HomeMy WebLinkAboutITEM V-C-1CITY OF AUBURN WASHINGTON AGENDA BILL APPROVAL FORM Agenda Subject: Change Order #5 to Contract No. CP0608A Date: December 6, 2007 Department: Parks, Arts and Attachments: Change Order No. 5 Budget Impact: Recreation and Architect Letter of Ex lanation Administrative Recommendation: City Council approve Change Order No. 5 to Contract with CP0608A Earthwork - T. J. Sahli Construction for the Game Farm Park Soccer Field Renovation and accept construction of Project No. CP0608A. Background Summary: This project provided for all of the earthwork (grading, paths, etc.) preparation for the Game Farm Park Soccer Field Renovation. Construction was completed in early September and play has been vigorous since that time. The original contract amount was 435,000.00. Five change orders were attached to this contract: Change Order No. 1 (5,000.00) Change Asphalt walkways to concrete Change Order No. 2 11,920.00 Add excavating and top rock to fields Change Order No. 3 9,400.00 Additional concrete walk and bleacher pad Change Order No. 4 4,140.00 Add 5 days for getting layout info/field approval Change Order No. 5 11,200.00 Remove walkways to access irrigation lines and reduce berm areas on west side of field. Added fill materials. Additional fill materials were required to achieve sub-grade and became Change Order 5 (per attached letter from SLA Architect). The contractor imported fill materials in the areas, where designed asphalt pathways were eliminated from the project and replaced with concrete, and to bring the site up to grade. No additional time was added to this project. The cost of this Change Order No. 5 is $11,636.80 with tax less retainage. With the acceptance of this change order, the contractor has fulfilled his responsibilities for this project and we request acceptance of the project. R1217-1 05.2 CP0608A Reviewed by Council & Committees: Reviewed by Departments & Divisions: ^ Arts Commission COUNCIL COMMITTEES: ^ Building ^ M&O ^ Airport ®Finance ^ Cemetery ^ Mayor ^ Hearing Examiner ®Municipal Serv. ^Finance ^ Parks ^ Human Services ^ Planning & CD ^ Fire ^ Planning ® Park Board ^Public Works ^ Legal ^ Police ^ Planning Comm. ^ Other Museum Board ^Public Works ^ Human Resources ^ Information Services Action: Committee Approval: ^Yes ^No Council Approval: ^Yes ^No Call for Public Hearing _/_/_ Referred to Until _/_/_ Tabled Until _/_/_ Councilmember: Backus Staff: Faber Meetin Date: December 17, 2007 Item Number: V.C.1 AU$U~~N ~ MORE THAN YOU IMAGjNED CITY OF AUBURN CONTRACT CHANGE ORDER AGREEMENT NO. _5_ Contract No., Project No. and Project Title: 0704,CP0-608A GAME FARM PARK SOCCER FIELD RENOVATION Contractor Name and Address: T. J. SAHLI CONSTRUCTION PO BOX 332 S EAH U RST, WA 98062 The Contractor is hereby directed to make the changes to the Contract as described herein. This document and all attachments are a supplement to the contract. All work, materials and measurements for the type of construction involved shall be in accordance with the contract documents of the above named project unless stated otherwise in this change order. Summary of Proposed Changes: 1. Remove walkways to allow access to irrigation mainlines and reduce cut of berm areas. 2. Fill material to make this change 3. The Contract time is extended by days. Item Sch. Sec. No. Item. Description Quantity Units Unit Price Total Price Sales Tax Remove Walkways N Add Fill Material $11,200 y N N N N Subtotal $ 11,200.00 Washington State Sales Tax (8.9%) on applicable items $ 996.80 TOTAL $ 12,196.80 Less Retainage $560.00 Total Due $ 11,636.80 Base Amount Total incl. Tax 1. Total Cost this C/O minus retaina e $ 11,200.00 $ 11,636.80 2. Total Cost Previous C/O $ 20,460.00 $ 21,508.94 3. Ori final Contract Amount $ 435,000.00 $ 473,715.00 4. Revised Contract Amount incl tax & retainage $ 506,885.94 This change order constitutes full and complete compensation for all labor, equipment, materials, overhead, profit, any and all indirect costs, and time adjustment to perform the above described changes. All other costs are non-compensible. CITY OF AUBURN CONTRACT CHANGE ORDER AGREEMENT NO. _5_ Contract No., Project No. and Project Title: 0704,CP0-608A GAME FARM PARK SOCCER FIELD RENOVATION Contractor: Inspector: Project Manager: City Engineer: Approved by: Date Date Date Date Mayor, City ofAuburn Date i- ~ .K November ?cl, ?0{} Uarvl !~'aUCr nir~ctctr f arks and T~ecreation ?5 11'est I~'lan St Aubt.rrn. ~~•' fl)/: Additional Fillmatcrals f`or'outsidc of'fietd areas, UCGlr; ~1r. Fahcr, As per ycx~r reyucst, I have revic~tird the proposal front TF Sahli, !'ot• the cbant~e for additional tilt import materials aClllerL~~ 5llb`~l'adrr alter elimination nt~asphalt walkrva~'s :areas ~~n the (eamc: Farm Park Soccer t~ictd Renovation. rafter adelitictnal rc:~•iew of the proposal, verilicatictn c~1' impart materai<tls. T rewmmcnd the aceeptancre cif TF Sah}i's proposal tier tht; adclitionll'i~>pirn materials to achieve subgrade elevations cyusicje of tlcld areas ~':he~~c aspht~lt path~~•ays were eliminated. TF Sahfi imported tiff materials in the areas where designed asphalt }artih~~'~l~'s ~iei-c eliminated from the prajert to hrin`, th~tsc areas tcf proper suh`~radc, and finish ~r~tdcs. 1. It~rnb~~al of'~~~alk~'`ay5 ryas. done to allt~w ttic~ s to irri~~atinn m~rinlincw, a'Iad reduce cut c~#`berm areas tm the west side of'the fields.. 2. Vo udditc~nal .time extension can the pc•ojoct. ! ;cec:rrrz;;.nd the ttt.eeptancc o1'the modific~ttctn prupi~sal h.' TF Sahli, till n;ater•ials within the scope of'~~•ork iUr Cart~c Farrn !'ark `Soccer H•ield Henuv~ttion. Sinccrcl~;; 51;~ 1,:,.a~nds~c~rpi; Architecture ~, ~~ . .~ f:rik J. Sncct, ASL~1, EtL..A (h'<itct i ill \lxrrai:., 1."t ~r~ ~a • J.a I'.u•r I ti' .\ 1 .u,1h~.;~,r lirhiien:u-r