HomeMy WebLinkAbout2025-0279 - AG-C-556 - - ARC Architects (3rd Amendment) RE: Cost Estimate - ARC Arcarchitects Docusign Envelope ID:9CF28D66-5D74-49A1-8F55-872A0D369257
THE CITY OF AUBURN AND ARC ARCHITECTS THIRD (3rd)
AMENDMENT TO AGREEMENT FOER SERVICES AG-C-556
RELATEING TO AUBURN CONSOLIDTAED RESOURCE CENTER
ARCHITECTURAL DESIGN
THIS AMENDMENT TO THE AGREEMENT is made and entered into by and between
the CITY OF AUBURN, a municipal corporation of the State of Washington, (hereinafter
referred to as the "CITY"), and ARC ARCHITECTS (hereinafter referred to as the
"PROVIDER"). The City and Provider agree to amend the Agreement AG-C-556
executed on the 28th day of March 2022.
The Changes to the Agreement are described as follows:
1. SCOPE OF SERVCIES: See Exhibit A, which is attached hereto and by this
reference made part of this agreement
2. COMPENSATION: This amendment increases the total amount of this
agreement by $12,500. As total compensation for the Provider's performance of
the services provided based on this Amended Agreement, the City shall pay the
Provider fees and costs not-to-exceed $145,111.00. See Exhibit A, which is
attached hereto and by this reference made part of this Agreement.
3. REFERENCED DOCUMENT: The contract and Amendment 1 and 2 are attached
as exhibits to this Agreement as reference.
THE REMAINING TERMS UNCHANGED: All other provisions of the Agreement
between the parties for AG-C-556 executed on the 28th day of March 2022, shall
remain unchanged, and in full force and affect.
IN WITNESS THEREOF, the parties hereto have executed this Agreement as of the day
and year first above written.
ARC ARCHITECTS CITY OF AUBURN
Signed by DocuSignetl by:
By: '1944 F
Authorized Signature Nancy Backus, Mayor
Date: 6/10/2025 Date: 6/11/2025
Approved as to form (Optional) Approved as to form:
(-Signed by
etal, brit),
Attorney for PROVIDER Paul Byrne, Deputy City Attorney
Amendment No 3 for Agreement No. AG-C-556
ARC Architects
ENG-182 Revised 12/22
Page 1 of 1
Docusign Envelope ID:9CF28D66-5D74-49A1-8F55-872A0D369257
119 5 MAIN STREET,STE 200,SEATTLE WA 98104-2579 206.322.3322 WWW.ARCARCHITECTS.COM
arc
05/28/2025
Attn:Jodi Davison,CDBG/Human Services Coordinator,City of Auburn,WA
Submitted via e-mail to JDavison@auburnwa.gov
RE:Professional Architectural Services Restart—Bid/Construction Administration
Jodi:
We are glad our contract extension of time remains in place,and we appreciate our request to update the
hourly fees as well as cover some additional scope needs.
The total proposal for the Auburn Consolidated Resource Center,which includes architectural and consultant
professional services in support of the"restart"for Bid and Construction Administration phases fortenant
improvements to the building located at 2826 Auburn Way N.is$12,500,inclusive of reimbursable expense.
Fee Summary
Design fees for the first phases were originally completed in 2021 on an estimated and approved budget using
a MACC of$1,400,000. As we completed the design phases,we updated the original cost assumption,and the
MACC was increased to approximately$2.1M. While that was a significant increase in the estimate of
construction costs for 2023,none of the design team ever requested additional fees.Since then,the project
went on"hold"and now that it is re-starting,ARC,along with our consultants are asking for a minimal up-tick in
fee.The rationale is as follows:
• Hourly rates have increased for all
• Referencing the"updated"MACC as well as the WA State Fee Schedule(2025 updated,schedule B):
o Last official cost estimate was$2.1 M x 10.08%=$211,680(total design allowable fee)
• CA suggested fee percentage(including bid phase)is 29%which equals$61,387
(allowable phase fee)
o NOTE:We show the fee schedule for reference only to see we are not requesting full amount
• Total team current request is$48,450,including expenses
o Subtract the remaining(under current contract budget)balance fee of$35,950
o The difference is$12,500
• Note,Exhibit A detail shows zero dollars for another cost estimate. We will tap into the remaining fee
that exists for that consultant to cover the cost of the new estimate.
