Agenda Subject: Consultant Agreement No. AG-C-327-A
Date: November 13, 2006
Attachments: Resolution No. 4109, Proposed
amendment NO.1 to Agreement #AG-C-327-A,
Budget Status Sheet
Administrative Recommendation:
City Council adopt Resolution No. 4109.
Department:
Finance
Budget Impact:
$
Background Summary:
When initially planned, and the Scope of Services agreed with David A. Clark Architects, the Golf Course
Clubhouse building included a restaurant and Pro Shop, but no banquet room facility. Mid way through
the design, the decision was made, first to provide an outdoor covered area for meetings and events, and
then to actually incorporate it into the building as a banquet room. This increased the building size by
one sixth, with commensurate increase in cost of design. This amendment provides for those increased
costs.
The cost of this increased effort for the A&E team is $ 41,000. The budget for the project, structured after
the decision to add this space to the scope was made, and for which bonds were authorized and sold,
included this increased cost of design, and so is not affected by this amended amount.
The original agreed Scope of Work also only envisioned preparation and handling of one set of
documents (drawings, specifications, calculations) necessary to acquire project permits. In actual events,
preparation of several different sets of documents was required, involving two separate
Grading/excavation permits, as well as the general building permit. These required extensive extra
services by the A&E team, particularly the Civil Engineer.
The cost of this additional service is $ 5,269. The budget for the project includes sufficient contingency in
the amount for the Design portion, to accommodate this increase.
The total not-to-exceed amount for this amendment is $ 46,269, increasing the agreement total to
$ 312,000. A project budget contingency of $ 265,000 remains in the Bond fund.
N1120-304.4.7
Reviewed by Council & Committees:
o Arts Commission COUNCIL COMMITTEES:
o Airport 0 Finance
D Hearing Examiner [8J Municipal Servo
o Human Services 0 Planning & CD
o Park Board OPublic Works
o Planning Comm. 0 Other
Reviewed by Departments & Divisions:
D Building 0 M&O
o Cemetery 0 Mayor
[8J Finance 0 Parks
o Fire D Planning
o Legal D Police
o Public Works 0 Human Resources
Action:
Committee Approval:
Council Approval:
Referred to
Tabled
OYes ONo
DYes ONo Call for Public Hearing _I-.J_
Until_I_I_
Until _1_1_
Councilmember: Cerino
Meetin Date: November 20, 2006
Staff: Coleman
Item Number: VIII.B.2
AUBURN * MORE THAN YOU IMAGINED
RESOLUTION NO.4 1 0 9
A RESOLUTION OF THE CITY COUNCil OF THE CITY OF
AUBURN, WASHINGTON, AUTHORIZING THE MAYOR AND CITY
CLERK TO EXECUTE FIRST AMENDMENT TO AGREEMENT FOR
PROFESSIONAL SERVICES AG-C-327 A BETWEEN THE CITY
AND DAVID A. CLARK ARCHITECTS, PlLC
WHEREAS, the City and David A. Clark Architects, PlLC have previously
entered into a professional services agreement approved on Resolution No.
3950 in December 2005; and
WHEREAS, the initial Scope of Services for the Auburn Golf Course
Clubhouse have changed to now include a banquet room facility, increasing the
building size by one sixth with commensurate increase in cost of design; and
WHEREAS, the original Scope of Work also only envisioned preparation
and handling of one set of documents and in actual events preparation of several
different sets of documents were needed, requiring extensive extra services; and
WHEREAS, the cost of the additional services total a not-to-exceed
amount of $46,269, increasing the agreement total to $312,000; and
WHEREAS, a project budget contingency of $265,000 remains in the
Bond fund.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF AUBURN,
WASHINGTON, HEREBY RESOLVES AS FOLLOWS:
Section 1. Purpose. The Mayor and City Clerk of the City of Auburn are
herewith authorized to execute First Amendment to Agreement for Professional
Services AG-C-327-A with David A. Clark Architects, PlLC. A copy of said
Resolution No. 4109
November 13,2006
Page 1 of 2
Agreement is attached hereto, denominated as Exhibit "A" and made a part
hereof as though set forth in full herein.
Section 2. Implementation. The Mayor of the City of Auburn is hereby
authorized to implement such administrative procedures as may be necessary to
carry out the directions of this resolution.
Section 3. Effective Date. This Resolution shall take effect and be in full
force upon passage and signatures hereon.
DATED and SIGNED THIS
DAY OF
,2006.
