HomeMy WebLinkAbout09-06-2005 ITEM II-A-1A� ►U
WASHINGTON
AGENDA BILL APPROVAL FORM
Agenda Subject:
Date:
Conduct Public Hearing on 2006-2011 TIP
August 23, 2005
Department:
Attachments:
I
Budget Impact:
Public Works
Draft 2006-2011 Six -Year TIP
$0
Administrative Recommendation:
City Council to conduct a public hearing on the adoption of the 2006-2011 Six -Year Transportation
Improvement Program (TIP).
Background Summary:
W0906-1
04.9.3
Reviewed by Council & Committees:
Reviewed by Departments & Divisions:
❑ Arts Commission COUNCIL COMMITTEES:
❑ Building
❑ M&O
❑ Airport ❑ Finance
❑ Cemetery
❑ Mayor
❑ Hearing Examiner ❑ Municipal Serv.
❑ Finance
❑ Parks
❑ Human Services ❑ Planning & CD
❑ Fire
❑ Planning
❑ Park Board EPublic Works
❑ Human Resources
❑ Police
❑ Planning Comm. ❑ Other
❑ Legal
E Public Works
Action:
Committee Approval: []Yes ❑No
Council Approval: []Yes []No
Call for Public Hearing
Referred to Until
Tabled Until
Councilmember: Wagner
Staff: Dowd
Meeting Date: September 6, 2005
Item Number: II.A.1
AUBURN* MORE THAN YOU IMAGINED
I
fl
V
- I I
. I I I ,
La "L,
It 'Ek,
- I I
. I I I ,
La "L,
00T11AN Y0(j IMAGINtV
Mayor
Pete Lewis
City Council
Rich Wagner, Public Works Committee Chairman
Bill Peloza, Public Works Committee
Roger Thordarson, Public Works Committee
Gene Cerino
Lynn Norman
Nancy Backus
Sue Singer
Staff
Dennis Dowdy Public Works Director
Dennis Selle City Engineer
Laura Philpot Traffic Engineer
Photos on the Cover Listed Left to Right: 1. 3`d Street Post Office Crosswalk; 2. Save Our
Streets Program Asphalt Overlay
i
Table of Contents
TitlePage................................................................................................................. i
.
Table o Contents........................:........................................................................... tt
Proiect List
Roadway Improvements
3`t Street SE/Cross Street SE.......................................................................1
AStreet SW Loop........................................................................................2
Auburn Way South Safety Improvements...................................................3
Urban Area Transportation System Management Improvements ...............4
A Street NW, Phase 1 (3`t Street NW to 140' Street NW) ...........................5
Citywide Intelligent Transportation System (ITS)......................................6
IStreet NE Corridor.....................................................................................8
M Street SE Grade Separation (E. Main to Auburn Way South) ................9
S 277th Street (AWN to Green River Bridge)............................................10
15th Street SW Reconstruction (C Street SW to UPRR)............................11
15th Street SW Preservation (C Street SW to UPRR).............................11A
A Street NW, Phase 2 (West Main Street to 3`t Street NW) .....................12
C Street NW (West Main Street to 3't Street NW)....................................13
D Street NW (37th Street NW to 44th Street NW)......................................14
F Street SE (4th Street SE to Auburn Way South).....................................15
M Street NE (East Main Street to 8th Street NE/Harvey Road).................16
SR -18 EB Ramp (6th St SE to AWS w/ Grade Separation at BNSF) ........
17
Intersection Improvements
Harvey Road/8th Street Capacity Improvcmcnt.........................................18
Non -Motorized Improvements
Auburn Way Corridor— Pedestrian Crossing..............................................7
Auburn/Pacific Trail (C St SW from 15`h St. SW to Pacific City Park) .... 19
West Main Street Non -Motorized (Interurban to Transit Ccntcr) .............20
BNSF/East Valley Hwy Pedestrian Undercrossing..................................21
A Street SE Pedestrian Improvement........................................................22
White River Trail Extension......................................................................23
37th St SE/R Street SE Connector..............................................................24
Six Year Transportation Improvement Program 2006-2011 ii
Table of Contents
Non -Motorized Improvements Continued...
Green River Trail, Phase 1 (Green River Access to Brannan Park) ..........25
Green River Trail, Phase 2 (Brannon Park to 41h St SE)............................26
Green River Trail, Phase 3 (4`h St SE to SR -18) ........................................27
Academy Drive Multi Use Trail................................................................28
Studies and Miscellaneous Improvements
A Street SE — Class 2 Trail (6th St to Ellingson along BNSF Yard) .......... 29
Auburn Black Diamond Road — Class 1 Trail...........................................30
KerseyWay Trail.......................................................................................31
Pavement Condition Rating Update...........................................................32
M Street SE (37`h St Se to 29`h St. SE).......................................................38
Annual Level of Effort Projects
S.277 th Street Wetland Mitigation............................................................33
Citywide Pedestrian Crossing Program.....................................................34
Citywide Roadway Safety Infrastructure Improvements ...........................35
Arterial Pavement Preservation.................................................................36
Arterial Crack Seal Program......................................................................37
Save Our Streets (SOS) Program
Local Street Improvement Program.....................................................:.....39
Appendices
City Wide Transportation Project Map..................................................Appendix A
Detailed Funding Spreadsheet............................................................... Appendix B
Six Year Transportation Improvement Program 2006-2011 ii
Roadway
Improvements
CAPITAL FACILITIES PLAN
2006-2011
Project Title: 3rd Street SE / Cross Street SE
Project No: C1006
Project Type: Capacity
Project Manager. Jennifer Dvorak
TIP #
Description:
Widen 3rd Street SE/Cross Street from 3 to 5 lanes at'A' Street to Auburn
Way South. Add a second
left turn lane
from northbound 'A' Street SE to westbound 3rd Street SE. The project
includes signal modifications.
Install a 12 inch
ductile iron water pipe from 'A' Street SE to Auburn Way So. The project is a continuation of the corridor enhanced by
the 3rd St. SW Grade Separation project. It will improve mobility and is
consistent with the Comprehensive Plan.
Progress Summary:
Design is completed. Property Acquisition is being completed in 2005.
Construction is scheduled to begin in 2005,
but will likely carry over into 2006 due to signal equipment procurement.
Impact on Operating Budget Once Completed:
The annual maintenance cost for this project is estimated to be $1,757.
Current Year Budget: 2006
YTD Actual
Budget
Budget Expenditures
Balance
Adopted Budget
-
Budget Amendments
Adjusted Budget
Activity:
2005 YE
2006 Year End
Total ProJect
Prior to 2005
Estimate 2006 Buduat
Prelect Total
Q.g9
Funding Sources:
Unrestricted Street Revenue 41,045
159,536 -
200,581
200,581
Grants 162,159
1,173,841 -
1,336,000
1,336,000
Root 2 9,419
--
9,419
9,419
Impact Fees
216,000 148000
364,000
364,000
Total Funding Sources: 212,623
1,549,377 148 000
1,910$000
1 910 000
Expenditures:
Design 166,129
18,000 -
184,129
184,129
Right of Way 46,494
530,000 -
576,494
576,494
Construction
1,001,377 148,000
1,149,377
1,149,377
Total Expenditure: 212,623
1,549,377 148 000
1,910,000
1 910 000
Forecasted Project Cost:
2007 2008 2009
2010 2011
Total
Expenditure
Funding Sources:
2006-2011
Be and 2011
Unrestricted Street
Revenue - - -
- -
Grants --
Rest2 - - -
- _
-
Impact Fees
148,000
Total Funding Sources:
146,000
Expenditures:
Design - - -
-
-
Right ofWay -
-
Construction
148 000
Total Expenditure:
148,000
CAPITAL FACILITIES PLAN
2006-2011
Project Title:
'A' Street Loop
Project No:
PR529F
Project Type:
Capacity
Project Manager:
Jennifer Dvorak
TIP #
Description:
This project is the final phase of the 3rd Street SW Grade Separation Project. It will construct a new asphalt
road
connecting A Street SW and Division Street and thereby provide multiple access routes into the Auburn Station
Garage. Landscape strips, sidewalks, driveways, lighting and storm drainage will be included.
Progress Summary:
Design and Right of Way are being completed in 2004. Construction scheduled for 2005.
Impact on Operating Budget Once Completed:
The annual maintenance cost for this project is estimated to be $851.
Current Year Budget: 2006 YTD Actual
Budget
Budoet Expenditures
Balance
Adopted Budget
-
Budget Amendments
Adjusted Budget
Activity: 2005 YE
2006 Year End
Total Project
Prior to 2005 Estimate 2006 Budget
Prolect Total
Q.Q9
Funding Sources:
Unrestricted Street Revenue 17,403 100,742 -
118,145
118,145
Grants 16,100 205,258 78,500
299,858
299,858
Bond Proceeds - - -
-
-
Impact Fees 66,500
66,500
66,500
Total Funding Sources: 33,503 306,000 145,000
484,503
484,503
Expenditures:
Design 33,503 6,000 -
39,503
39,503
Right of Way - 10,000 -
10,000
10,000
Construction 290,000 145,000
435,000
435,000
Total Expenditure: 33,503 306,000 145,000
484,503
484.503
Forecasted Project Cost:
2007 2008 2009 2010 2011
Total
Expenditure
Fundino Sources:
2006-2011
Beyond 2011
Unrestricted Street
Revenue - - - - -
-
Grants - - - - -
78,500
Bond Proceeds - - - - -
_
Impact Fees
66,500
Total Funding Sources:
145,000
Exoendltures•
Design - - - - -
RightofWay - - - - -
_
Construction
146,000
Total Expenditure:
145,000
CAPITAL FACILITIES PLAN
2006-2011
Project Title:
Auburn Way South Safety Improvements
Project No:
C1014
Project Type:
Non -Capacity (Safety)
Project Manager:
Jennifer Dvorak
TIP #
Description:
This project was created in response to a State safety study. The project includes safety improvements along Auburn
Way South (AWS) between 6th Street SE and M Street SE. The anticipated improvements include rechannelization of
AWS to limit left turns, a new traffic signal at the intersection of Auburn Way South and'F' Street SE signal
interconnection, and widening for an additional lane between D Street SE and 6th Street SE. This project will
significantly improve the safety of the corridor.
Progress Summary:
Construction is beginning summer 2005. It is expected that construction will carry over into 2006 due to delays related
to the Les Schwab access and signal equipment procurement.
Impact on Operating Budget Once Completed.
