2009 AGREEMENT FOR PROFESSIONAL SERVICES
AG-C-374
THIS AGREEMENT made and entered into by and befinreen the CITY OF
AUBURN, a Municipal Corporation in King County, Washington, hereinafter referred to
as "CITY," Carollo Engineers, P.C., an Arizona professional corporation, whose
address is 1218 Third Avenue, Suite 1600, Seattle, Washington, 98101, hereinafter
referred to as "CONSULTANT."
In consideration of the covenants and conditions of this Agreement, the parties
hereby agree as follows:
1. SCOPE OF WORK
See Exhibit A, which is attached hereto and by this reference made a part of this
Agreement.
2. TERM
The CONSULTANT shall not begin any work under this Agreement until
authorized in writing by the CITY. All work under this Agreement shall be completed by
December 31, 2010, and can be amended by both parties for succeeding years.
The established completion time shall not be extended because of any delays
attributable to the CONSULTANT, but may be extended by the CITY in the event of a
delay attributable to the CITY, or because of unavoidable delays caused by an act of
God or governmental actions or other conditions beyond the control of the
CONSULTANT. A prior supplemental Agreement issued by the CITY is required to
extend the established completion time.
3. COMPENSATION '
The CONSULTANT shall be paid by the CITY for completed services rendered
under the approved Scope of Work identified in Exhibit A. Such payment shall be full
compensation for work performed or services rendered and for all labor, materials,
Agreement for Professional Services AG-C-374
Page 1 of 12
supplies, equipment and incidentais necessary to complete the work. The
CONSULTANT shall submit an itemized invoice to the CITY prior to payment, in a form
similar to that attached to this Agreement.
Compensation for the work identified will be on a time and material basis, not to
exceed the following totals for the current year and succeeding years combined.
Design Services $ 850,300.00
Construction Services $ 103,500.00
Total Authorized Compensation $ 953,800.00
Compensation for work performed shall be based on the Schedule outlined in
Exhibit B of this Agreement. Exhibit B is attached hereto and by reference made a part
of this Agreement. Compensation to be paid to the CONSULTANT for authorized work
in succeeding years will be contingent upan availability of funds.
The CONSULTANT shall be paid by the CITY for direct non-salary cost, per
attached Exhibit B. These charges may include, but are not limited to the following
items: outside reproduction fees, courier fees, subconsultant fees, and materials and
supplies. The billing for non-salary cost, directly identifiable with the project, shall be
submitted as an itemized listing of charges supported by copies of the original bills,
invoices, expense accounts and miscellaneous supporting data retained by the
CONSULTANT. Copies of the original supporting documents shall be supplied to the
CITY upon request. Ali above charges must be necessary for the services provided
under the Agreement.
In the event services are required beyond those specified in the Scope of Work,
and not included in the compensation listed in this Agreement, a contract modification
shall be negotiated and approved by the CITY prior to any effort being expended on
such services or work shall be authorized in writing under the Management Reserve
Fund as detailed in Section 4.
Agreement for Professional Services AG-C-374
Page 2 of 12
4. MANAGEMENT RESERVE FUND
The CITY has established a Management Reserve Fund to provide flexibility of
authorizing additional funds to the Agreement for allowable unforeseen costs, or
reimbursing the CONSULTANT for additional work beyond that already defined in this
Agreement. Such authorization(s) shall be in writing, prior to the CONSULTANT
expending any effort on such services, and shall not exceed $25,000. This fund may
be replenished in a subsequent supplemental agreement. Any changes requiring
additional costs in excess of the Management Reserve Fund shall be negotiated and
approved by the CITY prior to any effort being expended on such services.
5. SUBCONTRACTING The CITY permits subcontracts for those items of work necessary for the
completion of the project. The CONSULTANT shall not subcontract for the
performance of any work under this AGREEMENT without prior written permission of
the CITY. No permission for subcontracting shall create, befinreen the C1TY and
subcontractor, any contract or any other relationship.
Compensation for any subconsultant work is included in Section 3 of this
Agreement and all reimbursable direct labor, overhead, direct non-salary costs and
fixed fee costs for the subconsultant shall be substantiated in the same manner as
outlined in Section 3. All subcontracts exceeding $10,000 in cost shall contain all
applicable provisions of this AGREEMENT.
6. RESPONSIBILITY OF CONSULTANT
The CONSULTANT shall be responsible for the professional quality, technical
accuracy, timely completion and the coordination of all studies, analysis, designs,
drawings, specifications, reports and other services pertormed by the CONSULTANT
under this Agreement. The CONSULTANT shall, without additional compensation,
correct or revise any errors, omissions or other deficiencies in its plans, designs,
drawings, specifications, reports and other services required. The CONSULTANT shall
Agreement for Professional Services AG-C-374
Page 3 of 12
perform its services to conform to generally-accepted professional engineering
standards and the requirements of the CITY. Any approval by the CITY under this Agreement shall not in any way
relieve the CONSULTANT of responsibility for the technical accuracy and adequacy of '
its services. Except as otherwise provided herein, neither the CITY'S review, approval
or acceptance of, nor payment for, any of the services shall be construed to operate as
a waiver of any rights under this Agreement or of any cause of action arising out of the
performance of this Agreement to the full extent of the law.
.
7. RESPONSIBILITY OF CITY
The CITY shall furnish the CONSULTANT available studies, reports and other data
pertinent to the CONSULTANT's services and the CONSULTANT shall be entitled to
use and rely upon all such information provided by the CITY or others in performing the
CONSULTANT's services under this Agreement.
.
8. INDEMNIFICATION/HOLD HARMLESS
The CONSULTANT shall indemnify and hold the CITY and its officers and
employees harmless from and shall process and defend at its own expense all claims,
demands, or suits at law or equity arising in whole or in part from the CONSULTANT'S
negligence or breach of any of its obligatians under this Agreement; provided that
nothing herein shall require the CONSULTANT to indemnify the CITY against and hold
harmless the CIT1' from claims, demands or suits based solely upon the conduct of the
. CITY, their agents, officers and employees and provided further that if the claims or
suits are caused by or result from the concurrent negligence of (a) the CONSULTANT'S
agents or employees and (b) the CITY, their agents, officers and employees, this
indemnity provision with respect to (1) claims or suits based upon such negligence, (2)
the costs to the CITY of defending such claims and suits, etc. shall be valid and
enforceable only to the extent of the CONSULTANT'S negligence or the negligence of
Agreement for Professional Setvices AG-C-374
Page 4 of 12
the CONSULTANT'S agents or employees. The provisions of this section shall survive
the expiration or termination of this Agreement.
9. INDEPENDENT CONTRACTOR/ASSIGNMENT
The parties agree and understand that the CONSULTANT is an independent contractor and not the agent or employee of the CITY and that no liability shall attach to
the CITY by reason of entering into this Agreement except as otherwise provided
herein. The parties agree that this Agreement may not be assigned in whole or in part
without the written consent of the CITY.
10. 1NSURANCE
CONSULTANT shall procure and maintain for the duration of this Agreement,
insurance against claims for injuries to persons or damage to property which may arise
from or in connection with the performance of the work hereunder by the
CONSULTANT, its agents, representatives, or employees.
CONSULTANT'S maintenance of insurance as required by the Agreement shall
nat be construed to limit the liability of the CONSULTANT to the coverage provided by
such insurance, or otherwise limit the City's recourse to any remedy available at law or
in equity.
CONSULTANT shall obtain insurance of the types and in the amounts described
below:
a. Automobile Liability insurance covering all owned, non-owned, hired and
leased vehicles, with a minimum combined single limit for bodify injury and
property damage of $1,000,000 per accident. Coverage shall be written on
Insurance Services Office (ISO) farm CA 00 01 or a substitute form providing
equivalent liability coverage.
b. Commercial General Liability insurance shall be written on ISO occurrence
form CG 00 01 and shall cover liability arising from premises, operations,
independent contractors, and personal injury and advertising injury, with limits
- - - - - -
Agreement for Professional Services AG-C-374
Page 5 of 12
no less than $1,000,000 each occurrence, $2,000,000 general aggregate.
The CITY shall be named as an insured under the CONSULTANT'S
Commercial General Liability insurance policy with respect to the work
performed for the CITY using the applicable ISO Additional Insured
endorsement or equivalent.
c. Worker's Compensation coverage as required by the Industrial Insurance
laws of the State of Washington.
d. Professional Liability insurance appropriate to the CONSULTANT'S
profession, with limits no less than $1,000,000 per claim and $1,000,000
policy aggregate limit.
