,0003,900,000
Traffic Impact Fees - - - - 250.000 1,400.000 1,650,000
Other 0 - - - - - -
Subtotal,Non-Motorized&Transit Projects:
Capital Costs 900,000 4,082,000 5,790,000 1,105,000 1,655,000 5,580,000 19,112,000
Funding Sources
Unrestricted Street Revenue 360,000 787,000 793,000 522,500 422,500 480,000 3,365,000
Grants 240,000 2,670.000 3,822,000 382.500 782.500 3.500,000 11,397,000
Traffic Impact Fees 50, 000 247600 400,033 - 250.000 1,40b.000 2,347,033
Other(Auburn School District) 50.000 53,000 327,443 - - - 430,443
Other(Development) - - 122,524 - - - 122,524
Other(MIT) - 125,000 125,000 - - - 260,000
Cap.Imp.Fund Balance - - - - - - -
REET2 200.000 200,000 200,000 200,000 200,000 200,000 1,200,000
Total Funding 900,000 4,082,000 5,790,000 1,105,000 1,655,000 5,580,000 19,112,000
Projects & Financing Plan Summary I I
City of Auburn Transportation Improvement Program
TIP# Pro.Eng.and Misc.Projects 2017 2018 2019 2020 2021 2022 Total
1 A Strout NW,Phase 1
Capital Costs 25.000 25.000 25,000 25,000 25,000 25,000 150,000
Funding Sources:
Unrestricted Street Revenue - - - - - - -
Secured Fed&Slate Grants - - - - - - -
Traffic Impact Fees 25.000 25.000 25,000 25,000 25,000 25.000 150,000
13 Mohawks Plastics Site Mitigation Prolect
Capital Costs 20,000 - - - - - 20,000
Funding Sources:
Unrestricted Cap.Imp.Funds - - - - - - -
Unsecured Grant - - - - - - -
Trafc Impact Fees 20.000 - - - - 20,000
27 A Street SE Safety Improvements'Study
Capital Costs 5,000 - - - - - 5,000
Funding Sources:
Unrestricted Street Revenue 5,000 - - - - - 5,000
Unsecured Grant - - - - - - -
Traffic Impact Fees - - - - - - -
29 S 272nd/277th Street St Corridor Environemental Monitoring
Capital Costs - 20,000 20,000 20,000 20,000 20,000 100,000
Funding Sources: ,
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - - - - - -
Traffic Impact Fees - 20,000 20,000 20,000 20,000 20,000 100,000
54 Kersey Way SE Corridor Study
Capital Costs 20,000 - - - 1.000,000 - 1,020,000
Funding Sources:
Unrestricted Street Revenue - - - - 200,000 - 200,000
Unsecured Grant - - - - 800,000 - 800,000
Traffic Mitigation Fees 20,000 - - - - - 20,000
Subtotal,Pro.Eng.and Misc.Projects:
Capital Costs 70,000 45,000 45,000 45,000 1,045,000 45,000 1,295,000
Funding Sources
Unrestricted Street Revenue 5,000 - - - 200,000 - 205,000
Grants - - - - 800,000 - 800,000
Traffic Impact Fees 45,000 45,000 45.000 45,000 45,000 45,000 270,000
Traffic Mitigation Fees 20,000 - - - - - 20,000
Total Funding 70,000 45,000 '45,000 45,000 1;045,000 - 45,000 1,295,000
12 Projects & Financing Plan Summary
City of Auburn Transportation Improvement Program
TIP# Roadway Preservation Projects 2017 2018 2019 2020 2021 2022 Total
7 15th Street SW Reconstruction
Capital Costs - - - - 375,000 3,000,000 3,375,000
Funding Sources:
Arterial Preservation Fund - - - - 75,000 500,000 575,000
Unsecured Grant - - - - 300,000 2.500.000 2,800,000
Other - - - - - - -
32 Lake Tapps Parkway Preservation(City Limit to Lakeland Hills Way)
Capital Casts 828,470 - - - - - 828,470
Funding Sources:
Arterial Preservation Fund 176,370 - - - - - 176,370
Secured Grant 652,100 - - - - - 652,100
Other - - - - - - -
28 Biannual Bridge Structure Preservation
Capital Costs - 50,000 - 50,000 - 50,000 150,000
Funding Sources:
Arterial Preservation Fund - 50,000 - 50,000 - 50,000 150,000
Unsecured Grant - - - - - - -
Other - - - - - - -
35 Annual Arterial Preservation Program
Capital Costs 500,000 ,900.000 836.720 1.017,560 1,800,000 1.800,000 6,854,280
Funding Sources:.
Arterial Preservation Fund 500.000 900,000 836,720 1,017,560 1,800.000 1,800,000 6,854,280 '
Unsecured Grant - - - - - - -
Other - - - - - - - .
36 Annual Arterial Crack Seal Program
Capital Costs 100,000 100,000 100,000 100.000 100,000 100,000 600,000
Funding Sources:
Arterial Preservation Fund 100,000 100,000 100,000 100,000 100,000 100,000 600,000
Unsecured Grant - - - - - - -
Other._ _ _ _ - - - - - - -
37 Local Streets Improvement Program
Capital Costs 2.550,000 2,550,000 1,750,000 1,750,000 1,750,000 1,750,000 12,100,000
Funding Sources:
Local SI Preservation Fund 500,000 500,000 - - - - 1,000,000
Transfer In(Utilities) 150,000 150,000 150,000 150,000 150,000 150,000 900,000
Sales Tax on Construction 1,900,000 1,900,000 1,600,000 1.600.000 1.600.000 1.600.000 10.200,000
46 Auburn Way North Preservation Phase 2
Capital Costs 120,000 1,508,000 - - - - 1,628,000
Funding Sources:
Arterial Preservation Fund 120,000 618,280 - - - - 738,260
Unsecured Grant - 889,720 - - - - 889,720
Other - - - - - - -
47 Auburn Way north Preservation Phase 3
Capital Costs - 222,440 1,727,840 - - - 1,950,280
Funding Sources:
Arterial Preservation Fund - 111,220 863,920 - - - 976,140
Unsecured Grant - 111,220 863,920 - - - 975,140
Other - - - - - - -
Projects & Financing Plan Summary 13
City of Auburn Transportation Improvement Program
TIP# Roadway Preservation Projects 2017 2018 2019 2020 2021 2022 Total
48 A St SE Preservation
Capital Costs - - 198.720 1,564,880 - .. 1,763,600
Funding Sources:
Arterial Preservation Fund - - 99,360 782.440 - - 881,800
Unsecured Grant - - 99,360 782.440 - - 881,800
Other - - - - - -
57 Arterial Bridge Deck Rehabilitation
Capital Costs - 100,000 100,000 100,000 100,000 100.000 500,000
Funding Sources:
Arterial Preservation Fund - 100,000 100,000 100,000 100,000 100,000 600,000
Unsecured Grant - - - - - - -
_ .Other _ _ ._._ _ __._ - - - - - - -
7Q BST NW Reconstruction
Capital Costs 1,470,000 - - - - - 1,470,000
Funding Sources:
Arterial Preservation Fund 1,470,000 - - - - - 1,470,000
Secured Grant - - - - - - -
Other - - - - - - -
" 71 15th Street NEINW Preservation(SR-167 to NE 8th Street)
Capital Costs 1,500,000 - - - - - 1,500,000 ,
Funding Sources:
Arterial Preservation Fund 750,000 - - - - - 760,000
Secured Grant 750,000 - - - - - 760,000
Other - - - - - - -
Subtotal.Preservation Proiects:
Capital Costs 7,068,470 5,430,440 4,713,280 4,582,440 4,125,000 6,800,000 32,719,630
Funding Sources
Arterial Preservation Fund 3.116,370 1,879,500 2,000,000 2,050,000 2,075.000 2,550,000 1.3,670,870
Grants 1,402,100 1,000,940 963,280 782,440 300,000 2,500,000 6,948,760
Local St Preservation Fund 2.550.000 2.550,000. 1,750.000 1.750.000 1.750.000 1.750,000_ 12,100,000
Total Funding 7,068,470 5,430,440 4,713,280 4,582,440 4,125,000 6,800,000 32,719,630
14 Projects & Financing Plan Summary
City of Auburn Transportation Improvement Program
Financial Constraint& Fund Balance Summary
PROJECT FINANCING SUMMARY: 2017 2018 2019 2020 2021 2022 Total
CAPITAL COSTS
Roadway Projects 875,080 1,329,500 4,158,920 29,794,550 49,784,600 39,552.500 125,495,150
Int.,Signal 8 ITS Projects 1,639,348 1,635,200 1,309,800 6,109,400 3.034,400 284,200 14,012,348
Non-Motorized Projects 900,000 4.082,000 5,790,000 1,105.000 1,655,000 5.586000 19,112,000
Prel.Eng.and Misc.Projects 70,000 45,000 45,000 45,000 1,045,000 45,000 1,295,000
Preservation Projects. 7.068,470 5,430,440 4,713,280 4,582,440 4,125,000 6.800.000 32,719,630
Total Costs 10,552,898 12;522,140 16,017,000 41,636,390 59,644,000 52,261,700 192,634,128
FUNDING SOURCES:
UnTestricted Street Revenue 760,000 933,000 1,073.000 1,487,500 1,602,500 480,000 6,336,000
Grants 2,537,065 5,410,940 8,334,280 20,048,640 36,160,940 22,500,000 94,991,865
Traffic Impact Fees 744,463 1,011,700 1,734,753 4,450,250 6,120,560 4,131,700 18,193,426
Traffic Mitigation Fees 20,000 34,000 - - - - 54,000
Local Street Pres.Fund 103 2,550,000 2,550600 1,750,000 1,750,000 1,750,000 1.750,000 12,100,000
Arterial Preservation Fund 105 3,366,370 1,879,500 2,000,000 2,050,000 2,075,000 2,550,000 13,920,870
Cap.Imp.Fund Balance - - - - - - -
REET2 475,000 525,000 550,000 550,000 550,000 550.000 3,200,000
Other(WSDOT) - - - - 1,500,000 3,500,000 6,000,000
Other(Development) - - 122,524 10.985.000 8,250,000 16,125,000 35,482,524
Other(Auburn School District) 50,000 53,000 327,443 - - - 430,443
Other(Muckleshoot Tribe) 50,000 125,000 125,000 140,000 1,385,000 675,000 2,500,000
Other(Green River College) - - - 175,000 250,000 - 425,000
Total Funding 10,652,898 12,522,140 16,017,000 41,636,390 59,644,000 52,261,700 192,634,128
Financial Constraint& Fund Balance Summary
2017 2018 2019 2020 2021 2022
Unrestricted Street Revenue 102
Beginning Fund Balance 1,340,000 1,155.000 797,000 304,000 (603,500) (1,621.000)
Forecast Annual Revenue 575,000 575,000 580,000 580,000 585.000 585.000
Project Expenses 760.000 933.000 1,073,000 1.487.500 1,602,500 480,000
End of Year Fund Balance 1.155.000 797.000 304.000 (603.500) (1,621.000) (1.516.000)
Traffic Impact Fees
Beginning Fund Balance 1,400,000 1,555,537 1,443,837 659,084 (2841,166) (7,961,726)
Forecast Annual Revenue 900,000 900,000 950,000 950,000 1,000,000 1.000,000
Project Expenses 744,463 1,011,700 1,734,753 4,450,250 6,120.560 4.131.700
End.of.Year.Fund.Balance 1,555837 1,443,837 659.084 (2,841,166) (7.961,726) _(11,093,426)
Traffic Mitigation Fees
Beginning Fund Balance 84,000 64,000 30,000 30,000 30.000 30,000
Forecast Annual Revenue - - - - - -
Project Expenses. 20.000. 34.000 - - - -
End of Year Fund Balance 64,000 30.000 30.000 30.000 30.000 30.000
Local Street Preservation Fund 103
Beginning Fund Balance 1;300,000 800,000 300,000 300,000 300,000 300,000
Forecast Annual Revenue 2,050,000 2,050.000 1,750.000 1,750.000 1,750,000 1,750,000
Project Expenses 2,550,000 2,550,000 1,750,000 1,750,000 1,750,000 1,750,000
Endlof Year Fund Balance 800,000 300.000 300,000 300.000 300,000 300,000
Arterial Preservation Fund 105
Beginning Fund Balance 1,540,000 73,630 94,130 94,130 44,130 69,130
Forecast Annual Revenue 1,900.000 1,900,000 2,000,000 2,000,000 2100,000 2,100,000
Project Expenses 3,366.370 1,879,500 2,000.000 2,050,000 2,075,000 2.550.000
End of Year Fund Balance 73,630 94,130 94,130 44.130 69,130 (380,870)
Grants
Secured Grants 1,442,100 - - - - -
Unsecured Grants 1.094.965 .6410.940 8.334.280 20.048,640 36,160,940 22.500,000
Projects & Financing Plan Summary 15
City of Auburn Transportation Improvement Program
ns SD .. . :,
* liji
,Do
THAN YOU ;1 GINEO
16 Projects & Financing Plan Summary
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP#'3
ARTERIAL STREET FUND(102)
Project Title: Auburn Way Corridor(4th St NE to 4th St SE) STIP#AUB-N/A
Project No: c409a0
Project Type: Non-Capacity
Project Manager: TBD LOS Corridor ID#2, 3
Description:
This project is based on a pre-design study to improve pedestrian accessibility, appearance, and link the downtown area along Auburn Way S between 4th Street NE and
4th Street SE. The project may include some pavement repairs. However,an overlay was completed as pad of the City's Arterial Pavement Preservation Program in
2007. Although this was considered•a temporary fix,the•scope has been modified to account for the pavement work. The project is approximately 0:5 miles long.
Progress Summary:
The pavement portion has been minimized due to the work completed in 2007 under the Arterial Pavement Preservation Program.
Future Impact on Operating Budget:
This project will have no impact on the operating budget for street maintenance.
Activity: 2016 YE Budget Forecast Project Cost
Funding.Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022. Beyond 2022 Total Project Cost
Unrestricted Street Revenue 78,251 - - - - 110,000 600,000 - - 788,251
Unsecured Grant - - - - - 708;700 2,400,000 - _ - 3,108,700
REET - - - - - - - - -
Traffic Impact Fees - - - - - - - - - -
Other Sources - - - - - - - - -
Total Funding Sources: 78,251 - - - - 818;700 3,000,000 - - 3,896,951
Capital Expenditures:
Design 78,251 - - - - 618,700 - - - 696,951
Right of Way - - - - - 200,000 - - - 200,000
Construction - - - - - - 3,000900 - - 3,000,000
Total Expenditures: 78,251 - - - - 818,700 3,000,000 - - 3,696,951
Roadway Improvement Projects 17
City of Auburn Transportation Improvement Program
Six Year Transportation ilmprovementPlan
TIP# 4
ARTERIAL STREET FUND(102)
Project Title: I Street NE Corridor(45th St NE to S 277th St) STIP#AUB-NIA
Project No: c415a0
Project Type: Capacity
Project Manager: TBD LOS Corridor ID#21
Description:
The final alignment of the !Street Corridor is being•analyzed as part of the Northeast Auburn Special Area Plan Environmental Impact Study. A portion of the ROW and
construction will be developer funded. The cross section will likely be a 5-lane arterial per the city's Comprehensive Plan.
Progress Summary:
This project is development driven. Prior expenditures were for design and construction of culvert crossing.
Future Impact on Operating.Budget:
The annual maintenance cost for this project is estimated to be$25,200.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - - - - - -
Unsecured Grant - - - - - - - - - -
Traffic Impact Fees 3,892 - - - - - - - - 3,892
Other Sources(Development) - - - - - 6,760,000 - - - 6,760,000
Other(Port of Seattle) - - - - - - - - - -
Total Funding Sources: 3,892 - - - - 6,760,000 - - - 6,763,892
Capital Expenditures:
Design 3,892 - - - - 460,000 - - - 463,892
Right of Way - - - - - 1,020,000 - - - 1,020,000
Construction - - - - - 5,280,000 - - - 5,280,000
Total Expenditures: 1,892 - - - - 6,760,000 - - - 6,763,892
Roadway improvement Projects 18
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP#5
ARTERIALSTREET FUND(102)
Project Title: M.Street Underpass•i3rd St SE to 8th St SE) STIP#AUB-N/A
Project No: c201a0
Project Type: Capacity
Project Manager: Ryan Vondrak LOS Corridor ID#6
Description:
Construction of a grade separated railroad crossing of M'Street.SE at the BNSF Stampede Pass tracks.