This project will have no impact on the operating budget for street maintenance. The State maintains the pavement on
SR -164.
Current Year Budget: 2006 YTD Actual Budget
Budget Expenditures Balance
Adopted Budget -
Budget Amendments
Adjusted Budget
Activity: 2005 YE 2006 Year End
Total Project
Prior to 2005 Estimate 2006 Budget Prolect To
Cost
Funding Sources:
Unrestricted Street Revenue 101,443 553,579 499,000 1,154,022
1,154,022
Grants 223,333 608,253 - 831,586
831,586
Developer Funds 98,000 - - 98,000
98,000
ImpactFees
Total Funding Sources: 422,776 1,161,832 499 000 2,083,608
2 083 608
Expenditures:
Design 400,894 15,832 - 416,726
416,726
Right of Way 21,882 6,000 - 27,882
27,882
Construction 1,140,000 499,000 1,639,000
1,639,000
Total Expenditure; 422,776 1,161,832 498 000 2,083,608
2 083 608
Forecasted Project Cost:
2007 2008 2009 2010 2011 Total
Expenditure
Funding sources: 2006-2011
Beyond 2011
Unrestricted Streat
Revenue - - - - - 499,000
Grants - - - - - -
DeveloperFunds - - - - - -
Im act Fees
Total Funding Sources: 499,000
Fxoenditures:
Design - - - - -
Right ofWay - - - - - -
Con499,000
Total Ex nditure: 499,000
TIP #
Description:
CAPITAL FACILITIES PLAN
2006-2011
Project Title:
Urban Area Transportation System Mgmt Improvements
Project No:
Project Type:
Non -Capacity
Project Manager:
Scott Nutter
TIP #
Description:
This project will modify four intersections to improve bus turning radii and will reconstruct 2nd Street SW between A
Street SW and A Street SE.
Progress Summary:
Design is expected to be completed in 2005. ROW procurement and Construction will take place in 2006.
Impact on Operating Budget Once Completed:
This project will have no impact on the operating budget for street maintenance.
Current Year Budget: 2006
YTD Actual
Budget
Budget
Expenditures
Balance
Adopted Budget
-
Budget Amendments
Adjusted Budget
Activity., 2005 YE
2006 Year End
Total Prclect
Pri" to 2005 EstlmaM
2006 Budget
Protect Total
�Qg(
Funding Sources:
Unrestricted Sheet Revenue -
5,000
5,000
5,000
Grants - 177,585
376,700
554,285
554,285
King County Metro - 27,715
72,300
100,015
100,015
Impact Fees
Total Funding Sources: 205,300
454,000
659,300
659,300
Expenditures:
Design - 205,300
-
205,300
205,300
Right of Way - -
50,300
50,300
50,300
Construction
403,700
403,700
403,700
Total Expenditure: 205p300
454,000
659p300
659,300
Forecasted Project Cost:
2007 2008 2009 2010
2011
Total
Expenditure
Funding sources:
2006-2011
Beyond 2011
Unrestricted Street
Revenue - - - -
-
5,000
Grants - - - -
-
376,700
King County Metro - - - -
-
72,300
Impact Fees
Total Funding Sources:
454,000
Expenditures:
Design - - - -
-
-
Right ofWay - - - -
-
50,300
Construction
403,700
Total Ex ditum:
454,000
CAPITAL FACILITIES PLAN
2006 2011
Project Title: A Street NIN Phase 1: 3rd Street to 14th Street NE
Project No: C207A
Project Type: Capacity
Project Manager., Bill Helbig
TIP #
Description:
Construct a multi lane arterial from 3rd St. NW to 14th St. NW. This project will improve mobility and
is tied development.
It is consistent with the comprehensive plan and contributes to the completion of a North-South arterial corridor.
Progress Summary:
The predesign (30% design) has been completed. A portion of the right-of-way has been acquired.
This project has .
Full design should begin in 2005. Mohawk Plastics has completed the construciton of a 2 -block stretch of the road
adjacent to their property.
Impact on Operating Budget Once Completed:
The annual maintenance cost for this project is estimated to be $17,568.
Current Year Budget: 2006 YrD Actual
Budget
Budget Expenditures
Balance
Adopted Budget
-
BudgetAmendments
Adjusted Budget
Activity., 2005 YE
2006 Year End
Total Project
Prior to 2005 Estima 2006 Budget
Proleot Total
029
Funding Sources:
Unrestricted Street Revenue 260,484 33,750 -
294,234
294,234
Grants - 216,250 1,225,700
1,441,950
5,346,950
Other 381,000 - 450,000
831,000
1,228,000
Impact Fees 39,149 10,000 82,300
131,449
867,449
Total Funding Sources: 680,633 260,000 1,758,000
2 698 633
7,736,633
Expenditures:
Design 47,829 250,000 323,000
620,829
620,829
Right of Way 251,804 10,000 1,435,000
1,696,804
1,696,804
Construction 381,000
381,000
5,419,000
Total Expenditure: 680,633 260,000 1,758,000
2698 633
7,736,633
Forecasted Project Cost.,
2007 2008 2009 2010 2011
Total
Expenditure
Fundina Sources:
2006-2011
Beyond 2011
Unrestricted Sheet
Revenue - - - - -
-
Grants 1,952,500 1,952,500 - - -
5,130,700
Other 397,000 - - - -
847,000
Impact Fees 368,000 368,000
818,300
Total Funding Sources: 2,717,500 2,320,500 -
6,796,000
Expendltures:
Design - - - - -
323,000
Right of Way - - - -
1,435,000
Construction 2,717,500 2,320500
5,038,000
Total Expenditure: 2,717,500 2 320 600
6,796,000
Description:
CAPITAL FACILITIES PLAN TIP #
2006-2011 6
Project Title:
Citywide Intelligent Transportation System
Project No:
C307A
Project Type:
Capacity
Project Manager:
Ryan Johnstone
Description:
This project includes interconnect and coordination for all signals in the City.
The project also includes traffic
management cameras, fiber optic interconnect and related hardware along SR -164 (Auburn Way So) and S. 277th
Street corridors. The project will construct a traffic control center at the existing M&O facility. This project is required for
special event traffic management and incident response.
Progress Summary:
Phase I, which includes Auburn Way South has been completed. Phase II,
S. 277th, will be completed in 2006. We are
expecting a Public Works Trust Fund Loan in the amount of $800,000 to provide the necessary match for the Federal
ITS Grant.
Impact on Operating Budget Once Completed:
The annual maintenance cost for this project is estimated to be $5,000.
Current Year Budget: 2006
YTD Actual Budget
Budget Expenditures Balance
Adopted Budget
-
BudgetAmendments
Adjusted Budget
Activity:
2005 YE 2006 Year End
Total Project
Prior to 2005
Estimate 2006 Budget Protect Total
—229
Funding Sources:
Unrestricted Street Revenue 11.446
55,535 - 66,981
66.981
Federal Grant -
863,981 800,000 1,663,981
1,663,981
Other -
300,000 800,000 1,100,000
1,100,000
King County
500,000 500,000
500,000
Total Funding Sources: 11,446
1,719,516 1 800 000 3,330,962
3 330 962
Ex enditures:
Design 11,446
300,000 200.000 511,446
511,446
Right of Way -
- - -
-
Construction
1,419,516 1400,000 2,819,516
2,819,516
Total Expenditure: 11,446
1,719,516 1600 000 3,330,962
3 330 962
Forecasted Project Cost:
2007 2008 2009
2010 2011 Total
Expenditure
Fundinn Sources:
2006-2011
Be and 2011
Unrestricted Street
Revenue - -
- - -
Federal Grant - - -
- - 800,000
Other - - -
- - 800,000
King County
Total Funding Sources:
1,600,000
Expenditures,
Design - - -
- - 200,000
Right of Way - - -
_ -
Construction1
400 000
Total Expenditure:
1 800 000
CAPITAL FACILITIES PLAN
2006-2011
Project Title:
T Street NE Corridor
Project No:
C415A
Project Type:
Capacity
Project Manager.
Scott Nutter
TIP #
Description:
The final alignment of the'I' Street Corridor is being analized as part of the Northeast Auburn Special Area Plan
Environmental Impact Study. A portion of the ROW and Construction may be developer funded. The cross section w
I
likely be a 5 -lane arterial per the City Comprehensive Plan. It will improve mobility and is consistent with the
Comprehensive Plan. it will complete a major north south arterial from 52nd St NE to Harvey Rd. Future sewer line
proposed to be a combination 10 in. & 30 in. line.
Progress Summary:
It is anticipated that a pre -design report will be completed in 2005. Additional coordination/detailed design in
partnership with developers may be required in 2006.
Impact on Operating Budget Once Completed:
The annual maintenance cost for this project is estimated to be $17,568.
Current Year Budget: 2006 YTD Actual Budget
Budget Expenditures Balance
Adopted Budget -
Budget Amendments
Adjusted Budget
Activity: 2005 YE 2006 Year End
Total ProJect
Prior to 2005 Estima 2006 Buda et Prolect Total
541
Funding Sources:
Unrestricted Street Revenue 5,000 40.000 - 45,000
45,000
Developer - - - -
-
Other - - - -
5,760,000
Impact Fees 10.000 10,000
10,000
Total Funding Sources: 5,500 40,000 10,000 55,000
5 815 000
Expenditures:
Pre-Desfgn & Design 5,000 40,000 10,000 55,000
515,000
Right of Way - - - -
1,020.000
Construction4,280,000
Total Expenditure: 5,000 40,000 10,600 55 000
5,815,000
Forecasted Project Cost:
2007 2008 2009 2010 2011 Total
Expenditure
Funding Sources: 2006-2011
Beyond 2011
Unrestricted Street
Revenue - - - - - -
Devefoper - - - -
Other 460,000 1,020,000 4,280,000 - - 5,760,000
Impact Fees 10,000
Total Funding Sources: 460,000 1,020,000 4,280,000 5,770,000
Expenditures'
Pre -Design & Design 460,000 - - - - 470,000
Right of Way - 1,020.000 - - - 1,020,000
Construction 4,280,000 4 280 000
notal Ex nditure: 460,000 1020 000 4,280,000 s 77o 0o0
CAPITAL FACILITIES PLAN TIP #
2006-2011 9
Project Title: 'M' Street Grade Separation- E.Main to AWS
Project No: C201A
Project Type: Capacity
Project Manager., Ingrid Gaub
Description:
Construction of a grade separated railroad crossing at M Street SE at the BNSF Stampede Tracks.
