HomeMy WebLinkAboutAG-C-580-A1 CP2406, Auburn Ave Theater Demo, Bluestone Environmental NW-----------------------------------------------------------------
Amendment No. 1 for Agreement No. AG-C-580
Bluestone Environmental NW
ENG-182, Revised 08/24, Legal Review 10/18
Page 1 of 1
THE CITY OF AUBURN AND BLUESTONE ENVIRONMENTAL NW
AMENDMENT TO AGREEMENT FOR SERVICES AG-C-580
RELATING TO PROJECT NO. CP2406, AUBURN AVE THEATER DEMOLITION
THIS AMENDMENT TO THE AGREEMENT is made and entered into by and between the
CITY OF AUBURN, a municipal corporation of the State of Washington (hereinafter referred to
as the “CITY”), and Bluestone Environmental NW (hereinafter referred to as the “PROVIDER”).
The City and Provider agree to amend the Agreement AG-C-580 executed on the 29th day of
October 2024.
The changes to the Agreement are described as follows:
1. CONTRACT TERM: The term of the Agreement for Professional Services is extended to
December 31, 2025.
2. SCOPE OF SERVICES: The scope of work is amended to include the following tasks that
will be performed in a good and professional manner: See Exhibit A, which is attached
hereto and by this reference made part of this Amendment
3. COMPENSATION: The amount of this amendment is $2,700.00. As total compensation for
the Provider’s performance of the services provided based on this Amended Agreement, the
City shall pay the Provider fees and costs not-to-exceed $22,700.00. See Exhibit B, which
is attached hereto and by this reference made part of this Agreement.
REMAINING TERMS UNCHANGED: All other provisions of the Agreement between the parties
for AG-C-580 executed on the 29th day of October 2024, shall remain unchanged, and in full
force and effect.
IN WITNESS WHEREOF the parties hereto have executed this Agreement as of the day and
year first above written.
BLUESTONE ENVIRONMENTAL NW CITY OF AUBURN
By: ___________________________ ____________________________
Authorized signature Nancy Backus, Mayor
Date:__________________________ Date:________________________
Approved as to form (Optional): Approved as to form:
________________________________ _____________________________
Attorney for (Other Party) Jason Whalen, City Attorney
Docusign Envelope ID: 6828F1CD-77C2-44EB-8A9F-7451A5D8510C
11/25/2024 11/26/2024
BE-0207-A UST Assess
Bluestone Environmental NW
253.951.2024
November 4, 2024
City of Auburn
Public Works Engineering Division
Mr. Samim Qayoomi
25 West Main Street
Auburn, WA 98001
Subject:Service Authorization, UST Decommissioning Assessment
Project Number BE-0207-A
Old Auburn Theater
10 Auburn Avenue
Auburn, WA 98002
Dear Mr. Qayoomi:
Thank you for requesting Bluestone Environmental NW (Bluestone) to assist you with a
underground storage tank (UST) assessment during the decommissioning process. Per
your request, we are sending this proposal to authorize our services.
Bluestone is committed to providing a level of service that suits our client’s
requirements. If the proposed efforts are not in alignment with your needs, please
contact us to discuss how we can better assist you.
For this authorization, the understood efforts you have requested include:
Observation and documentation of UST removal.
Collect assessment soil samples.
Prepare decommissioning and assessment documentation for the removed UST.
These tasks are further described below.
EXHIBIT ADocusign Envelope ID: 6828F1CD-77C2-44EB-8A9F-7451A5D8510C
BE-0207-A UST Assess
Page 2 of 3
SOIL ASSESSMENT – UST REMOVAL
Bluestone understands that the underground storage tank (UST) will be made
accessible to observe the removal of the tank. To complete the assessment efforts,
three soil samples will be collected. Specifically, one sample will be collected 6-12-
inches below the bottom of the UST basin and two samples will be collected from the
bottom 1/3 of the UST basin sidewalls (one side wall and one end wall). Soil samples
will be submitted for laboratory analysis by Method NWTPH-Dx.
DECOMMISSIONING DOCUMENTATION
The UST decommissioning will be documented by a certified UST decommissioning
assessor. A letter report providing a certificate of removal will be provided. The
certificate of removal will be issued upon receipt of payment.
A UST decommissioning report will be prepared to document the assessment efforts.
The report will include text, summary analytical tables, and figures to show the sampled
locations and the approximate location of the UST, and a discussion of our findings.
Analytical results will be compared to appropriate cleanup levels (Method “A” ) set by
Ecology under the MTCA Cleanup Regulation (dated November 2007, revised in August
2023).
Project Parameters
The parameters for the proposed costs regarding the efforts discussed above are based
on the following.
Site access will be available to Bluestone personnel.
The UST area and surrounding area will be cleared of obstructions that would
prevent access to the UST / UST excavation.
The UST is 500-gallon size or less.
Observation efforts will be completed within one 8-hour day.
Weekend and/or night work will not be required. .
Docusign Envelope ID: 6828F1CD-77C2-44EB-8A9F-7451A5D8510C
BE-0207-A UST Assess
Page 3 of 3
Proposed Costs
Our estimated costs to complete the proposed tasks are listed below.
Proposed Services Low Proposed
Costs
High Proposed
Costs
UST Removal Observations and Assessment
Activities
$1,200 $1,500
Decommissioning and Assessment
Documentation Preparation
$900 $1,200
Total of Proposed Costs $2,100.00 $2,700.00
All charges for our services will be on a time-and-materials basis, in accordance with
our current Environmental Services Fee Schedule. Our total fee for this project will not
exceed our proposed costs without a change in the presented scope of services and
only with your authorization. Invoices are payable within 30 days of the invoice date as
outlined in the attached our terms of services agreement.
Limitations
The proposed services and costs have been designed and prepared based on our
understanding of site conditions based on our conversations with the client. Discovered
conditions beyond those addressed in our proposed services may warrant additional
charges if activities and/or tasks outside of our proposed scope are performed.
Authorization
These efforts will be performed after receipt of authorization to proceed from the City of
Auburn.
Closing
We appreciate the opportunity to provide our services. Please contact us if you have
questions regarding our proposed services or costs.
Sincerely,
Bluestone Environmental NW
Dan Hatch
President
EXHIBIT B
Docusign Envelope ID: 6828F1CD-77C2-44EB-8A9F-7451A5D8510C