HomeMy WebLinkAbout11-04-1996 Special Council Mtg CITY OF AUBURN
AUBURN CITY COUNCIL SPECIAL MEETING
NOVEMBER 4, 1996 STUDY SESSION
MINUTES
The study session convened at 5:00 PM. Those in attendance included Mayor Charles A. Booth,
and Councilmembers Fred Poe, Rich Wagner, Jeanne Barber, Stacey Brothers, Sue Singer, and
Gene Cerino. Councilmember Trish Borden arrived at 5:15 PM. Staff in attendance included Fire
Chief Bob Johnson, Utilities Engineer Dwight Holobaugh, City Engineer Dennis Dowdy, Public
Works Director Frank Currie, Acting Parks & Recreation Director Dick Deal, and City Clerk Robin
Wohlhueter.
I. Introduction
Mayor Booth briefed the Council on the purpose of the meeting to discuss 1997 Capital
Improvement Projects. This is an opportunity for Councilmembers to ask any questions they may
have with regard to proposed capital improvement projects.
II. 1997 Capital Improvement Projects
A. Parks/Cemetery/Golf Course/Library
Acting Parks & Recreation Director Dick Deal presented capital improvement projects for
the Parks Division, Mountain View Cemetery, Auburn Golf Course, and the proposed
Agreement for Library Services Pending Annexation of the City of Auburn into the King
County Rural Library District.
Capital Improvement Projects, funded through a King County Historic Preservation
reimbursable grant and paid from Fund No. 328, include: roof repairs to the barn and out
buildings at Olson Canyon in the amount of $24,500. Other anticipated projects, funded
by the King County 1989 reimbursable bond issue, are enhancements to Mill Pond in the
amount of $325,000 and the White River Trail in the amount of $600,000. Brannan Park
Trails. Funded by the Real Estate Excise Tax are Brannan Park Trail budgeted at
$20,000 and development of the Public Art program budgeted at $50,000. $14,000 is
anticipated to repair the hand railing of the footbridge at Dykstra Park paid with Gas Tax
Funds for recreation trails.
Mr. Deal explained the Cemetery Fund is an Enterprise Fund which is self-supporting..
This Fund accounts for Mountain View Cemetery's operations. All capital projects are
paid by revenue and interest earned from the Endowed Care Fund. In this fund is
approximately $750,000 and $350,000 in the Interest Fund. Anticipated Cemetery
improvements for 1997 include: construction of a storm water system in Section 8
budgeted at $150,000; landscape improvements to the Cemetery entrance and Mountain
View Drive improvements budgeted at $20,000; and $35,000 for installation of a wrought
iron fence around Pioneer Cemetery.
City Council Special Meeting Minutes
November 4, 1996
Page No. 2
In response to a question raised regarding grave stone maintenance, Mr. Deal explained
prior to Memorial day 10,000 grave stones are edged. It is the family responsibility to
edge grave stones. Sometimes community service assistance is used for maintenance of
grave stones.
Improvements planned for the Auburn Golf Course are funded from 1997 green fee
revenue. With revenue down this year, Mr. Deal noted some projects were not complete.
For 1997 $53,000 is budgeted to renovate the 15th hole, $59,500 is budgeted to renovate
the 16th hole, $10,000 to secure the south end of the Golf Course adjacent to Glenn
Karra, a new development; and $4,000 to construct a mower cleaning facility behind the
maintenance facility.
Councilmember Singer asked when a new club house at the Golf Course is anticipated.
Mr. Deal explained drainage improvements and a new irrigation system is needed prior to
building a new club house. Mr. Deal predicted three to five years before a new club
house is built. Concerns were raised regarding existing asphalt. The City will seal coat
asphalt areas to bring it up to grade.
Mr. Deal reviewed each section of an Agreement for Library Services pending annexation
of the City of Auburn into the King County Rural Library District (revised October 30,
1996) with Council, Mayor and staff. By meeting the timelines in the draft Agreement, Mr.