Project also
includes construction of the bypass and road connection between M Street SE and Auburn Black Diamond
Road.
2006 will focus on developing partnership agreements and applying for grants/ PWTFL.
Progress Summary:
The pre -design report has been completed. We are searching for grant funding.FAST has committed Design money
when they get it. This project will score well in TIB's AIP program once it reaches Construction, but
not beforeA
Public Works Trust Fund Loan for $1.17 M is anticipated in 2008/2009.
Impact on Operating Budget Once Completed:
The annual maintenance cost for this project is estimated to be $21,827.
Current Year Budget: 2006 YTD Actual
Budget
Budget Expenditures
Balance
Adopted Budget
Budget Amendments
Adjusted Budget
Activity: 2005 YE
2006 Year End
Total Project
Prior to 2005 Estimate 2006 Buda et
Protect Total
_220
Funding Sources:
Unrestricted Street Revenue - -
-
490,000
Grants - - -
-
15,872,600
Other- - -
-
8,078,000
Impact Fees 245,000 5,000 20,000
270,000
525,000
Total Funding Sources: 245,000 5,000 20,000
270,000
24 965 800
Expenditures:
Design 245,000 5,000 20,000
270,000
1,677,600
Right of Way - - -
-
8,516,000
Construction
14,772 000
Total Expenditure: 245,000 5,000 20,000
270,000
24,965,600
Forecasted Project Cost:
2007 2008 2009 2010 2011
Total
Expenditure
Funding Sources:
2006-2011
Beyond 2011
Unrestricted Street
Revenue - - - 490,000 -
490,000
Grants 240,000 4,200,000 7,362,600 4,070,000 -
15,872,600
Other - 700,000 466,000 2,440,000 4,472,000
8,078,000
Impact Fees 55,000 100,000 100,000
275,000
Total Funding Sources: 295,000 5,000,000 7,928,600 7,000,000 4,472,000
24,715,600
Expenditures:
Design 295,000 1,000,000 112,600 - -
1,427,600
Right of Way - 4,000,000 4,516,000 - -
8,516,000
Construction 3,300,000 7,000,000 4 472 000
14,772,000
Total Expenditure: 295,000 5,000 000 7,928,600 7000 000 4,472,000
24 715 600
CAPITAL FACILITIES PLAN TIP #
2006-2011 10
Project Title: South 277th -(AWN to Gr@en River Bridge)
Project No: C222A
Project Type: Capacity
Project Manager: Scott Nutter
Description:
This project includes major widening including the addition of three lanes, one in westbound and one eastbound and a
Class 1 trail. Water CFP shows a low priority project in the vicinity which may be accomodated by a developer. (Water
CFP Proj DS -603-108,109 and Proj DS -601-109,110)
Progress Summary:
The NE Auburn area is currently undergoing an Environmental Impact Statement that includes the impacts of future
development in the vicinity of this project. 2005 monies are to coordinate with potential developers and to assist in
seeking of grant funding for the project.
Impact on Operating Budget Once Completed:
The annual maintenance costs for this project is estimated to be $10,541.
Current Year Budget: 2006
YTD Actual
Budget
Budget Expenditures
Balance
Adopted Budget
-
BudgetAmendments
Adjusted Budget
Activity.
2005 YE
2006 Year End
Total Project
Prior to 2005
Esumata 2006 Buda ef
Prolaat To
Cost
Funding Sources:
Unrestricted Street Revenue -
5,000 -
5,000
5,000
Grants -
- -
-
2,243,200
Developer Contributions -
- -
-
750,000
Impact Fees 4,091
5,000
9,091
71,791
Total Funding Sources: 4,091
5,000 5,000
14,091
3,069,991
Expenditures:
Design 4,091
5,000 5,000
14,091
264,091
Right of Way -
- -
-
675,000
Construction -
2 30,900
Total Expenditure: 4,51
5 000 5 000
14,091
3 069 991
Forecasted Project Cost.
2007 2008 2009
2010 2011
Total
Expenditure
Funding Sources:
2006-2011
Be and 2011
Unrestricted Street Revenue - - -
- -
Grants - 100,0,000
00 100
200,000 1,643,200
2,243,200
Developer Contributions - 200,000 200,000
100,000 250,000
750,000
Impact Fees 25,000
37,700
67,700
Total Funding Sources: 300,000 325,000
300,000 2,130,900
3,060,900
Expendltures:
Design - 125.000 125,000
- -
255,000
Right of Way - 175,000 200,000
300,000 -
675,000
Construction
2130,900
2,130,900
Total Expenditure: 300,000 325,000
300,000 2130 900
3,060,900
CAPITAL FACILITIES PLAN TIP #
2006-2011 11
Project Title: 15th Street SW Reconstruction (C Street SW to UPRR)
Project No:
Project Type: Access Mariagement/Pavement Preservation
Project Manager., TBD
Description:
Rehabilitate 15th Street SW between 'C'Street SW and the Union Pacific Railroad.
The project will also construct landscaped
medians which will continue the access management treatment that is currently West of the Union Pacific Railroad Tracks.
Progress Summary:
Impact on Operating Budget Once Completed:
This project will have no impact on the operating budget for street maintenance.
Current Year Budget: 2006
YTD actual Budget
Budget
Expenditures Balance
Adopted Budget
Budget Amendments
Adjusted Budget
Activity: 2005 YE
2006 Year End
Total Project
Prior to 2005 Estimate
2006 Budoet Protect Tot.
cost
FundingSources:
Unrestricted Street Revenue -
- -
540,000
Grants - -
- -
2,160,000
Public Works Trust Fund - -
- -
-
Impact Fees
Total FundingSources:
2 700 000
Ex ndhures:
Design - -
- -
450,000
Right of Way - -
- -
-
ConsWctlon
2,250,000
Tobi Expenditure:
2,700,000
Forecasted Project Cost:
2007 2008 2009 2010
2011 Total
Expenditure
Fund1my Sources:
2006-2011
Be rad 2011
Unrestricted Street
Revenue - 90,000 450,000 -
- 540,000
Grants - 360,000 1,800,000 -
- 2,160,000
Public Works Trust Fund - - - -
- -
Im act Fees
Total Funding Sources: 450,000 2,250,000
2,700,000
Expenditures:
Design - 450,000 - -
- 450,000
Right of Way - - - -
-
Construction 2,250,000
2,250,000
Total Expenditure: 450,000 2,250,000
2 700 000
CAPITAL FACILITIES PLAN TIP #
2006-2011 11A
Project Title: 15th Street SW Preservation (C Street SW to UPRR)
Project No:
Project Type: Temporary Pavement Repairs
Project Manager: TBD
Description:
The North 1/2 of 15th Street SW is 100% alligator cracked in the wheel paths. This is a potential route for a new King County
Metro Sewer line which would necessitate the reconstruciton of the failed roadway sections. A temporary fix is scheduled to hol
the road together for mobility and safety. This includes some patch work followed by a double chip seal.
This type of work is
expected to hold the roadway together for approximately 4 to 6 years.
Progress Summary:
Impact on Operating Budget Once Completed:
This project will have no impact on the operating budget for street maintenance.
Current Year Budget: 2006 YTD Actual
Budget
Budget Expenditures
Balance
Adopted Budget
-
Budget Amendments
Adjusted Budget
Activity: 2005 YE
2006 Year End
Total Project
Poor to 2003 Estimate 2006 Budget
Prolett Total
cost
Funding sources:
Unrestricted Street Revenue - 175.000
175,000
175,000
Gents - - -
-
-
Public Works Trust Fund - - -
-
-
Impact Fees
Total Funding Sources: 175,000
175,000
175,000
Expenditures:
Design - - 10,000
10,000
10,000
Righto/Way - - -
-
-
consvucdon 165,000
105,000
165,000
Total Expenditure: 175,000
175,000
175,000
Forecasted Project Cost:
2007 2006 2009 2010 2011
Total
Expenditure
Funding sources:
2006.2011
Beyond 2011
Unrestricted Street
Revenue - - - - -
175,000
Grants - - - - -
Public Works Trust Fund - - - - -
-
Im act Feea
Total Funding sources:
175,000
Expenditures:
Design - - - - -
10,000
Rlghtor Way - - - - -
_
Construction
165,000
Total Ex enditum:
175,000
CAPITAL FACILITIES PLAN TIP #
2006-2011 12
Project Title: A Street NW, Phase 2 (West Main Street to 3rd Street NW)
Project No:
Project Type: Capacity
Project Manager. TBD
Description:
Construct a multi lane arterial. This project will connect A Street NW Phase 1 to the Sound Transit Station and the
Central Business District.
Progress Summary:
Impact on Operating Budget Once Completed.
The annual maintenance cost for this project is estimated to be $1,405.
Current Year Budget: 2006
YTD Actual
Budget
Budget
Expenditures
Balance
Adopted Budget
-
BudgetAmendments
Adjusted Budget
Activity:
2005 YE
2006 Year End
Total Project
Prior to 2005
Estima
2006 Budget
Prolect Total
,Si9St
Funding sources:
Unrestricted street Revenue -
-
-
-
Giants -
-
- -
-
1,038,000
Bond Proceeds -
-
-
-
1,250,000
Impact Fees
362,000
Total Funding Sources:
2,650,000
Expenditurev
Design -
-
-
-
200,000
Right of Way -
-
-
-
1,200,000
Construction
1,250 000
Total Expenditure:
2,650,000
Forecasted Project Cost:
2007 2008 2009
2010
2011
Total
Expenditure
Funding sources:
2006.2011
Beyond 2011
Unrestricted Street
Revenue - - -
-
-
-
-
Grants - - -
1,038,000
-
1,038,000
-
Bond Proceeds - - -
-
1250.000
1,250,000
Impact Fees 200,000
162,000
362000
Total Funding Sources: 200,000
1,200,000
1,250,000
2,650,000
-
Expenditures:
Design - - 200,000
-
-
200,000
-
Right ofWay - - -
1,200,000
-
1,200,000
-
Construction
1,250,000
1,250,000
Total Expenditure: 200,500
1 200 000
1,250,000
2 650 000
CAPITAL FACILITIES PLAN TIP #
2006-2011 13
Project Title: C Street NW (Main Street to 3rd Street NW)
Project No:
Project Type: Non -Capacity
Project Manager: TBD
Description:
Restore/ Reconstruct existing pavement. Remove RR tracks no longer used. All Improvements will be done within th
existing ROW. This should have minimal impacts to adjacent properties.
Progress Summary:
Impact on Operating Budget Once Completed:
This project will have no impact on the operating budget for street maintenance.