Progress Summary:
100% Design'Drawings and right of way acquisition were completed in 2011. Construction started in early 2012 and was completed in 2014. Project is now in PWTFL debt
repayment. Other Agencies are King County Metro Sewer, Port of Seattle, Port of Tacoma, and BNSF Railway
Future Impact on OperatingiBudget:
The annual maintenance cost for this project is estimated to be$21,827.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 ,Total Project Cost
Unrestricted Street Revenue - - - - - - - - - -
Secured Grants(Fed,State) 9,731,904 - - - - - - - - 9,731,904
REET2 1,140,000 - - - - - - - - 1,140,000
Traffic Impact Fees(Construction) 4,309,782 - - - - - - - - 4,309,782
Traffic Impact Fees(Debt Service) 279,423 130,654 130,080 129,500 128,920 128,350 128,000 127,500 2,244,500 3,426,927
Traffic Mitigation Fees 660,000 - - - - - - - - 660,000
PWTFL(30 years) 3,284,857 - - - - - - - - 3,284,857
Other(Agencies) 3,090,514 - - - - - - - - 3,090,514
22,217,057 130,654 130,080 129,500 128,920 128,350 128,000 127,500 2,244,500 22,359,127
Capital Expenditures:
Design 2,688,924 - - - - - - - - 2,688,924
Right of Way 3,358,443 - - - - - - - - 3,358,443
Construction 16,169,690 - - - - - - - 16,169,690
PWTF Debt Service 279,423 130,654 130,080 129,500 128,920 128,350 128,000 127,500 2,244,500 3,426,927
•22,217,057 130,654 130,080 129,500 128,920 128,350 128,000 127,500 2,244,500 22,359,127
Roadway Improvement Projects 19
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 6
ARTERIAL STREET FUND(102)
Project Title: S,272nd1277th.St Corridor Capacity& Non-Motorized Trail Improvements STIP#AUB-42
Project No: c222a0
Project Type: Capacity
Project Manager Ryan Vondrak LOS Corridor ID# 15
Description:
This project includes preliminary engineering, design, right of way acquisition and construction of major widening onS'277th Street, including the addition of three lanes, one
westbound and two eastbound, a Class 1 trail,and•storm improvements. The project extends from Auburn Way North toL Street NE, approximately 0.9 miles.
Progress Summary:
Federal design and ROW grant was secured in 2012 through PSRC and state construction grant was secured in 2013 through TIB. Design consultant was selected in 2013.
Envirionmental permitting and design are in process. Staff is coordinating with the City of Kent and King County to complete annexation of the roadway into the City of Auburn.
Auburn and Robertson,PropertiesGroup executed a project participating agreement in 2013. RPG is contributing funds and dedicating all necessary roadway frontage to the
City.
Future Impact on Operating Budget:
The annual maintenance costs for this project is estimated to be$27,250.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 •2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue 390,336 17,906 - - - - - - - 408,242
Secured Federal Grant 960,009 60,691 - - - - - - - 1,020,700
Secured State Grant 4,000,000 - - - - - - - 4,000,000
Traffic Impact Fees 3,719 931,800 - - - - - - - 935,519
Other(RPG) 1,300,000 1,000,000 - - - - - - - 2,300,000
Other(105 Fund) - - 200,000 - - - - - - 200,000
Total Funding Sources: 2,654,064 6,010,397 200,000 - - - - - - 8,864,461
Capital Expenditures:
Pm-Design 10,448 - - - - - - - - 10,448
Design 1,343,616 61,000 - - - - - - - 1,404,616
Right of Way 1,300,000 36,870 - - - - - - - 1,336,670
Construction - 5,912,527 200,000 - - - - - - 6,112,527
Total Expenditures: 2,654,064 6,010,397 200,000 - - - - - - 8,864,461
Roadway Improvement Projects 20
•
City of Auburn Transportation /improvement Program
Six Year Transportation Improvement Plan TIP# 8
ARTERIAL STREET FUND(102)
Project Title: A Street NW, Phase 2 (W Main-St to 3rd St NW) STIP#AUB-NIA
Project No: cpxxxx
Project Type: Capacity
Project Manager: TBDLOS Corridor ID# 18
Description:
Construct a multi-lane arteriaffrom W Main St to 3rd St NW. This project will improve the connection between A St NW, Phase 1 to the•Sound TransitStation and Central
Business District. Also this project will create a new connection between A St SW and A ST SE ro relieve major congestion and improve circulation. This project could•be
partially or fully funded by development and/or Soundtransits parking garage/access improvements..The project is approximately 0.2 miles long.
Progress Summary:
The parking garage constructed by the Auburn Regional Medical Center completed a portion of this project in 2009.
Future Impact on Operating Budget:
This project will have no impact on the operating budget for street maintenance.
Activity:, 2016.YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
•
Unrestricted Street Revenue - - - - - - - - - -
UnsecuredGranf - - - - - - - - - _
Traffic Impact Fees - - - - - - - - -
Other (Developer) 150,000 - - - - 3,000,000 - - - 3,150,000
Total Funding Sources:, 150,000 - - - 3,000,000 - - - 3,150,000
Capital Expenditures:
Design - - - - - 250,000 - - - 250,000
Right of Way - - - - - - - - _
Construction 150,000 - - - - 2,750.000 - - - 2,900,000
Total Expenditures: 150,000 - - - 3,000,000 - - - 3,150,000
Roadway Improvement Projects 21
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan
ARTERIAL STREET FUND (102) TIP# 9
Project Title: Auburn Way S Improvements (Hemlock St SEto Academy Dr SE) STIP#AUB-N/A
Project No: cpxxxx
Project Type: Capacity
Project Manager: TBD LOS CorridorID#4
Description:
Widen Auburn Way,S between Hemlock'St,SE and Academy Dr SE to accomodate two general purpose lanes in each direction, center turn lanes, access management
medians, U-turns, curb, gutter, sidewalk, illumination, transit stop improvements, new traffic signals, Intelligent Transportation Systems, streetscape and storm
improvements. The project length is approximately two miles.
Progress Summary:
Conceptual corridor plan will be coordinated with the MIT and WSDOT in 2016. This project is planned as a partnership between the City of Auburn and the MIT. Pre-
design effort will produce a project construction cost estimate..Major grant funding is expected to come from future federal competitions.This project will extend corridor
improvements along Aubum Way S completed under previous projects.
Future Impact on Operating Budget:
The annual maintenance cost for this project is estimated to be$25,000.
Activity: 2016 YE Budget, Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond.2022, Total Project Cost
Unrestricted Street Revenue - - - - - - - - - -
Unsecured Federal Grant - - - - - 1,720,000 4,580,000 8,650,000 16,435,000 31,385,000
Traffic Impact Fees - 100,000 50,000 - - 140,000 385,000 675,000 1,282,500 2,632;500
Other(MI7) - 100,000 50,000 - - 140,000 1;385,000 675,000 1,282,500 3,632,500
Total Funding Sources: - 200,000 100,000 - - 2,000,000 6,350,000 10,000,000 19,000,000 37,660,000
Capital Expenditures:
Pre-Design - 200.000 100,000 - - - - - - 300,000
Design - - - - - 2,000,000 3,000,000 - - 5,000,000
Right of Way - - - - - - 3,350,000 - - 3.350,000
Construction - - - - - - - 10,000,000 19,000,000 29.000,000
Total Expenditures: - 200,000' 100,000 - - 2,000,000 6,350,000 10,000,000 19,000,000 37,650,000
Roadway Improvement Projects 22
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 11
ARTERIAL STREET FUND(102)
Project Title: M Street NE (E Main St to 4th St NE) STIP#AUB-NIA
Project No: asbdl2
Project Type: Capacity
Project Manager: TBD • LOS Corridor ID#5
Description:
This project will construct a complete four-lane streetsection on M St NEbetween south of E Main St and 4th St NE.
Progress Summary:
Pre-design is planned to be completed during 2017 to refine project scope, alignment, and cost.
Future Impact on Operating Budget:
The annual maintenance cost for this project is estimated to be $1,500.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources:. Prior to 2016 Estimate 2017 2018 2019- - 2020 2021 2022- Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - - - - -
Unsecured State Grant - - - 280,000 1,000,000 - - - - 1',280,000
Traffic Impact Fees - - 50,000 70,000 250,000 - - - - 370,000
Other - - - - - - - - - -
Total Funding Sources: - - 50,000 350,000 1;250,000 - - - - 1,650,000
Capital Expenditures:
Pre-Design - - 50,000 - - - - - - 50,000
Design - - - 350,000 - - - - - 350,000
Right of Way - - - - 100,000 - - - - 100,000
Construction - - - - 1,150,000 - - - 1050,000
Total Expenditures:, - - 50,000 350,000 1,250,000 - - - - 1,650,000
Roadway Improvement,Projects 23
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan
TIP#12
ARTERIAL STREET FUND(102)
Project Title: Grade-Separated Crossing of BNSF'Railyard STIP#AUB-N/A
Project No: cpxxxx
Project Type: Capacity
Project Manager: TBD LOS Corridor ID# N/A
Description:
This project will grade-separate the crossing of the BNSF Railyard, either from•SR-18 to 6th Street SE or_from 15th Street SW to A Street SE. The first alternative would
realign the SR-18 eastbound ramp, grade separate the main north/south line and the Stampede Pass line, and connect to 6th Street SE. The second alternative would
provide a new corridor from 15th Street SW to A Street SE in the vicinity of 12th Street SE and 17th Street SE, either via an overpass or underpass of the BNSF Railyard.
This new east/west connection will improve access and circulation associated with the potential redevelopment of the BNSF yard as•an intermodal freight facility.
Progress Summary:
Future Impact on Operating Budget:
TBD
Activity: 2016 YE Budget, Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond.2022 Total Project Costi
Unrestricted Street Revenue - - - - - - - - - -
Unsecured Grant - - - - - - - - - -
Traffic Impact Fees - - - - - - - - - -
Other - - - - - - - 1,125,000 31,000,000 32,125,0001
Total Funding Sources: - - - - - - - 1,126,000 31,000,000 32,125,000
Capital Expenditures:
Design - - - - - - - 1,125,000 2,500,000 3,625,000
Right of Way - - - - - - - - 4,000,000 4,000,000
Construction - - - - - - 24,500,000 24,500,000•
Total Expenditures: - - - - - - - 1,125,000 31,000,000 32,125,000
Roadway Improvement Projects 24
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan
ARTERIAL STREET FUND(102) TIP#15
Project Title: 8th Street NE Widening (Pike St NE to R St NE) STIP#AUB-N/A
Project No: cpxxxx
Project Type: Capacity
Project Manager: TBD LOS Corridor ID# 19
Description: -
Widen 8th Street NE to extend the five-lane cross-section which currently exists to the west of Pike St NE to R St NE by providing an additional travel lane along the
south side of the roadway.This is a'planning level cost estimate.
Progress•Summary:
Future Impact on Operating Budget:
The annual maintenance cost for this project is estimated to be $600.
•
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond2022 Total Project Cost,
Unrestricted Street Revenue - - - - - - - - - _
Unsecured Grant - - - - 060,000 800,000 - - - 1,160,000
Traffic Impact Fees - - - - 90,000 200,000 - - - 290,0001
Other - - - - - - - - - -
Total Funding Sources: - - - - 450,000 1,000,000 - - - 1,460,000
Capital Expenditures:
Design - - - - 200,000 - - - - 200,000
Right of Way - - - - 250,000 - - - - 250,000'
Construction - - .. - - 1,000,000 - - 1,000,000
Total Expenditures: - - - - 450,000 1,000,000 - - - 1,450,000
Roadway Improvement Projects 25
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan
TIPtt 16
ARTERIAL STREET FUND(102)
Project Title: 49th Street-NE (Auburn Way N to I St NE) STIP#AUB-N/A
Project No: cpxxxx
Project Type: Capacity
Project Manager: TBD LOS:Corridor ID# 29
Description:
Construct a new east/west corridor from Auburn Way•N to I St NE. The existing 49th Street corridor.extends B St NW to the west. Thisproject also includes a traffic
signal at the intersection of Auburn Way North and 49th Street. This roadway was evaluated and recommended in the NE Special Planning Area. It is anticipated that
this will be constructed by future development. It is approximately 0.75 miles long.
Progress Summary:
Future Impact on Operating Budget:
The annual maintenance cost for this project is estimated to be $27,050.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond2022 Total Project Coat
Unrestricted Street Revenue - - - - - - - - - -
Unsecured Grant - - - - - - - - - -
Traffic Impact Fees - - - - - - - - - -
Other(Development) - - - - - 850,000 2,500,000 - - 3,350,000
Total Funding Sources: - - - - - 850,000 2,500,000 - - 3,350,000
Capital Expenditures:
Design - - - - - 250,000 - - - 250,000
Right of Way - - - - - 600,000 - - - 600,000
Construction - - - - - 2,500,000 - - 2,500,000
Total Expenditures: - - - - - 850,000 2;500,000 - - 3,360,000
Roadway Improvement Projects 26
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan
ARTERIAL STREET FUND(102) TIP# 25
Project Title: 46th Place•S Realignment STIP#AUB-N/A
Project No: cpxxxx
Project Type: Capacity
Project Manager: TBD LOS Corridor ID#•N/A
Description:
The project will realign 46th Place S to the south of S 321st Street.The realignment will move the 46th Place S intersection with S 321st Street approximately 350 feet to
the east of the current location. This will create two T-intersections (44th Avenue S and 46th Place S) in place of the existing four-leg intersection. The existing 46th Place
S will be dead-ended to the south of S 321st Street. The project will improve safety and traffic operations at the intersections.
Progress Summary:
Right-of-way for the realigned roadway will be dedicated as part ofan adjacent development project.
Future Impact on Operating Budget:
The annual maintenance cost for this project is estimated to be$1,750.
Activity: 2015 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - - - - - -
Unsecured Grant - - - .. - - 575,000 - - 575,000
Traffic Impact Fees - - - - - - 250,000 - - 250,000
Other - - - - - - - -
Total Funding Sources: - - - - - - 825,000 - - 825,000
Capital Expenditures:
Design - - - - - - 125,000 - - 125,000
Right of Way - - - - - - 25,000 - - 25,000
Construction - - - - - - 675,000 - - 675,000
Total Expenditures: - - - - - - 825,000 - - 825,000
Roadway improvement Projects 27
City of Auburn Transportation.Improvement Program
Six Year Transportation Improvement Plan TIP# 33
CAPITAL IMPROVEMENT FUND(328) .
Project Title: Neighborhood Traffic Safety Program STIP#AUB-NIA
Project No: cpxxxx
Project Type: Non-Capacity
Project Manager: TBD LOS Corridor ID# N/A
Description:
This project will implement neighborhood traffic calming strategies including street lighting, speed cushions, signage, speed radar signs, mini roundabouts, chicanes,
traffic circles; and other approved traffic calming devices. Projects will be selected annually based on neighborhood meetings, public surveys, and engineering studies:
Progress Summary:
Future Impact on Operating Budget:
This project will have no impact on the•operaling•budget for street maintenance.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 ' Total Project Cost
Fund Balance - - - - - - - - - -
Unsecured Grant - - - - - - - - - -
REET 2 - 194,000 100,000 150,000 150,000 150,000 150,000 150,000 - 1,044,000
Other - - - - - - - -
Total Funding Sources: - 194,000 100,000 150,000 150,000 150,000 150,000 150,000 - 1,044,000
Capital Expenditures:
Design - - - - - - - - - -
RightolWay - - - - - - - - - -
Construction - 194,000 100,000 150,000 150,000 150,000 150,000 150,000 - 1,044,000
Total Expenditures: - 194,000 100,000 160,000 160,000 150,000 150,000 150,000 - 1,044,000
•
Roadway Improvement Projects 28
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 40
ARTERIAL STREET FUND(102)
Project Title: 124th Ave SE Corridor Improvements (SE312th to SE 318th) STIP#AUB-NIA
Project No: cpxxxx
Project Type: Capacity
Project Manager: TBDLOS Corridor ID#23
Description:
This project will fund the design, right-of-way acquisition,and construction of a four-lane section with bicycle and pedestrian facilities on 124th Ave SE between SE 318th
St and SE 312th St, and improvements to the signalized intersection of SE 312th St and 124th Ave SE(including adding bike lanes, dual westbound left-turn lanes, dual
southbound through-lanes, a northbound right-turn pocket, ITS'improvements, and pedestrian safety improvements).