The insurance policies are to contain, or be endorsed to contain, the following
provisions for Automobile Liability and Commercial General Liability insurance:
a. The CONSULTANT'S insurance coverage shall be primary insurance as
respects the CITY. Any insurance, self insurance, or insurance pool
coverage maintained by the CITY shall be excess of the CONSULTANT'S
insurance and shall not contribute with it.
b, The CONSULTANT'S insurance shall be endorsed to state that coverage
shall not be cancelled by either party, except after thirty (30) days prior written
notice has been given to the CITY.
All insurance shall be obtained from an insurance company authorized to do
business in the State of Washington. Insurance is to be placed with insurers with a
current A.M. Best rating of not less than A-:VII.
The CONSULTANT shall furnish the City with certificates of insurance and a
copy of the amendatory endorsements, including but not necessarily limited to the
additional insured endorsement, evidencing the insurance coverage required by this
section, before commencement of the work. The CITY reserves the right to require that
complete, certified copies of all required insurance policies be submitted to the CITY at
Agreement for Professional Services AG-C-374
Page 6 of 12
any time. The CITY will pay no progress payments under Section 3 untii the '
CONSULTANT has fully complied with this section.
11. NONDISCRIMINATION
The CONSULTANT may not discriminate regarding any services or activities to .
which this Agreement may apply directly or through contractual, hiring, or other
arrangements on the grounds of race, color, creed, religion, national origin, sex, age, or
where there is the presence of any sensory, mental or physical handicap.
12. OWNERSHIP OF RECORDS AND DOCUMENTS
' The CONSULTANT agrees that any and all drawings, computer discs,
documents, records, books, specifications, reports, estimates, summaries and such
other information and materials as the CONSULTANT may have accumulated,
prepared or obtained as part of providing services under the terms of this Agreement by
the CONSULTANT, shall belong to and shall remain the property of the CITY OF
AUBURN. Any reuse of completed documents, other than for completion of the work
described therein by the City, its agent, or a surety should the City's original contactor
fail to complete the work, or use of partially completed documents without written
verification or concurrence by the CONSULTANT for the specific purpose intended will
be at the CITY'S sole risk and without liability or legal exposure to the CONSULTANT.
In addition, the CONSULTANT agrees to maintain all books and records relating to its
operation and concerning this Agreement for a period of six (6) years following the date
that this Agreement is expired or otherwise terminated. The CONSULTANT further
agrees that the CITY may inspect any and all documents held by the CONSULTANT
and relating to this Agreement upon good cause at any reasonable time within the six
(6) year period. The CONSULTANT also agrees to provide to the CITY, at the CITY'S
request, the originals of all drawings, documents, and items specified in this Section
Agreement for Professional Services AG-C-374
Page7of12
and information compiled in providing services to the CITY under the terms of this
Agreement.
13. CERTIFICATION REGARDING DEBARMENT, SUSPENSION, AND OTHER
RESPONSIBILITY MATTERS-PRIMARY COVERED TRANSACTIONS '
The prospective primary participant certifies to the best of its knowledge and
belief, that it and its principals:
(a) Are not presently debarred, suspended, proposed for debarment, declared
ineligible, or voluntarily excluded from covered transactions by any federal
department or agency;
(b) Have not within a three-year period preceding this proposal been convicted of
or had a civil judgment rendered against them for commission or fraud or a
criminal offense in connection with obtaining, attempting to obtain, or
performing a public (federal, state, or local) transaction or contract under a
public transaction; violation of federal or state antitrust statues or commission
of embezzlement, theft, forgery, bribery, falsification or destruction of records,
making false statements, or receiving stolen property;
(c) Are not presently indicted for or otherwise criminally or civilly charged by a
governmental entity (federal, state, or local) with commission of any of the .
offenses enumerated in paragraph "(b)" of this certification; and
(d) Have not within a three-year period preceding this application/proposal had
one or more public transactions (federal, state, or local) terminated for cause
or default.
Where the prospective primary participant is unable to certify to any of the
statements in this certification, such prospective participant shall attach an explanation
to this proposaL
Agreement for Professional Services AG-C-374
Page 8 of 12
I~_
14. TERMINATION OF AGREEMENT
This Agreement may be terminated by either party upon twenty (20) days written
notice to the other party, and based upon any cause. In the event of termination due to
the fault of other(s) than the CONSULTANT, the CONSULTANT shall be paid by the
CITY for services performed to the date of terminatian.
Upon receipt of a termination notice under the above paragraph, the
CONSULTANT shall (1) promptly discontinue all services affected as directed by the
written notice, and (2) deliver to the CITY all data, drawings, specifications, reports,
estimates, summaries, and such other information and materials as the CONSUL.TANT
may have accumulated, prepared or obtained in performing this Agreement, whether
completed or in process.
15. GENERAL PROVISIONS
15.1. This Agreement shall be governed by the laws, regulations and ordinances
of the City of Auburn, the State af Washington, King County, and where applicable,
Federal laws.
15.2. All claims, disputes and other matters in question arising out of, or relating
to, this Agreement or the breach hereof, except with respect to claims which have been
waived, will be decided by a court of competent jurisdiction in King County, Washington.
Pending final decision of a dispute hereunder, the CONSULTANT and the CITY shall
proceed diligently with the pertormance of the services and obligations herein.
15.3. In the event that any dispute or conflict arises between the parties while
this Agreement is in effect, the CONSULTANT agrees that, notwithstanding such
dispute or conflict, the CONSULTANT shall continue ta make a good faith effort to
cooperate and continue work toward successful completion of assigned duties and
responsibilities.
Agreement for Professional Services AG-C-374
Page 9 of 12
15.4. The CITY and the CONSULTANT respectively bind themselves, their
partners, successors, assigns, and legal representatives ta the other party to this
Agreement with respect to ail covenants to this Agreement. ,
15.5. This Agreement represents the entire and integrated Agreement between
the CITY and the CONSULTANT and supersedes all prior negotiations, representations
or agreements either oral or written. This Agreement may be amended only by written
instrument signed by both the CITY and the CONSULTANT.
15.6. Should it become necessary to enforce any term or obligation of this
Agreement, then all costs of enforcement including reasonable attomeys fees and
expenses and court costs shall be paid to the substantially prevailing party.
15.7. The CONSULTANT agrees to comply with all local, state and federal laws
.
applicable to its performance as of the date of this Agreement, ;
the
15.8. If any provision of this Agreement is invalid or unenforceable,
remaining provisions shall remain in force and effect.
15.9. This Agreement shall be administered by Lara Kammereck on behalf of
the CONSULTANT, and by the Mayor of the CITY, or designee, on behalf of the CITY.
Any written notices required by the terms of this Agreement shall be served on or
mailed to the following addresses:
City of Auburn Carollo Engineers, P.C.
Attn: Ryan Vondrak Attn: Lara Kammereck
25 W Main Street 1218 Third Avenue, Suite 1600
Auburn WA 98001 Seattle, WA 98101
Phone: 253.931.3086 Phone: 206.684.6532
Fax: 253.931.3053 Fax: 206.903.0419
E-mail: rvondrak@auburnwa.gov E-mail:lkammereck@carollo.com
15.10. All notices or communications permitted or required to be given under
this Agreement shall be in writing and shall be delivered in person or deposited in the
United States mail, postage prepaid. Any such delivery shall be deemed to have been
duly given if mailed by certified mail, return receipt requested, and addressed to the ~
Agreement for Professional Services AG-C-374
Page 10 of 12
address for the party set forth in 15.9 or if to such other person designated by a party to
receive such notice. It is provided, however, that mailing such notices or
communications by certified mail, return receipt requested is an option, not a
requirement, unless specifically demanded or otherwise agreed.
Any party may change his, her, or its address by giving notice in writing, stating
his, her, or its new address, to any other party, all pursuant to the procedure set forth in
this section of the Agreement.
15.11 This Agreement may be executed in multiple counterparts, each of which
shall be one and the same Agreement and shall became effective when one or more counterparts have been signed by each of the parties and
delivered to the other party.
Agreement for Professional Services AG-C-374
Page 11 of 12
CITY OF AUBURN
~
✓ Peter B. Lewis, Mayor
Date SEP 2 2009
ATTEST:
^ r ~
Dani le E. Daskam, City Clerk
APPROVED AS TO FORM:
r i
3 ,
~
Dani~~'I~B:~°HeW,Citjr_Attorney
C ENGI EERS, P.C.