Deal noted a new library facility could be up and running by late 1999. A question was
raised with regard to transferring ownership of the existing library facility. Mr. Deal
clarified, based on meetings with King County Library District, the direction being
considered is building new building at a different location in Les Gove Park. No
determination has been made with regard to the existing facility. The City has $4.5 million
for construction of a new facility. The County will pay $500,000 of the $4.5 million. The
new facility will be developed at a minimum of 15,000 square feet which is standard for a
resource library. Referring to expansion of the facility to 22,400+ square feet, Mr. Deal
acknowledged it would be a King County Library System expense. A request was made
to delete "all" from #6, third line. Parking is needed for Library and Park users. By
annexing into the King County Library System, Auburn will enhance its collection
comparable to other resource branch collections.
Discussion centered around designating a taxing district for library services. Because
residents of unincorporated King County are taxed for library services, they would incur
an additional obligation. King County's top priority in locating a new library facility is its
location and access. Mr. Deal clarified the City will fund $4.0 million for a new library
facility. There are three pieces of property, approximately an acre or less, the City has
considered in order to obtain entry off of Auburn Way South. Any property acquisitions
needed for Library access from Auburn Way South will be negotiated by King County.
Referring the number 8 of the proposed Agreement for Library Services Pending
Annexation of the City of Auburn into the King County rural Library District, Mr. Deal
indicated King County Library System already provides programs such as special
language collections; a genealogical collection; a literacy program; and outreach for low
income, homebound, and elderly populations.
Should the City choose to continue with the appointment of the Library Board and Friends
of the Library the King County Library District supports community contribution.
City Council Special Meeting Minutes
November 4, 1996
Page No. 3
Mr. Deal concluded his comments by discussing the schedule of annexation. To meet the
February 4, 1997 annexation vote, all documents need to be filed with King County no
later than early December, The interlocal agreement is scheduled before the Auburn
Library Board on November 6, 1996, to Planning & Community Development Committee
on Tuesday, November 12, 1996 and to City Council on November 18, 1996. A second
deadline was presented. A simple majority, 50% plus one, is required for approval of an
annexation into the King County Library System.
B. Streets/Utilities
Public Works Director presented Capital Projects proposed for 1997 for the Arterial Street
Fund (102). They include:
Description 1997 Prior Years Total
Studies/Plans/Preliminary Design 1997 Prior Total
ARTERIAL STREET (102) Cost Years Project
277th Street Predesign: $0 $600,000 $918,080
Street Widening, Bike Trail, RR grade
separation, Sewer Trunk line, future grants
8th Street Corridor Study $10,000 $ 2,938 $12,938
Harvey Road @ 8th Street at M to Auburn
Way North; preferred alignment; major
storm & water project; future grants
"C St SW/SR 18 WB Ramp 0 $966,413 $2.799,152
Predesign/row acquisition; ramp Auburn money
realignment; BNRR grade separation; spent on BN
future grants ( no construction money issue for grade
included) separation costs
"B" Street NW (30th-37th SE) LID $40,000 $80,004 $802,004
Street, curb & gutter, east side sidewalk
and storm capacity improvements on west
side
No construction date projected
"A" Street SW (Main down to C Street $10,000 0 $10,000
Crossing (3rd)
Preliminary design work; grant is on hold
to coordinate with "C" Street project
"M" Street SE (29th-37th) LID $10,000 0 $10,000
To gather information and parameters and
costs to property owners
Transit HUb $15,000 0 $15,000
Planning & coordination with METRO bus
hub @ 2nd & "B" Street SW
There would be a facility there and would
be coordinated with RTA.