Progress Summary:
Phase 1 improvements between SE 318th and SE 316th were completed by Green River College in 2012.
Future Impact on Operating Budget:
The annual maintenance cost for this project is estimated to be $3,500.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - - - - - -
Unsecured Grant - - - - 300,000 880,000 2,000,000 - - 3,180,000
Traffic Impact Fees - - - - 100,000 220,000 500,000 - - 820,000
Other - - - - - - - - -Total Funding Sources: - - - - 400,000 1,100,000 2,500,000 - - 4,000,000
Capital Expenditures:
Pre-Design - - - - - - - - - -
Design - - - - 400,000 - - - - 400,000
Right of Way - - - - - 1,100,000 - - - 1,100,000
Construction - - - - - - 2,500,000 - - 2,500,000
Total Expenditures: - - - - 400,000 1,100,000 2,500,000 - - - 4,000,000
Roadway Improvement Projects 29
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 41
ARTERIAL STREET FUND(102)
Project Title: R Street Bypass (M Street SE to SR-18) STIP#AUB-N/A
Project No: cpxxxx
Project Type: Capacity
Project Manager: TBD LOS Corridor ID#N/A
Description:
This project will complete the design and construction of the Bypass Rd,an arterial connection between M Street and'Auburn Black Diamond Road, paralleling the rail
line. The project will provide an arterial connection from the newly constructed M Street Underpass to the Auburn Black Diamond Road interchange with SR-18 to keep
both vehicular and freight traffic out of residential neighborhoods along R'Street SE north of the Stampede Pass line. The arterial connection may also provide
opportunities for partnering with the Muckleshoot Indian Tribe as they redevelop the Miles Pit area and as more definitive plans are developed for a potential new
WSDOT interchange on SR-18 in the vicinity of the project.
Progress Summary:
Future Impact on Operating Budget: .
The annual maintenance cost for this-project is estimated to be$2,500.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources:, Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - • - - - - - -Unsecured Grant - - - - - - - - - -
Trafric Impact Fees - - - - - - - 150.000 - 150,000
Other(Development) - - - - - - - 500.000 5,700,000 6,200,000
Total Funding Sources: - - - - - - - 650,000 5,700,000 6,350,000
Capital Expenditures:
Design - - - - - - - 650,000 - 650,000
Right of Way - - - - - - - - 1,800,000 1,800,000
Construction - - - - - - - - 3,900,000 3,900,000
Total Expenditures: - - - - - - - 650,000 5,700,000 6,350,000
Roadway Improvement Projects 30
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan
TIP# 42
ARTERIALSTREET FUND (102)
Project Title: SE 320th Street Corridor lmprovements(116th Ave SE to 122nd Ave SE) STIP#AUB-NIA
Project No: cpxxxx
Project Type: Capacity, Safety
Project Manager: TBD LOS Corridor ID# 25
Description:
SE 320th St is a primary route serving Green River College•and adjacent neighborhoods. There are very high volumes of pedestrians, bicyclists; and transit utilizing the
corridor.This project will fund the design, right-of-way acquisition, and construction of non motorized roadway and safety improvements including a roundabout at 116th
Ave SE, adding bicycle lanes,•sidewalks, and streetlighting between 122nd Ave SE and 116th Ave SE. Project length is•approximately .45 miles.
Progress Summary:
GRCC completed the design and construction for the segment between 124th Ave SE and 122nd Ave SE in 2013.Corridor pre-design is scheduled to start in 2016.
Construction schedule is pending•securing full funding.
Future Impact on Operating Budget:
This project isnot expected to have a significant impact on operating budgets. .
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost.
Unrestricted Street Revenue - 100,000 - - - - - - - 100,000
Unsecured Grant - - - - 480,000 530,000 2,953,440 - - 3,963,440
Traffic Impact Fees - - - - 120,000 132,500 328,160 - - 580,660
Other - - - - - - - - - -
Total Funding Sources: - 100,000 - - 600,000 662,500 3,281,600 - - 4,644,100
Capital Expenditures:
Pre-Design - 100,000 - - - - - - - 100,000
Design - - - - 600,000 250,000 - - - 850,000
Right of Way - - - - - 412,500 - - - 412,500
Construction - - - - - - 3,281,600 - - 3,281,600
Total Expenditures: - 100,000 - - 600,000 662,500 3,281,800 - - 4,644,100
Roadway Improvement Projects 31
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 43
ARTERIAL STREET FUND(102)
Project Title: Auburn Way S (SR-164) Corridor Safety Improvements (Muckleshoot Plaza to Dogwood) STIP#AUB-44
Project No: cp1218
Project Type: Capacity
Project Manager: Matt Larson LOS Corridor ID#4
Description:
This project will improve access management, including u-turns, upgrade transit stops and street lighting, widen to accomodate turn-lanes and pedestrian and bicycle
facilities, upgrade pavement markings, install pedestrian signals and audible pedestrian push buttons, and upgrade traffic signals to change the phasing and to improve
the visibility of the signal heads.
Progress Summary:
Grant funding was awarded in 2012. Design began in 2012 and construction is•scheduled for 2016.
Future Impact on Operating Budget:
This project is expected to have a neglible impact on operating budgets.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestncted Street Revenue 2,910 - - - - - - - - 2,910
Secured Grants 311,568 2;021,540 - - - - - - - 2,333,108
Unsecured Grant - - - - - - - - - -
Traffic Impact Fees 54,455 250,000 20,000 - - - - - - 324,455
Other(WSDOT) - 306,674 - - - - - - - 306,674
Total Funding Sources: 988,933 2,578,214 20,000 - - - - - - 2,967,147
Capital Expenditures:
Design 368,933 250,000 - - - - - - - 618,933
Right of Way - 100,000 - - - - - - - 100.000
Construction - 2,228,214 20,000 - - - - - - 2,248,214
Total Expenditures: 368,933 2,578,214 20,000 - - - - - - 2,967,147
Roadway Improvement Projects 32
City of Auburn Transportation Improvement Program,
Six Year Transportation Improvement Plan TIP# 49
ARTERIAL STREET FUND(102)
Project Title: W Valley Highway Improvements (15th Street NW to W Main Street) STIP#AUB-NIA
Project No: cpxxxx
Project Type: Capacity
Project Manager: TBD LOS Corridor ID#35
Description:
This project scope includes pavement rehabilitation and re-channelization, roadway widening, bicycle lanes; pedestrian facilities, roadway lighting, required:storm.system
improvements, and Intelligent Transportation System Improvements.
Progress Summary:
Survey, base mapping and pre-design are planned to be completed in 2018 to complete preliminary plans and refine project cost-estimate.
Future Impact on Operating Budget:
This project will have no impact on the operating budget for street maintenance.
Activity: 2016 YE Budget . Forecast Project Cost
Funding Sources:. Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - - - - -
Unsecured Grant - - - - - 480,000 2,400,000 - - 2;880,000
Traffic Impact Fees - - - - 100,000 120,000 600,000 - - 820,000
Other - - - - - - - - - -
Total Funding Sources: - - - - 100,000 600,000 3,000,000 - - 3,700,000
Capital Expenditures:
Design - - - - 100,000 600.000 - - - 700,000
Right of Way - - - - - - - - -
Construction - - - - - - 3.000.000 - - 3,000.000
Total Expenditures: - - - - 100,000 600,000 3,000,000 - - 3,700,000
Roadway improvement Projects , 33
City of Auburn Transportation Improvement,Program
Six Year Transportation Improvement Plan TIP# 58
ARTERIAL STREET FUND.(102),ARTERIAL PRESERVATION FUND(105)
Project Title: M'St SEStorm Improvements STIP#n/a
Project No: CP1511
Project Type: Non-Capacity, Preservation, Non-Motorized
Project Manager: Matt Larson LOS Corridor ID# 11
Description:
In partnership with city utility project this project will complete pavement,.sidewalk, and street lighting improvements on M St SE between 3rd St SE and E Main St.
Progress Summary:
Project design was-completed in 2016 and construction is scheduled to begin in 2016.
Future Impact on Operating Budget:
This project will have no impact on the operating budget for street maintenance.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016. Estimate 2017 -2018 2019 2020 4021 2022 Beyond4022 Total Project Cost
Unrestricted Street Revenue - - 125,000 - - - - - - 125,000
Unsecured Grant - - - - - - - - - -
Other(Sidewalk Imp.Funds) - 150,000 - - - - - - - 150,000
Other(Arterial Pres. Fund) - 150,000 50,000 - - - - - - 200,000
Total Funding Sources: - 300,000 175,000 - - - - - - 476,000
Capital Expenditures:
Pre-Design - - - - - - - - - -
Design - 30,000 - - - - - - - 30,000
Right of Way - - - - - - - - - -
Construction - 270,000 175,000 - - - - - - 445,000
Total Expenditures: - 300,000- 175,000 - - - - - - 475,000
Roadway Improvement Projects 34
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 59
ARTERIAL PRESERVATION FUND(105)
Project Title: Auburn Regional GrowthiCenter Access Improvements STIP#AUB-xx
Project No: cpxxxx
Project Type: Capacity
Project Manager: TBD LOS'Corridor ID#10
Description: The project would.improve the 3rd Street NW/NE/4th Street NE corridor through downtown Auburn. The project elements'include the realignment of side
street approaches, associated traffic signal upgrades, at the signalized intersections along the corridor, and illumination, ADA, and pavement rehabilitation along the
corridor.The improvements will improve traffic operations at the intersection with A Street NW by removing the need to operate the north/south approaches with split phase
due to the existing offset,will add a northbound left-turn movement at the intersection with Auburn Avenue, and realign the intersection of 4th St NE with Auburn Way north
to eliminate another split phase operation signal improving circulation and access.
Progress Summary:
Federal Grant funding application for design and ROW phases was submitted in 2016.
Future Impact on Operating Budget:
There is no impact to the street maintenance budget.
Activity: 2016 YE Budget Forecast Project Costs
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - - - - - -
Unsecured Federal Grant - - - 400,000 464,000 3,120,000 - - - 3,984,000
Traffic Impact Fees - - - 100,000 116,000 780,000 - - - i 996,000
Other - - - - - - - - - -
Total Funding Sources: - - - 600,000 580,000 3,900,000 - - - , 4,980,000
Capital Expenditures:
Design - - - 500,000 330,000 - - - - 830,000
Right of Way - - - - 250,000 - - - - 250,000
Construction - - - - - 3,900,000 - - - 3,900,000
Total Expenditures: - - - 500,000 580,000 3,900,000 - - 4,980,000
Roadway Improvernen!Projects 35
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan
ARTERIAL STREET FUND(102) TIP# 60
Project Title: 'M Street SE+Corridor(8th St SE to AWS) STIP#AUB-NIA
Project No: cpxxxx
Project Type: Capacity
Project Manager: TBD LOS Corridor ID#6
Description:
Widen M Street SE into a multi-lane arterial between 8th St SE and AWS. This project will improve•mobility and is tied to corridor development. It is consistent with the
Comprehensive Plan and contributes to the completion of a north/south arterial corridor.
Progress Summary:
Future Impact on Operating Budget
This annual maintenance cost for this project is estimated to be$8,000. .
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2016 2019 2020 2021 2022 Beyond 2022', Total Project Cost
Unrestricted Street Revenue - - - - - - - - - -
Unsecured Grant - - - - - 925,000 3,750,000 - - 4,675,000
Traffic Impact Fees - - - - - 750,000 750,000 - - 1,500,000
Other(Development) - - - - - 250,000 250,000 - - 500,000
Total Funding Sources: - - - - - 1,925,000 4,750,000 - - 6,675,000
Capital Expenditures:
Design - - - - - 650,000 - - - 650,000
Right of Way - - - - - 1,275,000 - - - 1,275,000
Construction - - - .. - - 4,750,000 - - 4,750,000
I
Total Expenditures: - - - - - 1,925,000 4,750,000 - - 6,675,000
Roadway Improvement Projects 36
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan
TIP# 61
ARTERIAL STREET FUND(102)
Project Title: SR-18 to Auburn Way South (SR-164) Bypass STIP#AUB-N/A
Project No: cpxxxx
Project Type: Capacity
Project Manager: TBD LOS Corridor ID#N/A
Description:
This project will permit and construct a new interchange at'SR-18 and over a mile of new classified roadway connecting the new interchange to Auburn Way South(SR-
164).This project will create a new road connecting SR-18 and SR-164 to bypass Auburns urban center serving the Muckleshoot Reservation and regional traffic to the
Enumclaw area.
Progress Summary:
This project was originally analyzed by WSDOTs Auburn Way South•(SR-164) Route Development Plan. The State Leglature allocated$15 Million for the new eastbound
SR-18 offramp serving this bypass road in 2017-2019. The Muckleshoot Indian Tribe•is anticipated to donate the property necessary to accomodate the offramp•and
connecting road to Auburn Way South.The route of the new roadway will be determined after completion of.a feasibility study.
Futureimpact on Operating Budget:
The annual maintenance cost for this project is estimated to be$37,500.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022. Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - - - - - -
Unsecured Grant - - - - - - - - - -
Tra/hc Impact Fees - - - - - - - - - -
Other(WSDOT) - - - - - - 1,500.000 3,500,000 10.000,000 15.000.000
Other(Development) - - - - - - 3,500,000 6,500,000 15,000,000 25,000,000
Total Funding Sources: - - - - - 5,000,000 10,000,000 25,000,000 40,000,000
Capital Expenditures:
Design - - - - - - 5,000,000 - - 5,000,000
Right of Way - - - - - - - 10,000,000 - 10,000,000
Construction - - - - - - - - 25,000,000 25,000,000
Total Expenditures: - - - - - - 5,000,000 10,000,000 25,000,000 40,000,000
Roadway Improvement Projects 39
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 62
ARTERIAL STREET FUND(102)
Project Title: Auburn Way-S Streetscape Improvements(SR-18 to M St SE) STIP#AUB-N/A
Project.No: cpxxxx
Project Type: Miscellaneous
Project.Manager: TBD LOS Corridor ID#3
Description:
This project will revitalize and beautify Auburn Way S from the SR-18 interchange to the intersection with M Street SE. Proposed improvements include: enhancement of
crosswalks and pedestrian linkages; new and repaired sidewalks;curb and gutter; pedestrian ramps; new landscaped medians; street trees; new lighting; pedestrian
benches;trash receptacles; recycling containers and other appropriate amenities:
Progress Summary:
Future Impact on Operating Budget:
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - 200.000 200.000 - - 400,000
Unsecured Grant - - - - - 1.750,000 2,600.000 - - 4,350,000
Traffic Impact Fees - - - - - - - - -
Other - - - - - - - - -
Total Funding Sources: - - - - - 1,950,000 2,800,000 - - 4,750,000
Capital Expenditures:
Design - - - - - 500,000 - - - 500,000
Right of Way - - - - - 1,450,000 - - - 1,450,000
Construction - - i - - - 2,800,000 - - 2,800,000
Total Expenditures: - - i - 1,950,000 2,800,000 - - 4,750,000
Roadway Improvement Projects 38
City of Auburn Transportation improvement Program
Six Year Transportation Improvement Plan TIP# 64
ARTERIAL.STREET FUND (102)
Project Title: Lea Hill Rd Segment 1 (R St NE to 105th PI SE) STIP#.AUB-N/A
Project No: cpxxxx
Project Type: Capacity
Project Manager: TBD LOS Corridor ID# 19
Description:
Widen the existing roadway to provide a four-lane cross section with pedestrian and bicycle facilities. The project includes widening the Green River Bridge.
Progress Summary:
Three parcels along the future roadway alignment were procured in 2014. Corridor pre-design effort is planned to begin in Iate.2016.
Future Impact on Operating Budget:
The annual maintenance cost for this project is estimated to be $18,300.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - - - -Unsecured Grant - - - - - 1,950,000 8,000,000 - - 9,950,000
Traffic Impact Fees 430,000 150,000 100,000 - .. 500,000 2,000,000 - - 3,180,000
Other - - - - - - - - - -
Total Funding Sources: 430,000 150,000 100,000 - - 2,450,000 10,000,000 - - 13,130,000
Capital Expenditures:
Design - 150,000 100,000 - - 1,950,000 - - - 2,200,000
Right of Way 430,000 - - - - 500,000 - - - 930,000
Construction - - - - - - 10,000,000 - - 10,000,000
Total Expenditures: 430,000 150,000 100,000 - - 2,450,000 10,000,000 - - 13,130,000
Roadway Improvement Projects 39
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan
ARTERIAL STREET FUND(102) TIP# 65
Project Title: Lea:Hill Rd Segment:2 (105th PI.SE to 112th Ave SE) STIP#AUB-NIA
Project No: cpxxxx
Project Type: Capacity
Project Manager: TBD • LOS Corridor ID# 19
Description:
Project includes widening the existing roadway to provide a four-lane cross-section including pedestrian and bicycle facilities.