Current Year Budget: 2006
YTD Actual
Budget
Budget
Expenditures
Balance
Adopted Budget
-
Budget Amendments
Adjusted Budget
Activity: 2005 YE
2006 Year End
Total Project
Prior to 2005 Estimate
2006 Budget
Project Total
999
Funding Sources:
Unrestricted Street Revenue -
30,000
30,000
30,000
Grants - -
-
-
-
REET - -
500,000
500,000
500,000
Impact Fees
Total Funding Sources:
530,000
530,000
530;000
Expenditures:
Design - -
30,000
30,000
30,000
Right of Way - -
-
-
-
Constructlon
500,000
500,000
500,000
Total Expenditure;
530,000
530,000
530,000
Forecasted Project Cost:
2007 2008 2009 2010
2011
Total
Expenditure
Funding Sources:
2006-2011
Beyond 2011
Unrestricted Street
Revenue - - - -
-
30,000
Grants - - - -
-
-
REET - - - -
-
500,000
Impact Fees
Total Funding Sources:
530,000
Expenditures:
Design - - - -
-
30,000
Right of Way - - - -
-
Construction
500000
Total Expenditure,
530,000
CAPITAL FACILITIES PLAN TIP #
2006-2011 14
Project Title: D Street NW (37th Street NW to 44th Street NW)
Project No:
Project Type: Capacity
Project Manager: TBD
Description:
Construct a four lane arterial per the city Comprehensive Plan. It will improve mobility
north/south. This
project is tied
to a pending development. It will complete a major north/south arterial from Ellingson
to S. 277th Street.
Progress Summary:
Impact on Operating Budget Once Completed:
The annual maintenance cost for this project is estimated to be $14,054.
Current Year Budget: 2006
YTD Actual
Budget
Budget
Expenditures
Balance
Adopted Budget
-
Budget Amendments
Adjusted Budget
Activity:
2005 YE
2006 Year End
Total Protect
Prior to 2005
Estimate
2006 Budget
Prolect Total
cost
Fundina Sources:
Unrestricted Street Revenue -
-
-
520,000
Grants -
-
-
-
2.240,000
Bond Proceeds -
Impact Fees
40,000
Total Funding Sources:
2,800,000
Expenditures:
Design -
-
-
-
200,000
Right of Way -
-
-
-
1,500,000
Construction
-
1,100 000
Total Expenditure:
2.800,000
Forecasted Project Cost:
2007 2008 2009
2010
2011
Total
Expenditure
Funding Sources:
2006-2011
Beyond 2011
Unrestricted Street
Revenue -
300,000
220,000
520,000
-
Grants - 160,000
1,200,000
880,000
2,240,000
-
Bond Proceeds -Impact
Fees - 40,000
40,000
Total Funding Sources: 200,000
1,500,000
1,100,000
2,800,000
Expenditures
Design - 200,000
-
-
200,000
-
RightofWay -
1,500,000
-
1,500,000
-
Construction
1,100,000
1,100,000
Total Expenditure; Z00,000
1,500,000
1 100 000
2,800,000
Description:
CAPITAL FACILITIES PLAN TIP #
Widen T' Street SE to 3 lanes, with parking allowed on both sides, to increase the roadway capacity. Install curbs,
2006-2011 is
Project Title:
F Street SE (4th Street SE to Auburn Way South)
Project No:
Project Type:
Capacity
Project Manager.,
TBD
Description:
Widen T' Street SE to 3 lanes, with parking allowed on both sides, to increase the roadway capacity. Install curbs,
gutters, sidewalks, and bike lanes as well as crash attenuation at the supports for the BNSF railroad bridge. The
project may include a traffic signal at F Street SE and 4th Street SE. This project improves mobility and safety. This
project also provides arterial relief for the 'M' Street SE Grade Separation Project.
Progress Summary.
Impact on Operating Budget Once Completed:
The annual maintenance cost for this project is estimated to be $851.
Current Year Budget., 2006 YTD Actual Budget
Budget Expenditures Balance
Adopted Budget -
Budget Amendments
Adjusted Budget
Activity: 2005 YE 20W Year End
Total Project
Prior to 2005 Estimate 2006 Butlgef Jed Total
Cost
Funding Sources:
Unrestricted Street Revenue - - -
-
Grants - - - -
1,480,000
Bond Proceeds - - - -
-
impact Fees
370,000
Total Funding Sources:
1 850 000
Expenditures:
Design - - - -
200,000
Right of Way - - - -
250,000
Construction
1,400 000
Total Ex nditure:
11850,000
Forecasted Project Cost.
2007 2008 2009 2010 2011 Total
Funding Sources: 2006-2011
Expenditure
Beyond 2011
Unrestricted Street
Revenue - - -
Grants 160,000 520,000 800,000 - - 1,480,000
Bond Proceeds - - -
Impact Fees 40,000 130,000 200,000 3-70,000
Total Funding Sources. 200,000 650,000 1,000,000 1,8501000
-
Exoenditures:
Design 200,000 - - - - 200,000
-
Right ofWay - 250,000- - - 250,000
-
Construction - 400,000 1,000 000 1 400 000
Total Expenditure. 200,000 650,000 11000,000 1 850 000
CAPITAL FACILITIES PLAN . TIP #
2006-2011 16
Project Title: M Street NE (E Main Street to 8th Street NE)
Project No:
Project Type: Capacity
Project Manager: TBD
Description:
Widen roadway to 4 lanes. Construct curb gutter and sidewalk. Modify existing signals.
This project will improve
safety, capacity and mobility. This project is consistent with the Comprehensive Plan.
Progress Summary:
Impact on Operating Budget Once Completed.
The annual maintenance cost for this project is estimated to be $3,514.
Current Year Budget: 2006
YTD Actual
Budget
Budget
Expenditures
_Balance
Adopted Budget
Budget Amendments
Adjusted Budget
Activity.,
2005 YE
2006 Year End
Total Pro/ect
Prior to 2005
Estimate
2006 Buda et
PP ect To
cost
Funding Sources:
Unrestricted Street Revenue -
-
-
_
Grants -
-
-
-
1,576,800
Bond Proceeds -
-
-
_
_
Impact Fees -
394,200
Total Funding Sources:
1,971,000
Expenditures:
Design _
_
_
_
166,000
Right of Way -
-
-
-
480,000
Construction
1,325 000
Total Expenditure:
1.971.000
Forecasted Project Cost.
2007 2008 2009
2010
2011
Total
Expenditure
Funding Sources:
2018-2011
Beyond 2011
Unrestricted street
Revenue - - _
Grants - - 132,800
644,000
800,000
1,576,800
Bond Proceeds - - _
_
_
-
Impact Fees - 33200
161,000
200,000
394200
Total Fundin Sources: 166,000
805,000
1,000,000
1,971,000
-
Expendltures:
Design - - 166,000
-
-
166,000
-
Right of Way - - -
480,000
-
480,000
-
Constructlon
325,000
1,000,000
1 325 000
Total Expenditure: 166,000
805,000
1,000,000
1 971 000
Description:
CAPITAL FACILITIES PLAN TIP #
Realign the SR18 eastbound ramp, build grade separation of main north south line and Stampede Pass line, and connect to 6th
2006-2011 17
Project Title:
Realign SR -18 EB Ramp at AWS, Grade Separate BNSF Yard '
Project No:
Project Type:
Capacity
Project Manager:
TBD
Description:
Realign the SR18 eastbound ramp, build grade separation of main north south line and Stampede Pass line, and connect to 6th
Street SE. Widen 6th Street SE roadway from 2 to 4 lanes including signal modifications at "A" Street and Auburn Way South.
This project improves traffic flow significantly due to the potential development of the BNSF yard to an intermodal freight facility.
Replace a small portion of sewer line along 6th Street SE.
Progress Summary:
An alternative to this project may be a grade separation at 15th Street SW/SE connecting A Street SE to C Street SW across
the BNSFrailyard.
Impact on Operating Budget Once Completed:
Not scheduled for completion until after 2010.
Current Year Budget: 2006 YTD Actual Budget
Budget Expenditures Balance
Adopted Budget -
BudgetAmendments
Adjusted Budget
Activity: 2005 YE 2006 Year End
Total Project
Prior to 2005 Estimate 2006 Budget Protect Total
j
Fundln Sources:
Unrestricted Street Revenue -
Grants - - - -
-
Other - - - -
32,000,000
Impact Fees
Total Funding Sources:
32 000 000
Expenditures:
Design - - - -
3,500,000
Right of Way - - - -
4,000,000
Construction
24 500,000
Total Ex ndlture:
32.000,000
Forecasted Project Cost:
2007 2008 2009 2010 2011 Total
Expenditure
Funding Sources: 2006-2011
Beyond 2011
Unrestricted Street
Revenue - --
Grants - --
Other - - - - 1,000,000 1,000,000
31,000,000
Impact Fees
Total Funding Sources: - 11000,000 1,000,000
31,000,000
Expenditures:
Design - - - - 1,000,000 1,000,000
2,500,000
Right of Way - - - - - -
4,000,000
Construction - - -24,500,000
Total Expenditure: 1,000000 1 00
,0000
31,000,000
Intersection
Improvements
CAPITAL FACILITIES PLAN TIP #
2006-2011 18
Project Title: Harvey and 8th Street NE Intersection Improvements
Project No:
Project Type: Capacity
Project Manager., TBD
Description:
Add an EB combined through and right tum lane on 8th Street NE approaching Harvey
Road. Modify traffic signals and
traffic channelization to accommodate the new lane. The additional lane (additional capacity) will improve traffic dela
s
and vehicle queuing at the intersection of Havey and 8th Street NE in all directions.
Progress Summary:
Impact on Operating Budget Once Completed:
The annual maintenance cost for this project is estimated to be $703.