Non-Motorized Plan $20,000 $78,000 $98,000
Completion of planning with about
$20,000 in actual improvements such as
City Council Special Meeting Minutes
November 4, 1996
Page No. 4
lane marking and signage
AWS (6th - 12th) Sidewalks $30,000 $130,900 $160,900
Completion of missing segments and Metrogrant
access to Les Gove Park & related
facilities
1996/1997 Sidewalk LID $105,000 $50,000 $155,000
Dogwood area - sidewalks, ramps, row
acquisition
TOTAL $210,000 $1,049,355 $4,907,074
REPAIR AND MAINTENANCE
(Including Preservation)
1996 Loop Repair $40,000 $0 $40,000
Replace damaged traffic signal detection
loops at various location
1997 Loop Repair $40,000 $0 $40,000
Replace damaged traffic signal detection
loops-various locations
1996 Pavement Markings $40,000 $0 $40,000
Replacement of lane markings and other
traffic channelization
1997 Pavement Markings $40,000 $0 $40,000
Replacement of lane markings and other
traffic channelization; Railroad/crosswalk
markings
1996 ISTEA Preservation $67,200 $378,800 $486,000
Pavement overlay of part of 15th Street
NW, parts of Auburn Way North & spot
repairs on "A" Street SE;
Oravetz Road Preservation $128,000 $36,800 $195,000
Pavement rehabilitation - Kennedy to
Kersey. Anticipated from 1/4% Real
Estate Excise Tax
1997/1998 Preservation (PWTF) $50,000 $750,000 $800,000
Approximately $800,000 projected
$50,000 match for routine annual program
for 10 years @ 66
SUBTOTAL $355,200 $415,650 $891,000
CONSTRUCTION
Traffic Signal @ 29th & "A" Street SE $8,010 $111,090 $120,000 =
Signal construction
Traffic Signal @ 17th & "A" Street SE $9.914 $117,500 $127,414
Signal construction
1997 Developer Participation $25,000 0 $25,000
Miscellaneous participation in extra
capacity for developer street projects
SUBTOTAL $42,924 $0 $273,414
City Council Special Meeting Minutes
November 4, 1996
Page No. 5
CAPITAL EQUIPMENT
Design Software $15,000 $0 $15,000
Partial auto-cad updates attributable to
projects
Reproduction Machine $10,000 $0 $10,000
Portion attributable to projects
SUBTOTAL $25,000 $0 $25,000
TOTAL ARTERIAL STREET $633,124 $1,693,595 $5,294,588
STORM DRAINAGE UTILITY
Renewal & Replacement
Auburn 400 Pond Cleaning $155,000 $0 $155,000
Done in early 1980's. They are 15 to 17
years old; cleaning project to restore
conveyance through the ponds. Backup
problem that may already be flooding
Algona
SUBTOTAL $155,000 $0 $155,000
Improvements
Comprehensive Plan Revision $100,000 $0 $100,000
Revise the current plan to include storm
water quality and potential annexation
Areas.
GIS $50,000 out $100,000 $100,00 out of
The geographic information system split of Storm Water/Sewer
among three utilities. Big part is potential Water
annexation areas, Lea Hill, West Hill, and
Lakeland.
North Central Storm Improvement Phase I $550,000 $0 $2,761,000
Completion of pump station near Brannan
Park (North central drainage area)
Central Storm Improvement Phase I $1,075,000 $0 $1,075,000
This used to take the water the Enumclaw
plateau. Design and phased construction
on "A" St. from 3rd Street up to Main to
Mill Creek.
"A" St SE Improvement Phase I $165,000 $0 $165,000
Street project for design and phased
construction near "A' St. SE & 17th - 21st
St. SE
Local Capital Storm Improvements $445,000 $0 $445,000
Small projects at locations not identified in
the Comprehensive Plan.
City Council Special Meeting Minutes
November 4, 1996
Page No. 6
South Central Storm Improvement Phase I $70,000 $0 $1,000,000
Design money for selection of many
infiltration of storm water in south basin.
Airport Detention Facility Expansion (12) $65,000 $0 $285,000
Alternatives analysis and design of
additional storage at the Airport
PR 557 $200,00 $0 $200,000
Construction of the 1995-96 local
improvements. This includes flood control
devices on piping along Riverview Drive
and Academy Drive.
