AGENDA BILL APPROVAL FORM
Agenda Subject:
Date: April 28, 2009
Permission to Advertise CP0901
Department:
Attachments:
Budget Impact:
Public Works
Bud et Status Sheet and Ma
$ 0
Administrative Recommendation:
City Council grant permission to advertise for bids for Project No. CP0901, 2009 Local Street Pavement
Preservation.
Background Summary:
The 2009 Local Street Pavement Preservation project will rehabilitate deficient pavement on 0.6 miles
local streets in and around the City's downtown area. This project is funded by the 103 (Local Street)
Fund. The attached map shows which streets will be rehabilitated as part of this project. Staff anticipates
adding additional streets to the project as the budget allows.
Advertising for bids is anticipated to begin in May 2009. Construction of this project is anticipated to
begin in June 2009 and be complete by September 2009.
W0504-7
04.9.1 CP0901
Reviewed by Council & Committees:
Reviewed by Departments & Divisions:
❑ Arts Commission COUNCIL COMMITTEES:
❑ Building ❑ M&O
❑ Airport ❑ Finance
❑ Cemetery ❑ Mayor
❑ Hearing Examiner ❑ Municipal Serv.
❑ Finance ❑ Parks
❑ Human Services ❑ Planning & CD
❑ Fire ❑ Planning
❑ Park Board SPublic Works
❑ Legal ❑ Police
❑ Planning Comm. ❑ Other
~ Public Works ❑ Human Resources
Action:
Committee Approval: ❑Yes ❑No
Council Approval: ❑Yes ❑No Call for Public Hearing
Referred to Until
Tabled
Councilmember: Wa ner
Staff: Dowd
Meetina Date: May 4, 2009
Item Number: V.C.4
AUBURN* MORE THAN YOU 1MAGINED
BUDGET STATUS SHEET
Project No: CP0901 Project Title: 2009 Local Street Pavement Preservation
Project Manager: Seth Wickstrom 0 Initiation/Consultant Agreement
Initiation Date: June 16. 2008 Q Permission to Advertise Date: April 28, 2009
Advertisement Date: 0 Contract Award
Award Date: 0 Change Order Approval
Q Contract Final Acceptance
The "Future Years" column indicates the projected amount to be requested in future budgets.
Funds Budaeted (Funds Available)
Funding
Prior Years
2008
2009
2010
Total
103 Fund - Local Street
2,200,000
2,200,000
103 Fund - Local Street (Carry-Forward from 2008)
221,200
430 Fund - Water'
500,000
500,000
431 Fund - Sewer*
500,000
500,000
432 Fund - Storm"
500,000
500,000
Total
0
0
3,921,200
0
3,700,000
'Utility funds are currently budgeted for Project CP0901, however no utility work is planned for this project.
Estimated Cost (Funds Needed)
Activity
Prior Years
2008
2009
2010
Total
Administration Costs
111,900
111,900
CP0762 - Les Grove Neighborhood Improvements (103 Funding Only)
1,200,000
1,200,000
CP0731 - 2007 Sewer Repair and Replacement Project (103 Funding Only)
250,000
250,000
CP0901 - 2009 Local Street Pavement Preservation
Design Engineering - City Costs««
3,000
3,000
Design Engineering - Consultant Costs
87,483
$7'483
Construction Estimate
557,107
657,107
Project Contingency (10°/a)
55,771
65,711
Construction Engineering - City Costs'"
1,000
1,000
Construction Engineering - Consultant Costs
5,000
5,000
2009 Design Costs for 2010 SOS Program
150,000
150,000
Total
0
0
2,421,200
0
2,421,200
*'City staff costs are charged against the Engineering Budget and not the ProJect E3udget, ana are no[ snown nere.
103 Local Street Budqet Status
Prior Years
2008
2009
2010
Total
""103 Funds Budgeted
0
0
(2,421,200)
0
(2,421,200)
103 Funds Needed
0
0
2,421,200
0
2,421,200
"'103 Fund Project Contingency O
0
0
0
0
0
103 Funds Required
0
0
0
0
0
430 Water Bud et Status
Prior Years
2008
2009
2010
Total
"'430 Funds Budgeted
0
0
(500,000)
0
(500,000)
430 Funds Needed
0
0
0
~
""*430 Fund Project Contingency
0
0
500,000
0
500,000
430 Funds Required
0
0
0
0
0
431 Sewer Bud et Status
Prior Years
2008
2009
2010
Total
•"431 Funds Budgeted
0
0
(500,000)
0
(500,000)
431 Funds Needed
0
0
0
0
0
"'431 Fund ProJect Contingency
431 Funds Required
0
0
0
0
500,000
0
0
0
500,000
0
432 S
torm Bud et s
tatus
Prior Years
2008
2009
2010
Total
`**432 Funds Budgeted
0
0
(500,000)
0
(500,000)
432 Funds Needed
0
0
0
0
0
**•432 Fund Project Contingency
432 Funds Requlred
0
0
0
0
500,000
0
0
0
500,000
0
•)7V6~5NY!"udget Status Sections indicates money the City has available. Page 1 of 1
j~ 30th ST NW ~ 30t
I f
OPTIONAL STREET
PROJECT NC3. CP0731 - 2007 Sewer
Repair and Replacement Project
Description of Work: Pavemenk
rehabilitation and overlay as part of project.