Current Year Budget., 2006
YTD Actual
Budget
Budget
Expenditures
Balance
Adopted Budget
Budget Amendments
AdJusted Budget
Activity: 2005 YE
2009; Year End
Total Protect
Prior to 2005 Estimate
2006 Budget
pmfect TO
cost
Funding Sources:
Unrestricted Street Revenue -
-
-
-
Grants - -
-
-
-
Other - -
-
-
Impact Fees
160,000
160,000
51Q000
Total Funding Sources:
160,000
160,000
510,000
Expenditures:
Design - -
60,000
60,000
60,000
Right of Way - -
100,000
100,000
100,000
Construction
350,000
Total Expenditure:
160,000
160,000
510,000
Forecasted Project Cost:
2007 2006 2009 2010
2011
Total
Expenditure
Funding Sources:
2006.2011
Beyond 2011
Unrestricted Street
Revenue
Grants
-
Other -
Impact Fees 350,000
510,000
Total Funding Sources. 350,000
510,000
-
Exoenditures:
Design _ _ _ _
_
60,000
-
Right of Way - - - -
-
100,000
-
Construction 350,000
350 000
Total Expenditure: 350,000
510,0001
Non-Motorized
Improvements
CAPITAL FACILITIES PLAN TIP #
2006-2011 7
Project Title: Auburn Way Corridor -Pedestrian Crossing
Project No: C409A
Project Type: Non -Capacity
Project Manager: Jennifer Dvorak
Description:
This project is to improve the pedestrian accessability, the appearance, and the tie to the downtown along Auburn Way
South between 4th Street NE and 4th Street SE.
Progress Summary.
The pre -design report has been completed.
Impact on Operating Budget Once Completed:
This project will have no impact on the operating budget for street maintenance.
Current Year Budget: 2006
YTD Actual
Budget
Budget
Expenditures
Balance
Adopted Budget
Budget Amendments
Adjusted Budget
Activity: 2005 YE
2006 Year End
Total Project
Prior to 2005 Estimate
2006 Budoet
Prolee:t Total
P29
Funding Sources:
Unrestricted Street Revenue - -
-
-
375.063
Grants - -
-
-
2,403,182
Other _ _
_
_
_
impact Fees
Total Funding sources:
2.778,245
Expenditures:
Design - -
-
-
167,112
Right of Way - -
-
-
208,891
construction -
2,402,242
Total Expenditure:
21778.245
Forecasted Project Cost:
2007 2008 2009 2010
2011
Total
Expenditure
Funding Sources:
2006.2011
Beyond 2011
Unrestricted Street
Revenue - - - 50,760
324,303
375,063
Grants - - - 325,243
2,077,939
2,403,182
Other - - _ _
-
Impact Fees
Total Funding Sources: - - 376,003
2,402,242
2,778,245
Exoendl[urea"
Design - - - 167,112
-
167,112
Right of Way - - - 208,891
-
208,891
Construction -
2,402,242
:1,402 242
Total Expenditure: 376,003
2,402,242
;! 778 245
Description:
CAPITAL FACILITIES PLAN TIP #
This project will construct a Class 1 meandering trail between the cities of Auburn and Pacific
2006-2011 19
Project Title:
Auburn/Pacific Trail (C Street SW)
Project No:
Striping will be installed along V Avenue SE in Pacific to connect a bike lane from where the
Project Type:
Class 1 Trail
Project Manager:
Jennifer Dvorak
Description:
This project will construct a Class 1 meandering trail between the cities of Auburn and Pacific
along the west side of C Street S
(Auburn) and Skinner Road (Pacific). It will start in Auburn at 1 � Street SW and end at the southern terminus of Skinner Road.
Striping will be installed along V Avenue SE in Pacific to connect a bike lane from where the
trail ends at Skinner Road to the
southern end of the Interurban Trail. The Class 1 trail will be approximately 2.05 miles and the striping portion will be 1.42 miles
Progress Summary:
This project is fully funded with STP funds. This will be under construction in 2006.
Impact on Operating Budget Once Completed:
The annual maintenance cost for this project is estimated to be $2,688.
Current Year Budget: 2006
YTD Actual Budget
Budget
Expenditures Balance
Adopted Budget
BudgetAmendments
Adjusted Budget
Activity: 2005 YE
2006 Year End
Total Project
Prior to 2005 Estims
2006 Budget Prolec't To
Cost
Funding Sources:
Unrestdcted Street Revenue - 5,400
26,600 32,000
32,000
Grants - 34,600
307,300 341,900
341,900
City of Pacific - -
22,000 22,000
22,000
Impact Fees
Total Fundino Sources: 40,000
366p900 395,900
395.900
Ex ditures:
Design - 40,000
39,200 79,200
79,200
Right of Way - -
- _
_
Construction -
316,700 316,700
316700
Total Expenditure: 40 000
355,900 395,000
396p900
Forecasted Project Cost:
2007 2008 2009 2010
Funding Sources:
2011 Total
2006-2011
Expentllture
Be and 2011
Unrestricted Street
Revenue - - - -
- 26,600
Grants - - - -
- 307,300
City of Pacific - - -
- 22 000
Impact Fees
Total FundingSources:
355,900
Expenditures.,
Design - - - -
Right of Way - - _ _
- 39,200
_ -
Construction -
316,700
Total Expenditure:
355 900
CAPITAL FACILITIES PLAN TIP #
2006-2011 20
Project Title: West Main Street Streetscape
Project No: C322A
Project Type: Non -Capacity
Project Manager: Scott Nutter
Description:
Develop bike lanes and restore sidewalk to link the Interurban Trail to Downtown Auburn and the Sound Transit
Center.
Progress Summary:
Federal STP funds are being obligated prior to January 1, 2005. Public
involvement will be completed in 2004; desig
is scheduled for 2005.
Impact on Operating Budget Once Completed:
This project will have no impact on the operating budget for street maintenance (rebuilding -in-kind project).
Current Year Budget: 2006
YTD Actual Budget
Budget Expendltures Balance
Adopted Budget
-
Budget Amendments
Adjusted Budget
Activity:
2005 YE 2006 Year End
Total Project
Prior to 1005
Estimate 2006 Budget pro TO
Cost
Funding Sources:
Unrestricted Street Revenue 129
9,300 100,100 109,529
109,529
Grants 826
59,700 641,100 701,626
701,626
Other
- _
-
Impact Fees
Total Funding Sources: 955
69,000 741,200 811,165
811,15
Expenditures:
Design 955
69,000 - 69,955
69,955
Right of Way -
- - _
_
construction -
741,200 741,200
741,200
Total Expenditure: 955
69,000 741,200 811 155
811 155
Forecasted Project Cost:
2007 2009 2009
Funding; Sources:
2010 2011 Total
2006-2011
Expenditure
Beyond 2011
Unrestricted Street
Revenue - - -
- - 100,100
Grants - - -
- - 641,100
OtherImpact
Fees
_
Total Funding Sources:
7411200
Expenditures:
Design
-
Right ofWay - - _
_ _ -
Construction -
741 200
Total Ex endlture:
741 200
CAPITAL FACILITIES PLAN TIP #
2006-2011 21
Project Title: BNSF/East Valley Highway Pedestrian Underpass
Project No: C229A
Project Type: Non -Capacity
Project Manager: Jennifer Dvorak
Description:
This project will construct an undercrossing of the BNSF Railroad in conjuction with a pedestrian bridge to allow a direct,
attractive non -motorized access between neighborhoods in the City of Pacific and schools in the City of Auburn.
Progress Summary:
The project predesign (30% design) is being completed in 2004. The current grant source is to supplement the design
of the project only. Additional design dollars are needed along with Construction and Right of Way. The City is applying
for grant resources. The City is anticipating $150,000 in Federal High Speed Rail Money (section 1103C).
Impact on Operating Budget Once Completed:
The annual maintenance cost for this project is estimated to be $420.
Current Year Budget: 2006 YTD Actual Budget
Budget Expenditures Balance
Adopted Budget -
Budget Amendments
Adjusted Budget
Activity: 2005 YE 2006 'Veer End
Total Project
Prior to 2005 Estimate 2006 Budoet p Qjgct Total
�Qgn
Funding Sources:
Unrestricted Street Revenue 3,817 - 3,817
3,817
Grants 75,206 224,794 - 300,000
2,610,000
KC Open Space Bond 36,944 3,056 - 40,000
40,000
Other
500,000
Total Funding Sources: 115,967 227,850 343 817
3,153,817
Expenditures:
Design 115,967 227,850 - 343,817
403,817
Right of Way - - - -
50,000
Construction
2.700.000
Total Expenditure: 115,967 227,850 343,817
3,153,817
Forecasted Project Cost:
2007 2008 2009 2010 2011 Total
Funding; Sources: 2006; - 2011
Expenditure
Be and 2011
Unrestricted Street
Revenue - --
Grants 110,000 1,200,000 1,000,000 - - 2,310,000
KC Open Space Bond - - _ _ _ -
Other 300,000 200,000 500,000
Total Funding Sources: 110,000 1,500,000 1,200,000 2,810,000
Expenditures,
Design 60,000 - - - - 60,000
Right of Way 50,000 - - - - 50,000
Construction 1,500,000 1,200,000 2 700 000
Total Expenditure. 110,000 1,500,000 1 200 000 2 810 000
CAPITAL FACILITIES PLAN TIP #
2006-2011 22
Project Title: A Street SE Pedestrian Improvement
Project No:
Project Type: Non -Capacity (Non -Motorized)
Project Manager: TBD
Description:
Design and construct pedestrain path on West side of A Street SE under railroad bridge on BNSF property to bypass
existing stairs and create an ADA accessbile travel path.
Progress Summary:
Impact on Operating Budget Once Completed:
This project will have no impact on the operating budget for street maintenance.
Current Year Budget: 2006 YTD Actual Budget
Budget Expenditures Balance
Adopted Budget -
Budget Amendments
Adjusted Budget
Activity: 2005 YE 2006 Year End
Total Project
Prior to 2005 Estimate 2006 Budget P pAlct Total
9QAt
Funding Sources:
Unrestricted Street Revenue - - -
43,000
Grants - - - -
150,000
Bond Proceeds - - - _
_
Impact Fees
Total Funding Sources:
193,000
Expenditures:
Design - - - -
55,000
Right of Way - - - _
_
Construction
138,000
Total Expenditure:
193,000
Forecasted Project Cost:
2007 2008 2009 2010 2011 Total
Expenditure
Fundinn Sources: 2006-2011
Be and 2011
Unrestricted Street
Revenue - 43,000 - - - 43,000
Grants - 150,000 - - - 150,000
Bond Proceeds - -Impact
Fees
Total Funding Sources: 193,000 193,000
Exaendltures,
Design - 55,000 - - - 55,000
Right of Way - - - - _ -
Constructlon 138,000 138 000
Total Expenditure- 193.000 193 000
CAPITAL FACILITIES PLAN TIP #
2006-2011 23
Project Title: White River Trail Extension
Project No:
Project Type: Non -Capacity (Non -Motorized)
Project Manager: TBD
Description:
The proposed project is the 1,050 foot extension of the existing Class 1 White River Trail from its terminus in Roegner Park to A
Street SE/East Valley Highway. The trail extension will link the existing pedestrian facilities from Riverside High School and Ilalko
Elementary School to A Street SE. This project will grant school children safe passage across the White River via the bridge on
A Street SE. It will also connect to Auburn's BNSF/East Valley Highway Undercrossing, providing direct access from the
residential areas in the city of Pacific to schools in Auburn.
