AGENDA BILL APPROVAL FORM
Agenda Subject: Date:
Final Acceptance for Contract 06-21 - Golf Course Clubhouse May 16, 2008
Department: Attachments: Budget Impact:
Finance Budget Status Sheet
Administrative Recommendation:
City Council accept construction of Project C327A0.
Background Summary:
This project provided the design and construction of a new clubhouse building at the City's Auburn Golf
Course. Design was completed in mid-2006, with construction start in October of 2006. Construction
was substantially complete of the Pro Shop and public spaces, providing City occupancy in early August
2007. The restaurant areas were completed and opened in December of 2007. All responsibilities of the
contract were fulfilled by May 16, 2007.
Reviewed by Council & Committees: Reviewed by Departments & Divisions:
? Arts Commission COUNCIL COMMITTEES: ? Building ? M&O
? Airport E Finance ? Cemetery ? Mayor
? Hearing Examiner E Municipal Serv. E Finance E Parks
? Human Services ? Planning & CD ? Fire ? Planning
? Park Board ?Public Works ? Legal ? Police
? Planning Comm. ? Other ? Public Works ? Human Resources
? Information Services
Action:
Committee Approval: ?Yes ?No
Council Approval: ?Yes ?No Call for Public Hearing
Referred to Until
Tabled Until
Councilmember: Cerino Staff: Coleman
Meeting Date: June 2, 2008 Item Number: V.C.1
AUBURN * MORE THAN YOU IMAGINED
May 20, 2008
Ms. Shelley Coleman,
City of Auburn
25 West Main Street
Auburn, WA 98001
Finance Director
RE: Auburn Golf Course Clubhouse Project
Briere & Associates Construction Contract
Harris & Associates
Program Managers
Construction Managers
Civil Engineers
Project #: c327a0
Contract #: 06-21
All required work has been completed by Briere & Associates per the terms of the referenced
construction contract for the Auburn Golf Course Clubhouse Project, with the exception of
certain specified activities to be completed as warranty items and performed as weather
allows. All project documentation and materials have been conveyed, and the responsibilities
of the Contractor completed.
I therefore recommend acceptance of this project as complete by the City. Enclosed is a draft
Agenda Bill, with accompanying Budget Status Sheet. Both are also available electronically,
and I will convey them in that form to your administrative staff.
I have also conveyed the Contractor's final application for payment to the accounting staff.
Upon acceptance of the contract as complete by the City Council, I will prepare and convey to
the appropriate State agencies the completion notices that will activate resulting approvals
from them; allowing final release of retainage approximately 60 days later.
Operations and Maintenance Manuals have already been conveyed to City Facilities and Golf
Course operations staffs. Final as-built plans will be conveyed upon their receipt from the
Architect. Upon release of retainage, I will convey all project files to the Facilities staff,
completing Harris & Associates efforts for this project.
Please feel free to contact me at (206) 571-3568 if you have any questions or want to discuss.
ordially,
Paul Berry
Project Manager
201 S. Division St., Auburn, Washington 98001 (253)333-2426 FAX (253) 333-2449
May 20, 2008
Paul Berry
Project Manager
Harris & Associates, Inc.
C/0 City of Auburn
25 West Main
Auburn, WA 98002
0
Re: Aubum Golf Course Clubhouse
Project completion
Dear Paul: U
I am recommending that the Auburn Golf Course Clubhouse project be
accepted as physically complete. There are a few items on the punch list that cannot
be competed due to weather concerns. As such, I recommend those items be moved to
the warranty portion of the project. E
Those items include, but are not limited to all exterior painting repair, sidewalk
repair, exterior caulking and interior kitchen floor repair. I have received a letter from Oq
Brier and Associates agreeing that they will complete those items as soon as the
weather permits.
In summary, I recommend that the project be closed out and accepted by the
City. M
Sincerely, w
F
David A. Clark
Architect of Record
A Washington Professional Limited Liability Company
Licensed Architects in Arizona, California, Colorado, Hawaii, Texas and Washington
BUDGET STATUS SHEET
Project No: c327a0, c327b0, c327c0 Project Title: Auburn Golf Course Clubhouse
Project Manager: Paul Berry
O Project Initiation
Initiation Date: O Permislon to Advertise Date: May 20, 2008
Advertisement Date: O Contract Award
Award Date: O Change Order Approval
• Contract Final Acceptance
Funds Budgeted (Funds Available
Funding Prior Years 2006 2007 • 2008 Total
437 Fund - from REET monies 285,519 236,072 521,591
Taxable Bonds 0 1,929,073 22,600 1,951,673
Non-Taxable Bonds 581,784 2,236,759 169,500 2,988,043
Total 0 867,303 4,401,9041 _ 192,100 5,461,307
Estimated Cost (Funds Needed)
Activity Prior Years 2006 2007 2008 Total
Utility Installations - Engineering (C327B) 265,100 265,100
Design - Consultant Costs 261,900 115,100 377,000
Project Management - Consultant Costs 62,900 212,600 17,000 292,500
Specialty Equipment 112,000 112,000
Construction by Contractors 209,703 3,572,604 123,900 3,906,207
Project Contingency 51,200 51,200
Admin, Permits, etc. 61,900 103,100 165,000
Construction - City Costs 5,800 5,800
Restaurant Concessionaire Costs 286,500 286,500
0
Total 0 867,303 4,401,904 192,100 5,461,307
437 Fund Budget Status
Prior Years 2006 2007 2008 Total
'437 Funds Budgeted 285,519 236,072 0 521,591
437 Funds Needed 285,519 236,072 0 521,591
437 Fund Project Contingency () 0 0 0 0 0
437 Funds Required 0 0 0 0 0
Taxable Bond Funds Budget Status
Prior Years 2006 2007 2008 Total
Taxable Bond Funds Budgeted 0 0 1,929,073 22,600 1,951,673
Funds Needed 0 0 1,929,073 22,600 1,951,673
` Fund Project Contingency () 0 0 0 0 0
Funds Required 0 0 0 0 0
Non-Taxable Bond Funds B udget Status
Prior Years 2006 2007 2008 Total
Non-Taxable Bond Funds Budgeted 0 581,784 2,236,759 169,500' 2,988,043
Funds Needed 0 581,784 2,236,759 169,500 2,988,043
Fund Project Contingency () 0 0 0 0
Funds Required 0 0 0 0 0