SUBTOTAL $2,720,000 $0 $6,071,000
EXPANSION
Developer Participation $150,000 $0 $150,000
City participation in oversizing developer
projects to benefit regional
Subtotal $150,000 $0 $150,000
TOTAL STORM DIVISION $3,025,000 $0 $6,221,000
Councilmember Wagner urged completion of the Storm Water Comprehensive Plan to reflect
$1,075,000. Frank Currie responded the $1,075,000 is left of out of what is not coming north
which is the same plan at a lesser magnitude. There are no planned land acquisitions other than
identification of land that may be $70,000 identified in the South Central Storm Improvement.
Utilities
Sewer
Renewal & Replacement
Sewer ReplaCement Program $1,006,000 $0 $1,006,000
Annual program that replaces old clay title
pipes and pipes with poor flow
characteristics. There are adverse grades
causing inefficient flows that will be repaired.
AWS "bottlenecks" Replacements $80,000 $0 $80,000
Remove 90 degree turns and adverse
grades causing inefficient flows in the
Auburn Way South sewer line. Identified
as a special project to improve the flow on
AWS because of the potential of
connecting the truck.
37th Street Easement $15,000 $0 $15,000
Clear easement to allow maintenance
access and alleviate root problems
Academy Line Upgrade $125.000 $0 $125,000
This is for inflow and infiltration of sewer
line in Academy Drive area
Subtotal $1,226,000 $0
City Council Special Meeting Minutes
November 4, 1996
Page No. 7
Improvements and Enhancements
Dogwood Interceptor $25,000 $325,000 $650,000
Design a new sanitary sewer line from
Dogwood to 17th Street SE for flow relief
should the Muckleshoot Indian Tribe
decide to extend the sewer line. City
would then eliminate the Dogwood pump
station.
Franchise Requirements $10,000 $0 $0
Line relocates required by King County
franchise agreement or lines outside the
City.
Sewer Comprehensive Plan $50,00 $0 $0
To update the 1982 Comprehensive
Sanitary Sewer Plan.
GIS $50,000 $100,000 $'~50,00
Cost share GIS system development and
enhancement.
Subtotal $135,000
Expansion
Unsewered Areas Inside the City $43,000 $0 $0
Develop preliminary engineering reports
and cost estimates for unsewered
developed areas. There are $10 million
proposed LID projects in unsewered
areas.
277th Street NE $200,000 $1,500,000 $2,500,000
Design metre trunk line in 277th (including
Green River Crossing)
Developer Participation $120,000 $0 $0
Participate in oversizing facilities
constructed by developers
"B" Street NW (280th - 277th) $87,500 $0 $0
Design and construct new sanitary sewer
line in B Street NW (from 280th to 277th)
"B" Street NW (ath - 5th ) $20,000 $0 $0
(Design only) new sanitary sewer line in B
Street NW (from 8th to 15th)
City Participation in LID Projects $50,000 $0 $0
A City % participation if any sanitary LID's
can be created
Subtotal $520,000
TOTAL SEWER DIVISION $1,881,500
City Council Special Meeting Minutes
November 4, 1996
Page No. 8
Questions were raised with regard to grant availability to replace existing sewers, an increase
sewer rates, and Sewer Fund working capital. Mr. Curde indicated he is not aware of any grants
available. Grants such as these were available from the federal government about 15 years ago
for development of sewage treatment plants. The City's Sewer Fund working capital is dependent
upon King County's portion of $1.1 million. The sewer operations expense exceeds the amount of
revenue on an annual basis. Revenue such as the sale of city property has supported sewer
operations. Mr. Curde urged the Council to consider revenue increases to support sewer
operations especially if the City decides to issue bonds.
The sewer replacement program, based on surveys conducted, has spent $200,000 to $300,000
a year. In 1997 staff anticipates and expense of $1,006,000. Dwight Holobaugh reported there
are approximately 20-25 miles of concrete and old clay tile pipes and pipes with poor flow
characteristics left greater than 40 year years old, eight times more than what is presented. Level
of funding is projected at approximately eight to fifteen years. On a monthly basis, staff cleans old
clay tile pipes to keep them operating. Mr. Curde noted Metro is pleased with the City's
replacement program. The City is required by agreement to spend 2% of its budget on
replacement.