BY:
Title: 32ta-~ 2. MA-c-so nj. NVOL-rME-a Federal Tax 0899222
BY:
Title: 1 E--'1j wI `w- I NS, P~2Tr-i~
- - - - - -
Agreement for Professional Services AG-C-374
Page 12 of 12
EXHIBIT A ,
SCOPE OF WORK
Exhibit A
Agreement No. AG-C-374
Page 1 of 1
EXHIBIT A
City of Auburn
Academy and Lakeland Hills Booster Pump Station Improvement
Project
SCOPE OF SERVICES
PROJECT OBJECTIVE
The City of Auburn has four major water service areas: a) Valley; b) Lea Hill; c) Academy, and
d) Lakeland Hills. The purpose of this project is to replace or improve the existing booster pump
stations in the Academy and Lakeland Hills service areas.
PROJECT BACKGROUND
The Academy service area currently serves approximately 2,684 Equivalent Residential Units
(ERUs) from two reservoirs (3.7 million gallons (MG)) that are supplied by the Academy Pump
Stations from Reservoir 1. The Janssen Addition Booster Pump Station supplies the boosted
zone in the Janssen Addition area. The pump station is a single pump facility with no reliable fire
flow or standby power capabilities. Additionally, the fire flow that is available does not meet the
current standards and is fed solely by gravity through a reverse check valve into the small-
elevated pressure zone.
The proposed Academy Booster Pump Station (ABPS) will replace the existing Janssen
Addition Pump Station with a new facility in a location to enhance operational and maintenance
activities and to provide adequate fire flow and meet domestic demand. The proposed station
will consist of a firm fire flow capacity with one stand-by pump to meet the fire flow demand
requirement of 1,500 gallons per minute (gpm) for two hours. Several sites are available in the
area that will be evaluated. The domestic demand will vary depending on the alternative
selected, as each alternative is a different boosted zone size. The facility must be easily
accessible and provide the abil ity for future expansion.
The Lakeland Hills service area serves approximately 1,718 ERUs from a single 1.0-MG at
grade reservoir supplied by finro groundwater wells. The boosted zone (Zone 5) is served by the
Lakeland Hills Booster Pump Station (LHBPS) located on the same property as the existing
storage reservoir. The LHBPS supplies both domestic and fire protection. There is a need for
additional storage within this pressure zone and the upgrade or replacement of the booster
pump station to meet fire flow demands. The new facilities must meet a fire flow demand of
3,125 gpm for three hours.
The proposed LHB PS will consist of a firm fire flow capacity with one stand-by pump to meet the
fire flow demand requirement of 3,125 gpm for three hours. The domestic pumping may be
increased to 750 gpm to account for increased customers and demand during peak conditions.
The facility needs to be evaluated to deter mine whether the pump station can be upgraded or
CAROLLO ENGINEERS SCOPE OF SERVICES- VERSION 7.1 PAGE 1 OF 46
8/26/09
pwlloco-pw-app:CazolblDocumentslClienflWAWubumllakeland Hills Pump StalbnWroJect ManagementlConVaclslExhibitA- Scope i
I
relocated to another site. A key element in the evaluation is determining the location of the
proposed reservoir.
PROJECT ASSUMPTIONS
1. Carollo Engineers, P.C. and its subconsultants and work performed by them will be
referred to as "ConsultanY" in this document.
2. The City of Auburn and its staff will be referred to as NCity" in this document.
3. The project will use WSDOT 2008 Standard S pecifications for Road, B ridge, and
Municipal Construction.
q. Project will use City of Auburn 2008 Contract Provis ions.
5. Technical Memoranda and related reports will be provided in five (5) hard copies and one
electronic copy as described in the individuat task scopes of work.
6. Meeting notes and related materials will be transmitted electronically via the project
website or by email.
7. Design Submittals including drawings and specifications will be provided as described in
the applicable task scopes of work.
8. The City will provide Autocad templates illustrating City standards for Consultant use.
9. The City will print and produce additional copies of all documents as necessary for its use.
10. The City shall arrange for access to and make all provisions for the Consultant to enter
upon public and private property as required for the Consultant to perform services
hereunder.
PROJECT CONSIDERATIONS '
1. The Consultant has no control over the cost of labor, materials, equi pment or services
furnished by others, or over the construction contractors' methods of determining prices,
or other competitive bidding or market conditions, practices or bidding strategies. Cost
estimates are based on the ConsultanYs opinion based on experience and judgment. The
Consultant cannot and does not guarantee that proposals, bids or actual Project
construction costs will not vary from cost estimates prepared by the Consultant.
2. The Consultant shall not be responsible for the means, methods, techniques, sequences,
or procedures of construction selected by the construction contractors or the safety
precautions and programs incident fo the work of the construction contractors and will not
be responsible for the construction contractors' failure to carry out work in accordance
with the Contract Documents.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 2 OF 46
8/26/09
pw;Noco-pw-app:CarolblDocumentslClientlWAwubumlLakeland Hllls Pump StationlProject ManagemenllGontractslExhibit A- Scope
3. The City shall furnish the Consultant available studies, reports and other data pertinent to
the Consultant's services and the Consultant shall be entitled to use and rely upon all
such information provided by the City or others in performing the ConsultanYs services.
TASK 100 - PROJECT MANAGEMENT
Manage the work of the project team from notice to proceed to project closeout. Plan for and
carry out regular communication with the City during the project. Plan for and carry out quality
management.
Subfask 101 Project /nitiation. Prepare a Project Management Plan (PMP) that describes
project roles and respon sibilities, lists contact information for the project team, describes
communications protocols, quality management, and that includes the scope of work, schedule,
and budget. The PMP will be introduced and discussed w ith the combined Consultant and City
project team at a Project Initiation Meeting. Establish and maintain a project website for City and
Consultant use as a repository of project documents and other information of general interest to
the project team. Documents such as reference documents, meeting agendas, notes, records of
comment, project calendar of upcoming events, Technical Memoranda, Reports, and similar
documents will be placed on the site for team use. Design deliverables such as drawings will not
be placed on the site.
Actlvities
1. Prepare a draft and final PMP for City review and use. The draft plan will be transmitted to
the City for review within five days of Notice to Proceed.
2. Organize and lead a Project Initiation Meeting on a schedule agreed to by the City. The
purpose of the Initiation Meeting (Workshop 101) is to introd uce project team members,
review and discuss the PMP, and discuss the project schedule, major activities,
deliverables, and com munications.
3. Revise the PMP after the Project Initiation Meeting and distribute it to the City.
4. Update the PMP once coincident with submittal of 90% level documents for the LHBPS to
reflect the transition to construction and other significant changes in the project plan.
5. Establish and maintain a project website.
City Input
. Schedule and provide location for Project Initiation Meeting.
. Review and comment on PMP.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 3 OF 46
8/26/09
pw 1locapw•app:CarollolDOCUmentslClienflWAWubum0.akeland HINs Pump StatlonlProject ManagemenAContracls\Ezhibii A- Scope
Assumptions
. The PMP will be updated finrice; once after City review of the draft PMP and once at the
midpoint of the project.
Deliverables
1. Draft PMP
2. First update PMP
3. Second update P MP
4. Project website
5. Agenda and notes for Project Initiation Meeting
Subtask 102 Project Management Meetings. Project management meetings will be
completed under this task to update the City on progress and management issues. Meetings will
be held at the Carollo offices. Agendas and meeting notes will be provided under this task to
assist in record keeping. A management decision log will also be developed and updated
monthly during the course of the Project.
Activities
1. Prepare agendas, m eeting notes, action item s, and decision log for project management
meetings. It is assumed that there will eighteen (18) 1-hour meetings at Carollo's offices.
City Input
. Attend meetings and review meeting notes and decision logs within three days of receipt.
Assumptions
. None.
Dellverables
1. Agendas, meeting notes, action items, and management decision log for eighteen (18)
meetings.
Subtask 103 Projecf Workshops. Project workshops will be completed under this task to
facilitate decision-making. Workshops will be held at the City of Auburn City Hall. Agendas and
meeting notes will be provided under this task to assist in record keeping. A decision log will
also be developed and updated monthly during the course of the Project.
1. Project workshops will be held as shown in the foltowing schedule. Prepare agendas and
meeting notes as well as meeting-related project information for each workshop.
Workshops will be 2 to 4 hours in length except as noted i n the task descriptions.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 4 OF 46
8/26/09
pw 1loco-pw•app:CarolblDaumentslCliertlWAWubumllakeland Hills Pump StationlPrpject ManagemenllContracislExhibR A- Scope
Task Workshop Title Workshop Objective
Number
101 Project Initiation Meeting Review PMP and introduce project team.
203-1 Alternatives Analysis Workshop #1 Review and confirm design criteria provided
by City.
Present alternatives analysis,evaluation
findings and select three alternatives f or
further evaluation.