Progress Summary:
Impact on Operating Budget Once Completed:
The annual maintenance cost for this project is estimated to be $168.
Current Year Budget: 2006 YTD Actual Budget
Budget Expenditures Balance
Adopted Budget -
Budget Amendments
Adjusted Budget
Activity: 2005 YE 2008 Year End
Total Project
Prior to 2005 Estimate 2008 Budget Ewmt Total
Cost
Funding Sources:
Unrestricted Street Revenue - - -
27,200
Grants - - - -
174,200
Bond Proceeds - - - -
Impact Fees
Total Funding Sources:
201,400
Expenditures:
Design - - - -
17,500
Right of Way - - - -
140,000
Construction
43,900
Total Expenditure:
201,400
Forecasted Project Cost:
2007 2008 2008 2010 2011 Total
Expenditure
Funding Sources: 2008 - 2011
Be and 2011
Unrestricted Street
Revenue - - 27,200 - - 27,200
Grants - - 174,200 - - 174,200
Bond Proceeds - - - - -
Impact Fees
Total Funding Sources: 201,400 201,400
Expenditures:
Design - - 17,500 - - 17,500
Right of Way - - 140,000 - - 140,000
Construction 43 900 43,900
Total Expenditure: 201,400 201 400
Description:
CAPITAL FACILITIES PLAN TIP #
This project using existing ROW connect 37th Street to'R' Street SE with a paved Class 1 Trail.
2006-2011 24
Project Title:
37th Street SEPR' Street Connector
Project No:
Project Type:
Class 1 Trail
Project Manager:
TBD
Description:
This project using existing ROW connect 37th Street to'R' Street SE with a paved Class 1 Trail.
Progress Summary:
This project is a good candidate for a Safe Walking Route grant
Impact on Operating Budget Once Completed:
Current Year Budget: 2006 YTD Actual Budget
Budget Expenditures Balance
Adopted Budget -
BudgetAmendments
Adjusted Budget
Activity: 2005 YE 2006 Year End
Total Project
Prior to 2005 Estimate 2006 Budget Prolect Total
929
Funding Sources:
Unrestricted Streat Revenue - - - -
-
Grants - - - -
50,400
Other - - - -
12,600
hn act Fees
Total Funding Sources:
63,000
Expenditures:
Design - - - -
13,000
Right of Way - - - -
-
Construc6on
50,000
Total Expenditure:
63,000
Forecasted Project Cost:
2007 2008 2009 2010 2011 Total
Expenditure
Funding Sources: 200E - 2011
Be and 2011
Unrestricted Street
Revenue - - - - - _
Grants - 50.400 - - - 50,400
Other - 12,600 - - - 12,600
Impact Fees
Total Funding Sources: 63,000 63,000
Exoenditures:
Design - 13,000 - - - 13,000
Right of Way - - - - _ -
Constructlon 50,000 50 000
Total Expenditure: 63,000 63,000
Description:
CAPITAL FACILITIES PLAN TIP #
Design and construct a Class 1 Non -Motorized Trail from Green River Beach Access to Brannan Park. Coordinate
2006-2011 25
Project Title:
Green River Trail, Phase 1
Project No:
Project Type:
Non -Motorized Trail
Project Manager:
TBD
Description:
Design and construct a Class 1 Non -Motorized Trail from Green River Beach Access to Brannan Park. Coordinate
with Auburn Parks Department and King County Parks.
Progress Summary.
Impact on Operating Budget Once Completed:
The annual maintenance cost for this project is estimated to be $2,856.
Current Year Budget., 2006 YTD Actual Budget
Budget Expendhures Balance
Adopted Budget -
Budget Amendments
Adjusted Budget
Activity., 2005 YE 2006 Year End
Total Project
Prim to 2005 Estimate 2006 Budoet �Pmfect TO a
cost
Funding Sources:
Unrestricted Street Revenue - - -
-
Grants - - - -
620,000
Bond Proceeds - - - -
-
Impact Fees
Total Funding Sources:
620,000
Expenditures:
Design - - - -
225,000
Right of Way - - - -
-
Construction
395 000
Total Expenditure:
620,000
Forecasted Project Cost.
2007 2008 2008 2010 2011 Total
Expenditure
Funding Sources: 2006 - 2011
Beyond 2011
Unrestricted Street
Revenue - - - - - -
Grants - 125,000 495,000 - - 620,000
Bond Proceeds - - - - - -
Impact Fees
Total Funding Sources: 125,000 495,000 620,000
Expenditures:
Design - 125,000 100,000 - - 225,000
Right of Way - - - - - -
Construcdon 395,000 395,000
Total Ex ndlture: 125,000 495,000 620,000
CAPITAL FACILITIES PLAN TIP #
2006-2011 26
Project Title: Green River Trail, Phase 2
Project No:
Project Type: Non -Motorized Trail
Project Manager: TBD
Description:
Design and construct a Class 1 Non -Motorized Trail from Brannan Park
to 4th Street SE.
Coordinate with Auburn
Parks Department and King County Parks.
Progress Summary:
Impact on Operating Budget Once Completed:
Not scheduled for completion until after 2010.
Current Year Budget: 2006
YTD Actual
Budget
Budget
Expenditures
Balance
Adopted Budget
-
Budget Amendments
Adjusted Budget
Activity:
2005 YE
2006'1'ear End
Total Project
Prior to 2005
Estimate
2006 Budoet
Prole ct Total
929
Funding Sources:
Unrestricted Street Revenue -
-
-
-
Grants -
-
-
-
450,000
Rev -Other -
-
-
-
280.000
Impact Fees
Total Funding Sources:
730,000
Expenditures:
Design -
-
-
-
150,000
Right of Way -
-
-
-
-
Construction
580,000
Total Ex dlture:
730 000
Forecasted Project Cost:
2007 2008 2009
2010
2011
Total
Expenditure
Funding Sources:
2000; - 2011
Be and 2011
Unrestricted Street
Revenue - - -
-
-
-
Grants - - -
120,000
330,000
450,000
-
Rev -Other - - -
30,000
150,000
180,000
100,000
Impact Fees
Total Funding Sources:
150,000
480,000
630,000
100,000
Expenditures:
Design - - -
150,000
-
150,000
-
Right ofWay - - -
-
-
-
-
construction
480 000
480,000
100,000
Total Expenditure:
150,000
480,000
630 000
100,000
Description:
CAPITAL FACILITIES PLAN TIP Al
Design and construct a Class 1 Non -Motorized Trail from 4th Street SE to SR 18. Coordinate with Auburn Parks
2006-2011 27
Project Title:
Green River Trail, Phase 3
Project No:
Project Type:
Non -Motorized Trail
Project Manager.
TBD
Description:
Design and construct a Class 1 Non -Motorized Trail from 4th Street SE to SR 18. Coordinate with Auburn Parks
Department and King County Parks.
Progress Summary:
Impact on Operating Budget Once Completed:
Not scheduled for completion until after 2010.
Current Year Budget: 2006 YTD Actual Budget
Budget Expenditures Balance
Adopted Budget -
Budget Amendments
Adjusted Budget
Activity: 2005 YE 2006 Year End
Total Project
Prior to 2005 Estimate 2006 Budaet Prolect 7IPA/
9W
Funding Sources:
Unrestricted Street Revenue - - -
-
Giants - - - -
575,000
Bond Proceeds - - - -
150,000
ImpactFees
Total Funding Sources:
725,000
Expenditures;
Design - - - -
725,000
Right of Way - - - -
-
Constructlon
Total Expenditure:
725,000
Forecasted Project Cost:
2007 2008 2009 2010 2011 Total
Expenditure
Funding sources: 2006.2011
Beyond 2011
Unrestricted Street
Revenue - - - - - -
-
Giants - - - - - -
575,000
Bond Proceeds - - - - 30,000 30,000
120,000
Impact Fees
Total Funding Sources: 30,000 30,000
695,000
Exaendlturea"
Design - - - - 30,000 30,000
695,000
Right of Way - - - - - -
-
Construction
Total Ex nditure: 30,000 30,000
695,000
Description:
CAPITAL FACILITIES PLAN TIP #
2006-2011 28
Project Title: •
Academy Drive Multi Use Trail
Project No:
Academy Drive
Project Type:
Non -Motorized Trail
Project Manager.,
TBD
Description:
Using the existing right of way, repair the damaged roadbed to a usable
multiuse trail on
Academy Drive
from the
Green River Road to Auburn Way South.
Progress Summary:
Impact on Operating Budget Once Completed:
Current Year Budget: 2006
YTD Actual
Budget
Budget
Expenditures
Balance
Adopted Budget
Budget Amendments
Adjusted Budget
Activity. -
2005 YE
2006 Year End
Total Project
Prior to 2005
Estimate
2006 Budaet
Prolect 712W
f�j
Funding Sources:
Unrestricted Street Revenue -
-
-
-
100,000
Grants -
-
-
-
900,000
Other -
-
-
-
-
Impact Fees
Total Funding Sources:
1,000,000
Expenditures;
Design -
-
-
-
150,000
Right of Way -
-
-
-
-
Construction
850,000
Total Expenditure:
1,000,000
Forecasted Project Cost:
2007 2008 2009
2010
2011
Total
Expenditure
Fundino Sources:
2006-2011
Beyond 2011
Unrestricted Street
Revenue - - 15,000
42,500
42,500
100,000
-
Grants - - 135,000
382,500
382,500
900,000
-
Other - - -
-
-
_
_
Impact Fees
Total Funding Sources: 150,000
425,000
425,000
1,000,000
0
Exoendlturea,
Design - - 150.000
-
-
150,000
-
Right or Way - - -
-
_
_
Construction
425,000
425,000
850 000
Total Expenditure: 150o000
425,000
425,000
1 000 000
0
Studies and
Miscellaneous
Improvements
CAPITAL FACILITIES PLAN TIP #
2006-2011 29
Project Title: A Street SE - Class 2
(Transit Center to Ellingson along BNSF)
Project No:
Project Type: Non -Capacity (Non -Motorized)
Project Manager- TBD
Description:
Feasibility study for the design and construction of a Class 2 pedestrian trail from the Transit Center from A Street SV
I
to A Street SE and along A Street SE to Ellingson Road along the BNSF right of way.
