HomeMy WebLinkAbout10-18-2004 ITEM V-D-1CITYOF
AGENDA BILL APPROVAL FORM
WASHINGTON
Agenda Subject
Date:
Final Pay Estimate No. 2 to Contract 03-07
October 11, 2004
Department:
Attachments: Budget Status Sheet,
I
Budget Impact:
Finance
Final Pay Estimate No. 2
Administrative Recommendation:
City Council approve Final Pay Estimate #2 to Contract 03-07 with Icon Materials and accept construction
of Project No. C312A, 2004 Runway Improvements Auburn Municipal Airport.
Background Summary:
City Council authorized the solicitation of bids for the runway improvement project on June 16, 2003.
This two-part project provided for the following: Schedule A provided runway pavement crack repair,
asphalt pavement construction of approximately 370 feet by 75 feet of runway, asphalt overlay of 3,400
feet by 75 feet of runway, and installation of subsurface edge drains along both sides of the runway;
Schedule B provided for construction of a new hold apron with subsurface edge drains, and associated
lighting and signing improvements. The project was completed in September 2004.
N1018-1
04.4.9.2
Reviewed by Council & Committees:
Reviewed by Departments & Divisions:
❑ Arts Commission COUNCIL COMMITTEES:
❑ Building ❑ M&O
❑ Airport ❑ Finance
❑ Cemetery ❑ Mayor
❑ Hearing Examiner ❑ Municipal Serv.
❑ Finance ❑ Parks
❑ Human Services ❑ Planning & CD
❑ Fire ❑ Planning
❑ Park Board ®Public Works
❑ Human Resources ❑ Police
❑ Planning Comm. ❑ Other
❑ Legal ® Public Works
Action:
Committee Approval: ❑Yes ❑No
Council Approval: ❑Yes ❑No Call for Public Hearing
Referred to Until _/
Tabled Until
Councilmember: Cerino Staff: Coleman
Meeting Date: October 18, 2004 Item Number: V.D.1
AUBURN * MORE THAN YOU IMAGINED
BUDGET STATUS SHEET
_Q PS&E @ XX%
0 Pre-bid Date: October 11, 2004
0 Award
• Const.
The "Future Years" column indicates the projected amount to be requested in future annual budget requests.
Funds Budceted (Funds Available)
$ 445,242$_
0 $_ _
445,242
$ 369,259
(900,000.00)
$ 369,259
$ 34,453
770,275.83 1
$ 34,453
$_ 51,046
(Fund Project Contingency) 01
$_ 51,046
01 0 1$ ____ '900,0001 0
Actual Cost
2004 Budget Status
0
0 $_ _
_(900,000.00)
0 $
(900,000.00)
0
0 1 $
770,275.83 1
0 $
770,275.83
(Fund Project Contingency) 01
0 $
(129,724.17)
0 1 $
(129,724.17)
Funds Required 01
0 1
01
01
0
CITY OF AUBURN CO. NO. 03:07
C312A 2004 Runway Improvements Auburn Municipal Airport
PAY ESTIMATE #2 & FINAL SCHEDULE A: Base Bid
ITEM
ESTIMATE
TOTAL
PERIOD
UNIT
UNIT COST
TOTAL COST
PERIOD COST
PERCENT EST.
NO.