203-2 Alternatives Analysis Workshop #2 Present alternatives analy sis evaluation
findings. Select recommended alternative.
501-1 30% Design Presentation, LHB PS Present and discuss 30% design submittal.
502-1 60% Design Presentation, LHB PS Present and discuss 60% design submittal.
503-1 90% Design Presentation, LHB PS Present and discuss 90% design submittal.
601-1 30% Design Presentation, ABPS Present and discuss 30% design submittal.
602-1 60% Design Presentation, ABPS Present and discuss 60% design submittal.
603-1 90% Design Presentation, ABPS Present and discuss 90% design submittal.
City Input
• Provide location for workshops.
Assum ptions
• None.
Deliverables
1. Agendas, presentation m aterials, meeting nvtes, and decisi on log for 9 workshops.
Subtask 104 Project Administration. Administer contracts and manage the project team.
Activities
1. Prepare and adm inister subcontracts with consultant team members.
2. Manage the project team to track time and budget, work elements accomplished, work
items planned for the next period, manpower, scope changes, time and budget needed to
complete this Scope of Services.
3. Prepare finrenty four (24) monthly project progress reports to accompany each monthly
invoice; identify accomplishments for the month, planned work next month, and identify
current or potential problems or changes. The reports will also include an Earned Value
report that shows numerical earned value based on project deliverable progress. The
report will also include a narrative describi ng progress measured against budget and
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 5 OF 46
8/26/09
pw.lloco-pw-app:CarolblDxumentslClientlWAWubumllakeland Hills Pump StationlProject ManagementlContraatslEuhibil A- Scope
schedule. In the event of schedule or budget lag, the report will indicate a plan to get the
project in line with the schedule and budget.
4. Create and maintain a working project schedule based on the schedule in the PM P.
Update the schedule at project milestones, up to nine (9) times, using a Microsoft Project
Gantt chart schedule, showing progress against a baseline establis hed in the PMP.
5. Prepare technical Record of Comment (ROC) documentation upon each milestone
submittal. Following receipt of Final ROC Responses on each submittal of the Project Log,
items that have been reviewed will become final decisions and will not be changed without
potential changes to ConsultanYs Scope, Schedule, and Budget.
Assum ptions
• The progress report will contain a summary of cost to date and remaining budget for each
major task.
• Schedule update will be included in the monthly progress report, and will account for all
activities and tasks defined in the Scope of Services including reviews by the City and
others.
City Input
. Receive, review, and process Consultant invoices in a timely manner.
Deliverab/es
1. 24 monthly progress reports, to include all elements described above.
2. ROC documentation as identified for each Task and Subtask.
TASK 200 - BASIS OF DESIGN REPORT
Basis of Design Report' (BODR) for each project to include identification of
Prepare a « ~
alternatives, alternatives analysis, the identification of the recommended alternative, preliminary
design, and updated pla nning level cost estimate.
Subfask 201 Review Existing Reports/Record Drawings. Obtain and review existing
documentation as may be available to establish existing conditions and visit project sites.
Activities
1. Organize and review available existing documentation including design drawings,
specifications, operational reports, utility bills, permits, environmental reports, and oth er
information provided by the City related to the project.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 6 OF 46
8/26/09
pw:1\oco-pw-app:CaroIlGDaumenlslClientlWAlAubum\Lakeland Hills Pump SlationlProject ManagementlCon7acfslEshibit A- Scope
2. Research existing util ity information to identify the location and character istics of existing
facilities within the project area as they may apply to identified alternative to be included in
the alternatives analy sis.
3. Evaluate and summarize existing data.
4. Visit the project sites once for familiarization.
5. Prepare a draft technical memorandum (TM) summarizing existing conditions (201.1).
6. Incorporate findings into the Basis of Design Report and Criteria ldentifica tion in Task 202.
City Input
• Provide all available relevant information.
• Assist the Consultant in eliminating data gaps. -
Assumptions
. The City will provide available information related to the project and as requested by the
Consultant in a timely manner.
• The Consultant will contact utility companies to obtain available information on existing
utilities in the project area.
. The City will provide access to the project sites for the ConsultanYs visit(s).
Deliverables
1. Draft TM 201.1, "Existing Conditions."
Subtask 202 ►dentify Criferia. Identify level of service and technical design criteria. Review
City design criteria and make recommendations for criteria that best fit the needs of the Project.
Activities
1. List level of service criteria based on the City's Comprehensive Water Plan.
2. Develop a list of proposed technical criteria based on City operational preferences and
industry standards.
3. Prepare a list of proposed criteria and transmit the list to the City. The City will review and
provide response on preferred criteria. Criteria will included, but not be limited to the
following.
. Flow characteristics, e.g. max day, peak day, peak hour, fire, .
. Reliability factors, redundancy,
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 7 OF 46
8126/09
pw \loco-pw-app:CarolblDocumentslClienllWAWuburnlLakeland HiNs Pump StationlProject ManagementlContraclsExhibit A- Scope
• Electrical power, voltage levels,
. Pump type, sizes and combinations,
. Building types, e.g. metal, CMU, ;
. Telemetry framework, e.g. radio, leased line, etc.
4. Research and coordinate with local utility companies to determine electrical power and
communications support requirements.
5. Prepare draft TM summarizing equipment and materials preferences, telemetry
architecture and operational requirem ents, and utility availability requirements.
6. Receive and respond to com ments in a Comment Response Log.
7. Incorporate selected criteria in Basis of Design Report, Task 204.
City Input ,
. Provide lists or descriptions of preferred equipment, materials, and architectural conce pts. • Coordinate with the City Building Department and review building codes.
• Coordinate with the local Fire Marshal on building requirements.
• Receive and review recommended criteria.
• Provide written response.
. Approve criteria.
Assumptfons
• City will review draft equipment, materials, and architectural criteria list and provide
preferred criteria.
• City will provide instrumentation and control criteria to the Cons ultant.
Deliverables
1. Draft TM 202.1 "Level of Service and Design Criteria."
2. Comment Response Log for TM.
3. Agenda and meeting notes for workshop.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 8 OF 46
8/26/09
, pw 1loco-pw-app;CarolblDocumentslClieatlWAWUbumllakeland Hills Pump StationlProject ManagemenflContracfslFxhibit A- Scope
Subtask 203 Identify, Evaluate, Reco mmend, Selecf, and Document Prefened
Alternatives. Use the existing hydraulic model developed for the Water Comprehensive Plan
Update, and results of Subtask 202 to identify and propose alternative project elements for both
the LHBPS and the ABPS. Work with the City to identify criteria, evaluate alternatives and m ake
recommendations for preferred alternatives to be carried fon+vard to design and construction.
Select the preferred alternative for each project and document the findings, incorporating resutts
of Tasks 201 and 202.
Activities
1. Assembte all available relevant information.
2. Convene a workshop (Workshop 203-1) to Identify alternative project elements for the
LHBPS and ABPS projects. Prepare and present a draft alternatives evaluation matrix.
The team will select three (3) alternatives for further evaluation.
3. Refine up to three (3) alternatives and complete an evaluation matrix comparing the
alternatives. Prepare a planning level estimate of probable construction costs, proposed
construction sequencing plan, proposed construction staging plan, proposed construction
schedule, anticipated facilities outage plan, and any permits necessary to complete the
final design and begin construction for each of three (3) alternatives.
4. Convene a workshop (Workshop 203-2) to present findings on the three alternatives and
select a recom mended proj ect for each site.
5. Prepare a draft TM 203.1 Alternatives Evaluation and Basis of Design incorporating
results of Tasks 201, 202, and 203.
6. Respond to City comments.
7. Prepare a Final T M 203.1 incorporating the City's comments. This document will become
the basis of design.
8. Log decisions in ROC Log.
9. Authorize field investigations for the preferred alternatives.
Clty Input
• Provide staff and location for project workshops.
. Review and comment on project deliverables.
. Select preferred alternative from alternatives evaluated.
. Authorize field investigations.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 9 OF 46
8/26/09
pw:l\ao-pw-app:CaroaolDocumenlslCliennWAWuburnlLakeland Hills Pump Sta6oolProjecl ManagementContractslExhiblt A- Scope
Assum ptlons
• Workshops 203-1 and 203-2 comprise alternatives selection for both the Academy and
Lakeland H ills service areas.
• TM 203.1 "Alternatives Evaluation and Basis of Design will include design criteria and the
results of alternatives analyses. The TM will be the basis of design.
