Award Contract 03-04
Department: Attachments: Budget Status Sheet, Budget Impact:
Public Works Bid Tab Summary, Map $ 0
Administrative Recommendation:
City Council award Small Works Contract 03-04, Project Number C306A, Coal Creek Springs Security
Hatches, to Gary Harper Construction Inc. on their Iow bid of $71,100.00 plus WA state sales tax of
$6,256.80 for a total contract price of $77,356.80.
Background Summary:
This project will provide for the removal of seven manhole frames and covers and replace them with
seven access hatches; removal of flow control vault top cover and replacement with a new top cover
complete with two access hatches and one valve box; and removal of the four knife gate valves and
replacement with four butterfly valves. The estimated project start and completion dates are, respectively,
January 2004 to March 2004.
A project budget contingency of $85,900 remains in the 430 Water Fund.
As noted on the Bid Tab Summary, the apparent Iow bidder, RW Scott Construction, claimed an error per
WSDOT Standard Specifications 1-03.1. Upon review of the documentation provided by RW Scott, staff
concurs and recommends that they be relieved of their responsibility.
W1215-5
O4.11.1 PR C306A
Reviewed by Council & Committees: Reviewed by Departments & Divisions:
[] Arts Commission COUNCIL COMMITTEES: [] Building [] M&O
[] Airport [] Finance [] Cemetery [] Mayor
[] Hearing Examiner [] Municipal Serv. [] Finance [] Parks
[] Human Services [] Planning & CD [] Fire [] Planning
[] Park Board []Public Works [] Human Resources [] Police
[] Planning Comm. [] Other [] Legal [] Public Works
Action:
Committee Approval: []Yes []No
Council Approval: []Yes []No Call for Public Hearing / /__
Referred to Until / /
Tabled Until / /
Councilmember: Wagner Staff: Dowdy
Meeting Date: December 15, 2003 Item Number: V.D.1
AUBURN * THAN YOU IMAGINED
IProJect No: C306A
BUDGET STATUS SHEET
Project Title: Coal Creek Springs Hatches
PS&E @ 100%
Prs-bid
Award X
Const. @ 0 %
Date: 12/02/03
The "Future Years" column indicates the projected amount to be requested in future annual budget requests.
Funds Budgeted (Funds Available)
Funding Prior Years 2003 2004' Future Years Total
430 Fund 100,000 75,000 175,000
Total 0 100,000 75,000 0 175,000
Estimated Cost (Funds Needed)
Activity Prior Years 2003 2004' Future Years Total
Design Engineering 3,300 3,300
Properb/Acquisition 0
Construction Estimate or Bid 77,400 77,400
Line item Changes 0
Change Order #1 0
Construction Contingency (5%) 3,900 3,900
Other 0 0
Construction En~lineering 5,000 5,000
Totar 0 3,300 86,300 0 89,600
430 Funds Budgeted
430 Funds Needed
(430 Fund ProJect Contingency)
430 Funds Required
430 Bud~let Status
Prior Years ~ 2003
100,000
3,300
0 (96,700)
0
2004 I Future Yearn ~ Total
75,000 175,000
86,300 89,100
tl,3000 00 (85,900)0
W1215-5A
Project Name:
Prepared by :
Pdnt Date :
BID TABULATION
BID TOTALS SUMMARY
C306A, Coal Creek Springs Security Hatches
City of Auburn
12/2/2003
ENGINEER'S ESTIMATE : $ 63,820.00
AVERAGE BASIC BID AMOUNT : $ 75,728.00
BASIC BID SPREAD AMOUNT : $ 35,820.00 Basic BID Amount Spread $ Spread %
LOW BIDDER : Gary Harper Construction Inc $ 71,100.00 $17,280.00 32.t 1%
Second Bidder : Pivetta Brothers Construction $ 78,860.00 $25,040.00 46.53%
Basic BID (Tax not Included) Total BID (Tax Included)
RW Scott Construction $ 54,180.00 $ 58,947.84
Gary Harper Construction Inc $ 71,100.00 $ 77,356.80
Pivetta Brothers Construction $ 78,860.00 $ 85,799.68
Rodarte Construction $ 84,500.00 $ 91,936.00
Scotty's General Construction NON-RESPONSIVE NON-RESPONSIVE
Nordic Construction $ 90,000.00 $ 97,920.00
Contractor claimed error per VVSDOT
Std. Specs 1-03.1. Contractor failed
to include all matedal costs in initial
bid.
12/3/2003 (2:01 PM)
h:\proj \bidtabs\C306A BT-Revised.xls
4