Agenda Subject:
Date:
Permission to Advertise Project No. C505A
September 8, 2005
Department:
Attachments:
Budget Impact:
Public Works
I Budget Status Sheet and Ma
$ 0
Administrative Recommendation:
City Council grant permission to advertise for bids for Project No. C505A, 2005 Annual Arterial Pavement
Preservation, Auburn -Black Diamond Road
Background Summary:
The purpose of this project is to complete paved preservation of 2,400 feet of Auburn -Black Diamond Rd.,
from just east of the Burlington Northern Santa Fe railroad crossing to the city limits. The failing road
segment will have the existing overlay planed off, concrete panels doweled together, and a structural
overlay installed on the existing subgrade and within its current alignment and road width.
The anticipated construction start date is November 2005 with completion by February 2006.
W0919-1
04.9.1 C505A
Reviewed by Council & Committees:
Reviewed by Departments & Divisions:
❑ Arts Commission COUNCIL COMMITTEES:
❑ Building ❑ M&O
❑ Airport ❑ Finance
❑ Cemetery ❑ Mayor
❑ Hearing Examiner ❑ Municipal Serv.
❑ Finance ❑ Parks
❑ Human Services ❑ Planning & CD
❑ Fire ❑ Planning
❑ Park Board ®Public Works
❑ Legal ❑ Police
❑ Planning Comm. ❑ Other
® Public Works ❑ Human Resources
Action:
Committee Approval: [-]Yes ❑No
Council Approval: ❑Yes ❑No Call for Public Hearing
Referred to UntilI—I—
Tabled Until— _/_!_
Councilmember: Wagner I Staff: Dowd
Meeting Date: September 19, 2005 Item Number: Item V.C.1
AUBURN* MORE THAN YOU IMAGINED
BUDGET STATUS SHEET
Project No: C606A Title: Auburn -Black Diamond Rd. Reconstruction
Q PS&E @ 80°h
O Pre-bid Dale: September, 2005
O Award
Const. @ 0%
Funds Budgeted (Funds Available)
Funding
2005
2006
Total
102 Arterial Street: Fund
500,000
500,000
Total
500,000
0
500,000
Estimated Cost (Funds Needed)
- Activity
2005
2006
Total
Design Engineering : -
20,000
20,000
PropertyAcquisition '
0
0
Construction Estimate:
420,000
0
420,000
Construction Contingency
40,000
40,000
Construction Engineering
20,000
20,000
Total
500,000
0
500,000
102 Budget Status (Arterial Street)
w0627 -4a
Print Date: 9/8/2005
2005
2006
Total
102Funds Budgeted
500,000
500,000
500.000
500,000
102 Funds Needed
(102 Fund Project Contingency)
102 Funds Required
0
0
0
w0627 -4a
Print Date: 9/8/2005
rA
Ci
01
0
1>
n
m
F
z
m
ww�
I
O
O
cyl
>
C
co
C
Z
>
F -
r sr SF
�()
Z>
;ou
m
;u cl)
co
F -
>
C)
_
r
KM
m
m
0
4TH PL
0
>
pm
m
Un
mw
O
14 11
1>
n
m
F
z
m
ww�
I
u ST
MIR
S ST SE --
Va
r sr SF
Fol
4TH PL
mw
num
jet
14 11
u ST
MIR