Deliverab/es
1. Draft TM 203.1 "Alternatives Evaluation and Basis of Design."
2. Final TM 203.1 "Alternatives Evaluation and Basis of Design."
3. Record of Comment Log update.
4. Agenda and meeting notes for three (3) workshops.
TASK 300 - FIELD INVESTIGATION _
Complete field investigations near th e beginning of the project to reflect the most recently
collected field data. Coordinate data collection between the City and Consultant staff. Complete
survey and geotechnical work on the recommended alternative site and pipeli ne alignments.
Subtask 301 Lakeland Hills Survey Services. Perform field survey and mapping services for
selected LHBPS, future reservoir sites, and related pipelines.
Activities
1. Perform property research and complete field survey and mapping at the selected project
site, suitable for design and construction docum ents. Establish horizontal controls and
provide information for construction documents. Set project benchmarks. Stake property
and easement boundaries.
City lnpuf
• City will obtain rights of entry.
. City will locate and mark utilities before survey.
. City will perform all property acquisition including appraisal, negotiations, and recording of
final documents.
Assum ptions
• Survey work will begin based on authorization as a result of selection of the preferred
alternative by the City.
CAROLLO ENGINEERS SCOPE OF SERVIGES - VERSION 7.1 PAGE 10 OF 46
8/26/09
pw:lloco-pw-app:CarolblDocumenlslClientlWAWuburn0.akeland HGIs Pump StationlProject ManagementlContraclsExhibit A- Scope
. Datum is City of Auburn current datu m.
. One pump station site is included in the survey.
. Pipelines may be located either in street rights of way or in easements.
• Pipelines may be up to a total of 1,000 linear feet.
• Surveyor will obtain horizontal and vertical control information.
. Survey will include all trees with trunk diameters greater than 4-inches.
. Sunrey will include all surface improvements and utilities to the limits of street rights of
way as appropriate for pump stations and pipelines.
• Sunrey for pipelines in easements will include all surface improvements and utilities within
30-feet either side of the proposed easem ent centerline.
• Surveys for pump station site will include all surface improvements and topography for the
site and 40-feet outside the site boundaries.
• Locate and include geotechnical borings in base mapping.
. Topographic survey will be to 1-foot contour interval accuracy.
• Surface and invert elevations for all existing gravity stormwater and sewage systems
manholes and catch basins w ithin 200-feet of pump station and reservoir sites w ill be
surveyed and included in mapping.
. Project vertical control points (2) w ill be established at each site and along each pipeline
alignment.
• Property boundaries will be staked.
• Survey documents will be recorded.
• No Surveying is required inside of buildings.
• Prepare base maps in Autocad 2006.
. Mapping and related pla ns will comply with Aubum Design Standards.
Deliverables
7. Base mapping for LHBPS site.
2. Base mapping pipeline alignment.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 11 OF 46
8/26/09
pw:Noco-pw-app:CarolblDocumantslClienflWAVwbumlLakeland Hills Pump StationlProject ManagementlContractslExhibft A- Scope
Subtask 302 Lakeland Hifls Geafechnical lnvestigation. Complete field exploration,
geotechnical analysis, and a Geotechnical Interpretive Report for design of the LHBPS and
associated pipelines.
Acf)vities
1. Prepare an exploration and traf fic control plan and provide the plan for review and
approval by the City prior to scheduling and completing fieldwork.
2. Retain a driller, provide field supervision and traffic control, and perform field exploration
and laboratory geotechnical services in support of design of LHBPS and pipelines.
3. Coordinate and supervise geotechnical borings at the pump station site for purposes of
determining foundation and groundwater conditions relevant to the design.
4. Coordinate and supervise geotechnical borings along the pipeline alignment.
5. Conduct laboratory tests to ascertain geatechnical engineering proper ties of the soil in the
construction zones for the pump station and pipelines. Control and dispose of drilling and
laboratory waste.
6. Interpret geotechnical conditions and make recommendations for foundation support,
trenching, trench support, dewatering, excavation, pipe bedding, backfill, compaction and
restoration.
7. Prepare draft Geotechnical Interpretive Report.
8. Receive and respond to com ments.
9. Assist the design team by answering questions during design; allow 10 man-hours for
telephonic and written consultation.
10. Prepare final Geotechnical Interpretive Report.
City Input
. City will obtain rights of entry.
Assum ptions
. Geotechnical work will begin on authorization of the City resulting from selection of the
preferred alternative.
• Rights of entry and street use permits provided by the City. . Boring locations are accessible to truck-mounted drill rigs.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 12 OF 46
8/26/09
pwlloco-pw-app:Caro11o1DocumentslCfientlWAV+uburnLLakeland Hills Pump S1aUonlProject ManagemendContractslEnhibit A- Scope
• Borings will be backfilled with bentonite chips and site restoration is limited to concrete
patches in roadways. Some surtace disturbance will be required at Pump Station sites
and is acceptable to the Owner. ,
• Utilities on private property are located by the City.
• Drill cuttings will be drummed and disposed of off-site.
• One borehole at the pum p station site.
• One borehole at the beginning, end, and every 500-linear feet along pipeline alignments,
up to 1,000 linear fest, or a total of up to three (3) boreholes.
• No Phase I or Phase II environm ental analyses for contaminated soils will be performed
prior to fieldwork. Provisions will be made for field screening, sam pling, drumming,
profiling, and disposal of hazardous materials if encountered in the dri11 holes.
Deliverab/es
1. Field exploration and traffic plan lakeland Hills Boaster Pump Station and pipeline sites.
2. Field and laboratory reports.
3. Draft Geotechnical Interpretive Report, Lakeland Hills Booster Pump Station and
Associated Pipelines, 4. Comment responses.
5. Final Geotechnical Interpretive Report, Lakeland Hills Booster Pump Station and
Associated Pipelines.
Subfask 303 Optlona/ Servlces. Provide optional services upon written authorization by the
City for LHBPS site. Prepare proposed scope of work, schedule, and budget for review and
approval by the City. Optional services may include the following activities.
Activities
1. Perform background noise study at pump station sites for purpose of determining ambient
noise levels relative to increases in noise related to construction equipment and
permanently installed equipment.
2.. Provide Ambient Noise Report and recom mendations for sound attenuation m easure that
may be required for both construction and permanently installed equipment.
3. If hazardous materials are encountered during geotechnical exploration, obtain sam ples,
analyze samples in accordance w ith Washington State regulati ons, and notify Owner.
Control and dispose of drilling and laboratory waste.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 13 OF 46
8/26/09
pw:\laco-pw-app:CarollolDocumenlslClientlWA%AubumlLakeland Hills Pump StationlProject ManagemenpConVactslExhibif A-Scope
City Input
. Review scope, budget, and schedule.
. Authorize work.
Assumptions
. Ambient noise measures consist of one weekday and one-weekend day measurements
for 24 consecutive hours on each of two days.
Deliverables
1. Ambient Noise Levei Report and Noise Control Recommendations.
2. Hazardous materials lab analysis.
Subtask 304 Academy Booster Pump Stativn Survey Services. The Consultant will perform
field survey and mapping services for selected ABPS site and related pipel ines.
Actlvfties
1. Perform survey and mapping at selected project sites, suitable for design and construction
documents. Establish horizontal controls and provide information for construction
documents. Set project benchmarks. Stake property and easement boundaries.
Cify lnput
. City will obtain rights of entry.
. City will locate and mark utilities before survey.
. City will perform all property acquisition including appraisal, negotiations, and recording of final documents.
~ Assum ptlons
• Survey work will begin based on authorization as a result of selection of the preferred
alternative by the City.
. Datum is City of Auburn current datu m.
• One pump station site is included in the survey.
. Pipelines may be located either in street rights of way or in easements.
. Pipelines may be up to a total of 2,500 linear feet.
. Surveyor will obtain horizontal and vertical control information.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 14 OF 46
8/26/09
pvr\bco-pw-app:CarollolDceumentslClientlWAV+ubum~lakeland Hills Pump StationlProject ManagementlContractslExhibit A- Scope
. Survey wiil include all trees with trunk diameters greater than 4-inches.
. Survey will inctude all surface improvements and utilities to the limits of street rights of
way as appropriate for pump stations and pipelines.
. Survey for pipelines in easements will include all surface improvements and utilities within
30-feet either side of the proposed easem ent centerline.
. Surveys for pump station site will include all surface improvements and topography for the
site and 40-feet outside the site boundar ies in accordance with City design standards.
. Locate and include geotechnical borings in base mapping.
. Topographic survey will be to 1-foot contour interval accuracy. . Surface and invert elevations for all existing gravity stormwater and sewage systems
manholes and catch basins w ithin 200-feet of pump station and reservoir sites w ill be
surveyed and included in mapping.