Progress Summary:
Future Impact on Operating Budget:
The annual maintenance cost for this project is estimated to be $24,100.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 - 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - - - - - - -
Unsecured Grant - - - - - - 2,900,000 7,100,000 - 10,000,000
Traffic Impact Fees - - - - - - 600,000 1,400,000 - 2,000,000
Other - - - - - - - - - -
Total Funding Sources: - - - - - - 3,500,000 8,500,000 - 12,000,000
Capital Expenditures:
Design - - - - - - 2,000,000 - - 2,000,000
Right of Way - - - - - - 1,500,000 - - 1,500,000
Construction - - - - - - - 8,500,000 - 8;500,000
Total Expenditures: - - - - - - 3,500,000 8,500,000 - 12,000,000
Roadway Improvement Projects 40
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 66
ARTERIAL STREET FUND(102)
Project Title: LeaiHill Rd Segment 3 (112th Ave SE to 124th Ave SE) STIP#AUB-NIA
Project No: cpxxxx
Project Type: Capacity
Project Manager: TBD LOS Corridor ID# 19
Description:
Project includes widening the existing roadway to provide a four-lane cross-section including pedestrian and bicycle facilities.
Progress Summary:•
Future.lmpact on Operating Budget:
The annual maintenance cost for this project is estimated to be$20,300.
Activity: • 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - - - - - -
Unsecured Grant - - - - - - - 750,000 2;500,000 3,250,000
Traffic Impact Fees - - - - - - - 250,000 500,000 750,000
Other - - - - - - - - - -
Total Funding Sources: - - - - - - - 1,000,000 3,000,000 4,000,000
Capital Expenditures:
Design - - - - - - - 500,000 - 500,000
Right of Way - - - - - - - 500,000 - 500,000
Construction - - - - - - - - 3,000,000 3,000,000
Total Expenditures: - - - - - - - 1,000,000 3,000,000 4,000,000
Roadway Improvement Projects 4I
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan
ARTERIAL STREET FUND (102) TIP# 72
Project Title: W Valley Highway Improvements (SR-18 to 15th St-SW) STIP#AUB-NIA
Project-No: cpxxxx
Project Type: Capacity
Project Manager: TBD - LOS Corridor ID# 35
Description:
This project scope includes-pavement rehabilitation and re-channelization,.pedestrian and bicycle facility improvements, improved roadway lighting, required storm system
improvements, intersection signal replacement at 15th St SW, and Intelligent Transportation System Improvements.
Progress Summary:
Survey, base mapping and pre-design-are planned to be completed in 2016 to complete preliminary plans and refine project cost-estimate.
Future Impact on Operating Budget:
This project will have no impact on the operating budget for street maintenance.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior.to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022' Total Project Cost
Unrestricted Street Revenue - - - - - - - - - -
Unsecured Grant - - - - 400,0001 2,000,000 - - - 2,400,000
Traffic Impact Fees - - - 100,000 100,000' 500,000 - - - 700,000
Other - - - - - - - - - -
Total Funding Sources: - - - 100,000 500,000 2,500,000 - - - 3,100,000
Capital Expenditures:
Design - - - 100,000 500,000 - - - - 600,000
Right of Way - - - - - - - - - -
Construction - - - - - 2,500,000 - - - _ 2,500,000
Total Expenditures: - - - 100,000 500,000 2,500,000 - - 3,100,000
Roadway Improvement Projects 42
City of-Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 72
ARTERIAL STREET FUND (102)
Project Title: W Valley Highway Improvements (SR-18 to 15th St SW) STIP#AUB-NIA
Project No: cpxxxx
Project Type: Capacity
Project•Manager: TBD LOS Corridor ID# 35
Description:
This project scope includes pavement rehabilitation and re-channelization, pedestrian and bicycle facility improvements, improved roadway lighting, required storm system
improvements, intersection signal replacement at 15th St SW, and Intelligent Transportation System Improvements.
Progress Summary:
Survey, base mapping and pre-design are planned to be completed in 2016 to complete preliminary plans and refine project cost-estimate.
Future Impact on Operating Budget:
This project will have no impact on the operating budget for street maintenance.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - - - - - -
Unsecured Grant - - - - 400,000 2,000,000 - - - 2,400,000
Traffic Impact Fees - - - 100,000 100,000 500,000 - - - 700,000
Other - - - - - - - - - _ -
Total Funding Sources: - - - 100,000 500,000 2,500,000 - - - 3,100,000
Capital Expenditures:
Design - - - 100,000 500,000 - - - - 600,000
Right of Way - - - - - - - - - -
Construction - - - - - 2,500,000 - - - 2,500,000
Total Expenditures: - - - 100,000 500,000 2,600,000 - - - 3,100,000
Roadway Improvement Projects 43
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement_Plan TIP #.74
ARTERIAL STREET FUND(102)
Project Title: R St SE Corridor Extension STIP#AUB-XX
Project No: cpxxxx
Project Type: Capacity
Project Manager: TBD LOS Corridor ID#XX
Description:
This project will construct a new segment of R St SE approximately .7 miles long between 17th St SE and the future bypass road connecting M St SE and Auburn Black
Diamond road.
Progress Summary:
Future Impact on Operating Budget:
The annual maintenance cost for this project is estimated to be$25,000.
Activity: 2016 YE Budget Forecast Project Cost Total Project
Funding Sources: Prior to 2016 Estimate 2017 - 2018 2019 2020 2021 2022 Beyond 2022 Cost
Unrestricted Street Revenue - - - - - - -
Unsecured Grant - - - - - - - - - -
Trafc Impact Fees - - - - - - - - - -
Other(Development) - - - - - - 2,000,000 8,000,000 - 10,000,000
Total Funding Sources: - - - - - - 2,000,000 8,000,000 - 10,000,000
Capital Expenditures:
Design - .. - - - - 2,000,000 - - 2,000,000
Right of Way - - - - - - - - - -
Construction - - - - - - - 8,000,000 - _ 8,000,000
Total Expenditures: - - - - - - 2,000,000 8,000,000 - 10,000,000
Roadway Improvement Projects 44
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 2
ARTERIAL STREET FUND(102)
Project Title: A St Traffic Signal Improvements STIP#AUB-NIA
Project No: cpxxxx
Project Type: Non-Capacity
Project Manager: TBD LOS Corridor ID#2
Description:
This project will replace two A St traffic signals at E Main Street and 2nd•St SE. These are two of the oldest•signals in the City that have both exceeded their serviceable
life span. New signal improvements will match the City's new decorative downtown standard, meet ADA accessibtity requirements,and include battery backup power
supplies.
Progress Summary:
Design is•scheduled to be completed in 2019. Preliminary underground improvements have been completed at each intersection in advance of the project. Portions of
this project is being completed by adjacent development.
Future Impact on Operating Budget:
This project will have no impact on the operating budget for street maintenance.
•
Activity: 2016YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 -Total Project Cost
Unrestricted Street Revenue - - - - 125,000 250,000 - - - 375,000
Grants(Fed,State,Local) - - - - - 650,000 - - - 650,000
Traffic Impact Fees - - - - - - - - - _
Other(REE72 in 328) - - - - - - - - -
Total Funding Sources: - - - - 125,000 900,000 - - - 1,025,000
Capital Expenditures:
Design - - - - 125,000 - - - - 125,000
Right of Way - - - - - - - - -
Construction - - - - - 900,000 - - 900,000
Total Expenditures: - - - - 125,000 900,000 - - - 1,025,000
Intersection, Traffic Signal, & Intelligent Transportation Systems Improvement Projects 45
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 14
ARTERIAL STREET FUND(102)
Project Title: M'Street SES& 12th Street SE Traffic.Signal STIP#AUB-N/A
Project No: cpxxxx
Project Type: Capacity
Project Manager TBD LOS Corridor ID#6
Description:
This project includes the design, right of way acquisistion and construction of a new traffic signal.
Progress Summary:
Future Impact on Operating Budget:
The annual maintenance cost for this project is estimated to be$6,600.
Activity: 2016,YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022• Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - - - - - - -
Unsecured Grant - - - - - 500,000 - - - 500,000
Traffic Impact Fees - - - - - - - - -
Other(Development) - - - - - 125,000 - - - 125,000
Total Funding Sources:• - - - - - 625,000 - - - 625,000
Capital Expenditures:
Design - - - - - 75,000 - - - 75,000
Right of Way - - - - - 50,000 - - - 50,000
Construction - - - - - 500,000 - - - 500,000
Total Expenditures: - - - - - 625,000 - - - 625,000
Intersection, Traffic Signal, & Intelligent Transportation Systems Improvement Projects 46
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 17
ARTERIAL STREET FUND(102)
Project Title: Harvey Rd NE &8th St NE:Intersection Improvements STIP#AUB-N/A
Project No: cp0611
Project Type: Capacity
Project Manager None LOS Corridor ID#5,19
Description:
Add one eastbound through/right turn-lane on 8th St NE to the west of Harvey Rd: Modify traffic signals and traffic channelization to accommodate the new lane. The
additional lane will reduce traffic delays and queuing at the intersection of Harvey Rd and 8th St NE in all directions. This project will reconstruct M St NE from 4th St NE'to 8th
St NE, a segment of roadway approximately 0.3 miles long with a four-lane cross-section. The reconstruction will address the existing poor pavement condition and fill in any
gaps in the•sidewaik network.
Progress Summary:
Project was completed in 2010. Ongoing budget is for PWTFL debt payments.
Future Impact on Operating Budget:
This project will have no impact on the operating budget for street maintenance.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - - - - -
Unsecured Grant - - - - - - - -
Traffic Impact Fees(Debt Service) 521,510 85,600 85,383 85,200 84,800 84,400 84,400 84,200 489,400 1,604,893
Traffic Impact Fees 204,500 - - - - - - - - 204,500
PWTF 1,527,300 - - - - - - - - 1,527,300
Total Funding Sources: 1,731,800 85,600 85,383 85,200 84,800 84,400 84,400 84,200 489,400 1,809,393
Capital Expenditures:•
Design 327,500 - - - - - - - - 327,500
Right of Way 200,400 - - - - - - - - 200,400
Construction 1,203,900 - - - - - - 1,203,900
Long Term Debt:PWTF 521,510 85,600 85,383 85,200 84,800 84.400 84,400 84,200 489,400 1,604,893
Total Expenditures: 1,731,800 85,600 85,383 85,200 84,800 84,400 84,400 84,200 489,400 l 8D9,393
Intersection, Traffic Signal, & Intelligent Transportation Systems Improvement Projects 47
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 18'
ARTERIAL STREETFUND(102)
Project Title: M Street SE & 29th Street SE Intersection Safety Improvements STIP#AUB-N/A
Project No: CPXXXX
Project Type: Non-Capacity, Safety
Project Manager: TBD LOS Corridor ID# 27
Description:
This project includes the design and construction of a new traffic signal.
Progress Summary:
M St SE&29th St SE is currently an all-way stop controlled intersection, experiences significant congestion in the peak traffic hours, and has a documented high collision
history. Design is scheduled to be initiated in 2016. Construction will be completed when project is fully funded.
Future Impact on Operating Budget:
The annual maintenance cost for thisproject is estimated to be $5,000.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - 50,000 - - - 100,000 - - - 150,000
Unsecured Grant - - - - - 300,000 - - - 300,000
Traffic Impact Fees - - - - - - - - - -
Other - - - - - - - - - -
Total Funding Sources:. - 50,000 - - - 400,000 - - - ' 450,000
Capital Expenditures:
Design - 50,000 - - - - - - - 50,000
Right of Way - - - - - - - - - -
Construction - - - - - 400.000 - - 400,000
Total Expenditures: - 50,000 - - - 400.000 - - - 450,000
Intersection, Traffic Signal, & Intelligent Transportation Systems Improvement Projects 48
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan -
ARTERIAL STREET FUND(102) TIP# 19
Project Title: Auburn Way N & 1st Street NE Signal Improvements STIP#AUB-N/A
Project No: cpxxxx
Project Type: Non-Capacity
Project Manager: TBD LOS Corridor ID#2
Description:
This project will construct a new traffic signal with controller cabinet and battery backup along with necessary intersection improvements.
Progress•Summary:
Design is scheduled to be completed in 2018.
Future Impact on Operating Budget:
This project will have no impact on the operating budget for street maintenance.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022. Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - 50,000 125,000 - - - - 175,000
Grants(Fed,State,Local) - - - - 425,000 - - - - 425,000
Traffic Impact Fees - - - - - - - - - -
Other(REET2 in 328) - - - - - - - - - -
Total Funding Sources: - - - 50,000 550,000 - - - - 600,000
Capital Expenditures:
Design - - - 50,000 - - - - - 50,000
Right of Way - - - - 50,000 - - - - 50,000
Construction - - - - 500,000 - - 500,000
Total Expenditures: - - - 50,000 550,000 - - - - I 600,000
Intersection, Traffic Signal, & Intelligent Transportation Systems.Improvement Projects 49
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 20
ARTERIALSTREET FUND(102)
Project Title: R Street SE &.21st Street SE Intersection Safety Improvements STIP#AUB-N/A
Project No: CPXXXX
Project Type: Non-Capacity,-Safety
Project Manager: TBD LOS Corridor ID# 16
Description:
This project includes the design and construction of intersection safety improvements.
Progress:Summary:
R St SE&21st St SE is currently a two-way stop controlled i intersection, experiences significant congestion in the peak traffic hours, and has a documented high collision
history. Analysis to determine appropriate intersection control and design is scheduled to be completed in 2016.Construction will be completed when project is fully
funded. Interim improvements are being constructed in 2016 to improve the pedestrian crossing in partenrhsip with the Muckleshoot Indian Tribe.
Futureimpact on Operating Budget:
The annual maintenance cost for this project is estimated to be$5,000.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019' 2020 2021 2022. Beyond 2022 Total Project Cost
Unrestricted Street Revenue - 75,000 - - - 100,000 - - - 175,000
Unsecured Grant - - - - - 700,000 - - - 700,000
Traffic Impact Fees - - - - - - - - -
Traffic Mitigation Funds - - - - - - - - -
Other - - - - - - - - -
Total Funding Sources: - 75,000 - - - 800,000 - - - 875,000
Capital Expenditures:
Design - 75,000 - - - - - - - 75,000
Right of Way - - - - - - - - - -
Construction - - I - - - 800.000 - - 800,000
Total Expenditures: - 75,000 - - - 800,000 - - - 875,000
Intersection, Traffic Signal, & Intelligent Transportation Systems Improvement Projects 50
City of Authtrn Transportation Improvement Program
Six Year Transportation Improvement Plan
ARTERIAL STREET FUND(102) TIP# 21
Project Title: W Main St& C St Traffic Signal Upgrade STIP#AUB-NIA
Project No: cp1406
Project Type: Non-Capacity
Project Manager Luis:Barba LOS Corridor ID# 11
Description:
Reconstruct the existing traffic signal at C St NW and W Main St.The new C St NW signal would provide protected left-turn phasing for C St, and would provide
additional safety related to the railroad pre-emption.
Progress Summary:
Design started in 2014 and construction is expected to start in 2016. This project scope was modified in 2016 to construct only the new traffic signal at C St and W Main
St.The traffic signal at Auburn Ave•and E Main.St is included in TIP#2 and will be designed and constructed after the completion of the Main Street Urban Design
Concept has been completed and approved.
FutureImpact on Operating Budget:
This project will have no impact on the operating budget for street maintenance.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022. Beyond 2022 Total Project Cost
Unrestricted Street Revenue - 320,000 20,000 - - - - - .340,000
Grants(Fed,State,Locat) - - - - - - -
Traffic Impact Fees - - - - - - - - - -
Traffic Mitigation Fees 26,856 123.144 - - - - - - 150,000
Other - - - - - - - -
Total Funding Sources: 26,856 443,144 20,000 - - - - - - 490,000
Capital Expenditures:
Design 26,856 20,000 - - - - - - - 46,856
Right of Way - - - - - - - - - -
Construction - 423,144 20,000 - - - - - 443,144
Total Expenditures: 26,856 443,144 20,000 - - i - - - - 490,000
Intersection, Traffic Signal, & Intelligent Transportation Svstems,lmprovement Projects 51
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan
CAPITAL IMPROVEMENT FUND1(328) TIP# 34
Project Title: Traffic Signal Improvements STIP#AUB-N/A
Project No: Various
Project Type: Non-Capacity(Annual)
Project Manager: •Scott Nutter LOS Corridor ID# N/A
Description:
This project funds end of life capital replacement for traffic signal and Intelligent Transportation System equipment including cabinets,video detection cameras, field
network devices, traffic cameras, battery backup components; and other related equipment. This project also funds minor safety improvements, operations improvements,
and Accessible Pedestrian Signal Improvements based on the criteria adopted in the City's Public Right-of-Way Accessibility Transition Plan.
