AGENDA BILL APPROVAL FORM
Agenda Subject: Date:
Permission to Advertise CP0759 Aril 28, 2008
Department: Attachments: Budget Status Sheet, Budget Impact:
Public Works Vicinity Ma and Overview Ma $ 0
Administrative Recommendation:
City Council grant permission to advertise for bids for Project No. CP0759, Olympic Middle School
Pedestrian Improvements.
Background Summary:
This project will construct crosswalks, flashing beacon signs and a 1,265 lineal foot asphalt path along the
east side of H Street SE near Olympic Middle School. All work is to be within existing right-of-way or on
school district property.
Advertisement for bids is scheduled to occur in May 2008, with construction anticipated to occur in July
and August of 2008.
The total project cost is estimated to be $221,200. A project increase of $36,200 from the 102 Arterial
Street fund may be necessary; however, it will not require a budget adjustment since it is anticipated that
the budgeted expenditures in the 102 fund will not be exceeded this year.
W0505-3
04.12.1 CP0759
Reviewed by Council & Committees: Reviewed by Departments & Divisions:
? Arts Commission COUNCIL COMMITTEES: ? Building ? M&O
? Airport ? Finance ? Cemetery ? Mayor
? Hearing Examiner ? Municipal Serv. ? Finance ? Parks
? Human Services ? Planning & CD ? Fire ? Planning
? Park Board EPublic Works ? Legal ? Police
? Planning Comm. ? Other E Public Works ? Human Resources
Action:
Committee Approval: ?Yes ?No
Council Approval: ?Yes ?No Call for Public Hearing
Referred to Until
Tabled Until
Councilmember: Wagner Staff: Dowd
Meeting Date: May 5, 2008 Item Number: V.C.2
AUBU N *MORE THAN YOU IMAGINED
BUDGET STATUS SHEET
Project No: CP0759 Project Title: Olympic Middle School Pedestrian Improvements
Project Manager: Leah Dunsdon
O Project Initiation
Initiation Date: September 4, 2007 Qi Permision to Advertise Date: April 28, 2008
Advertisement Date: O Contract Award
Award Date: O Change Order Approval
O Contract Final Acceptance
The "Future Years" column indicates the projected amount to be requested in future budgets.
Funds Budgeted (Funds Available)
Funding Prior Years 2008 2009 Future Years Total
102 Fund - Federal Grant 3,100 181,900 185,000
Total 3,100 181,900 0 0 185,000
Estimated Cost (Funds Needed)
Activity Prior Years 2008 2009 Future Years Total
Design Engineering - City Costs 1,720 14,680 16,400
Design Engineering - Consultant Costs 1,380 3,220 4,600
Construction Estimate 162,000 162,000
Project Contingency (10%) 16,200 16,200
Construction Engineering - City Costs 15,000 15,000
Other - (School District)** 7,000 7,000
Total 3,100 218,100 0 0 221,200
1 n? A rfa,ri2l Rfroa,t Ri irlnat State rs
Prior Years 2008 2009 Future Years Total
*102 Funds Budgeted (} (3,100) (181,900) 0 0 (185,000)
102 Funds Needed 3,100 218,100 0 0 221,200
*102 Fund Project Contingency () 0 0 0 0 0
102 Funds Required 0 36,200 0 0 36,200
* (# ) in the Budget Status Sections indicates money the City has available.
** Auburn School District: $6,000 for education and $1,000 for enforcement.
4/28/2008 9:50 AM
H:\PROJ\CP0759-OlympicMiddleSchoolPedlmp\Budget\CP0759-BudgetStatusSheet.xls
I--
ff-To
I I
I I
21ST ST SE
W
N
H
Y
LIL
19TH ST SE
I
I
20TH ST SE
I,
I
LEGEND
I I li t? F,?
CITY OF AUBURN
CTTY OF
jkt ?17 P,N CP0759, OLYMPIC MIDDLE SCHOOL
WASHINGTON PEDESTRIAN IMPROVEMENTS
SCALE: I" = 200'
_ NEW CENENT CONCRETE
F--j NEW ASPHALT PATH
III II OR = CROSSWALK
NEW HYDROSEEDING
EXISTING BIALDING
SCHOOL ZONE FLASHING SEACCN
Figure 2
Overview Map
w
A
12-
h
U? w
U a
a
4 ly 1 L
PL
J
3E 8?
A
LEGEND
PROPOSED PATH
PROPOSED CROSSWALK
Project
70Y, A Qm ov
CIC1L rim nrn
E
U
C= OF CITY OF AUBURN Figure 1
CP0759, OLYMPIC MIDDLE SCHOOL
WASHINGTON PEDESTRIAN IMPROVEMENTS Vicinity Map
SCALE: I" = 1/8 MILE