Progress Summary:
Impact on Operating Budget Once Completed:
The annual maintenance cost for this project is estimated to be $3,696
Current Year Budget: 2006 YTD Actual Budget
Budget Expenditures Balance
Adopted Budget
BudgetAmendments
Adjusted Budget
Activity: 2005 YE 2006 Year End
Total Project
Prior to 2003 Estimate 2006 Budoet Prolmj Tota/
Cpat
Funding Sources:
Unrestricted Street Revenue - - -
75,000
Grants - - - -
-
Other - - - -
Impact Fees
Total Funding Sources:
75,000
Expenditures:
Design - - - -
75,000
Right of Way - - - -
-
Construction
Total Expenditure:
75,000
Forecasted Project Cost:
2007 2008 2009 2010 2011 Total
Expenditure
Funding Sources: 2006-2011
Beyond 2011
Unrestricted Street
Revenue - 75,000 - - - 75,000
Grants - - - - - -
Other - - - -
Impact Fees
Total Funding Sources: 75,000 75,000
Expenditures:
Design - 75,000 - - - 75,000
Right of Way - - - - -
Construction
Total Ex enditure: 75,000 76,000
CAPITAL FACILITIES PLAN TIP #
2006-2011 30
Project Title: Auburn Black Diamond Non -Motorized Class I Trail
Project No:
Project Type: Study
Project Manager: TBD
Description:
Widen roadway shoulders to accommodate bicyclists and pedestrians. It will provide a multi -modal enhancement to a
regional recreation bike route. Mitigate expected impacts to wetlands adjacent to the road.
Progress Summary:
It is antcipated that a pre -design study will be completed by the end of 2005. It is anticipated that ROW and constructio
dollars will be reflected in the 2007-2012 Transportation Improvement Plan.
Impact on Operating Budget Once Completed:
The annual maintenance cost for this project is estimated to be $1,260.
Current Year Budget: 2006 YTD Actual Budget
Budget Expenditures Balance
Adopted Budget -
Budget Amendments -
Adjusted Budget
Activity: 2005 YE 2006 Year End
Total Project
Prior to 2005 Estimate 2006 Budaet Prolect .rote/
929
Funding Sources:
Unrestricted street Revenue - 35,000 - 35,000
35,000
Grants - - - -
-
Bond Proceeds - - - -
Impact Fees
Total Funding sources: 35,000 35,000
35,000
Ex ditures:
Design - 35,000 - 35,000
35,000
Right of Way - - - -
-
Construction
Total Expenditure: 35,000 35 000
35,000
Forecasted Project Cost:
2007 2008 2009 2010 2011 Total
Expenditure
Funding Sources: 2006-2011
Beyond 2011
Unrestricted Street
Revenue - - - - - -
Grants - - - - - -
Bond Proceeds - - - - -
Impact Fees
Total Funding sources:
Expenditures:
Design -
Right ofWay - - - - - -
Construction
Total Expenditure:
CAPITAL FACILITIES PLAN TIP #
2006-2011 31
Project Title: Kersey Way Trail
Project No:
Project Type: Study
Project Manager: TBD
Description:
Feasibility study for design and construction of a Non -Motorized Equestrian Accessible trail along Kersey Way to
connect R Street SE, the Stuck River Horse Trail and the Lakeland Hills neighborhood non -motorized trails.
Progress Summary:
It is antcipated that a pre-design/feasibility study will be completed by end of 2005.
Impact on Operating Budget Once Completed:
The annual maintenance cost for this project is estimated to be $1,680.
Current Year Budget: 2006 YTD Actual Budget
Budget Expenditures Balance
Adopted Budget -
Budget Amendments
Adjusted Budget
Activity: 2005 YE 2006 Year End
Total Project
Prior to 2005 Estimate 2006 Budget Emigat Total
.929
Funding Sources:
Unrestricted Street Revenue - 40.000 - 40.000
40,000
Grants - - - -
-
Other
Impact Fees
Total Funding Sources: 40 000 40,000
40,000
Expenditures:
Design - 40,000 - 40,000
40,000
Right of Way - - - -
-
Construction
Total Ex endlf im: 40,000 40,000
40,000
Forecasted Project Cost:
2007 2008 2009 2010 2011 Total
Expenditure
Funding Sources: 2006; - 2011
Beyond 2011
Unrestricted Street
Revenue - - - - - -
Grants - - - - - -
Other - - - - -
Impact Fees
Total Funding Sources:
Expenditures:
Design - - - - -
Right ofWay - - - - - -
Construction
Total Ex ndltum;
CAPITAL FACILITIES PLAN TIP #
2006-2011 32
Project Title: Pavement Condition Rating Update
Project No:
Project Type: Non -Capacity (Annual)
Project Manager. TBD
Description:
Update the Pavement Condition Rating of the Classified Street System. Due to traffic
loads that classified streets
encounter they need to be re-evaluated on a more frequent schedule to stay current.
Progress Summary:
Impact on Operating Budget Once Completed.
This project will have no impact on the operating budget for street maintenance.
Current Year Budget: 2006
YTD Actual
Budget
Budget
Expenditures
Balance
Adopted Budget
Budget Amendments
Adjusted Budget
Activity: 2005 YE
2006 Year End
Total Project
Prior to 2005 Esdma
2006 Budget
Protect TO
QQ9
Funding Souroes:
Unrestricted Street Revenue - -
50,000
50,000
50,000
Grants - -
-
-
-
REET Funding - -
-
-
Impact Fees
Total Funding Sources:
50,000
50,000
50,00
Expenditures:
Design - -
50,000
50,000
50,000
Right of Way - -
-
-
-
constructlon
Total Expenditure:
60,000
50 000
50,000
Forecasted Project Cost:
2007 2008 2009 2010
2011
Toral
Expenditure
Funding Sources:
2006-2011
Beyond 2011
Unrestricted street
Revenue - - - -
-
50,000
Grants - - - -
-
REST Funding - - - -
-
Impact Fees
Total Funding sources:
50,000
Expendltures:
Design - - - -
-
50,000
Right of Way - - - -
-
-
Constructlon
Total Ex end/tura:
50,000
Description:
CAPITAL FACILITIES PLAN TIP #
Rehabilitate' M' Street SE between 29th Street SE and 37th Street SE, including construction of new pedestrian
2006-2011 38
Project Title:
M St SE (37th / 29th)
Project No:
Project Type:
Non -Capacity
Project Manager:
Scott Nutter
Description:
Rehabilitate' M' Street SE between 29th Street SE and 37th Street SE, including construction of new pedestrian
facilities and replacement of a sanitary sewer line for 1/2 the project. Sewer will be budgeting approximately $400,000
towards there improvements and will be eligible to be counted as our match to the Federal Earmark grant.
Progress Summary:
The pre -design study is completed and we expect design to be completed by end of the year 2005.
Impact on Operating Budget Once Completed:
No operating impact because this is design study only.
Current Year Budget: 2006 YTD Actual
Budget
Budget Expenditures
Balance
Adopted Budget
-
Budget Amendments
Adjusted Budget
Activity: 2005 YE
2006 Year End
Total Project
Prior to 2005 Estimate 2006 Budget
Protect Total
Cost
Funding Sources:
REET2 10,000 75,000 325,000
410,000
410,000
Grants - - 400,000
400,000
400,000
Impact Fees
Total Funding Sources: 10,000 75,000 725,000
810,000
810,000
Expenditures;
Design 10,000 75,000 -
85,000
85,000
Right of Way - --
-
-
Construction 725 000
725,000
725,000
Total Expenditure: 10,000 76,000 725,000
810,000
810.000
Forecasted Project Cost:
2007 2008 2009 2010 2011
Total
Expenditure
Funding Sources:
2006 - 2011
Be and 2011
REET2 - - - - -
325,000
Grants - - - - -
400,000
Impact Fees
Total Funding Sources:
725,000
Expenditures:
Design - - - - -
-
Right ofWay - - - - -
-
Construcdon
725,000
Total Expenditure:
725 000
Annual Level of
Effort
p
rojects
CAPITAL FACILITIES PLAN TIP #
2006-2011 33
Project Title: So 277th Wetland Mitigation
Project No: C410A
Project Type: Non -Capacity
Project Manager: Scott Nutter
Description:
Wetland mitigation for the 277th Street Grade Separation project.
Progress Summary:
This is a 10 year obligation begun in 2004.
Impact on Operating Budget Once Completed:
This project will have no impact on the operating budget for street maintenance.
Current Year Budget: 2006 YTD Actual Budget
Budget Expenditures Balance
Adopted Budget -
Budget Amendments
Adjusted Budget
Activity: 2005 YE 2009; Year End
Total Project
Prior to 2005 Estimate 2006 Buda et Pro,red To al
(zQ9
Funding Sources:
Unrestricted Street Revenue 22,607 35,600 15,000 73,207
178,207
Grants - - - -
-
BondProceeds - - - -
Impact Fees
Total Funding Sources: 22,607 35,600 15,000 73,207
178,207
Expenditures:
Design - 3,000 3,000 6,000
27,000
Right of Way - - - -
-
Construction 22,607 32600 12,000 67,207
151.207
Total Ex ndlture: 22,607 35,600 - 15,000 73 207
178,207
Forecasted Project Cost:
2007 2008 2009 2010 2011 Total
Expenditure
Funding Sources: 2008 - 2011
Beyond 2011
Unrestricted Street
Revenue 15,000 15,000 15,000 15,000 15,000 90,000
30,000
Grants - - - _ _
_
Bond Proceeds
impact Fees
Total Funding Sources. 15,000 15,000 15,000 15,000 15,000 90,000
30,000
Exoend/turos:
Design 3,000 3,000 3,000 3,000 3,000 18,000
6,000
Right of Way - - - - _
Construction 12,000 12,000 12,000 12,000 12,000 72000
24,000
Total Expenditure: 15,000 15,000 15,000 15,000 15,000 90,000 1
30 000
CAPITAL FACILITIES PLAN TIP #
2006-2011 34
Project Title: Citywide Pedestrian Crossing Program
Project No:
Project Type: Non -Capacity (Annual)
Project Manager: TBD
Description:
This project provides for pedestrian safety studies at various locations citywide. Projects are prioritized
annually based
on safety issues and pedestrian demands. Budget Notes: This is an annual
level of effort project used to fund small pedestrian safety studies and improvement projects.
