Agenda Subject: Consultant Agreement No. AG-C-348 Date: December 9, 2008
Department: Attachments: Budget Impact:
Public Works Budget Status Sheet, Ma $ 0
Administrative Recommendation:
City Council grant permission to enter into Consultant Agreement No. AG-C-348 with Anchor
Environmental LLC for Engineering Services for Project No. CP0819, Mill Creek Culvert Replacement at
Peasley Canyon Road.
Background Summary:
Staff has determined that the Peasely Canyon culvert is failing. Some of the pipe joints are separated
and water appears to be flowing through the road bed. Staff considers this situation a major risk to road
stability. This project will replace the existing failing culverts with a new culvert structure capable of
passing the existing sediment bed load while meeting fish passage requirements. The scope of work
provides for an alternatives analysis to select the most cost effective and constructible replacement.
Under this agreement, Anchor Environmental LLC will prepare the plans and specifications for the bidding
of Project No. CP-0819, Mill Creek Culvert Replacement at Peasely Canyon Road. The not-to-exceed
amount for this agreement is $220,000.
W1215-8
A3.16.9, 04.8.1 CP0819
Reviewed by Council & Committees: Reviewed by Departments & Divisions:
❑ Arts Commission COUNCIL COMMITTEES: ❑ Building ❑ M&O
❑ Airport ❑ Finance ❑ Cemetery ❑ Mayor
❑ Hearing Examiner ❑ Municipal Serv. ❑ Finance ❑ Parks
❑ Human Services ❑ Planning & CD ❑ Fire ❑ Planning
❑ Park Board ®Public Works ❑ Legal ❑ Police
❑ Planning Comm. ❑ Other ® Public Works ❑ Human Resources
Action:
Committee Approval: ❑Yes ❑No
Council Approval: ❑Yes ❑No Call for Public Hearing
Referred to Until
Tabled Unt_il
Councilmember: Wagner Staff: Dowd
Meeting Date: December 15, 2008 Item Number: V.C.5
AUBURN* MORE THAN YOU IMAGINED
BUDGET STATUS SHEET
Project No: CP0819 Project Title: Mill Creek Culvert Replacement at Peasely Canyon Road
Project Manager: Tim Carlaw
Initiation/Consultant Agreement
Initiation Date: O Permision to Advertise Date: December 9, 2008
Advertisement Date: O Contract Award
Award Date: O Change Order Approval
O Contract Final Acceptance
The "Future Years" column indicates the projected amount to be requested in future budgets.
Funds Bud eted Funds Available
Funding Prior Years 2008 2009 Future Years Total
432 Fund - Storm Capital Outlay 100,000 1,000,000 0 1,100,000
Total 0 100,000 1,000,000 0 1,100,000
Estimated Cost Funds Needed
Activity Prior Years 2008 2009 Future Years Total
Design Engineering - City Costs 3,000 12,000 15,000
Design Engineering - Consultant Costs 0 220,000 220,000
Construction Estimate 725,000 725,000
Project Contingency (15%) 108,750 108,750
Construction Engineering - City Costs 20,000 20,000
Construction Engineering - Consultant Costs 10,000 10,000
Total 0 3,000 1,095,750 0 1,098,750
432 Storm Budget Status
Prior Years 2008 2009 Future Years Total
*432 Funds Budgeted 0 (100,000) (1,000,000) 0 (1,100,000)
432 Funds Needed 0 3,000 1,095,750 0 1,098,750
*432 Fund Project Contingency 0 97,000 0 0 1,250
432 Funds Required 0 0 95,750 0 0
* ) in the Budget Status Sections indicates Money the City has available.
EAAGENDA\W1215-8A.x1s 1 of 1
S 318th ST
W PL ►nw a `k
ao aye ~ rzj
S 32 th ST W
n
324TH ST s.
W
S 324TH PL w '4`r
S 32M ST
x
L 2nd
rn
MT. VIE W S 328th ST CEMETERY MAIN U
S
CULVERT a ~ 1st
REPLACEMENT 44
C', rn
S 331
,a 3rd S
`S 4th St SW
pEASLEY C41,,Q STATE HYy 8
~d
S 336th ST
w
a SUPERMALL
co
S 34 th ST
suPatsti►tI, w r sir
th v ST
W o
r BOUNDARY BLVD 4~ cs
ow3
Al
11th AVE N
34 th
10th AVE N 10th AVE N
S 34 th 9th z AVE a N
~ U
AUBURN STORM DRAINAGE U LrrY MAINTENANCE
°F PEASLEY CANYON CULVERT REPLACEMENT
WASHINGTON VICINITY MAP N
AWist 2008
W1215-8B HWTOSCAI