Progress Summary:
Project continues to complete various intersection improvements.
Future Impact on Operating Budget:
This project will have no impact on the•operatingthudget for street maintenance.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Cap. Imp.Fund Balance - - - - - - - - - -
Unsecured Grant - - - - - - - - - -
REET2 - 175,0001 175,000 175,000 200,000 200,000 200,000 200,000 - 1,325,000
Other - - - - - - - - - -
Total Funding Sources: - 175,000 175,000 175,000 200,000 200,000 200,000 200,000 - 1;325,000
Capital Expenditures:
Design - 25,000 25,000 25,000 25,000 25,000 25,000 25,000 - 175,000
Right of Way - - - - - - - - - -
Construction - 150,000 150,000 150,000 175,000 175,000 175,000 175,000 - 1,150,000
Total Expenditures: - 175,0001 175,000 175,000 200,000 200,000 200,000 200,000 - 1,325,000
Intersection, Traffic Signal, & Intelligent Transportation Systems Improvement Projects 52
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP # 38
ARTERIAL STREET FUND (102)
Project Title: C Street SW& 15th Street-SW Intersection Improvements STIP#AUB-NIA
Project No: cpxxxx
Project Type: Capacity
Project Manager: TBD LOS Corridor ID#12, 13
Description:
This project will install a southbound right-turn pocket, re-channelize the intersection to provide two southbound through lanes, and replace the existing spanwire:traffc
signal with a new traffic signal.
Progress Summary:
Design is planned to begin in 2020. Construction will be sheduled once full funding is secured.
Future Impact on Operating Budget:
The annual maintenance cost for this project is estimated to be$2;500.
Activity: 2016 YE Budget Forecast Project Cost Total Project
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022Cost
Unrestricted Street Revenue - - - - - - - - - -
Unsecured Grant - - - - - - 800,000 - - 800,000
Traffic Impact Fees - - - - - 200,000 200,000 - - 400,000
Other - - - - - - - - -
Total Funding Sources: - - - - - 200,000 1,000,000 - - 1;200,000
Capital Expenditures:
Design - - - - - 200,000 - - - 200,000
Right of Way - - - - - - - - - -
Construction - - - - - - 1,000,000 - - 1:000.000
Total Expenditures: - - - - - 200,000 1,000,000 - - - 1,200,000
Intersection, Traffic Signal, & Intelligent Transportation Systems Improvement Projects 53
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 39
ARTERIAL STREET FUND(102)
Project Title: 124th Avenue SE & SE 320th Street Intersection:Improvements STIP#AUB-NIA
Project No: cpxxxx
Project Type: Capacity
Project Manager: TBD LOS Corridor ID#23, 25
Description:
This project will fund the design, right-of-way acquisition,and construction of improvements to the intersection of SE 320th St and 124th Ave SE. The intersection is
located at the main entrance to Green River College and will require additional on-site improvements to be constructed.
Progress Summary:
Future Impact on Operating Budget:
The annual maintenance cost for this project is estimated to be$2,500.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019, 2020 2021 2022. Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - 175,000 150,000 - - 325,000
Unsecured Grant - - - - - - 1,200,000 - - 1,200,000
Traffic Impact Fees - - - - - - - - -Other(SRC) - - - - - 175,000 250,000 - - 425,000
Total Funding Sources: - - - - - 360,000 1,600,000 - - 1,950,000
Capital Expenditures:
Design - - - - - 350,000 - - - 350,000
Right of Way - - - - - - 100,000 - - 100,000
Construction - - - - - - 1,500,000 - - 1,500,000
-
Total Expenditures: - - - - - 350,000 1,600000 - - 1,950,000
Intersection, Traffic Signal, & Intelligent Transportation Systems Improvement Projects 54
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 45
ARTERIAL STREET FUND(102)
Project Title: 124th.Avenue'SE 8, SE 284th Street.Intersection Safety Improvements STIP#AUB-N/A
Project No: cpxxxx
Project Type: Capacity, Safety
Project Manager: TBD LOS Corridor ID#23,40, 41
Description:
This project will complete the design phase for intersection safety and capacity improvements.
Progress Summary:
Future Impact on Operating Budget:
TBD
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - - - - - _
Unsecured Grant - - - - - 450,000 - - - 450,000
Traffic Impact Fees - - - - 100,000 150,000 - - - 250,000
Other - - - - - - - - - -
Total Funding Sources: - - - - 100,000 600,000 - - - 700,000
Capital Expenditures:
Design - - - - 100,000 - - - - 100,000
Right of Way - - - - - 50,000 - - - 50,000
Construction - - - - - 550,000 - - - 550,000
Total Expenditures: - - - - 100,000 600,000 - - - 700,000
Intersection, Traffic Signal, & Intelligent Transportation Systems Improvement Projects 55
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 50
ARTERIAL STREET FUND(102)
Project Title: ITS Dynamic Message Signs STIP#AUB-N/A
Project No: cpxxxx
Project Type: Non-Capacity (ITS)
Project Manager: TBD LOS Corridor ID#N/A
Description:
This project funds the design and construction of Dynamic Message Signs at various locations throughout the City. Dynamic message signs are an important ITS tool for
providing information to roadway users. Priority locations for sign placement are based on the Comprehensive Transportation PlansITS map•and include Auburn Way N,
Auburn Way S, W Valley Highway, E Valley Highway, Lake Tapps Parkway, and Lea Hill Rd.
Progress•Summary:
The first phase of this project is scheduled to begin in 2016 or sooner if grant funding becomes available.
Future'Impact on Operating Budget:
The annual maintenance cost for this project is estimated to be$5,000.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022Beyond2022 Total Project Cost
Unrestricted Street Revenue - - 100,000 30,000 30,000 30,000 30,000 - - 220,000
Unsecured Grant - - - 120,000 120,000 120,000 120,000 - - 480,000
Traffic Impact Fees• - - - - - - - - - -
REET2(328 Fund) - 100,000 - - - - - - - 100,000
Other(MIT) - 50,000 - - - - - - - 50,000
Total Funding Sources: - 150,000 100,000 150,000 150,000 150,000 150,000 - - 850,000
Capital Expenditures:
Design - 15,000 10,000 15,000 15,000 15,000 15,000 - - 85,000
Right of Way - - - - - - - - - -
Construction - 135,000 90,000 135,000 135,000 135,000 135,000 - - 765,000
Total Expenditures: - 160,000 100,000 150,000 150,000 150,000 150,000 - - 860,000
Intersection, Traffic Signal, & Intelligent Transportation Systems Improvement Projects 56
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan .
ARTERIAL STREET FUND (102) TIP# 51
Project Title: Lake Tapps Parkway ITS Expansion STIP#AUB-N/A
Project No: cpxxxx
Project Type: Capacity
Project Manager: TBD LOS Corridor ID# 17
Description:
The project funds the design, coordination, permitting, and construction of new ITS infrastructure along:Lake Tapps Parkway from Lakeland Hills Way to East Valley
Highway, and along East Valley Highway to Lakeland Hills Way. The proposed ITS infrastructure includes conduit, fiber,VMS signage, cameras, network communication
upgrades, and weather stations along the route.
Progress Summary:
Federal Grant application was submitted to PSRC in May 2014. Project was awarded design funds in 2016.Construction.funding grant application was submitted in 2016.
Future Impact on Operating Budget:
The annual maintenance cost for this project is estimated to be $5,000.
Activity: 2016YE Budget Forecast Project Cost
Funding Sources: Prior to2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - - - _ - -
Secured Federal Grant - 82,950 - - - - - - - 82,950
Unsecured Federal Grant 711,000 7.11,000
Traffic Impact Fees - 22,050 189,000 - - - - - - 211,050
Other - - - - - - - - -
Total Funding Sources: - 105,000 900,000 - - - - - - 1,006,000
Capital Expenditures:
Design - 105,000 900,000 - - - - - - 1,005,000
Right of Way - - - - - - - - - -
Construction - - - - - - - - -
Total Expenditures: - 105,000 900,000 - - - - - - 1;005,000
Intersection, Traffic Signal, & Intelligent Transportation Systems Improvement Projects 57
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 52
ARTERIAL STREET FUND(102) i
Project Title: A Street SE &:Lakeland Hills Way SE-Intersection Safety&Capacity Improvements STIP#AUB-NIA
Project No: CPXXX
Project Type: Capacity, Safety
Project Manager: TBD LOS Corridor ID# 10, 34
Description:
This project will study traffic operations, safety, and prepare a preliminary design for intersection improvements.
Progress Summary:
Analysis, preliminary design, and construction cost estimate will be initiated in 2016. Future phases will be programmed.as funding becomes available.
Futurelmpact on Operating'Budget:
This project will have.no impact on the operating budget forstreetmaintenance.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - - - . -
Unsecured Grant - - - - - - - - - -
Traffic Impact Fees - 50,000 25,000 - - - - - - 75,000
Other - - - - - - - - - _
Total Funding Sources: - 50,000 25,000 - - - - - - 75,000
Capital Expenditures:
Design - 50,000 25,000 - - - - - - 75,000
Right of Way - - - - - - - - -
Construction - - - - - - - - - -
Total Expenditures: - 50,000 25,000 - - - - - - 75,000
Intersection, Traffic Signal, & Intelligent Transportation Systems Improvement Projects 58
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement:Plan TIP# 53
ARTERIAL STREET FUND,(102)
Project Title: Auburn Way S & 12th,Street SE Intersection Improvements STIP#AUB-N/A
Project No: cp1114
Project Type: Capacity, Safety
Project Manager: TBD LOS Corridor ID#3
Description:
The project will design multi-modal intersection improvementsat the AWS/12th Street SE intersection. The improvements will include pedestrian access improvements,
channelization improvements to add bicycle lanes, new traffic signal, and ITS upgrades.
Progress Summary:
Design is scheduled to be completed in 2016. Portions of these improvements will be coordinated with WSDOT's planned paving project for 2017.
Future Impact on Operating Budget: •
This project will have no impact on the operating budget for street maintenance.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021• 2022 Beyond 2022_ Project Cost
Unrestricted Street Revenue - :50,000 150,000 - - - - - - - 200,000
Unsecured Grant - - - - - - - -
Traffic Impact Fees - - - - - - - - - -
Other - - - - - . - - - - -
Total Funding Sources: - 50,000 150,000 - - - - - - 200,000
Capital Expenditures:
Design - 50,000 150,000 - - - - - - 200,000
Right of Way - - - - - - - - - -
Construction - - - - - - - - -
Total Expenditures: - 50,000 150,000 - - - - - 200,000
•
Intersection, Traffic Signal, & Intelligent Transportation Systems Improvement Projects 59
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement,Plan TIP# 63
ARTERIAL STREET FUND(102)
Project Title: 29th Street SE& R Street SE Intersection Improvements STIP#AUB-N/A
Project No: cpxxxx
Project Type: Capacity
Project Manager: TBD LOS Corridor ID# 16, 27
Description:
This project funds the design, right-of-way acquisition and construction of intersection capacity and•safety improvements at the 29th St-SE/R St SE intersection.
Progress Summary:
Future Impact on Operating.Budget:
This project will have no impact on the operating budget for street maintenance.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - - - -
Unsecured Grant - - - - - 1,300,000 - - - 1,300,000
Traffic Impact Fees - - - - 100,000 500,000 - - - 600,000
Other - - - - - - - - - -
Total Funding Sources: - - - - 100,000 1,800,000 - - - 1,900,000
Capital Expenditures:
Design - - - - 100,000 350,000 - - - 450,000
Right of Way - - - - - 450,000 - - - 450,000
Construction - - - - - 1,000,000 - - - 1,000,000
Total Expenditures: - - - • 100,000 1,800,000 - - - 1,900,000
Intersection, Traffic Signal, & Intelligent Transportation Systems.lmprovement Projects 60
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 68
ARTERIAL STREET FUND(102),ARTERIAL PRESERVATION FUND(105)
Project Title: A Street SE & 37th Street SE Intersection Improvements STIP#AUB-53
Project No: CP1502
Project Type: Non-Capacity, Safety
Project Manager: Luis,Barba LOS Corridor ID# 10
Description:
Widen the intersection for a u-turn, install an interconnected traffic signal,overlay the intersection, and upgrade curb ramps. •
Progress Summary:
Federal Grant was awarded in 2014. Arterial Preservation Fund 105 will participate in this project to overlay portions of A St SE. Budget for 2016 includes 10%local
match;there is a potential of receiving 100%grant funding for the construction phase if project is advertised by September 30,2017.
Future Impact on Operating Budget:
The annual maintenance cost for this project is estimated to be $2,500.
Activity: 2016 YE Budget - Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019; 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue 1,933 53,067 - - - - - - - 55,000
Secured Federal Grant 8,295 600,000 183,965 - - - - ' - 792,260
Traffic Impact Fees - - - - - - - - - -
Arterial Preserv. Funds(105) - 87,240 - - - - - - - _ 87,240
Total Funding Sources: 10,228 740,307 183,965 - - - - - - 934,500
Capital Expenditures:
Pre-Design 9,873 - - - - - - - - 9,873
Design 355 135,272 - - - - - - - 135,627
Right of Way - 66,400 - - - - - - - 66,400
Construction - 538,635 183,965 - - - - - - 722,600
Total Expenditures: 10,228 740,307 183,965 - - - - - - 934,500
Intersection, Traffic Signal, & Intelligent Transportation Systems Improvement Projects 61
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan
ARTERIAL STREET FUND(102) TIP# 69
Project Title: 22nd Street!NE&tStreet NE;intersection STIP#AUB-xx
Project No: CPI513
Project Type: Capacity (Safety)
Project Manager: TBD LOS Corridor ID#21
Description:
This project will design a modem roundabout at the 22nd Street NE and!! Street.NE intersection in place of the existing all-way stop-control. The proposed design will
improve bicycle and pedestrian safety and ADA accessibility.
Progress Summary:
State grant was awarded.for design in.2015. Construction phase is dependant on securing future grants or other local funding.
Futurelmpact on Operating Budget
There is no impact to the street maintenance budget.
Activity: 2016 YEI Budget Forecast Project Cost
Funding Sourcos: Prior to 2016 Estimate' 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - 25,000 - - - - - - - 25,000
Secured State Grant 1,712 198,288 - - - - - - - 200,000
Unsecured Grant - - - 940,000 - - - - - 940,000
Traffic Impact Fees 2,872 52,128 - 235,000 - - - - - 290,000
Other - - - - - - - - - -
Total Funding Sources: 4,684 275,416 • 1,175,000 - - - - - 1,455,000
Capital Expenditures:
Pre-Design 4,584 - - - - - - - - 4,584
Design - 275,416 - - - - - - - 275,416
I Right of Way - - - - - - - - -
Construction - . - 1,175,000 --
-
- -
- - I 1,175,000
Total Expenditures: 4,684 275,416 1,175,000 1 1,455,000
Intersection, Traffic Signal, & Intelligent Transportation Systems Improvement Projects 62
City of Auburn Transportation Itnprovement Program
Six Year Transportation Improvement Plan
ARTERIAL STREET FUND(102) TIP# 10
Project Title: F Street SE Non-Motorized Improvements (Downtownto Les Gove) • STIP#AUB-49
Project No: cp1416
Project Type: Capacity, Non-Motorized
Project Manager: Seth Wickstrom LOS Corridor ID#'N/A
Description:
The F St SE project includes pavement rehabilitation, installation of curbs,.gutters, bike lanes, sidewalks,ADA improvements, utility undergrounding, LED street lighting,
new two way center left turn-lane, crash attenuation at the supports for the BNSFrailroad bridge, initiation of Auburn Staff Bikeshare pilot program, wayfinding signage
and a"Bicycle Boulevard"designation of roadway connections between Auburn City Hall and the'•Les Gove Park Campus. This project improves mobility and safety
along the corridor•and will complete•a gap in the non-motorized network between Auburn's Downtown and the-Les Gove Community Campus. The major infrastructure
improvements are approximately 0.3 miles long and the"Bicycle Boulevard" improvements are just over a mile long.
