WHEREAS, the original agreement for design services between the City
of Auburn and JGM for the construction of Lakeland Hills Park, Roegner Park,
Mill Pond, and the White River trail was executed as Resolution No. 2059; and
WHEREAS, the funding for the projects was approved by voters in the
1989 King County Open Space Bond Issue and adequate funds are still available
to complete the design and construction of this project; and
WHEREAS, all projects except the White River trail have been completed
and are great additions to our park system; and
WHEREAS, design and permitting delays, and modifications to the original
plan requested by permitting agencies have resulted in delays and increased
design costs: and
WHEREAS, the completion of the White River Trail from Game Farm Park
to Roegner Park has been identified as a priority project in the City of Auburn
Parks Plan and the Non-Motorized Transportation Plan.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF AUBURN,.
WASHINGTON, IN THE REGULAR MEETING DULY ASSEMBLED, HEREWITH
RESOLVES AS FOLLOWS:
Resolution No. 3101
June 30, 1999
Page 1
Section 1. The amendment for additional services between the! City of
Auburn and JGM which is denominated as Exhibit "A", attached hereto land
incorporated herein, is hereby approved by the City Council of the City of Auburn.
Section 2. The Mayor is hereby authorized to implement such
administrative procedures as may be necessary to carry out the directiw,~s of this
legislation.
DATED and SIGNED this ~/' day of ~i/~ ,1999.
CITY OF AUBURN
CHARLES A. BOOTH
MAYOR
ATTEST:
City Clerk
APPROVED AS TO FORM:
Michael, J. Reynolds,
City Attorney
Resolutibn No. 31G1
June 30, lg99
Pa~e 2
,
Incorporated P.S. Principals:
David McNeal, FASI,A
Site Planning Tbcodore XVall,
ASLA
Urban Design CTS Associates:
Craig Lewis. ASLA
Park and Recreation Planning
Roger Dane, ASIA.
Mr. Fred Ostmann dUN
Project Manager
Department of Public Works
25 W. Main Street By
Auburn, Washington 98002
Project: Whim River Trail Extension
RE: Revised Fee Proposal for Completion of Construction Documents plus
Conceptual Stream Plan for Department of Fisheries and Wildlife
Dear Mr. Ostmann:
Based on our meeting in our office on June 23, 1999, we are providing a revision of our
June 17, 1999 proposal to include a conceptual stream plan for Coal Creek Spring.
Project Delays and Salary Escalation
Our January 20, 1999 memo to Mr. Dick Deal outlines our request for additional
compensation due to project delays since our initial contract was signed in 1997.
Design Revisions
1. Reconciliation of new survey information furnished by City with previous surveys
from INCA Engineers and M.A. Segale.
2. Realignment of trail around dike blow-out area (former bridge site) in the Game Farm
Wilderness Park and subsequent revisions to all drawings (layout, grading, planting).
3. Design of the new trail structure (concrete armored culvert or similar construction)
crossing the back channel area upstream of the dike blow out.
4. Stuck River Drive road design revisions due to Segale construction of berms and
fencing along road edge.
5. Additional site visits by JGM and engineering subconsultants to review changed site
conditions since subconsultants original fee proposals.
6. Design of wing walls or similar construction for added protection of Ballard Bridge
abutment.
Resolutibn 31G1
E~'t "A"
Page 1
204 - 11 lth Avenue NE Bellevue, WA 98004 Tel: 425.454.5723 Fax: 425.454.4685 E-mail: jgm@jgm-inc.com Web Site: www. jgm-inc.com
fMCTS
Mr. Fred Ostmann
page 2
Additional Design Work
The following tasks are items of additional work we identified after our meetings with
the City and State Department of Fisheries on June 1 and 3, 1999:
1. Design of two (2) interpretive signs as required by Shoreline Permit for this project.
2. Deletion/revision of previous design work for trail segment in area of former bioswale
and culvert in Game Farm Wilderness Park that was modified by M. Segalc.
3. Modifications at ~rail Station 0+ 17. The recent Cky of Auburn roadwork on Oravetz
Road has installed a new drainage structure and modified the drainage conditions at this
former culver~ site. PND will evaluate the hydraulic conditions for the design of a
hydraulic drop from the new road culvert and possible low head structure at the trail
crossing. Additionally, they will conduct research of the drainage basin and perform a
hydraulic analysis to verify the anticipated flows.
4. Research two previously unknown existing concrete culverts exposed by rec, ent City
of Auburn roadwork on Oravetz Road. These culverts were not shown on any survey
and were not previously visible because of heavy vegetative growth. They are located
approximately at trail Station 1+70. PND proposes reviewing these culverts in the field
to determine if they are active and if they have any drainage impacts to trail design. At
this time, PND expects this work to take less than 2 hours to complete and would be
incorporated with one of their additional site visits. They are assuming the culverts are
blocked off and trail modifications will not be required. However, if they learn otherwise
from their investigation, additional design work may be required.
5. PND will prepare the erosion control plan for the entire project.
6. Additional meetings with the City of Auburn staff and Washington Department of Fish
and Wildlife.
7. Concept plan for Coal Creek Spring Fish Habitat Improvements to include one
engineers plan, cross-sections using available information, and one conceptual landscape
plan.
Increased Project Costs
The table on the following page summarizes the increases in project costs for each of the
above items and shows a breakdown of these costs by JGM and our two engineering
subconsultants:
Resolution 31(11
JUne'. 30, 1919~
Eft "A"'
Page 2
CTS
Mr. Fred Ostmann
page 3
JGM **PSM ***PND
Project Delays and Salary $3,100 $1,000
Escalation
Design Revision
1. Survey Reconciliation 500
2. Realignmentof Trail 1,000 - -
3. Crossing Back Channel 800 - 3,:500
4. Road Realignment 600 - 4,000
5. Additional Site Visits 1,600 1,300 1,800
6. Ballard Bridge Added 800 2,600 -
Protection
Additional Design Work
1. Interpretive Signs 5,220 - -
2. Trail Revision @ Bioswale 500 - [900]
3.0+17 Drainage Design 400 - 3,000
4. Research Culverts - - 2,00
5. Erosion Plan 400 - 6,500
6. Additional Meetings 1,470 - 1,320
7. Conceptual Stream Design 800 - 2,7'90
Increase Cost by Consultant 17, 190 4,900 22,210
Total Increase Cost *$ 44,300
*Not including reimbursable
expenses @ cost plus 10%
**PSM o Peterson Strehle Martinson - Structural Engineers
***PND - Peratrovich Nottingham Drage - Civil/Shoreline Engineers
Assumptions
PND has noted that additional survey work may be required from the City to perform the
erosion control plan and drainage modifications at Station 0+17. It is assumed that the
City can provide this information in a timely way in AutoCAD format.
Should you have any questions or if we can be of additional assistance, please contact
tlS.
Sincerely,