CITY OF AUBURN
CONTRACT CHANGE ORDER AGREEMENT NO. l
Contract No.: Contract 24-23
Project Name: Duct Cleaning for City Facilities
Contractor: Northwest Abatement Services
PO Box 39220
Lakewood,WA 98496
The Contractor is hereby directed to make the changes to the Contract as described herein. This document and all attachments
are a supplement to the contract. All work, materials, measurements and unit bid prices for the type of construction involved shall
be in accordance with the contract documents of the above named project unless stated otherwise in this change order.
Summary of Proposed Changes:
1. Duct cleaning for the entire building in addition to the recreation center and administrative offices.
The Contract time is extended by working days.
Sec. Quantity Unit Price Total Price
Item Sch. No. Item Description Units Units �$1 +��
C01-1 n/a n/a Additional duct cleaning 1 LS 5,475.00 $ 5,4 5.00
Subtotal $ 5,475.00
Washington State Sales Tax(10.3°/0)on applicable items $ 563.93
TOTAL 1 $ 6,038.93
Base Amount Total incl. Tax
1. Total Cost this C/O $ 5,475.00 $ 6,038.93
2. Total Cost Previous C/O -
3. Original Contract Amount $ 83,162.00 $ 91,727.69
4. Revised Contract Amount $ 88,637.00 $ 97,766.62
This change order constitutes full and complete compensation for all labor, equipment, materials, overhead, profit, any and all
indirect costs, and time adjustment to perform the above described changes. All other costs are non-compensable. All other
terms and conditions of the Contract remain unchanged.
Counterparts: This agreement may be executed in multiple counterparts, each of which shall be one and the same Agreement
and shall become effective when one or more counterparts have been signed by each of the parties and delivered to the other
party.
DocuSigned by:
1-Contractor:
.L ai44, 9/9/2024
D48O246B Date
Project Manager: Fisa titoo� 9/9/2024
ibbb414etCbs42d
DocuSigned by Date
Approved by: N.� 9/9/2024
O"tfik of Auburn Date
Signed by
Approved as to form: iaS0-N UM-a(/0N 9/9/2024
�epuiyCify Attorney Date
ENG-028, Revised 01/21 Page 1 of 1