Progress'Summary:
Preliminary design and survey work was completed in 2009. Federal Grant was secured in 2014 for design and ROW phases. Design phase was initiated in 2015.
Construction grant funding was applied for in 2016:
Future Impact on Operating Budget:
The•annual maintenance cost:for this project is estimated to be$4,100.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - 40,000 - 150,000 - - - - - 190,000
Secured Federal Grant 141,070 338,930 40,000 - - - - - - 520,000
Traffic Impact Fees 24,935' 105,065 - 190,000 - - - - - 320,000•
Unsecured Federal Grant - - - 2,162,000 - . - - - 2,162,000
Total Funding Sources: 166,005 483,995 40,000 2,502,000 - - - - - 3,192,000
Capital Expenditures:
Design 166,005 433,995 40,000 - - - - - - 640,000
Right of Way - 50,000 - - - - - - - 50,000
Construction - - - 2,502,000 - - _ 2,502,000
Total Expenditures: 166,005 483,995 40,000 2,502,000 - - - - - 3,192,000
Non-Motorized& Transit Improvement Projects 63
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement°Plan
ARTERIALSTREET FUND(102) TIP# 23
Project Title: Riverwalk Drive SE Non-Motorized:lmprovements STIP#AUB-NIA
Project No: cpxxxx
Project Type: Non-Motorized
Project Manager: TBD LOS Corridor ID# 27
Description:
This project is planned as a partnerhsip between the City of Auburn and the Muckleshoot Indian Tribe to improve pedestrian safety by constructing sidewalks, street
lighting,and related storm improvements on Riverwalk Drive SE between Auburn Way S and Howard Road SE.This project will close a major gap in sidewalk system and
ties into the proposed improvements on Auburn Way South.
Progress.Summary:
Design is anticipated to begin in 2018. Construction will be completed when funds are available.
Future Impact on Operating Budget:
The annual maintenance cost for this project is estimated to be 510,000.
Activity: 2016 YE Budget Forecast Project Cost Total Project
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Cost
Unrestricted Street Revenue - - - 125,000 125,000 - - - - 250,000
Unsecured Grant - - - - 1,250,000 - - - - 1,250,000
Traffic Impact Fees - - - - - - - -Other(MIT) - - - 125,000 125,000 - - - - 250,000
Total Funding Sources: - - - 250,000 1,500,000 - - - - 1,750,000
Capital Expenditures:,
Design - - - 250,000 - - - - - 250,000
Right of Way - - - - - - - - - -
Construction - - - - 1,500,000 - - - - - 1,500,000
Total Expenditures:• - - - 250,000 1,500,000 - - - - 1,750,000
Non-Motorized& Transit Improvement Projects 64
City ofAnburn Transportation Improvement Program
Six Year Transportation ImprovementPlan
TIP# 24
ARTERIAL STREET FUND (102)
Project Title: Academy Drive MultiUse Trail STIP#AUB-NIA
Project No: cpxxxx
Project Type: Class 1 Trail (Capacity)
Project Manager: TBD LOS Corridor ID# NIA
Description:
This project will use existing Acadamy Dr right-of-way to.create a multi-use trail between the Green River Rd and Auburn Way S.
Progress Summary:
Future Impact on Operating Budget:
The annual maintenance cost for this project is estimated to be $25,000.
I
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - 42,500 42,500 - - 85,000
Unsecured Grant - - - - - 382,500 382,500 - - 765,000
Traffic Impact Fees - - - - - - - - - -
Other - - - - - - - - - -
Total Funding Sources: - - - - - 425,000 425,000 - - 850,000
Capital Expenditures:
Design - .. - - - 100,000 - - - 100,000
Right of Way - - - - - - - - - -
Construction - - - - - 325,000 425,000 - - 750,000
Total Expenditures: - - - - - 425,000 425,000 - - 850,000
Non-Motorized& Transit Improvement Projects 65
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan
ARTERIAL STREET'FUND(102) TIP# 26
Project Title: METRO Shuttle: Lakeland Hills Shuttle STIP#AUB-N/A
ProjectNo: NA
Project Type: Other
Project Manager: Joe Welsh LOS Corridor ID# N/A
Description:
Operating costs•associated with the Commuter Shuttle (PT497)from the Lakeland Hills neighborhood to Auburn Station and King County Metro Transit's Route 910.
Progress Summary:
The Lakeland Hills route began in 2009, the community shuttle in 2010. Lakeland Hills Sounder Shuttle is a partnership route with KC Metro and Pierce transit currently
authorized through March 2016. Route 910 is a KC Metro Transit'Now Partnership Program.
•
FutureImpact on Operating Budget:
This project will have no impact on the operating budget for street maintenance.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources:, Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - 240,000 260,000 260,000 280,000 280,000 280,000 280,000 - 1,880,000
Unsecured Grant - - - - - - - - - -
REET - - - - - - - - -
Other(Agencies) - - - - - - - - - -
Total Funding Sources:. - 240,000 260,000 260,000 280,000 280,000 280,000 280,000 - 1,880,000
Capital Expenditures:
Design - - - - - - - _ - -
Right of Way - - - - - - - - - -
Transit Service - 240,000 260,000 260,000 280,000 280,000 280,000 280,000 - 1:880,000
Total Expenditures:, - 240,000 260,000 260,000 .280,000 280,000 280,000 280,000 - 1,880,000
Non-Motorized& Transit Improvement Projects 66
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan
ARTERIAL STREET FUND (102) TIP# 30
Project Title: CitywideRedestrian Accessibility and:Safety Program STIP#AUB-NIA
Project No: cpxxxx
Project Type: Non-CapacitylAnnual)
Project Manager: Pablo Para LOS Corridor ID# N/A
Description:
This is an annual program to fund small pedestrian improvement projects at locations throughout the City. Projects are prioritized annually based on pedestrian
demands, existing deficiencies, and citizen requests.
Progress Summary:
Future Impact on Operating Budget:
This project will have no impact on the operating budget for street maintenance.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - 75,000 100,000 100,000 100.000 100,000 100,000 100,000 - 675,000
Unsecured Grant - - - - - - - - - -
REET - - - - - - - - -
Trafric Impact Fees - - - - - - - - - -
Other - - - - - - - - - -
Total Funding Sources: - 75,000 100,000 100,000 100,000 100,000 100,000 100,000 - 676,000
Capital Expenditures:
Design - 10,000 10,000 10,000 10,000 10,000 10,000 10,000 - 70,000
Right of Way - - - - - - - - -
Construction - 65,000 90,000 90,000 90,000 90,000 90.000 90,000 - 605,000
Total Expenditures: - 75,000 100,000 100,000 100,000 100,000 100,000 100,000 - 675,000
Non-Motorized& Transit Improvement Projects 67
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 31
•
ARTERIAL STREET FUND(102)
Project Title: Citywide:ArteriahBicycle &.Safety Improvements STIP#AUB-N/A
Project No: cpxxxx
Project Type: Non-Capacity (Safety)
Project Manager: Various LOS Corridor ID# NIA
Description:
This is a bi-annual program to fund bicycle andhsafety improvements on classified roadways. Projects are prioritized annually based upon field studies and community
feedback.
Progress Summary:
Future'Impact on Operating Budget:
This project will have no impact on the operating budget for street maintenance.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - 90,000 - 100,000 - 100,000 - 100,000 - 390,000
Unsecured Grant - - - - - - - - -
Traffic Impact Fees - - - - - - - - - -
Other - - - - - - - - - _
Total Funding Sources: - 90,000 - 100,000 - 100,000 - 100,000 - 390,000
Capital Expenditures:
Design - 10,000 - 10,000 - 10,000 - 10,000 - 40,000
Right of Way - - - - - - - - - -
Construction - 80,000 - 90,000 - 90,000 - 90,000 - 350,000
Total Expenditures: - 90,000 - 100,000 - 100,000 - 100,000 - 390,000
Non-Motorized.& Transit Improvement Projects 68
City of-Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 32
CAPITAL IMPROVEMENT FUND(328)
Project Title: Citywide ADA& Sidewalk Improvements STIP#AUB-N/A
Project No: varies
Project Type: Non-Capacity(Annual)
Project Manager: Jai'Carter LOS Corridor ID#N/A
Description:
This project funds citywide accessibility improvements to the public right-of-way sidewalk system'including adding/upgrading curb ramps, removing barriers to access and
completing gaps. Improvements-are programmed annuallybased on the criteria adopted in the City's Public Right-of-Way Accessibility Transition Plan.
Progress Summary:
Future'lmpact on Operating Budget:
This project will have no impact on the operating budget for street maintenance.
Activity: 2016YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 .2018 2019 2020 - 2021 2022 Beyond 2022 Total Project Cost
Cap.Imp.Fund Balance - 147,500 - - - - - - - 147,500
Unsecured Grant - - - - - _ - _ - -
REET2 - 425,000 200,000 200,000 200,000 200,000 200,000 200,000 - 1,625,000
Other - - - - - _ - _ - - -
Total Funding Sources: - 572,500 200,000 200,000 200,000 200,000 200,000 200,000 - 1,772,500
Capital Expenditures:
Design - - - - - _ - _ - -
RightofWay - - - - - - - - - -
Construction - 572,500 200,000 200,000 200,000 200,000 200,000 200,000 - 1,772,500
Total Expenditures: - 572,500 200,000 200,000 200,000 200,000 200,000 200,000 - 1,772,500
Non-Motorized& Transit Improvement Projects 69
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 44
ARTERIAL STREET FUND (102)
Project Title: Downtown Transit Center Access Improvements STIP#AUB-N/A
Project No: cpxxxx
Project Type: Non-Capacity, Transit
Project•Manager: TBD LOS Corridor ID# N/A
Description:
This project will modify channelization•and curb radii to improve turning radii for transit vehicles atthe southwest corner of S Division St&3rd•St SW, and the southeast
corner of A St SW&2nd St SW.
Progress Summary:
Future Impact on Operating Budget:
The annual•maintenance cost for this project is estimated to minimal.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources:. Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022, Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - 50,000 - - - - 50,000
Unsecured Grant - - - - 200,000 - - - - 200,000
Traffic Impact Fees - - - - - - - - - _
Other - - - - - - - - - -
Total Funding Sources: - - - - 250,000 - - - - 250,000
Capital Expenditures:
Design - - - - 30,000 - - - - 30,000
Right of Way - - - - - - - - - -
Construction - - - - 220,000 - - - - 220,000
Total Expenditures: - - - - 250,000 - - - - 250,000
Non-Motorized& Transit Improvement Projects 70
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 55
ARTERIAL PRESERVATION FUND(105)
Project Title: Auburn Way South (SR-164) Sidewalk Improvements STIP#AUB-xx
Project No: cpxxxx
Project Type: Capacity
ProjectManager: TBD LOS Corridor ID#4
Description:
The project will construct missing sidewalks along both sides of Auburn Way S. The existing sidewalks currently end to the east of the intersection with 17th Street•SE:and
restart to the west of the intersection with Muckleshoot Plaza. The sidewalk gap extends for approximately 1,700 feet.
Progress Summary:
Federal Grant funding was applied for in 2016.
Future Impact on Operating Budget:
There is no impact to the street maintenance budget.
Activity: 2016 YE Budget Forecast Project Costs
Funding Sources:, Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - 52,000 238,000 - - - - 290,000
Unsecured Federal Grant - - - 208,000 952,000 - - - - 1!160,000 -
Trafc Impact Fees - - - - - - - -
Other - - - - - - - - -
Total Funding Sources: - - - 260,000 1,190,000 - - - - 1,450,000
Capital Expenditures:
Design - - - 260,000 - - - - - 260,000
Right of Way - - - - - - - - -
Construction - - - - 1,190,000' - - - - 1;190,000
Total Expenditures: - - - 260,000 1,190,000 - - - - 1,450,000
Non-Motorized& Transit Improvement Projects 71
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 56
ARTERIAL STREET FUND(102)
Project Title: Evergreen Heights•Safe Routes to School Improvements Phase 1 STIP#AUB-NIA
Project No: cpxxxx
Project Type: Capacity, Non-Motorized
Project Manager: TBD LOS Corridor ID#37
Description:
The project will widen S 316th Street from 52nd Avenue S to the west of the Evergreen Elementary School frontage,to accommodate the addition of.bike lanes and
sidewalks along the north side of the street, matching the existing roadway cross-section to the east of the school.The 5 316th Street improvements include the vertical
realignment of the existing roadway along the school frontage which creates sight-distance problems associated with the school driveways and at the intersection with
56th Avenue S:
The 56th Avenue S approach to S 316th Street will be realigned to the east to remove the offset between the street approach and school driveway, and a roundabout will
be constructed'at the S 316th Street/56th Avenue S intersection replacing the existing all-way stop-control.Other project elements include street lighting and required
storm water system improvements.
Progress Summary:
Grant funding application was submitted in 2016.Auburn School district partnership includes direct financial contruibution and ROW dedication. Private development
contribution has been secured.
Futureilmpact on Operating Budget:
This project will have no impact on the operating;budget for street maintenance.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - - - - -
Unsecured State Grant - - 200,000 300.000 1,420,000 - - - - 1,920,000
Traffic Impact Fees - - 50,000 57,000 400,033 - - - - 507,033
Other(Aubum Sch.District) - - 50,000 53,000 327,443 - 430,443
- 430,443
Other(Private Development) - - - - 122,524 - - - - 122,524
Total Funding Sources: - - 300,000 410,000 2,270,000 - - - - 2,980,000
Capital Expenditures:
Design - - 300,000 200,000 - - - - - 500.000
Right of Way - - - 210,000 - - - - - 210.000
Construction - - - - 2,270,000 - - - - 2,270,000
Total Expenditures: - - 300,000 410,000 2,270,000 - - - - 2,980,000
Non-Motorized& Transit Improvement Projects 72
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 67
ARTERIAL STREET FUND (102)
Project Title: BNSFB A:St SE PedestriantrossingImprovements STIP#AUB-N/A
Project No: cpxxx
Project Type: Capacity,,Safety, Non-Motorized
Project Manager: TBD LOS Corridor ID# 10
Description:
This project will fund the permitting, design, and construction of a new pedestrian underpass of the BNSF Railway mainline tracks south of 41st St SE and a new
signlized pedestrian crossing of A St SE.This project is needed to improve pedestrian walking routes and safety.
Progress-Summary:
Consultant feasibility analysis was completed to refine project scope, alignment, and identify design issues. Future proejct phases will be completed when grant funding is -
secured.
FutureImpact on Operating Budget:
This annual maintenance cost for this project is estimated to be$5,500.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022. Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - - - - - -
Unsecured Federal Grant - - - - - - 400,000 3,500,000 - 3,900,000
Traffic Impact Fees - - - - - - 250,000 1,400,000 - 1,650,000
Other - - - - - - - - - -
Total Funding Sources: - - - - - - 650,000 4,900,000 - 5,550,000
Capital Expenditures:
Design - - - - - - 650,000 - - 650,000
Right of Way - - - - - - - - - -
Construction - - - - - 4,900,000 - 4,900,000 r
Total Expenditures: - - - - - - 650,000 4,900,000 - 5,550,000
Non-Motorized& Transit Improvement Projects 73
City of Auburn Transportation Improvement Program
, * a
/�� IT"
r. r® �'' 1
A'js
O,, IHAN YOU NAG INEl°
Non-Motorized& Transit Improvement Projects 74
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan, TIP# I
ARTERIAL STREET FUND(102)
Project Title: A Street NW-Phase 1 (3rd St NW to 14th St NW) STIP#AUB-N/A
Project No: c207a0
Project Type: Capacity, EnvironmentaliMonitoring
Project Manager: Matt Larson LOS Corridor ID# 18
Description:
Constructed a new multi-lane arterial from 3rd Street NW to 14th Street NW completing a missing link along the corridor. This•project improves mobility and was tied to
corridor development. The project length was approximately three-quarters ota mile. The City purchased ROW from the northern property owner. If the property
develops any access to A ST NW,•some or a portion of those funds may be reimbursed to the City(total cost was$251,000).
Progress•Summary:
Pre-design was completed prior to 2007. Final design and environmental permitting were completed in 2011. Construction was completed•in 2012. The project is now in
the wetland maintenance monitoring period required until 2023.