. Project vertical control points (2) w ill be established at each si te and along each pipeline
alignment.
. Property boundaries will be staked.
. Survey documents will be recorded.
. No Surveying is required inside of buildings.
. Prepare base maps in Autocad 2006.
. Mapping and related plans will comply with Auburn Design Standards.
Deliverables
1. Base mapping for ABPS site.
2. Base mapping pipeline alignment.
Subtask 305 Academy Booster Pump Station Geotechnical Investigatfon. Consultant will
complete field exploration, geotechni cal analysis, and a Geotechnical Interpretive Report for
design of the ABPS and associated pipelines.
Activifies
1. Prepare an exploration and traf fic control plan and provide the plan for review and
approval by the City prior to scheduling and completing fieldwork.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 15 OF 46
8/26/09
pw.Uoco-pw-app:CarollolDceumenls\ClienQWAlAubum\Lakeland Hllls Pump SlatbnlProJecl ManagemenllContractslExhibA A- Scope
2. Retain a driller, provide field supervision and traffic control, and perform field exploration
and laboratory geotechnical services in support of design of ABPS and pipelines.
3. Coordinate and supervise geotechnical borings at the pump station site for purposes of
determining foundation and groundwater conditions relevant to the design.
4. Coordinate and supenrise geotechnical borings along the pipeline alignment.
5. Conduct laboratory tests to ascertain geotechnical engineering proper ties of the soil in the
construction zones for the pump station, reservoir, and pipeli nes. Control and dispose of
drilling and laboratory waste.
6. Interpret geotechnical conditions and make recommendations for foundation support,
trenching, trench support, dewatering, excavation, pipe bedding, backfill, compaction and
restoration.
7. Prepare draft Geotechnical Interpretive Report.
8. Receive and respond to com ments.
9. Assist the design team by answering questions during design; allow 10 man-hours for
telephonic and written consultation.
10. Prepare final Geotechnical Interpretive Report.
City Input
. City will obtain rights of entry.
Assum ptions
. Geotechnical work will begin on authorization of the City resulting from selection of the
preferred alternative.
. Rights of entry and street use permits provided by the City.
. Boring locations are accessible to truck-mounted drill rigs.
. Borings will be backfilled with bentonite chips and site restoration is limited to concrete
patches in roadways. Some surface disturbance will be required at Pump Station sites
and is acceptable to the Owner.. Utilities on private property are located by the City.
. Drill cuttings will be drummed and disposed of off-site.
. One borehole at the pum p station site.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 16 OF 46
8/26/09
pw,\\oco-pw-app:CarolloWocumentslClianflWAWubumlLakeland Hills Pump StationlProject ManagemennContraclslEOibil A- Scope
• One borehole at the beginning, end, and every 500-linear feet along pipeline alignments,
up to 2,500 linear feet, or up to six (6) boreholes.
. No Phase I or Phase II environmental analyses for contaminated soils will be performed
prior to fieldwork. Provisions will be made for field screening, sam pling, drumming,
profiling, and disposal of hazardous materials if encountered in the drill holes.
Deliverab/es
1. Field exploration and traffic plan Academy Booster Pump Station and pipeline sites.
2. Field and laboratory reports.
3. Draft "Geotechnical Interpretive Report, Academy Booster Pump Station and Associated
Pipelines."
4. Comment responses.
5. Final "Geotechnical Interpretive Report, Academy Booster Pump Station and Associated
Pipelines."
Subtask 306 Optional Services. Provide optional services upon written authorization by
the City for the ABPS site. Prepare proposed scope of work, schedule, and budget for review
and approval by the City. Optional services may include the following activities.
Activities
1. Complete title search, mark property corners, and file record of survey for one (1) new
parcel acquired by the City to support property acquisition process.
2. Pertorm background noise study at pump station site for purpose of determining ambient
noise levels relative to increases in noise related to construction equipment and
permanently installed equipment.
3. Provide Ambient Noise Report and recom mendations for sound attenuation m easure that
may be required for both construction and permanently installed equipment.
4. If suspected hazardous materials are encountered during geotechnical exploration, obtain
samples, analyze samples in accordance with Washington State regulations, and notify
Owner. Control and dispose of drilling and laboratory waste.
City Inpuf
• Review scope, budget, and schedule.
• Authorize work:
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 17 OF 46
8/26/09 pwlloco-Dw•app:CarollolDocumentslClientlWAlAubumU.akeland Hllls Pump StationlProject ManagemenriContractslExhibil A- Scope
Assum ptions
• Ambient noise measures consist of one weekday and one-weekend day measurements
for 24 consecutive hours on each of iwo days.
Deliverables
1. Record of Survey and Legai Description for one (1) new parcel.
2. Ambient Noise Level Report and Noise Control Recommendations.
3. Hazardous materials lab work.
TASK 400 - LAND ACQUISITION AND PUBLIC INFORMATION
ASSISTANCE
Provide land acquisition and public information assistance beginning coincident with Task 200
and continuing through construction. Assist in acquiring permits as described. Subtask 401 Lakeland Hills Pump Station Land Acquisition. Assist the City in acquisition of
land.
Activities
1. Identify land acquisition requirements for alternatives including parcel size and location as
part of Subtask 203.
City Input
• Negotiation and finalize land acquisition.
Assumptions
. The City will appraise, negotiate, and acquire all land.
DelPverables
1. None.
Subtask 402 Lake/and Hills Public Outreach Assistanc e. Provide information materials in
support of the City's public outreach program and meetings with City council or committees
during all phases of the project as required.
Actfvities
1. Prepare conceptual el evation drawings in 3D for use during alternatives analy ses and for
public information and/or council meetings. Assume two elevations are prepared showing
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 18 OF 46
8/26/09
pw:llao-pw-app:CarollolDocumentslClientlWAWubum\Lakeland Hflls Pump StationlProject ManagemenflConUacLslExhibit A- Scope
the pump station from two directions including surrounding surface features. Drawings will
be presented on display boards appropriate for use in public meetings.
2. Prepare graphics that illustrate alternatives considered for use during public information
meetings. Assume finro graphics presented as display boards.
3. Prepare for and attend meetings.
City Input
• Arrange for and coordinate public or council meetings.
Assum ptions
. There will be one (1) public outreach event to include P ublic Works Committee or Council
Meeting, Public Open House meetings, Homeowners' meetings.
. The City will plan, schedule, and facilitate public outreach activities.
• The Consultant will provide technical assistance, presentation materials, and present
materials during the activi ties.
Deliverables
1. Graphics as des cribed.
Subtask 403 Academy Booster Pump Station Land Acquisition. Assist the City in
acquisition of land.
Activities
1. Identify land acquisition requirements for alternatives including parcel size and location as
part of Subtask 203. .
City Mpuf
. Negotiation and finalize land acquisition.
Assum ptions
• The City will appraise, negotiate, and acquire all land.
Deliverables
1. None. ,
Subtask 404 Academy Booster Pump Station Public Outreach Asslstance. Provide
information materials in support of the City's public outreach program and meetings with City
council or committees during all phases of the project as required,
CAROLLO ENGtNEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 19 OF 48
8/26/09
pw:lNocp-pw-app:CarollolDxumentslCliantlWAlAubumlLakeland HNIs Pump SlatlonlProject ManagemenflConVacb{Fxhibit A-Scope
Activities
1. Prepare conceptual el evation drawings in 3D for use during alternatives analy ses and for
public information and/or council meetings. Assume two elevations are prepared showing
the pump station from two directions including surrounding surface features. Drawings will
be presented on display boards appropriate for use in public meetings. '
2. Prepare graphics that illustrate alternatives considered for use during pub lic information
meetings. Assume two graphics presented as display boards. ,
3. Prepare for and attend public or cou ncil meetings.
Cify Input
. Arrange for and coordinate meetings.
Assumptions ;
. There will be one (1) public outreach events to include Pub{ic Works Committee or .
Council Meeting, Public Open House meetings, Homeowners' meetings. '
• The City will plan, schedule, and facilitate public outreach activities.
. The Consultant will provide technical assistance, presentation materials, and present
materials during the activities.
Deliverables
1. Graphics as described.
TASK 500 - LAKELAND HILLS CONSTRUCTION DOCUMENTS
Prepare design and construction docum ents for the LHBPS and associated pipel ines. Prepare
submittals for review by the City at the 30%, 60%, 90%, and Bid Documents stages of design '
completion. The City will provide design guidelines for instrumentation design.
Perform internal quality management during preparation of documents, and provide a formal,
internal, coordinated review prior to submittal of the 90% documents.