See further detail in the fee proposal dated 5/30/25 for"Architectural and Engineering Services"attachment to
this letter.
Should the construction cost estimate,when undated aoain under this proposalexceed 20%of last cost
update,we reserve the right to amend our fee accordingly.
City of Auburn Consolidated Resource Center Proposal Restart-Page I 1
Docusign Envelope ID:9CF28D66-5D74-49A1-8F55-872A0D369257
119 5 MAIN STREET,STE 200,SEATTLE WA 99104-2579 206.322.3322 WWW.ARCARCHITECTS.COM
Project Understanding
By understanding,the City is now the owner of this property and the facility. While the city is not revising the
design,it is our understanding that you would like to receive a new project cost estimate to reflect a fall of 2025
bid date. For ourestimating use,you have shared with us some current facility cost expectations generated
from a facility conditions report. They are a)roof-top mechanical units**b)building plumbing(below slab
clean-out)work,c)parking lot asphaltic cement overlay. While we do not intend to increase the design scope
for these items,we will reference these estimates in providing the new project cost update.
**design to support the tenant improvement space and cost assumptions were included in all our original
documents
Sincerely,
Daniel Podoll I Principal,Project Manager
ARC Architects:(206)900-0324
Attachments:
Exhibit A—Fee Proposal—Architectural/Engineering Services
City of Auburn Consolidated Resource Center Proposal Restart-Page 12
Docusign Envelope ID:9CF28D66-5D74-49A1-8F55-872A0D369257
City of Auburn Community Resource Center-RESTART for Bid/CA EXHIBIT A
FEE PROPOSAL-ARCHITECTURAL/ENGINEERING SERVICES
5/30/2025
FEE SUMMARY fee overhead amount remarks
WSFS Basic Service Consultants 10.08% $2,100,000 $211,680 $211,680 2025 Schedule B,CA suport
CA 29% $61,387 for _'_ _ _ides bid phase
architect $31,070 I S31,070
structural 55,000 1.1 $5,500 OCE
mechanical,plumbing,FS $7,000 1.1 $7,700 Fsi
electrical/IT/security 53,000 1.1 $3,300 TFWB
Specialty Consultants
estimator $0 1.1 $0 will tap into remaining fee
SUBTOTAL I $47,570 I
ESTIMATED EXPENSES fee overhead amount remarks
architect $800 1.1 in addition to orig 5880 mileage to Auburn
structural S0 1.1 SO see original fee
mechanical,plumbing,FS 50 1.1 $0 see original fee
electrical/IT SO 1.1 $0 see original fee
ESTIMATED EXPENSES $880
Total CA fee S48,450 including expense
Current Contracted CA fee $35,950 remaining balance
TOTAL ADDITIONAL SERVICE REQUEST I S12,500 I
(2025)ARC BILLING RATES
Managing Principal/Project Manager(P) S220 $162
Project Manager A-1/3-5(PM) $145
Staff Designer RCG(SD) $120
Tasks P PM SD remarks
task 1-specifications
specification updates/completion 12 8 8
division 00-01 coordination 12 6 6
task 2-bid/CA/closeout
restart/document re-packaging 4 8 10 valid
construction support 18 8 32 (4wks)in addition to orig duration
punch and backpunch 4 0 12 new from original
Meetings
pre-bid 4 4 4 city led
CA pre-con 4 4 4 city led
construction admin meetings 8 0 16 OAC in addition to orig
Hours 66 38 92
Hourly Rate 5220 5145 $120
Subtotal Fee $14,520 $5,510 $11,040
TOTAL ARCHITECTURAL FEE I S31,070 I
1 S48,450 I GRAND TOTAL