ITEM DESCRIPTION
QUANTITY
QUANTITY
QUANTITY
TYPE
QTY -
Al
Mobilization
1
1
0
LS
62,000.00
$
62,000.00
$
-
100%
A2
Construction Staking
1
1
0.25
LS
20,000.00
$
20,000.00
$
5,000.00
100%
A3
Temp. Flagging, Marking, and Signing
1
1
0.25
LS
87,600.00
$
87,600.00
$
21,900.00
100%
A4
Soil Stabilization Fabric
3,170
3286
1161
SY
1.60
$
5,257.60
$
185.60
104%
A5
Crack Cleaning and Sealing
20,000
13010
34101
LF
0.75
$
9,757.50
$
2,557.50
65%
A6
Pavement Crack Reconstruction
470
560
0
LF
9.00
$
5,040.00
-
119%
A7
Pavement Milling
1,340
365
365
SY
3.00
1,095.00
$
1,095.00
27%
A8
Pavement Pulverization
3,085
3085
0
SY
3.00
$
9,255.00
-
100%
A9
'Quarry Spalls
1,055
1055
0
CY
29.00
$
30,595.00
$
-
100%
A10
Unclassified Excavation
2,640
2640
0
CY
15.00
39,600.00
$
-
100%
All
Import Borrow
525
351.16
351.16 'TON
22.00
$
7,725.52
$
7,725.52
67%
Al2
Aggregate Subbase Course
2,360
1883.94
0
TON
11.00
$
20,723.34
$
-
80%
A13
Temporary Erosion Control
1
1
0.25
LS
1,500.00
$
1,500.00
$
- 375.00
100%°
A14
Crushed Aggregate Base Course
515
513.61
0
TON
15.00
7,704.15
$
-
100%
A15
Bituminous Surface Course
4,700
5185.29
4845.41
TON
43.00
222,967.47
208,352.63
.110%
A16
Runway and Taxiway Painting
5,300
5320
5320
SF
0.65
3,458.00
$
3,458.00
100%
A17
Subsurface Edge Drain
5,965
5965
0
LF
12.00
i $
71,580.00
$
-
100%
Ali
Transverse Edge Drain
270
270
0
LF
16.00
4,320.00
$
-
100%
Al
Transverse Edge Drain in Pavement
310
310
0
LF
42.00
$
13,020.00
$
-
100%
A20
Catch Basin - Type 1
4
4
0
EA
1,400.00
$
5,600.00
$
-
100%
A21
Seeding and Fertilizing
1.20
1.2
1.2
AC
1,000.00
$
1,200.00
$
1,200.00
100%
A22
Adjust Existing Runway Edge
8
0
0
EA
300.00
$
-
$
0%
h:\proj\pe\C312A PE#2.xiS
Period Dates
Begin: September 2, 2004
End: September 20, 2004
1 of 4
SCHEDULE TOTAL $ 251,849.25
9/20/2004 at 11:02 AM
CITY OF AUBURN
C312A
PAY ESTIMATE #2 & FINAL
CO. NO. 03-07
2004 Runway Improvements Auburn Municipal Airport
SCHEDULE B: Hold Apron Construction
ITEM
NO.
ITEM DESCRIPTION
ESTIMATE
QUANTITY
TOTAL
QUANTITY
PERIOD
QUANTITY
UNIT
TYPE
UNIT COST
TOTAL COST
PERIOD COST
PERCENT EST. -
QTY
B1
Mobilization
1
1
0
LS
4,000.00
$
4,000.00
-
100%
B2
Construction Staking
1
1
0.25
LS
2,000.00
2,000.00
$
500.00
100%
B3
Temp. Flagging, Marking, and Signing
1
1
0.25
LS
4,000.00
$
4,000.00
$
1,000.00
100%
B4
Demolition
1
1
0
LS
4,000.00
$
4,000.00
$
100%
B5
Pavement Milling
460
460
0
SY
3.00
$
1,380.00
$
-
100%
B6
Paint Removal
430
465
465
SF
2.00
$
930.00
$
930.00
108%
B7
Unclassified Excavation
200
200
0
CY
15.00
$
3,000.00
$
-
100%
B8
Unsuitable Excavation
30
53
38
CY
15.00
$
795.00
$
570.00
177%
B9
Import Borrow
45
0
0
TON
22.00
$
$
-
0%
B10
Aggregate Subbase Course
300
407.86
180.37
TON
11.00
$
4,486.46
1,984.07
136%
B11
Temporary Erosion Control
1
1
0.1
LS
300.00
$
