AGENDA BILL APPROVAL FORM
Agenda Subject:Date:
Award Contract 09-06 June 19, 2009
Department:Attachments:Budget Impact:
Budget Status Sheet,
Public WorksMap$ 0
Administrative Recommendation:
Public Works Committee approve award of Contract 09-06, Project Number CP0611, M St NE/Harvey Rd
th
Street Improvements, to the lowest responsible bidder.
and 8
Background Summary:
The purpose of the project is to reconstruct M Street NE from 4th Street NE to 8th Street NE, remedying
the existing poor pavement condition with new pavement that will meet current and projected traffic
needs, and widening the roadway to allow four lanes of traffic. Approximately 1500 feet of aged 10” sewer
line and 35 water meters and service lines will be replaced in M Street NE. The project will also modify
the intersection of M Street NE/Harvey Road and 8th Street NE to increase intersection capacity and
improve the level-of-service. This will be achieved by adding a third eastbound (through/right) lane to 8th
Street NE, prior to the intersection.
th
The bid opening was held on June 30, 2009, which did not allow enough time for staff to compile the bid
tabulation prior to the Public Works Committee and City Council packet development; a revised Agenda
Bill specifying the contractor and contract amount will be distributed at the Public Works Committee and
th
City Council meetings on July 6.
Currently, the total estimated project cost is $2,400,000 of which $1,800,000 is from a Public Works Trust
Fund Loan, $417,000 is from City utility funds, and the remaining funds are budgeted from the 102
Arterial Street Fund. A project contingency remains as follows: $66,850 in the 102 Fund and $2,000 in the
431 Sewer Fund. Updated information regarding budget status will be presented with the revised Agenda
Bill.
W0706-6
Reviewed by Council & Committees:Reviewed by Departments & Divisions:
Arts Commission COUNCIL COMMITTEES: Building M&O
Airport Finance Cemetery Mayor
Hearing Examiner Municipal Serv. Finance Parks
Human Services Planning & CD Fire Planning
Park Board Public Works LegalPolice
Planning Comm. OtherPublic Works Human Resources
Action:
Committee Approval: Yes No
Council Approval: Yes NoCall for Public Hearing___/___/____
Referred to _________________________________ Until ____/___/____
Tabled ______________________________________ Until___/___/____
Councilmember:Staff:
Wagner Dowdy
Meeting Date:
Item Number:
: July 6, 2009
BUDGET STATUS SHEET
Project No: CP0611Project Title: 8th St NE and Harvey Rd/M St NE Improvements
.
Year End
Permision to Advertise
Initiation Date:11/2/2007Date: June 19, 2009
Contract Award
Advertisement Date: 6/15/2009
Change Order Approval
Award Date: ___________
Contract Final Acceptance
The "Future Years" column indicates the projected amount to be requested in future budgets.
Funds Budgeted (Funds Available)
Prior Years20082009Future YearsTotal
Funding
102 Fund - Impact Fees
15,50021,750201,000238,250
102 Fund - Public Works Trust Fund Loan80,0001,720,0001,800,000
431 Fund - Portion of Sewer R+R Prgm6,400200,000206,400
432 Fund - Storm150,000150,000
430 Fund - Portion of Water R+R Prgm67,00067,000
Total15,500108,1502,338,00002,461,650
Estimated Cost (Funds Needed)
Prior Years 2008
(Actual)(Actual)2009Future Years
ActivityTotal
Design Engineering - City Costs15,50029,80015,00060,300
Design Engineering - Consultant Costs76,950173,050250,000
Construction Estimate1,750,0001,750,000
Project Contingency (5%)87,50087,500
ROW Acquisition1,400198,600200,000
Construction Engineering - City Costs35,00035,000
Construction Engineering - Consultant Costs10,00010,000
Total15,500108,1502,269,15002,392,800
W0706-6A1 of 2
BUDGET STATUS SHEET
Project No: CP0611Project Title: 8th St NE and Harvey Rd/M St NE Improvements
.
102 Arterial Street Budget Status
2008
Prior Years(Actual)Future Years
2009Total
Funds Budgeted(15,500)(101,750)(1,921,000)0(2,038,250)
Funds Needed15,500101,7501,854,15001,971,400
00(66,850)0(66,850)
Project Contingency
00000
Funds Required
431 Sewer Budget Status
2008
Prior Years(Actual)Future Years
2009Total
Funds Budgeted0(6,400)(200,000)0(206,400)
Funds Needed6,400198,000204,400
00(2,000)0(2,000)
Project Contingency
00000
Funds Required
432 Storm Budget Status
2008
Prior Years(Actual)Future Years
2009Total
Funds Budgeted00(150,000)0(150,000)
Funds Needed150,000150,000
00000
Project Contingency
00000
Funds Required
430 Water Budget Status
2008
Prior Years(Actual)Future Years
2009Total
Funds Budgeted00(67,000)0(67,000)
Funds Needed67,00067,000
00000
Project Contingency
00000
Funds Required
* ( # ) in the Budget Status Sections indicates Money the City has available.
W0706-6A2 of 2