Prepare and subm it probable esti mates of construction cost with three (3) subm ittals, and an
Engineer's Estimate with the Bid Documents.
Provide an electronic Microsoft Excel spreadsheet comment response form to record Consultant
response to City comments made on drawings. Respond in writing to written comments that
require discussion or elaboration using the Excel form. Provide hard copy and electronic form
responses to the City. Update the ROC throughout the construction document preparation
process. '
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 20 OF 46
8/26/09
pw.llao-pw-app:CarolblDocumentslCliennWAV+ubumllakeland Htlls Pump StationlProjecl ManagementlConVactslFxhibit A- Scope
Subtask 501 Lakeland Hills Booster Pump Station 30% Plans, Specifcations and
Estimate (PS&E) Submittal. Prepare 30% completion level drawings and specifications based
on the selected alternative resulting from Task 2.
Acfivities
1. Complete and incorporate field investigations, Task 300, including survey and
geotechnical exploration.
2. Prepare drawings and specifications in accordancewith the Design Submittal
Requirements, Exhibit A to this Scope.
3. Prepare two (2) conceptual elevations in 3D illustrative format. Elevations will include finro
exterior elevations. 4. Prepare presentation m aterials based on 3D i Ilustrations and site plans for use at one
Public Outreach meeting for LHBPS.
5. Prepare probable estim ate of construction cost at a level commensurate with the
completion level of the design documents.
6. Prepare and transm it submittat documentation.
7. Coordinate and facilitate a design workshop (Workshop 501-1) within five working days of
the 30% submittal to brief selected City staff on elements of the design and answer initial
questions.
8. Review City comments on the subm ittal and respond in writing to comments within five
working days of receipt of comments.
9. Update the ROC.
City Input
• Receive and transmit design submittal documents to City staff for review.
. Manage and coordinate comments on submittal documents prior to transmittal to the
Consultant.
. Comment on the design submittal according to the agreed schedule i n the spreadsheet
comment response form.
. Arrange for appropriate City staff to attend the design review workshop, I
` Assumptions
. Completion level of documents at each submittal is listed in Attachment A, Design
Submittal Requirements, attached to this Scope of Work.
GAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 21 OF 46
8/26/09
pw:Noco-pw-app:CaroBolDocumentslCliennWAWubumlLakeland Hills Pump SlationlProject Mana9ementlContraclsExhlbitA- Scope
. The City will provide design guidelines for instrumentation and controls design.
. The Consultant's instrumentation design will supplement the City-provided guidelines,
resulting in a contractor-designed instrumentation system and will be based on inclusion
of the following elements:
- Control Strategies
- Instruments - System panels and enclosures
- PLC Hardware requirements
- Wireless Communication (if applicable)
- PLC Software requirements
- Instrument Schedules
- InpuUOutput (I/O) List '
- Testing, Calibration, C ommissioning
. The City's sole source contractor will design the instrumentation and controls system
based on the City's guidelines and the ConsultanYs specifications.
. 3D illustrations will be in 24x36 inch format.
. Five, Full size sets of drawings in 24x36 inch hard copy format, staple-bou nd, and one (1)
electronic copy as an Adobe Acrobat ".PDF file.
. Five sets of Specifications will be in 8,5x11 page format, comb-bound and one *.PDF file.
Deliverables
1. 30% level design documents.
2. Two (2) 3D illustrations.
3. Written response to com ments.
4. ROC update.
5. Agenda, meeting notes for one design review workshop.
Subtask 502 Lakeland Hills Booster Pump Staflon 60% PS&E Submittal. Prepare 60%
completion level drawings and specifications based on the results of the 30% review. A
technical review workshop to discuss initial comments and questions on the 60% PS&E
submittal.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 22 OF 46
8/26/09
pw:lloco-pw-app:Carollo\DocumenlslClientlWAlAubumllakeland Hills Pump StalionlProJecl ManagemennContractsEchibit A- Scope
Activities
1. Prepare a TM, 503.1 "60% Design Transmittal" summarizing design changes since the
30% submittal and review including the comment log to show how the Consultant has
responded to comments and how the design has progressed.
2. Prepare drawings and specifications in accordance with the Design Submittal
Requirements, Exhibit A to this Scope.
3. Prepare probable estim ate of construction cost at a level commensurate with the
completion level of the design documents.
4. Prepare and transm it submittal documentation.
5. Coordinate and facilitate a design workshop (Workshop 502-1 ) within five working days of
the 60% submittal to brief selected City staff on elements of the design and answer initial
questions.
6. Review City comments on the submittal and respond in writing to comments within five
working days of receipt of comments.
7. Update the ROC.
Clty Input
• Receive and transmit design submittal documents to City staff for review.
. Manage and coordinate comments on submittal documents prior to transmittal to the
Consultant.
• Comment on the design submittal according to the agreed schedule i n the spreadsheet
comment response form.
. Arrange for appropriate City staff to attend the design review workshop.
Assum ptions
. Completion level of documents at each submittal is listed in Attachment A, Design
Submittal Requirements, attached to this Scope of Work.
• Five sets of Full size drawings in 24x36 inch hard copy format, staple bound and one (1)
electronic copy as an Adobe Acrobat *.PDF file.
. Five sets of Specifications will be in 8.5x11 page format, comb-bound and one'.PDF file.
Deliverab/es
1. TM 503.1 "60% Design Transmittal."
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 23 OF 46
8/26/09
pw;lloco-pw-app:CarolblDocumentslClientlWAlAuburnlLakeland Hills Pump SlatbnlProjecl ManagemennConUactslExhibit A- Scope
2. 60% level design documents.
3. Written response to com ments.
4. ROC update.
5. Agenda, meeting notes for one design review workshop.
Subfask 503 Lakeland Hills Booster Pump Station 90% PS&E Submitfal. Prepare 90%
completion level drawings and specifications based on the results of the 60% review. A
technical review workshop to discuss initial comments and questions on the 90% PS&E
submittaL
Activities
1. Prepare a TM, 503.1 "90% Design Transmittal" summarizing design changes since the
60% submittal and review including the comment log to show how the Consultant has
responded to comments and how the design has progressed.
2. Prepare drawings and specifications in accordance with the Design Submittal
Requirements, Exhibit A to this Scope.
3. Prepare probable estim ate of construction cost at a level commensurate with the
completion level of the design documents.
4. Perform formal internal coordinated check of documents to determine that documents
meet design intent, C ity of Auburn Design Standards, standards of the industry, City staff
equipment and materiats preferences, are consistent w ith the specifications and are
othenNise ready-for bid.
5. Prepare and transm it submittal documentation.
6. Coordinate and facilitate a design workshop (Workshop 503-1) within five working days of
the 90% submittal to brief selected City staff on elements of the design and answer initial
questions.
7. Review City comments on the submittal and respond in writing to comments within five
working days of receipt of comments.
8. Update the ROC.
City Input
• Receive and transmit design submittal documents to City staff for review.
. Manage and coordinate comments on submittal documents prior to transmittal to the
Consultant.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 24 OF 46
8/26/09
pw:\loco-pw-app:CerollolDocumentslClfenflWAV+ubumlLakeland Hllls Pump SlalfonlProject ManagemenflContractslEzhibit A- Scope
,
• Comment on the des ign submittal according to the agreed schedule i n the spreadsheet comment response form.
. Arrange for appropriate City staff to attend the design review workshop.
Assumptions
• Completion level of documents at each submittal is listed in Attachment A, Design
Submittal Requirements, attached to this Scope of Work.
• Five sets of full size drawings in 24x36 inch hard copy format, staple-bound, and one (1)
electronic copy as an Adobe Acrobat *.PDF file.
• Five full size sets of Specifications will be in 8.5x11 page format, comb-bound and one
".PDF file.
Deliverab/es
1. TM 503.1 "90% Design Transm ittal."
2. 90% level design documents. •
3. Written response to com ments.
4. ROC update.
5. Agenda, meeting notes for one design review workshop.
Subtask 504 Lakeland Hills Booster Pump Staflon Bid Documents. Prepare Bid Documents
comprising plans and specifications based on the results of the 90% design review.
Activities
1. Prepare drawings and specifications in accordance with the Design Submittal
Requirements, Exhibit A to this Scope.
2. Prepare Engineer's Estimate for transmittal to the City Clerk prior to bid opening.
3. Prepare and tra nsmit submittal documentation.
City Inpuf
• Review Bid Documents for City approval and printing.
Assum ptions
. City will prepare the Bid Advertisement and Bid Proposal package.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 25 OF 46
8/26/09
pw:\bco-pw-app:CarolbWocumentslClienflWAWubumlLakeland Hills Pump SUUOnIProject ManagamenllConVactsExhibit A- Scope
. Completion levei of documents at each submittal is listed in Attachment A, Design
Submittal Requirements, attached to this Scope of Work.