WATER
Renewal and Replacement
Lea Hill Reservoir Protective Coating $200,000 $0 $200,000
Painting of reservoir for appearance
and corrosion protection (inside and
outside)
Lea Hill Pump Station Rehabilitation $25,000 $0 $130,000
Design the rehabilitation of Lea Hill PS
for capacity, power efficiency
Academy Booster Pump Station $25,000 $0 $100,000
Rehabilitation
Design the rehabilitation of Academy
pump station for capacity, power
efficiency and reliability
3rd Street SW Pipeline Replacement $105,000 $0 $105,000
(from C Street to G. north and south)
Replace existing 6-inch pipeline with
112-inch to improvement fire flow and
distribution
Leak Detection Repair $10,000 $0 $10,000
Remove leaks discovered during the
leak detection program at various
locations
Franchise Requirements $10,000 $0 $10,000
Relocate pipelines within franchise
area as required by King County
Coal Creek Booster Pump $10,000 $0 $125,000
Design the rehab of Coal Creek
Design the rehabilitation of Coal Creek
pump station for capacity, power
efficiency and reliability
85th Avenue South asbestos pipe $10,000 $0 $120,000
City Council Special Meeting Minutes
November 4, 1996
Page No. 9
replacement
Design the replacement of existing
asbestos cement water pipeline (not
used any longer)
112th Avenue SE Asbestos Pipe $10,000 $0 $200,000
Replacement
Design the replacement of existing
asbestos pipeline
Subtotal $405,000
Improvement and Enhancements
"C" Street Interconnection $30,000 $0 $30,000
Connect existing 10: and 16" pipelines
in C Street SW near SR 18 for better
fire flow and distribution
"A" Street SW Pipeline $150,000 $0 $150,000
Construct 12" line on A Street SW'- SR
18 to 2nd Street SWfor Better Fire flow
and distribution.
Watershed Fencing $40,000 $0 $80,000
Install fences around the West Hili and
Coal Creek Springs watersheds for
water quality control
Lea Hill Rezone $50,000 $0 $50,000
Design new PRV Stations in Lea Hill to
adjust pressures to current City
Standards
Lea Hill Pipelines $75,000 $0 $75,000
Design new transmissionlines from the
Lea Hill Pump Station to the Reservoir
pressure zone
Lakeland Hills Rezone $100,000 $0 $100,000
Adjusts pressure zones to eliminate
private pressure release valves and
provide adequate city pressure. The
intent is for the City to provide
pressure.
Academy Rezone $120,000 $0 $120,000
Reduces the number of pressure
reducing stations on the Enumclaw
plateau
Water Comp Plan Amendment $30,000 $0 $30,000
Prepare amendment to the 1995
Comprehensive Plan to address
potential annexation areas
Corrosion Control Facilities $85,000 $0 $1,800,000
Design for pH adjustment facilities to
comply with the lead and copper rule.
(EPA prescribes process to monitor the
acidity in water)
City Council Special Meeting Minutes
November 4, 1996
Page No. 10
GIS $50,000 $100,000 $150,000
Cost share GIS system development
and enhancement
Water Resources Protection $250,000 $0 $250,000
Aquifer evaluation for potential
contaminants, and development of
management strategies
Coal Creek Springs Improvement $185,000 $0 $185,000
Rehabilitation and improvement of
collection system for efficiency and
increased quantities
8th Street NE Parallel Pipeline $170,000 $0 $170,000
Parallel 12-inch pipeline as part of Well
7 (City Park) transmission (from K .
