AGENDA BILL APPROVAL FORM
Agenda Subject: Date:
Final Pay Estimate #2 to Emergency Contract 07-01 Februarv 20, 2007
Department: I Attachments: Final Pay Estimate #2 Budget Impact:
Public Works $0
Administrative Recommendation:
City Council approve Final Pay Estimate #2 to Emergency Contract 07-01 in the amount of $2,539.31, for
a total contract price of $9,184.40, with VLS Construction, Inc. and accept construction of Project No.
CP0722, 3rd Street NE Hydrant DamaQe.
Background Summary:
On December 30, 2006, Maintenance and Operations staff responded to an emergency call from the Fire
Department about a fire hydrant at 3rd and 'B' Streets NE as the fire hydrant had been struck by an errant
vehicle. Upon notification of the Mayor, an emergency condition was determined to exist and VLS
Construction, Inc., was called out to make repairs. The contractor was called upon to perform the work in
accordance with RCW 39.04.280(1 )(c), which allows for waiver of competitive bidding requirements in
emergency situations, and Auburn City Code 13.10.050, which authorizes the Mayor to enter into
emergency contracts. These determinations were ratified by the Auburn City Council on January 16,
2007, through Resolution No. 4137.
The scope of work included removal of the broken concrete sidewalk panels, repair of the water main,
replacement of the fire hydrant and pipe, replacement of the subgrade, backfilling, replacement of the
concrete sidewalk, and repair of the roadway and lawn. This work will be paid from the City's General
Fund and restitution from the driver will be sought.
W0305-3
04.11.1 CP0722
Reviewed by Council & Committees: Reviewed by Departments & Divisions:
o Arts Commission COUNCIL COMMITTEES: o Building o M&O
o Airport o Finance o Cemetery o Mayor
o Hearing Examiner o Municipal Servo o Finance o Parks
o Human Services o Planning & CD o Fire o Planning
o Park Board l8lPublic Works o Legal o Police
o Planning Comm. o Other I8l Public Works o Human Resources
Action:
Committee Approval: DYes ONo
Council Approval: DYes DNa Call for Public Hearing -'-'-
Referred to Until -'-1-
Tabled Until -'-'-
Councilmember: Wagner 1 Staff: Dowdv
Meeting Date: March 5, 2997 litem Number: V.C.5
AUBURN * MORE THAN YOU IMAGINED
CITY OF AUBURN
CP07~~
PAY ESTIMATE #2 & FINAL
CO. NO. 07-01
3rd Street Hydrant Damage
SCHEDULE A: Water UtIlity Repair
ITEM ESTIMATE TOTAL PERIOD UNIT UNIT COST TOTAL COST PERIOD COST PERCENT EST.
NO. ITEM DESCRIPTION QUANTITY QUANTITY QUANTITY TYPE QTY.
RemoveIReplace concrete, install Fire Hydrant
1 supplied by City 1 0.612293333 0.169287333 FA 15.000.00 $ 9,184.40 $ 2,539.31 61%
SCHEDULE TOTAL $
2,539.31
Period Dates
Begin: Jan 21, 2007
End: Jan 27, 2007
h:\proj\pe\CP0722 PE.xls
1 of 3
2/20/2007 at 10:18 AM
CO. NO. 07-01
1M OJ"' Ut}'PIK' OIMI~
SCHEDULE A: Water Utility Repair
Contract
NO TAX
Retainage (-5%)
SCHEDULE TOTAL $
TOTAL CONTRACT AMOUNT TO DATE
TOTAL PAYMENT TO CONTRACTOR
PAYMENT DUE CONTRACTOR:
h:\Pro.i\pe\CP0722 PE.x1s
CITY OF AUBURN
PROJI;CT SUMMARY
PAY ESTIMATE #2 & FINAL
Original Contract Contract Change
Amount Orders
$
15,000.00 $
$
15,000.00 $
Period Dates
Begin: Jan 21, 2007
End: Jan 27, 2007
2 of 3
Total Payment
$
9,184.40 $
$
(459.22) $
$
8,725.18 $
$
$
9,184.40
8,725.18 $
CP0722, 3rd Street Hydrant Damage
CO. NO. 07-01
This Period
Percent/Contract
2,539.31
61%
(126.97)
2,412.34
2,412.34
$
2,412.34
2120f2007 at 10:18 AM
CONTRACTOR:
VLS Construction, Inc.
PO Box 630
Ravensdale, WA 98051
Phone: 425-432-3306
CITY OF AUBURN
e~O'22
PAY ESTIMATE # 2 & FINAL
CO. NO. 07-01
The undersigned has reviewed and approved this final pay estimate. I agree that it is a true and correct statement
showing all monies due me from the City of Auburn under this contract; that I have carefully examined the final pay estimate
estimate and understand it and that I hereby release the City of Auburn from any and all claims of whatsoever
nature which I may have, arising out of this contract, which are not set forth in this estimate.
$
2,412.34
PAYMENT DUE TO CONTRACTOR =
Signatures:
Contractor
Inspector
Project Manager
City Engineer
Date
h:\proj\pe\CP0722 PE.xls
3of3
Date
Date
do- /1.--0 ) 01
~t.. zc;,o7
Date
2f16/2007 at 2:42 PM