HomeMy WebLinkAboutITEM V-C-2
CITY OF
AUBURN
WASHINGTON
AGENDA BILL APPROVAL FORM
Agenda Subject: Date:
Permission to Advertise Project No. CP0760 Jul 24, 2008
Department: Attachments: Budget Impact:
Public Works Budget Status Sheet, Ma $ 0
Administrative Recommendation:
City Council grant permission to advertise for bids for Project No. CP0760 Auburn Way North Pedestrian
Crossing
Background Summary:
This project will construct a new pedestrian crossing on Auburn Way North near 42nd Street NE with the
following:
1. A pedestrian activated signal to stop traffic;
2. A median island refuge;
3. Crosswalk striping and truncated dome warning strips;
4. Advance warning signage;
5. Lighting; and
6. ITS Camera, fiber cables and vaults, and video detection cameras.
Currently, the total estimated project cost is $336,000, of which $325,000 is from state grant funds. A
project increase of $11,000 may be necessary, but will not require a budget adjustment since budgeted
expenditures in the 102 Fund will not be exceeded this year. The total project cost will be re-evaluated
prior to awarding the project and the final required project budget increase within the 102 Fund will be
determined.
W0804-2
04.9.1 CP0760
viewed by ounce Committees: Reviewed-by Departmen ts Divisions:
M&O
Arts Commission COUNCIL COMMITTE S: Building
Airport Finance Cemetery Mayor
Hearing Examiner Municipal Serv. Finance Parks
Human Services Planning & CD Fire
l
L Planning
Police
Park Board Public Works ega
Planning Comm. Other Public Works Human Resources
Action:
Committee Approval: Yes No
r Public Hearin
ll f
C
pN
B
g
a
o
o
Yes
Council Approval:
Referred to Until I I
Tabled Until _T 7-
Councilmember: Wagner Staff: Dowd
Meeting Date: August 4, 2008 Item Number: V.C.2
AUBURN* MORE THAN YOU IMAGINED
BUDGET STATUS SHEET
Project No: CP0760 Project Title: Auburn Way N Pedestrian Crossing at 42nd St. SE
Project Manager: Jacob Sweeting
Initiation Date: September 17, 2007
0 Initiation/Consultant Agreement
0 Permision to Advertise
0 Contract Award
0 Change Order Approval
0 Contract Final Acceptance
Date: July 28, 2008
Advertisement Date:
Award Date:
The "Future Years" column indicates the projected amount to be requested in future budgets.
Funds Budgeted (Funds Available)
Funding Prior Years 2007 2008 Future Years Total
102 Fund - State Grant 325,000 325,000
Total 0 0 325,000 0 325,000
Estimated Cost (Funds Needed)
Activity Prior Years 2007 2008 Future Years Total
Design Engineering - City Costs 25,000 25,000
Design Engineering - Consultant Costs 35,000 35,000
Design Engineering - WSDOT Costs 1,000 1,000
Construction Estimate 238,000 238,000
Project Contingency (10%) 24,000 24,000
Construction Engineering - City Costs 10,000 10,000
Other - (Education & Enforcement) 3,000 3,000
Total 0 0 336,000 0 336,000
102 Arterial Street Budqet Status
Prior Years 2007 2008 Future Years Total
'102 Funds Budgeted () 0 0 (325,000) 0 (325,000)
102 Funds Needed 0 0 336,000 0 336,000
'102 Fund Project Contingency () 0 0 0 0 0
102 Funds Required 0 0 11,000 0 11,000
" ( # ) in the Budget Status Sections indicates Money the City has available.