Street NE to Auburn Way North)
15th Street SW Pipeline $145,000 $0 $145,000
Provide additional capacity from A
Street SE across to 15th Street at C
Street SW
C Street SW Pipeline $85,000 $0 $85,000
Pipeline at 3rd Street across RR tracks
to C Street SW
Cross Street Pipeline $5,000 $0 $5,000
Design new pipeline in Cross from A
St. to Auburn Way South
Subtotal $1,570,000
Expansion
Interlocal Agreement#4 - Lakehaven $15,000 $0 $1,300,000
Negotiate potential
emergency/wholesale intertie and
assumption agreement with Lakehaven
Aaby Drive Intertie $75,000 $0 $75,000
Complete water line loop from Sunning
Hills to Aaby Drive for emergency
supply
Interlocal Agreement #3 - Algona $0 $50,500 $50,500
Construct meter stations for wholesale
water service to AIgona
Interlocal Agreement #2 - Water District
#11 l/Covington
Green River PS Station and Intertie $40,000 $460,000 $892,500
P.S. (what the City Other
Construct 2 new pump stations for will spend) participation
Lea Hill Intertie and backup supply
to Lea Hill Service
104th Avenue SE Pipeline
Supply line (16-inch) to feed the $40,000 $160,000 $502,500
City Council Special Meeting Minutes
November 4, 1996
Page No. 11
new Lea Hill Pump Station from the
south.
Green River Crossing Project
New river crossing for backup $70,000 $280,000 $592,500
supply to Lea Hill and wholesale to
Covington and Water District #111
304th Transmission Pipeline
Transmission line from the new Lea
Hill Pump Station to 116th Avenue $80,000 $720,000 $855,000
SE in Lea Hill
Water Resources
Well 6. Building/Equipment $102,960 $257,040 $937,500
Drill new well, construct wellhouse and
install equipment including
transmission pipelines
Well 7. Building/Equipment $268,125 $669,375 $937,500
Construct Well 7 well house and install
equipment including transmission
pipelines
Water Rights Legal Counsel $90,000 $50,000 $180,000
Continue water right strategy and
negotiations with Tribe and DOE for
additional water supply
Aquifer Capacity Evaluation $600,000 $0 $1,400,000
Aquifer investigation to quantity
capacity and support new water right
Shallow Monitoring Wells $230,000 $0 $400,000
Monitoring wells to determine
hydraulic continuity between shallow
aquifer and rivers
River Gauging Stations $160,000 $0 $160,000
Gauging Stations in Green and White
Rivers to measure flows upstream and
downstream of the City
Well 5B and 5C $165,000 $0 $165,000
Develop wells conveyed by the
Lakeland Company as part of
annexation agreement
Developer Extension Participation $200,000 $0 $200,000
Participate in oversizing lines constructed
by developers, when larger sizes are
needed by City/Lakeland Hills reservoir for
pressure and storage
Lakeland Reservoir $55,000 $0 $3,000,000
City Council Special Meeting Minutes
November 4, 1996
Page No. 12
New Lakeland Reservoir design and
analysis
Subtotal $5,010,500
TOTAL WATER DIVISION $6,985,500
Frank Currie pointed out many projects are necessary in order to obtain water rights. Water is
needed and necessary. A question was raised regarding the budget estimate for legal counsel in
obtaining water rights. Mr. Curried explained the need for supplemental water rights. The budget
amount reflects not only legal counsel, but other agreements and applications with surrounding
jurisdictions. The Muckelshoot Indian Tribe did not object or reserve their right to object to
supplemental water rights. The strategies used in negotiation varies on a daily basis. Staff will be
monitoring wells to identify the aquifer.
C. Computer Enhancement
Diane Supler explained the company who supports the City's current computer system (Banyon
Vines) is no longer supporting network software. A consultant is currently developing a long term
technology plan (3-years). Preliminary estimate is $85,000 to change network server that
includes a new server, and conversion assistance for remote sites such as M & O and Library.
The NT network system is predominately being used at this time. It is anticipated this project will
be complete in the late fall of 1997.
Ms. Supler discussed the proposed Airport budget to repair the hangar roof and fuel facility. The
Planning & Community Development Committee reviewed the bids submitted sometime ago and
all the bids were rejected. These items will be amended to current year budget and reflected in
the 1997 budget.
The meeting adjourned at 7:00 PM.
Approved this r~fi~ay of ~/-~~--J-/-'~, 1996
Charles A. Booth, Mayor Robin Wohlhueter, City Clerk