City Council award Small Works Contract 07-11, Project CP0721, Sewer Relining, 19th Drive NE and
Riverview, to Michels Corporation on their low bid of $69,512.00 plus WA state sales tax of $6,186.57 for
a total contract price of $75,698.57.
Background Summary:
The purpose of this project is to eliminate inflow and infiltration through the pipe joints in approximately
1,500 lineal feet of sanitary sewer pipe located in 19th Street NE, Riverview Drive, and 22"d Street NE.
Recent TV inspection of this pipe system shows very heavy inflow of groundwater. Since the streets
have recently been resurfaced and the sewer pipe is in good conditions, the project intent shall be met
using trenchless techniques such as pipe relining.
Construction should start in September and should take approximately one month to complete.
The funds for this project are included in the 431 Sewer Repair & Replacement Program and a budget
contingency of $32,516 remains in that fund.
W0820-2
04.6.3 CP0721
Reviewed by Council & Committees: Reviewed by Departments & Divisions:
^ Arts Commission COUNCIL COMMITTEES: ^ Building ^ M&O
^ Airport ^ Finance ^ Cemetery ^ Mayor
^ Hearing Examiner ^ Municipal Serv. ^ Finance ^ Parks
^ Human Services ^ Planning & CD ^ Fire ^ Planning
^ Park Board ®Public Works ^ Legal ^ Police
^ Planning Comm. ^ Other ®Public Works ^ Human Resources
Action:
Committee Approval: ^Yes ^No
Council Approval: ^Yes ^No Call for Public Hearing _/_/_
Referred to Until _/_/_
Tabled Until _/_/_
Councilmember: Wa ner Staff: Dowd
Meeting Date: August 20, 2007 _ Item Number: V.C.5
~~8~~ ~ MORE THAN YOU IMAGINED
BUDGET STATUS SHEET
Project No: CP0721 Project Title: Sewer Relining, 19th Dr NE and Riverview Dr NE
Project Manager: Fritz Timm
Q Project Initiation
Initiation Date: April 23, 2007 Q Permision to Advertise Date: August 7, 2007
Advertisement Date: July 10. 2007 ~ Contract Award
Award Date: Q Change Order Approval
Q Contract Final Acceptance
The "Future Years" column indicates the projected amount to be requested in future budgets.
Funds Budgeted (Funds Available)
Funding Prior Years 2007 2008 Future Years Total
431 Fund -Sewer (Portion of Sewer
Replacement Fund) 130,000 130,000
Total 0 130,000 0 0 130,000
Estimated Cost (Funds Needed)
Activity Prior Years 2007 2008 Future Years Total
Design Engineering -City Costs 15,000 15,000
Construction Contract Bid 75,699 75,699
Authorizied Contingency (5%) 3,785 3,785
Construction Engineering -City Costs 10,000 10,000
0
Total 0 104,484 0 0 104,484
431 Sewer Bud et Status
Prior Years 2007 2008 Future Years Total
*431 Funds Budgeted () 0 (130,000) 0 0 (130,000)
431 Funds Needed 0 104,484 0 0 104,484
*431 Fund Project Contingency () 0 25,516 0 0 25,516
431 Funds Required 0 0 0 0 0
* (#) in the Budget Status Sections indicates Money the City has available.
H:\PROJ\CP0721-Sewer19thDrRvrview\Budget\CP0721 Budget Status Sheet 08-07-07.x1s 1 of 1
BID TABULATION
BID TOTALS SUMMARY
Project Name: CP0721, Sewer Relining, 19th Dr NE/Riverview Dr NE
Prepared by: City of Auburn
Bid Date: 8/7/07
ENGINEER'S ESTIMATE: $ 82,785.00
AVERAGE BASIC BID AMOUNT: $ 74,712.75
BASIC BID SPREAD AMOUNT: $ 10,401.50 Basic BID Amount Spread $ Spread
LOW BIDDER: Michels Corporation $ 69,512.00 -$13,273.00 -16.03%
Second Bidder: Insituform Technologies, Inc. $ 79,913.50 -$2,871.50 -3.47%
Basic BID (Tax not Included)
Michels Corporation $ 69,512.00
Insituform Technologies, Inc. $ 79,913.50
Total BID (Tax Included)
$ 75,698.57
$ 87,025.80
8/8/2007 (10:46 AM)
h:\proj\bidtabs\CP0721 BT.xls
SEWER RELINING, 19TH DR NE & RIVERVIEW DR NE
VICINITY MAP
Sheet 1 of 1