Future Impact on Operating Budget:
The annual maintenance cost for this project is estimated to be$25,830.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue 123,276 - - - - - - - - 123,276
Secured Grants(Fed;State) 6,562,702 - - - - - - - - 6,562,702
Traffic Impact Fees 1,189,853 80,000 25,000 25,000 25,000 25,000 25,000 25,000 125,000 1,544,853
Other(Developer) 383,381 - - - - - - - - 383,381
Total Funding Sources: 8,259,212 80,000 26,000 26,000 25,000 25,000 25,000 25,000 125,000 8,614,212
Capital Expenditures:
Design 2,247,331 - 10,000 10,000 10,000 10,000 10,000 10,000 30,000 2,337,331
Right of Way 821,341 - - - - - - - - 821,341
Construction 5,000,640 - - - - - - - - 5,000,640
Monitoring 189,900 80,000 15,000 15,000 15,000 15,000 15,000 15,000 95,000 454.900
Total Expenditures: 8,259,212 80,000 25,000 25,000 25,000 25,000 25,000 26,000 126,000 8,614,212
Preliminary Engineering and Miscellaneous Projects 75
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 13
ARTERIAL STREET FUND(102), CAPITAL IMPROVEMENT FUND(328)
Project Title: Mohawks Plastics Site Mitigation Project STIP#AUB-N/A
Project No: cp0767
Project Type: Non-Capacity
Project Manager: Jeff Dixon LOS Corridor ID#N/A
Description:
The project consists of the design, construction; maintenance and monitoring of approximately 2.2-acres of wetland creation and approximately 0:4-acres of wetland
enhancement within the Goedecke South Property owned by the Sewer Utility in order to compensate for approximately 1.6-acre wetland loss on the Mohawk Plastics
property(Parcel#1321049056). The project was approved under an existing agreement approved by.Resolution No.4196, June 2007.
Progress Summary:
The City received the DOE WO Certification, WDFW HPA, and on May 7, 2009, the Army Corps of Engineers (Corps)404 wetland permit(NWS-2007-1913).
Subsequently, bid specifications and construction plans were prepared and construction began in October 2009. Construction was completed in January 2010 and the
project is currently within the 10-year monitoring period,which involves annual maintenance, monitoring and reporting. Staff anticipates to recieve early release from the
monitoring period in 2016 or 2017.
Future Impact on Operating Budget:
It is anticipated that annual maintenance, monitoring and reporting on the performance of the wetland mitigation project will be required for a period of 10 years, in
conformance with permit requirements. After the successful conclusion of this 10=year monitoring period,which is anticipated to be in December 2019, ongoing
operation expenses should be minimal.
Activity: 2018 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost.
Fund Balance - - - - - - - - -
Unsecured Grant - - . - - - - - - -
Traffic Impact Fees 496.106 20,000 20,000 - - - - - .. 536.106'
REET 2(328) 78,283 - - - - - - - - 78,283'
Total Funding Sources: 574,389 20,000 20,000 - - - - - - 614,389
Capital Expenditures:
Design - - - - - - - - -
Right ofWay - - _ - - - - - - _
Construction 574,389 20,000 20,000 - - - - - - 614,389
Total Expenditures: 674,389 20,000 20,000 - - - - - - 614,389
Preliminary Engineering and Miscellaneous Projects 76
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 27
ARTERIAL STREET FUND(102)
Project Title: A Street SE Safety Improvements Study STIP#AUB-N/A
Project No: cp1110
Project Type: Safety(Non-Capacity)
Project Manager: James WebbLOS Corridor ID#10, 33
Description:
Study the A Street SE corridor between 6th Street SE:and Lakeland Hills Way SE including 41st St SE from D St SE to C St SE. The study will review the safety and
access needs of the traveling'publicand the adjacent properties.
Progress Summary:
In-house pre-design was completed to refine project scope, alignment, and identify design issues. 2016 design will complete conceptual corridor plan for future
improvements.
Future Impact on Operating Budget:
This study will have no impact on the operating budget for street maintenance.
Activity: ,2016.YE Budget Forecast Project Cost
Funding Sources:. Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total.Project Cost
Unrestricted Street Revenue 1,230 50,000 5,000 - - - - - - 56,230
Unsecured Grant - - - - - - - - -Traffic Impact Fees - - - - - - - - - -
Ofher - - - - - _ - - - - -
Total Funding Sources: 1,230 50,000 5,000 - - - - - - 56,230
Capital Expenditures:
Design 1,230 50,000 5,000 - - - - - - 56,230
Right of Way - - - - - - - ..
Construction - - - - - - - -
Total Expenditures: 1,230 50,000 5,000 - - - - - - - 56,230
Preliminary Engineering and Miscellaneous Projects 77
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 29
ARTERIAL STREET FUND(102)
Project Title: S 272nd/277th St Corridor Capacity& Non-Motorized Trail Improvements STIP#N/A
Project No: cpxxxx
Project Type: Environmental Monitoring
Project Manager TBD LOS Corridor ID# 15
Description:
This project will compelte the environmental monitoring requirements related to the S 277th St corridor wideningproject between Auburn Way North and 1St NE.
•
Progress Summary:,
10 year monitoring period is expected to begin in 2018 after final completion.
Future Impact on Operating Budget:
There is no impact on future operatingbudgets.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022. Total Project Cost
Unrestricted Street Revenue - - - - - - - - - -
Unsecured Fed/State Grant - - - - - - - - - -
Traffic Impact Fees - - - 20,000 20,000 20,000 20,000 20,000 100,000 200,000
Other - - - - - - - - - -
Total Funding Sources:• - - - 20,000 20,000 20,000 20,000 20,000 100,000 200,000
Capital Expenditures:•
Design - - - - - - - - - -
RightofWay - - - - - - - - - -
Construction - - - - - - - - - -
Monitoring - - - 20,000 20,000 20,000 20,000 20,000 100,000_ 200,000
Total Expenditures:• - - - 20,000 20,000 20,000 20,000 20,000 100,000 200,000
Preliminary Engineering and Miscellaneous Projects 78
City of Auburn Transportation.Improvement Program
Six Year Transportation Improvement Plan TIP# 54
ARTERIAL STREET FUND(102)
Project Title: Kersey Way SE Corridor Study STIP#AUB-NIA
Project No: cpxxxx
Project Type: Capacity
Project Manager: TBD LOS Corridor ID#36
Description:
This project will study improvements to the Kersey Way SE corridor from the White River Bridge to the southern city limits. The study will develop the scope and costs for
horizontal/vertical geometric roadway improvements, roadside hazard mitigation, street lighting and non-motorized trail construction. The project length is approximately
two miles.
ProgressSummary:
Design study will begin in 2016 following the completion of the update to the Comprehensive Transportation Plan.
Future Impact on Operating Budget:
This project will have no impact on the operating budget for street maintenance.
Activity: 2016YE Budget Forecast Project Cost
Funding Sources:. Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Unrestricted Street Revenue - - - - - - 200,000 - - 200,000
Grants(Fetl,State,Local) - - - - - - 800,000 - - 800,000
Traffic Mitigation Fees - 30,000 20,000 - - - - - - 50,000
Other - - - - - - - - - -
Total Funding Sources: - 30,000 20,000 - - - 1,000,000 - - 1,060,000
Capital Expenditures:.
Design - 30,000 20,000 - - - 1,000,000 - - 1,050,000
Right of Way - - - - - - - - -
Construction - - - - - - - - -
Total Expenditures: - 30,000 20,000 - - - 1,000,000 - - 1,060,000
Preliminary Engineering and Miscellaneous Projects 79
City of Auburn Transportation Improvement Program
T
Us .-
'
� �
Au
a
�rop,..„,....0 THAN Muf�'1-t4GiNE°
Preliminary Engineering and Miscellaneous Projects 80
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 7
ARTERIAL PRESERVATION FUND (105)
Project Title: 15th•Street SW Reconstruction STIP#AUB-NIA
Project No: cpxxxx
Project Type: Preservation
Project Manager: TBD LOS Corridor ID# 12
Description:
This project will evaluate improvements to the Union Pacific at grade rail crossings as well as the vertical sight distance to the Interurban Trail crossing to the west of the
tracks.This project was originally scoped to include pavement preservation. The pavement preservation component could still be combined with this project, but is also
eligible for the Arterial Pavement Preservation Program. A planning level cost estimate is provided.
Progress Summary:
Future Impact on Operating Budget:
This project will have no impact on the operating budget for street maintenance.
Activity: 2016 YE. Budget Forecast Project Cost
Funding.Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022• Beyond 2022 Total Project Cost
Arterial Presentation Fund - - - - - - 75,000 500,000 - 575,000
Unsecured Grant - - - - - - 300,000 2,500,000 - 2,800,000
Other - - - - - - - - -Total Funding Sourcos: - - - - - •375,000 3,000,000 - 3,375,000
Capital Expenditures:
Design - - - - - - 375,000 - - 375,000
Right of Way - - - - - - - - -
Construction - - - - - - - 3,000,000 - 3,000.000
Total Expenditures: - - - •- - 375,000 3,000,000 - 3,375,000
Preservation Projects 81
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 22
ARTERIAL•PRESERVATION,FUND(105)
Project Title: Lake Tapps Parkway Preservation (City Limit to Lakeland Hills Way) STIP#AUB-51
Project•No: cpxxxx
Project Type: Preservation
Project Manager: Jai Carter LOS•Corridor ID# 17
Description: The Lake Tapps Parkway Preservation project will complete a patch and overlay of pavement'between the Auburn/Sumner City limit and Lakeland Hills Way
including all required ADA improvements to curb ramps, sidewalks, and pedestrian signals.
Progress Summary:
Federal grant was awarded in 2014.
Future Impact on Operating Budget:
There is no impact to the street maintenance budget.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Fund Balance - 26,480' 176,370 - - - - - - 202,850
Secured Grant - 97,900 652,100 - - - - - - 750,000
Other - - - - - - - - - -
Total Funding Sources:. - 124,380: 828,470 - - - - - - 962,860
Capital Expenditures:.
Design - 124,380 - - - - - - - 124,380
Right of Way - - - - - - - - - -
Construction - - 828,470 - - - - - - •828,470
Total Expenditures:. - 124,380. 828,470 - - - - - - 962,850
Preservation Projects 82
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 28
ARTERIAL PRESERVATION FUND(105)
Project Title: Annual BridgeStructure Preservation STIP#AUB-NIA
Project No: Various
Project Type: Non-Capacity, Preservation
Project Manager: Jai Carter LOS Corridor ID# N/A
Description:
This is an annual program to fund improvements to bridge structues identified by the city's annual bridge inspection program.
Progress Summary:
Future Impact on Operating Budget:
This project will have no impact on the operating budget for street maintenance.
Activity: .2016 YE Budget Forecast Project Cost
Funding Sources:, Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Arterial Preservation Fund - - - 50,000 - 50,000 - 50,000 - 150,000
Grants(Fed State,Local) - - - - - - - - - -
Other - - - - - - - - - -
_
Total Funding Sources:, - - - 50,000 - 50,000 - 50,000 - 160,000
Capital Expenditures:,
Design - - - 5,000 - 5,000 - 5,000 - 15,000
Right of Way - - - - - - - - -
Construction - - - 45,000 - 45,000 - 45,000 - 135,000
Total Expenditures: - - - 50,000 - 50,000 - 50,000 - 150,000
Preservation Projects 83
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement,Plan TIP# 35
ARTERIAL-PRESERVATION FUND(105)
Project Title: Arterial Street Preservation-Program STIP#AUB-N/A
Project.No: varies annually
Project Type: Non-Capacity, Preservation
Project Manager: Jai Carter LOS Corridor ID#N/A
Description: Implement regular pavement maintenance and/or rehabilitation of various classified streets citywide. These projects may include a combination of overlays,
rebuilds, and spot.repairs. This program is funded through-a 1% utility tax that was adopted by City Council during 2008. .
Progress-Summary:
The 2015 construction cycle included the completion of the 2014 preservation project and participation in two utility projects in-addition to the annual 2015 project. 2016
projects included providing matching funds for three federally funded preservation projects, participating in one utlity project,and completing the 2015 preservation project.
Future Impact on Operating Budget:
There is no impact to the street maintenance budget.
Activity: 2016 YE. Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Arterial Preservation Fund 4,106,338 478,699 500,000 900,000 836,720 1,017,560 1,800,000 1,800,000 - 11,439,317
Secured Federal Grant - - - - - - - - -
Other(ICON) 132,000 - - - - - - - - 132,000
Total Funding Sources:. 4,238,338 478,699 500,000 900,000 836;720 1,017,560 1,800,000 1,800,000 - 11,571,317
Capital Expenditures:
Design 200,000 - 50,000 50,000 36,720, 117,560 120,000 120,000 - 694,280
Right of Way - - - - - -
Construction 4,038,338 478,699 450,000 850,000 800,000 900,000 1,680,000 1,680,000 - 10,877,037
Total Expenditures: 4,238,338 478,699 600,000 900,000 836,720 1,017,560 1,800,000 1,800,000 - 11,571',317
Preservation Projects 84
City ofAuburn Transportation Improvement Program
Six Year Transportation ImprovementPlan TIP# 36
ARTERIAL PRESERVATION FUND FUND(105)
Project Title: Annual Arterial Crackseal Program STIP#AUB-NIA
Project No: cpxxxx
Project Type: Non-Capacity, Preservation
Project Manager: Jai Carter LOS Corridor ID# NIA
Description:
Implement regular maintenance of various classified streets by sealing newly formed cracks. Sealing the cracks will prolong the•life•of the pavement by stopping water
from draining into the sub-base of the road.
Progress Summary:
Future Impact on Operating Budget:
There is no impact to the street maintenance budget.
Activity: Previous 2 Years 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Arterial Preservation Fund 100,000 - 100,000 100,000 100,000 100,000 100,000 100,000 - 700,000
Unsecured Grant - - - - - - - - - -
Other - - - - - - - - - -
Total Funding Sources: 100,000 - 100,000 100,000 100,000. 100,000 100,000 100,000 - 700,000
I
Capital Expenditures:.
Design 10,000 - 10,000 10,000 10,000' 10,000 10,000 10,000 - 70,000
Right of Way - - - - - - - - - -
Construction 90,000 - - 90,000 90,000 90,0001 90,000 90,000 90,000 - 630,000
Intel Expenditures: 100,000 - 100,000 100,000 100,000' 100,000 100,000 100,000 - 700,000
Preservation Projects 85
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 37
LOCAL.STREET PRESERVATION FUND(103)
Project Title: Local Street Improvement Program STIP#AUB-N/A
Project No: Various
Project Type: Non-Capacity, Preservation
Project Manager: Jai Carter LOS Corridor ID# N/A
Description:
The program preserves local(unclassified) streets. The work includes crack sealing, asphalt patching, pre-leveling, asphalt overlays and roadway reconstruction.
Beginning in 2013 sales tax on construction was dedicated by council to-fund-this program.
Progress Summary:
This program has successfully completed overlays, chip seals and complete reconstructions since 2005: The program will focus on completing reconstruction needs in
addition to regular maintenancetreatments.
Future Impact on Operating Budget:
There is no impact to the street maintenance budget.
Activity: Previous 2 years 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond.2022 Total Project Cost
Local Street Preserv.Fund - 755,900 500,000 500,000 - - - - - 1,755,900
Transfer In(Utilities) 300,000 150,000 150,000 150,000 150,000 150,000 150,000 150,000 - 1,350,000
Sales Tax on Construction 3,653,965 1,450,000 1,900,000 1,900,000 1,600,000 1,600,000 1,600,000 1,600,000 - 15,303,965
Other - - - - - - - - - -
Total Funding Sources: 3,963,965 2,355,900 2,550,000 2,550,000 1,760,000 1,760,000 1,750,000 1,750,000 - 18,409,865
Capital Expenditures:
Design 600,000 300,000 300,000 300,000 300,000 300,000 300,000 300,000 - 2,700,000
Right of Way - - - - _ _ .. - - -
Construction 3,353,965 2,055,900 2,250,000 2,250,000 1,450,000 1,450,000 1,450,000 1,450,000 - 15,709,865
Total Expenditures: 3,963,966 2,355,900 2,550,000 2,550,000 1,760,000 1,760,000 1,760,000 1,750,000 - 18,409,865
Preservation Projects 86
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP#46
ARTERIAL PRESERVATION FUND(105)
Project Title: Auburn Way N Preservation Phase 2 (8th St NE to 22nd St NE)- STIP#AUB-xx
Project No: cpxxxx
Project Type: Non-Capacity, Preservation
Project Manager: TBD LOS Corridor ID#1/2
Description: This project will grind'and ovedayAuburn Way N from the 22nd Street NE to 8th Street NE, remove-unused driveways,-and upgrade all'curb ramps and
pedestrian signals to meet ADA requirements.