NE fSM ~ srn
eva P~ 5~ a
E" BRANNAN PA K 4r
W PARK r $ s o sr ~~s a~ pf rsr p~ .
m
z z
aR~ w
x
~T a se ai
H aL tv
tn sr Ne r ~S PROJECT (VO. CP0731 - 2007
k SVANSo
z P"R" Sewer Repair and Replacernent
F
Project
W 21at NE Description af Work: Pavement
F ~acn'ST NE T"E rehabilitation and overlay as part of sE 3
_ 19ch DR project.
1___ ~ W th ST NE 17th pr NE or,
~
„ 16th 9T NE 18th
15th sE T W
v w
14th ST NE z ~ M 19a
t
OPTIONAL STREETS ~ ~ z
w [y SM Sf ~ 1!M K SE
9? ~ z er RR ~
PROJECT NO. CP0901- 2009
~ W~r SE ' 31E
~~eM R V)
W E E C y~ w ~ o' w
Local Street Pavement 12th E., T E ` ~ •
11 C .pO NE „
~ 5T NE ~ 0
Preservation w ' T,
Description of Work: Pavement NE0. PROJECT NO. CP0901- 2009
rehabilitation and overlay. s azotn
BPAROWN RK Local Street Pavement g
6th ~ x z P P N~s - s L pL ~K lsM ^ n
eth Preservation 532 ~ aFUL LDR Description of Work: Pavement d
5t 5 1 NE PARK AVE PARK ath z g rehabilitation and overlay. tRLM
4th ST NE F E' Q"
¢ m z URN ra :W
z 3r
~ z ~ isr rr e^ c~
F ~ z nd x x F C
F
3 ~ z ~ Q a SCH L-, tat o p- R PL ~y U PL ~ u~,„, :
MA[ a ~
S 1 t N ~'y EAS MAIN
S W~ W~
3 w
~ Ist ST 5W X E- m ~ rWii N ~ zoa sr eE' m m
~ m m m rA oe~ 0 2nd E' 9 F, c ~ r~a in
~ o w w ST SE a r~n E.•
3rd SW U
} ¢ CR0SS` 4th w ST C ST SE .
9
Ul 0 6" '
A ~
BUX OT(1N
t/g
ISTATE HWY B4~p&URL tlTON
6t. Bl 6NT 'Wp
th xo xo
BCh A"
F
~ t
ain ST ~ "n E h
pRQJECT NO. CP0762 - Les Gove
sw a~ ~ ST Ee LES
aen m covE Neighborhood Improvernent
3 N ~
~
ic,c I otn ST praject phase 1
! SSCFI SE Q G] G oL a
Description of Work: Overlay and
Z` n -21 E re bui l d p a v e m e n t a s p a r t o f p r o j e c t. ExIc
~ C.S ~ DR
13TH 5E
F.r s. Sw PAR tatn sE ~ a 14TH
Se
g~ 15th E i o °1 F ~2 w 15th ST s~ f
02' ` l6th SE IBth ST ~Q
17th ST SE $K~AY
gE 1'7 SE
~Q~ C PL c v~ 18th S ly w 1`~~~'g~ ~ 18th 9T 19th
N ti V~ 19th S ~ SE E
20th ST
N ~
MDCKLESHOOT o a' ~
y e~.~~U tF'i~ E vFi zam G ~ SpU o o ~ w te ~ ST aE
I 21st ° TN o°n W Z sx~ucerxesrr
~ CASlNO 3 Znd ~r~
cen.~a ox se 22nd ST SE o vi PARK
22nd F~~ x OE/l~C 23rd ST 9E 3rd 8 E
23~ ~ wan ,q, m
cE'A 24th T 24th ST 5E o
1C" 5E 25th 5T SE 25th 9T 9E eeu sr se a'
Q, k
PROJECT NO. CP0901 ~
LEGEND
~ PROJECT NO. CP0901 PROJECT STREET
~ OTHER 2009 SOS STREET 0 1,000ft 2,0 OOft
W0504-7B SCALE: 1 inch = 2,000 feet