Progress Summary:
Anticipated by the end of 2005 the crossing on 3rd Street NW near post office will be completed and a pedestrian
crossing on I Street NE near Top Foods will be completed.
Impact on Operating Budget Once Completed:
This project will have no impact on the operating budget for street maintenance.
Current Year Budget: 2006 YTDActual
Budget
Budget Expenditures
Balance
Adopted Budget
-
Budget Amendments
Adjusted Budget
Activity: 2005 YE
2006 Year End
Total Project
Prior to 2005 Estimate 2006 Budget
PMt,-ct Total
cov
Funding Sources:
Unrestricted Street Revenue - 20,000 50,000
70,000
320,000
Grants - - -
-
-
Bond Proceeds - - -
-
Impact Fees
Total Funding Sources: 20,000 50,000
70,000
320.000
Expenditures:
Design - 5,000 7,500
12,500
50,000
Right of Way - - -
-
-
Construction 15,000 42,500
57,500
270,000
Total Expenditure: 20,000 50,000
70,000
320,000
Forecasted Project Cost:
2007 2008 2009 2010 2011
Total
Expenditure
Funding Sources:
2005 - 2011
Beyond 2011
Unrestricted Street
Revenue 50,000 50.000 50,000 50,000 50,000
300,000
Grants - - - - -
_
Bond Proceeds
Impact Fees
Total Funding Sources: 50,000 50,000 50,000 50,000 50,000
300,000
Expenditures:
Design 7,500 7.500 7,500 7.500 7,500
45,000
Right of Way - - - - -
-
Construction 42,500 42,500 42,500 42,500 42,500
255 000
Total Expenditure: 50,000 50,000 50,000 50,000 50 000
300,000
CAPITAL FACILITIES PLAN TIP #
2006-2011 35
Project Title: Citywide Roadway Safety Infrastructure Improv.
Project No:
Project Type: Non -Capacity (Safety)
Project Manager: Varies
Description:
This project provides for infrastructure improvements to enhance traffic safety. Projects are prioritized annually based on
field studies.
Progress Summary:
Example projects completed include Guardrail for Dravetz Road, Terrace Drive, and Lake Tapps Parkway. Suggested
candidates for 2006 project: install "Qwick Kurbs" near RR crossings, or uphill edge of roadway guardrail on Lake Tapps
Parkway.
Impact on Operating Budget Once Completed:
This project will have no impact on the operating budget for street maintenance.
Current Year Budget: 2006
YTD Actual
Budget
Budget
Expenditures
Balance
Adopted Budget
-
Budget Amendments
Adjusted Budget
Activity: 2005 YE
2006 Year End
Total Project
prior to 2005 Estimate
2006 Budget
Prolect Total
9"1
Funding Sources:
Unrestricted Street Revenue - -
50,000
50,000
550,000
Grants - -
-
-
-
BondProceeds - -
-
-
Impact Fees
Total Funding Sources:
50,000
50,000
550,000
Expenditures:
Design - -
5,000
5,000
55,000
Right of Way - -
-
-
-
Construction
45,000
45000
495,000
Total Expenditure:
50P000
50,000
550,000
Forecasted Project Cost:
2007 2006 2009 2010
2011
Total
Expenditure
Funding Sources:
2006.2011
Beyond 2011
Unrestricted street
Revenue 100,000 100,000 100,000 100,000
100,000
550,000
Grants - - - -
Bond Proceeds - - - -
-
_
Impact Fees
Total Funding Sources: 100,000 100,000 100,000 100,000
100,000
550,000
Expenditures:
Design 10,000 10,000 10,000 10,000
10,000
55,000
Right of Way - - - -
-
_
Construction 90,000 90,000 90,000 90,000
90,000
495 000
Total Ex nditure: 100,000 100P000 100,000 100,000
100,000
550!000
CAPITAL FACILITIES PLAN TIP #
2006-2011 36
Project Title: Annual Arterial Pavement Preservation
Project No:
Project Type: Non -Capacity (Annual)
Project Manager: Varies
Description:
Implement regular maintenance and/or rehabilitation of various classified streets.
Progress Summary:
Moving money to'C' Street NW as the 2006 Candidate for Pavement Reconstruction. Completed Auburn Black
Diamond Road in 2005.
Impact on Operating Budget Once Completed:
This project will have no impact on the operating budget for street maintenance.
Current Year Budget: 2006 YrD Actual Budget
Budget Expenditures Balance
Adopted Budget
BudgetAmendments
Adjusted Budget
Activity: 2005 YE 2006 Year End
Total Project
Prior to 2005 Estimate 2006 Budget Prolect TO
_Qxt
Funding Sources:
Unrestricted Sheet Revenue - - - -
-
Grants _ _ _ _
-
REETFunding - 500,000 - 500,000
3,000,000
Impact Fees
Total Fundino Sources: 500,000 500,000
3,000,000
Expenditures:
Design - 20,000 - 20,000
220,000
Right of Way - - - -
-
Construction 480,000 480,000
2,780,000
Total Expenditure: 500,000 500,000
3,000,000
Forecasted Project Cost:
2007 2008 2009 2010 2011 Total
Expenditure
Funding Sources: 2006. 2011
Beyond 2011
Unrestricted Street
Revenue - - - - -
Grants - - - - _ -
REETFunding 500,000 500,000 500,000 500,000 500,000 2.,500,000
Impact Fees
Total Funding Sources: 500,000 500,000 500,000 500,000 500,000 2 500p00
Expenditures:
Design 40,000 40,000 40,000 40,000 40,000 200,000
Right of Way - - - - - _
Construction 460,000 460,000 460000 460,000 460,000 2,300000
Total Expenditure: 500,000 500,000 500,000 500,000 500P000 2,600 000
CAPITAL FACILITIES PLAN TIP #
2006-2011 37
Project Title: Annual Arterial Crack Seal Program
Project No:
Project Type: Non -Capacity (Annual)
Project Manager: TBD
Description:
Implement regular maintenance and/or rehabilitation of various classified streets.
Progress Summary:
Impact on Operating Budget Once Completed.
This project will have no impact on the operating budget for street maintenance.
Current Year Budget: 2006
YTD Actual
Budget
Budget
Expenditures
Balance
Adopted Budget
Budget Amendments
Adjusted Budget
Activity: 2005 YE
2006 Year End
Total Project
Prior to 2005 Est/mate
2006 Budget
Prolect TO
rggt
Funding Sources:
Unrestricted Street Revenue - -
80,000
80,000
480,000
Grants - - -
-
-
-
REET Funding - -
-
Impact Fees
Total Funding sources:
80,000
80,000
480.00
Expenditures:
Design - -
5,000
5,000
30,000
Right of Way - -
-
-
_
Construction
75 000
75,000
450,000
Total Expenditure:
80,000
80 000
480 000
Forecasted Project Cost:
2007 2008 2009 2010
2011
Total
Expenditure
Funding Sources:
2006-2011
Beyond 2011
Unrestricted Street
Revenue 80,000 80.000 80,000 80,000
80,000
480,000
Grants - - - -
-
-
REETFunding - - - -
-
Impact Fees
Total Funding Sources: 80,000 80,000 80,000 80,000
80,000
480,000
Expenditures:
Design 5,000 5,000 5,000 5,000
5,000
30,000
Right of Way - - - -
-
-
Construction 75,000 75,000 75,000 75,000
75,000
450000
Total Expenditure: 80,000 80,000 80,000 80,000
80,000
480 000
Save Our Streets
(SOS) Program
CAPITAL FACILITIES PLAN TIP #
2006-2011 39
Project Title: Local Street Improvement Program
Project No: Varies
Project Type: Non -Capacity
Project Manager., Seth Wtckstrom
Description:
This program was created after Proposition 1 was passed in the November
2004 ballot, setting the City's property tax levy
limits and creating a dedicated local street fund to be used solely for local street improvements. The program will consist
of a number of different contracts focused on the preservation of local streets (unclassified streets) within the City of
Auburn. These contracts will include work such as crack sealing, asphalt patching, pre -leveling, asphalt overlays, and
pavement reconstruction.
Progress Summary.
Approxiately 12 miles of local residential streets were crack sealed in 2005.
Approximately 8 miles of those streets are
having an asphalt overlay completed in 2005. Reconstruction of V Street SE between 29th Street SE and 37th Street
SE is scheduled for 2006, design is expected to be completed in 2005.
Impact on Operating Budget Once Completed.,
None
Current Year Budget: 2006
YTD Actual Budget
Budget Expenditures Balance
Adopted Budget
-
BudgetAmendments
Adjusted Budget
Activity:
2005 YE 2006 Year End
Total Project
Prior to 2005
Estimate 2906 Outlast PPr lett Total
_Q9
Funding Sources:
Levy Lid Lift -
200,000 269,400 469,400
5,869,400
G 04 Sales Tax -
680,000 - 680,000
680,000
Property Tax -
- 230.600 230,600
910,600
REET2 -
- 540,000 540,000
1,140,000
Utility Trench Impact Funds -
150,000 150,000 300,000
300,000
Interest on 103 Fund -
- 10,000 10,000
6,690.000
Interest on the 328 Fund
170,000 170,000
170,000
Total Funding Sources:
1,200,000 1 200 000 2 400 000
15,760,000
Expenditures:
Design -
200,000 - 200.000
868.000
Right of Way -
- - -
-
Construction
1,000,000 1200,000 2200,000
8,212000
Total Expenditure:
1,200,000 1 200000 2,400p000
9 080 000
Forecasted Project Cost.
2007 2008 2009
2010 2011 Total
Expenditure
Funding Sources:
2006.2011
Beyond 2011
Levy Lid Lift 900,000 1,200,000 1,500,000
1,800,000 - 5,669,400
-
G 04 Sales Tax - - -
- - _
_
Property Tax - - -
- - 230,600
REET2 170,000 170,000 170,000
170,000 - 1,220,000
Utility Trench Impact Funds 150,000 150,000 150,000
150,000 - 750,000
Interest on 103 Fund - - -
- - 10,000
-
Interest on the 328 Fund
Total Funding Sources: 1,220,000 1,520,000 1,820,000
2,120,000 7,880,000
Expenditures:
Design 122,000 152,000 182,000
212,000 - 868,000
Right of Way - - -
_ -
..
Construction 1,098 000 1,368 000 1,638,000
1,908,000 7,212,000
Total Expenditure.- 1,220 000 1,520,000 1 820 000
2o120,000 7 880 000
Appendix A.o
City Wide Project
Map
Appendix Be.
Detailed Funding
Spreadsheet