300.00
$
30.00
100%
B12
Crushed Aggregate Base Course
100
123
-17.17
TON
15.00
$
1,845.00
$
(257.55)
123%
B13
Bituminous Surface Course
115
111.06
111.06
TON
43.00
$
4,775.58
$
4,775.58
97%
B14
Runway and Taxiway Painting
950
950
950
SF
0.65
$
617.50
$
617.50
100%
B15
18" RCP Storm Pipe
33
32
0
LF
60.00
$
1,920.00
$
-
97%
B16
Subsurface Edge Drain
155
155
0
LF
12.00
$
1,860.00
$
-
100%
B17
Transverse Edge Drain
20
20
0
LF
16.00
$
320.00
$
-
100%
B18
Seeding and Fertilizing
0.10
0.1
0.1
AC
1,000.00
I $
100.00
$
100.00
100%
B19
Lighting and Signing Complete
r1
1
0.5
LS
6,500.001$
6,500.00
$
3,250.00
1000/0
h:\proj\WC312A PE#2.xls
Period Dates
Begin: September 2, 2004
End: September 20, 2004
2of4
SCHEDULE TOTAL $ 13,499.60
t CITY OF AUBURN C312A, 2004 Runway Improvements Auburn Municipal Airport
PROJECT SUMMARY CO. NO. 03-07
PAY ESTIMATE #2 & FINAL
TOTAL PAYMENT TO CONTRACTOR
PAYMENT DUE CONTRACTOR:
h:\prollpe\C312A PE#2.xls
Period Dates
Begin: September 2, 2004
End: September 20, 2004
3of4
$ 698,395.59 $ 275,432.11
$ 275,432.11
9/20/2004 at 11:02 AM
Original Contract
Contract Change
Amount
Orders
Total Payment
This Period . Percent/Contract
SCHEDULE A: Base Bid
Contract
$
627,772.00
$ -
$
629,998.58
$
251,849.25 100%
Sale's Tax (+8.8%)
$
55,243.94
$ -
$
55,439.88
$
22,162.73
Retainage (-5%)
$
-
$ -
$
31,499.93
$
12,592.46
SCHEDULE TOTAL
$
683,015.94
$ -
$
653,938.53
$
261,419.52
SCHEDULE B: Hold Apron Construction
Contract
$
42,102.50
$ -
$
42,829.54
$
13,499.60 102%
Sales Tax (+8.8%)
$
3,705.02
$ -
$
3,769.00
$
1,187.96
Retainage (-5%)
$
-
$ -
$
2,141.48
$
674.98
SCHEDULE TOTAL
$
45,807.52
$ -
$
44,457.06
$
14,012.58
TOTAL PAYMENT TO CONTRACTOR
PAYMENT DUE CONTRACTOR:
h:\prollpe\C312A PE#2.xls
Period Dates
Begin: September 2, 2004
End: September 20, 2004
3of4
$ 698,395.59 $ 275,432.11
$ 275,432.11
9/20/2004 at 11:02 AM
• V, CITY OF AUBURN CO. NO. 03-07
C312A 2004 Runway Improvements Auburn Municipal Airport
PAY ESTIMATE #2 & FINAL
CONTRACTOR:
Icon Materials
PO Box 88050
Tukwila WA 98138
Phone: 206.575.3200 fax 206.575.3207
The undersigned has reviewed" and approved this final pay estimate. I agree that it is a true and correct statement
showing all monies due me from the City of Auburn under this contract; that I have carefully examined the final pay estimate
estimate and understand it and that I hereby release the City of Auburn from any and all claims of whatsoever
nature which I may have, arising out of this contract, which are not set forth in this estimate.
PAY AMOUNT DUE CONTRACT = $ 275,432.11
Signatures:
Contractor �/IfDate 1127101
City Inspector Lam- Date G' -7. o
kUZJDate / C/
City Project Manager
W&H Pacific Project Manager Date D
City Engineer Date 2
hAproj\pe\C312A PE#2.xls 4 of 4 9/20/2004 at 11:02 AM