CITY OF AUBURN
PETER B. LEWIS
MAYOR
ATTEST:
Danielle E. Daskam,
City Clerk
Resolution No. 4109
November 13, 2006
Page 2 of 2
AMENDMENT NO.1 TO AGREEMENT NO. AG-C-327 -A BETWEEN
THE CITY OF AUBURN AND DAVID A. CLARK ARCHITECTS, PLLC
RELATING TO PROJECT NO. c327aO, AUBURN GOLF COURSE CLUBHOUSE
THIS AMENDMENT is made and entered into this day of
, 200_, by and between the CITY OF AUBURN, a
municipal corporation of the State of Washington (hereinafter referred to
as the "CITY"), and David I. Clark Architects, PLLC (hereinafter referred to
as the "CONSUL TANT"), as an Amendment to the Agreement between
the parties for AG-C-327 -A executed on the 19th day of December 2005.
The changes to the agreement are described as follows:
1. CONTRACT TERM: The term of the Agreement for Professional
Services remains unchanged.
2. SCOPE OF WORK: The scope of work is amended to include the
following tasks:
A. Architectural and Engineering services, as described in the original
agreement, to accommodate an expanded program scope;
specifically including the enlargement of the building for a banquet
room to accommodate approximately 150 diners. The room is to
be fully part of the clubhouse structure, with full provision of
building systems, and Code compliant exiting
B. Provision of additional Architectural and Engineering services to
provide drawings, calculations, and other required documents for
two Grading and Excavation permits, separate from the General
Building permit documents to be prepared under the original
Agreement.
3. CLARIFICATION OF SERVICE TERMS: The responsibilities of
the CONSULTANT during construction of the work of the program scope
for which this agreement provides services, shall be as specifically defined
in AlA standard form B163, previously referenced in, and attached to, the
original Agreement.
4. COMPENSATION: The amount of this amendment is $ 46,269.
The total contract amount is increased to a total of $ 312,000.
Resolution No. 4109, Exhibit "AU
Amendment NO.1 for Agreement No. AG-C-327-A
David A. Clark Architects, PLLC
Page 1 of 2
REMAINING TERMS UNCHANGED: That all other provisions of the Agreement
between the parties for AG-C-327 -A executed on the 19th day of December 2006, shall
remain unchanged, and in full force and effect.
IN WITNESS WHEREOF the parties hereto have executed this Agreement as of the
day and year first above written.
David A. Clark Architects, PLLC
CITY OF AUBURN
By:
David Clark, AlA
Peter B. Lewis, Mayor
ATTEST:
Danielle E. Daskam, Auburn City Clerk
Resolution No. 4109, Exhibit "A"
Amendment NO.1 for Agreement No. AG-C-327-A
David A. Clark Architects, PLLC
Page 2 of 2
BUDGET STATUS SHEET
I Project No: c327aO
Project Manager: Paul Berry
Project Title:
Auburn Golf Course Clubhouse
Date: November 1, 2006
o Project Initiation
o Permision to Advertise
o Contract Award
@ Consultant Contract Amendment Approval
o Contract Final Acceptance
Initiation Date:
Advertisement Date:
Award Date:
The "Future Years" column indicates the projected amount to be requested in future budgets.
Funds Bud
Funding Prior Years 2005 Future Years Total
437 Fund - from REET monies 700,000 700,000
Bonds 4,800,000 4,800,000
Total 0 0 5,500,000 5,500,000
Activity Prior Years 2005 2006 Future Years Total
Utility Installations - Engineering (C327B) 350,000 350,000
Design - Consultant Costs 325,000 325,000
Project Management - Consultant Costs 230,000 230,000
Specialty Equipment 160,000 160,000
Construction by Contractor - Estimate 3,400,000 3,400,000
Project Contingency (15%) 250,000 250,000
Admin, Permits, etc. 55,000 55,000
Construction - City Costs 600,000 600,000
Construction Engineering - Consultant Costs 30,000 30,000
I Other - Reserve Bond Amounts, Bond Costs 100,000 100,000
Total 0 0 5,500,000 5,500,000
Estimated Cost (Funds Needed)
# Bond Funds Budgeted ( )
Funds Needed
* Fund Project Contingency ( )
Funds Required
o
o
o
o
437 Fund Bud et Status
2005 2006 Future Years
700,000 0
o 0
000
o 700,000 0
Bond Funds Bud et Status
2005 2006 Future Years
o 4,800,000 0
o 0
000
o 4,800,000
Total
700,000
o
o
700,000
Prior Years
*437 Funds Budgeted ()
437 Funds Needed
437 Fund Project Contingency ( )
437 Funds Required
o
o
Prior Years
Total
4,800,000
o
o
4,800,000
# in the Budget Status section indicates money to be obtained through a general obligation bond for the overall Golf Course
Clubhouse Project
E:\AGENDA\N1120-3A.xls