Progress Summary:
Federal Grant funding was applied for in 2016.
Future Impact on Operating Budget:
There is no impact to the street maintenance budget.
Activity:. 2016 YE! Budget Forecast Project Costs
Funding Sources: Prior to 2016 Estimate. 2017 2018 2019 2020 2021 2022 Beyond 2022 .Total Project Cost
Arterial Preservation Fund - - 120,000 618,280 - - - - - 738,280.E
Unsecured Federal Grant - - - 889,720 - - - - - 889;7201
Other - - - - - - - - _ -
Total Funding Sources: - - 120,000 1,608,000 - - - - 1,628,000,
Capital Expenditures:
Design - - 120,000 - - - - - - 120,000'
Right of Way - - - - - - - - - -
Construction - - - 1,508,000 - - - - - 1,508,00011
Total Expenditures: - - 120,000 1,608,000 - - - - - 1,628,000r-I
Preservation Projects 87
City ofAuburn Transportation Improvement Program
Six Year Transportation Improvement:Plan TIP#47
ARTERIAL PRESERVATION FUND(105)
Project Title: Auburn Way N Preservation•Phase 3 (4th StSE to 8th St NE) STIP#AUB-xx
Project No: cpxxxx
Project Type: Non-Capacity, Preservation
Project Manager: TBD LOS Corridor ID#2
Description: This project.will grind and•oveday Auburn Way N from approximately 8th Street NE to approximately 4th St SE, remove unused driveways, and:upgrade all
curb ramps and pedestrian signals to meet ADA requirements.
Progress Summary:
Federal Grant funding was applied for.in 2016.
Future Impact on Operating Budget:
There is no impact to the street,maintenance budget.
Activity: 2016 YE Budget Forecast Project Costs
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Arterial Preservation Fund - - - 111220 863,920 - - - - 975,140
Unsecured Federal Grant - - - 111,220 863,920 - - - - 975:140
Other - - - - - - - - - -
Total Funding Sources: - - - 222,440 1,727,840 - - - - 1,950,280,
Capital Expenditures:
Design - - - 222,440 - - - - - 222,440'
Right of Way - - - - - - - - - -
Construction - - - - 1,727,840 - - - - 1,727,840'
Total Expenditures: - - - 222,440 1,727,840 - - - - 1,950,280
Preservation Projects 88
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement'Plan TIP#48
ARTERIAL PRESERVATION FUND(105)
Project Title: A St SEPreservation (E Main•St to 17th St SE) STIP#AUB-xx
Project No: cpxxxx
Project Type: Non-Capacity, Preservation
Project Manager: TBD LOS Corridor ID#10
Description: This project will grind and•overlayA St SE between E Main:St and 17th St SE, remove unused driveways, and upgrade all curb ramps and pedestrian•signals
to meet ADA requirements.
Progress Summary:
Federal Grant funding was applied for in 2016.
Future Impact on Operating Budget:
There is no impact to the street maintenance budget.
Activity: 2016 YE Budget Forecast Project Costs
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022_Total Project Cost
Arterial Preservation Fund - - - - 99,360 782,440 - - - 881,800
Unsecured Federal Grant - - - - 99,360 782,440 - - - 881,800
Other - - - - - - - - - -
•
Total Funding Sources: - - - 198,720 1;564;880 - - 1,763,600
Capital Expenditures:
Design - - - - 198,720 - - - - 198;720
Right of Way - - - - - - - - -
Construction - - - - - 1,564,880 - - - 1,564,880
Total Expenditures: - - - 198,720 1,564,880 - - - 1,763,600
Preservation Projects 89
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement'Plan TIP# 57
ARTERIAL PRESERVATION FUND(105)
Project Title: Bridge Deck:Preservation STIP#AUB-NIA
Project No: cpxxxx
Project Type: Non-Capacity, Preservation
Project Manager: Scott Nutter LOS Corridor ID# N/A
Description:
This is a biannual program to fund the rehabilitation of bridge decks as identified by the City's•annual bridge inspection program.
Progress Summary:
R St SE StuckRiver Bridge deck repairs were completed in 2014.
Future.lmpact on Operating Budget:
This project will have no impact on the operating budget for street maintenance.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Arterial Preservation Fund - - - 100,000 100,000' 100,000 100,000 100,000 - 500,000
Utility Tax - - - - - - - - - -
Bond proceeds - - - - - _ - - - - -
Total Funding Sources: - - - 100,000 100,000 100,000 100,000 100,000 - 500,000
Capital Expenditures:.
Design - - - - - - - - - -
RightofWay - - - - - - - - - -
Construction - - - 100,000 100,000 100.000 100,000 100,000 - 500,000
Total Expenditures: - - - 100,000 100,000 100,000 100,000 100,000 - 500,000
Preservation Projects 90
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 70
ARTERIAL PRESERVATION FUND(105)
Project Title: B St NW Reconstruction STIP#AUB-N/A
Project No: CP1520
Project Type: Non-Capacity, Preservation
Project Manager: Jai Carter LOS Corridor ID# N/A
Description: The project will reconstruct the failed pavement sectiombetween 37th ST NW and north of 49th'St NW.
Progress Summary:
Design began in 2016. construction is scheduled for 2017.
Future Impact on Operating Budget:
There is no impact.lo the street maintenance budget.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2019 2020 2021 2022 Beyond 2022 Total Project Cost
Arterial Preservation Fund - 300.734 1,470,000 - - - - - - 1,770,734
Unsecured Federal Grant - - - - - - - - -
Other - - - - - - - - -
Total Funding Sources: - 300,7341 1,470,000 - - - - - - 11770,734
Capital Expenditures:
Design - 300;734'' - - - - - - - 300,734
Right of Way - - - - - -
Construction - - 1,470,000 - - - - - - 1,470,000
Total Expenditures: - 300,734T 1,470,000 - - - - - - 11770,734
Preservation Projects 9I
City of Auburn Transportation Improvement Program
Six Year Transportation Improvement Plan TIP# 71
ARTERIAL PRESERVATION.FUND(105)
Project Title: 15th Street NE/NW Preservation (SR-167 to 8th St NE) STIP#AUB-47
Project No: cpxxxx
Project Type: Non-Capacity, Preservation
Project Manager: Jai Carter LOS Corridor ID#9
Description: The project proposes to grind and overlay 15th Street NW/NE from the SR167 to Auburn Way N; and grind and overlay Harvey Road NE from Auburn Way N.
to 8th Street NE. The project will;restore 7:57 lane miles of.pavement, upgrade 30 curb ramps to meet current ADA standard, as well as remove unused driveway openings
as an upgrade to non ADA compliant pedestrian facilities. The project funds the design, coordination, permitting, and construction of the pavement preservation project.
Progress Summary:
Federal Grant Funding was securred in 2014.
Future Impact on Operating Budget:
There is no impact to the street maintenance budget.
Activity: 2016 YE Budget Forecast Project Cost
Funding Sources: Prior to 2016 Estimate 2017 2018 2011 2020 2021 2022 Beyond 2022 Total Project Cost,
Arterial Preservation Fund - 67,500 750,000 - - - - - - 817,500
Secured Federal Grant - 67,500 750,000 - - - - - - 817,500,
Other - - - - - - - - - _
Total Funding Sources: 135,000 1,500,000 - - - - - - - 1,636,000
Capital Expenditures:
Design - 135,000 - - - - - - - 135,0001
Right of Way - - - - - - - - -
Construction - - 1,500,000 - - - - - - 1,500,000'
Total Expenditures: - 135,000 1,500,000 - - - - - - 1,635,0001
Preservation Projects 92
+ a + + a a - + a + a a + a a + +• + +.
ji
1a @@ � aaza ' aak2 ` ' ' ' � - Sa ° -11 ? I � $ aao°1 S11I8 Ei �'€ € m € ; off 9C 99. , z 00 .1540€ 0• = s € e. til €: € € € � =rE22 oc =k^r`t ;t2 ' 0 hitt€ i ssgggzzaos
¢ ¢¢ ¢ ¢ ¢ d 'a : E=-0' a ae-� g' g :1- : tt g ,i ; ` c ; £ a ` : : = .ra: E a s a e a- 233 3 -�-t. c- s0' ! 1 2.222 E ' - a • a 'E • • 9
Y ¢ '€2• ¢ a n E2 nU ¢ �rFnnn ¢ ¢ ¢ ¢ Inn ¢. 1 y E ¢ ¢ a ¢ L~ ¢ 'i ' gr
g HI '
6 [ ¢ ¢¢
W -2 W e e g e 2 2 t e t t - .S f [ [ 2 C d
5 _ € E E E E S •S E 8
-
77, g Emm 'igg § gg § mgggs ggmg g gg' ggr $ gggg ? � ggggg •gg i ' ggggggg. gggg g g � g g $
g g. eg. mimggg E, gm g g g o g s - g
� m - m " : " " - m " m ms - 2 . ¢ mgm2 - s m "grill s ,, N' " ma m - r s, o � “ 16, §. n' s cg '.g g166 -- o <1;a
E E s s g
Mg , . . . . E . g „ g . , , g . g • ga g � gi g, gga $ , , . g . . . g o g g
•
qq , g . 5 . g , g , , , , , , gg , . , . . ggg g ggg. gggggg g g o s . . ggg s g s
6• " m N •a o . ” " - r ssso $ ry ii g" s 8 g. §
-
z
E g a s sg • g g o s g s a g s o s g .g g g g g g § m § m $ g g $ s g g . iiig.
3 " S m tr2 76'm of o8 in. m 2 g SI '6 6o " . 8 _ „, 'g' o s $ g g g g, " m 8 4 N q.
E
—
L
gg g gg s g 88K • g g g g Egs - a g gog g g $d6 _ .
. N " " N• 8 • 8 w S _
a . � -
m a_
a ,a r m
ote'rE , gg . gg & g g o ' g ' gd6 coo g gs g gg § § gg' g 2- l
a
U E " •
c —
g H. g EE g g og - g s g. gsl § g g g g g g § ss
a
N
c —
ilz 2 ^ m g g $ g a , , s g g g g A g ` . . , g g s g g g , g . g x s . . . a
aA m , a rzag oaCi
{{p�� o
m
U� + a 5 'e, 'e, _ HMI!
a J ' ! 7 : 0 1 .0 .4 " " " 1 " ." 55
3 _ 11
a 9 9 a 5 : , e III
1 55 , 1 E 7 ' e ' : s : a C ! ! _
ID
a a a a a a a a a s a a ¢ a a ¢ aiiii o,
: : : : a `z 4 = a 'z 3 3 3 3 'z 4 3 3 3 4 3 4 a: S : S : 7 11 2 3 h. • : : : a . : r
a ca-
w • : _ C li 6
z F £m N• 1 'E 2 z E € € ] E E • c i E •€ e E t c - .1 8 t E .F a o I.
. = aF n . a : e a c € i i 2 S 0 u09g. t o I • F @ E e c a, •9 £ ; e F e
5 8 _ _ _ E E u t e e c t [ E E e E L E L £ E. a u t ¢ 2 3 9 e i ¢ E ..
: : 2 w 2 z ,i, i 1 I E ;j6
_ g1. 1. ° 9 `m F i z z' i E o e Int° 2 :.
E 1 E : 2 c e - �•. w L u & - E E : '4.' m! n S
z �„ ,L e 2 n F m _ _ } e '^ E o - 9 tm : ¢ = S I d 6 = • =v° • $ > [ a E � 9 m a e � E a' 3u� ¢ `a n {'
•
EZ t F m F c i t e - a S ws , 4 i 2 = 2 ! a . I s : a t / ¢ _`e _ e F E 2 $ a F .2 2 E S u� ; $ 2 1 1 ^. ¢E F € - £ .; L 1! l'
E E RE E - S o n = 4e Iiii
t E n = i : 2 at ° 1e a s °2 � $ e E s o fill [a 2' - -8 umi -s g c g is g '2 rt F:' _ A m ` Y c
'' az 2 n t - ' W. c E L o ,, a t a w R 'e 2 . d o S r e: - F • .W $$a ie.
E F e F .F : s s m gs: a j 22 U -m E € _ t - : E y y ' E q ': E d i s • E 3 € ^ r t ~
3 . E E l ° a d n F • a = 'F 5 E` E 3 i & F 1 . @@ a E n E' n : i !-,- @ c' f e` n ; Zia
8 E E : ” c• d 1 n a i -;',3
El ;£ > u°v ¢• r § w E n A w i m r ° _ • ' a 1 2 2. £ ` E • 5 w: s 9 •. .- +_a a. f I t T _ S@ ua ' • F m• • ,a, n e :E ' E
a y z o` c• ye E „ _ a •i
� 3 �s w3. 3_ W d1$ �q sepal „ � ' m • WmF. : f RF �L + ; • mm 3. � •E33W-_ e o. tlE 'g3 `-Em amW S � '�'� c9d. L �� Ei:a€ tai
i a a E€ F E. i a l 6 l '1 € . of p e g a 'i dot yC n • j' o "E' � % L a' pG aE € gaa g E tj' E� “ q Q C:•> 0 1 m' ' w J t E �Z�i c= gr a
F F a E o F F i E 2 5e F F i G F t b £ C ,3' ,£S ”' N ° ,S t F x 1 m 3 F•a 3 : P t s• F _ e 3 3 3 x z 9 [ 6.n F !>`-a F
Da - ^ - ..w " ? . . . . . : . rR : . S . . 779444 : . . . . anis G : a : .r . rr,. . : :. Ya : rlrr
HIM
3 3 3 S 4 3 9 3 6 I ° 4 / a a i rig i z i z z z ^ „ „ i „ s i rcii ,. i . . ` . . . . E 3 3 3 i ? ? i ? i s i a V all
$ zc `: a 8e9 3 3 33 3 3
HMI U V > J' J > J S J V U
V V a ,• U U
(Il'1'(II .
City of Auburn 2017 - 2022 Transportation Improvement Program (TIP) AUBURN
WASHINGTON
saaa:Rse' 6
3
l
O 1 16
D.,.. .5'k-:MI ST'Sj
?.
y 70 z 4-1
37711 Sl',NW 17'f11 sr NE -+a
....
I.
•
L '.-7. I W
6 id m <
D 7'. 41" Sr.11}1111 ST 353 414 ST �1 wlnl r
69 h
_ , w
Z m
= 6S 66
f 51II TiNe y F*DR2IIII T
49 71 ,�
56 Z w
x w ♦$
• 40
�SAUIniW:RSYIo A 7 z X ( ' �. , -i.
- U VI N y + n ii X��lr
1� 6-�imiwoj 42 lir....s3J 1 1 . Sr Nr ilibillimminmm.sv.swamisl ..'i 17 39. 18 :
/
j I . tg -.„
�
59.`" 11 % /1
55 R 1 l A Y
ttLWAf,,, N.A.S2'1 " I:MAIN ST ! ,.; f
'b 2 3 /
i • J
y v III /
'InSLFY CANYON .t. Ig �44 t 41 ? ... .
aI, v.
s ��� // ,i. . ; 1
ofe
7') " i i) 48 60i! 4se
53 f
i;ISTti sr sw
7
..null sr
55 (61
3
yW 0
......m."\.
I
r
a , ,
24
1x "
'6
bk
a, ."'dP
OL
2.1111 Sf SS 0 1
J•
J. _ ...
68ST SF ..
V .. 'l.l�l\�JVtov\1n>•9W y4r
67 4
. Oar fF
fF.
k
9}
til
- ..
1 r
i
r
y
73 N
Z... ... (L _ ;
a m
z x59
6
I fi-
W
hiliki---1
•
19
No
47 I 22 �I 5
1 r
oil
,; a� ,i.—,I'Y VF0..I `
IIII ::t i
Svc,
Sw
IV,
' IIr S St..y.—...5-41H-ST-
... -81 H-ST-'SN--
tire ` J I
1100 •1.100 ','.00
imim Intersection and ITS Improvements soi=mo Preservation City of Auburn I I( I
Appendix B rritit.:41On 1.=IN IS W
OIttttttt . Non-Motorized/Transit Improvements Roadway Improvements Parks 'I''1'Ili 1-'2
---,-r ,
,r11.11;um loin shown IS I'or amend rercicnec 1,111 1,1 r,.