. One Full size set of original drawings will be in 24x36 inch 4-m il mylar copy format,
unbound.
. One set of Bid Document specifications, unbound hard copy and one electronic copy in
Adobe Acrobat ".PDF format.
Deliverables
1. Bid Documents.
2. Engineer's Estimate.
TASK 600 - ACADEMY BOOSTER PUMP STATION CONSTRUCTION '
DOCUMENTS Prepare design and construction docum ents for the ABPS and associated pipelines. Prepare
submittals for review by the City at the 30%, 60%, 90% and Bid Documents stages of design
completion. The City will provide design guidelines for instrumentation design.
Perform internal quality management during preparation of documents, and provide a formal, internal, coordinated review prior to submittal of the 90% documents.
Prepare and subm it probable esti mates of construction cost with three (3) subm ittals, and an
Engineer's Estimate with the Bid Documents.
Provide an electronic Microsoft Excel spreadsheet comment response form to record Consultant
response to City comments made on drawings. Respond in writing to written comments that
require discussion or elaboration using the Excel form. Provide hard copy and electronic form
responses to the City. Update the ROC throughout the construction docum ent preparation
process.
. Subtask 601 Academy Booster Pump Station 30% PSBE Submiifal. Prepare 30%
completion level drawings and specifications based on the selected alternative resulting from
Task 2.
Activities
1. Complete and incorporate field investigations, Task 300, survey, geotechnical exploration,
and environmental site assessment.
2. Prepare drawings and specifications in accordance with the Design Submittal
Requirements, Exhibit A to this Scope.
3. Prepare two (2) conceptual exterior elevations i n 3D illustrative format.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 26 OF 46
8/26/U9
pw:lWcapw-app:CazdblDocuments\ClientlWAV+ubum\Lakeland Hills Pump StaUonlProject ManagemenflContractsl6ihibit A- Scope
4. Prepare presentation m aterials based on 3D i Ilustrations and site plans for use at one
Public Outreach meeting for ABPS.
5. Prepare probabte estim ate of construction cost at a level commensurate with the
completion level of the design documents.
6. Prepare and transm it submittal documentation.
7. Coordinate and facilitate a design workshop (Workshop 601-1) within five working days of
the 30% submittal to brief selected City staff on elements of the design and answer initial
questions.
8. Review City comments on the subm ittal and respond in writing to comments within five
working days of receipt of comments.
9. Update the ROC. '
CJty /nput
• Receive and transmit design submittal documents to City staff for review.
• Manage and coordinate comments on submittal documents priorto transmittal to the
Consultant.
• Comment on the design submittal according to the agreed schedule i n the spreadsheet
comment response form.
• Arrange for appropriate City staff to attend the design review workshop.
Assum ptions
. Completion level of documents at each submittal is listed in Attachment A, Design
Submittal Requirements, attached to this Scope of Work.
• The City will provide design guidelines for instrumentation and controls design.
. The ConsultanYs instrumentation design will supplement the City-provided guidelines,
resulting in a contractor-designed i nstrumentation system and will be based on i nclusion
of the following elements:
- Control Strategies
- Instruments
- System panels and enclosures
- PLC Hardware requirements
- Wireless Communication (if applicable)
- PLC Software requirements
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 27 OF 46
8/26/09
pwUaco-pw•app:Carollo\DocumentslCllenflWAlAuburnllakeland Hills Pump StatbnWrojecl ManagemeMConVactsExhibil A -Scope
- instrument Schedules
- InpuUOutput (I/O) List
- Testing, Calibration, C ommissioning
. The City's sole source contractor will design the instrum entation and controls system
based on the City's guidelines and the ConsultanYs specifications.
. Submittals will include five (5) hard copies and one (1) electronic copy in Adobe Acrobat
*.PDF format.
. 3D illustrations will be in 2436 inch format.
. Five sets of full size drawings in 2436 inch hard copy format, staple-bound, and one (1)
electronic copy as an Adobe Acrobat *.PDF file.
. Five sets of Specifications in 8.5x11 page format, comb-bound and one *PDF file.
Deliverables
1. 30% level design documents.
2. Two (2) 3D, board illustrations.
3. Written response to com ments.
4. ROC update.
5. Agenda, meeting notes for one design review workshop.
Subtask 602 Academy Booster Pump Station 60% PS&E Submittal. Prepare 60%
completion level drawings and specifications based on the results of the 30% review. A
technical review workshop to discuss initial comments and questions on the 60% PS&E
submittaL
Activities
1. Prepare a TM, 603.1 "60% Design Transmittal summarizing design changes since the
30% submittal and review including the comment log to show how the Consultant has
responded to comments and how the design has progressed.
2. Prepare drawings and specifications in accordance with the Design Submittal
Requirements, Exhibit A to this Scope.
3. Prepare probable estim ate of construction cost at a level commensurate with the
completion level of the design documents.
4. Prepare and transm it submittal documentation.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 28 OF 46
8/26/09
pw.lWco-pw-app:CarollolDocurtmnts\ClientlWAlAUburn\Lakeland Hills Pump StalanlProject ManagemenflConbaclsExhibit A- Scope
5. Coordinate and facilitate a design workshop (Workshop 601-1) within five working days of
the 60% submittal to brief selected City staff on elements of the design and answer initial
questions.
6. Review City comments on the submittal and respond in writing to comments within five
working days of receipt of comments.
7. Update the ROC.
City Input
• Receive and transmit design submittal documents to City staff for review.
• Manage and coordinate comments on submittal documents prior to transmittal to the
Consultant.
• Comment on the des ign submittal according to the agreed schedule i n the spreadsheet
comment response form.
. Arrange for appropriate City staff to attend the design review workshop.
Assumptions
• Completion level of documents at each submittal is listed in Attachment A, Design
Submittal Requirements, attached to this Scope of Work.
. Submittals will include five (5) hard copies and one (1) electronic copy in Adobe Acrobat
*.PDF format.
• Five sets of full size Drawings in 2406 inch hard copy format, staple-bound, and one (1)
electronic copy as an Adobe Acrobat *.PDF file.
. Five sets of Specifications will be in 8.5x11 page format, comb-bound and one *.PDF file.
Deliverables
1. TM 603.1 "60% Design Transmittal."
2. 60% level design documents.
3. Written response to com ments.
4. ROC update.
5. Agenda, meeting notes for one design review workshop.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 29 OF 46
8/26/09
pw:lloco-pw•app:CarolblDaumentslClienllWAWubumllakaland Hills Pump StationlProjecl ManagemenllContractslFachibit A• Scope
Subtask 603 Academy Booster Pump Stafion 90% PSBE Submitfal. Prepare 90%
completion level drawings and specifications based on the results of the 60% review. A
technical review workshop to discuss initial comments and questions on the 90% PS&E
submittal.
Activifies
1. Prepare a TM, 603.1 "90% Design Transmittal" summarizing design changes since the
60% submittal and review including the comment log to show how the Consultant has
responded to comments and how the design has progressed.
2. Prepare drawings and specifications in accordance with the Design Submittal
Requirements, Exhibit A to this Scope.
3. Prepare probable estim ate of construction cost at a level commensurate with the
completion level of the design documents.
4. Perform formal internal coordinated check of documents to determine that documents
meet design intent, C ity of Auburn Design Standards, standards of the industry, City staff
equipment and materials preferences, are consistent w ith the specifications and are
otherwise ready for bid.
5. Prepare and transm it submittal documentation.
6. Coordinate and facilitate a design workshop (Workshop 603-1) within five working days of
the 90% submittal to brief selected City staff on elements of the design and answer initial
questions.
7. Review City comments on the subm ittal and respond in writing to comments within five
working days of receipt of comments.
8. Update the ROC.
City Input
. Receive and transmit design submittal documents to City staff for review.
. Manage and coordinate comments on submittal documents prior to transmittal to the
Consultant.
. Comment on the design submittal according to the agreed schedule i n the spreadsheet
comment response form.
• Arrange for appropriate City staff to attend the design review workshop.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 30 OF 46
8/26/09
pw:Hoco-pw-app:CarollolDocumentslCfientlWAWubumllakeland Hills Pump StationXProJect ManagemenQContractslExhibii A- Scope
Assum ptions
• Completion level of documents at each submittal is listed in Attachment A, Design
Submittal Requirements, attached to this Scope of Work.
. Five sets of full size Drawings in 24x36 inch hard copy format, staple-bound, and one (1)
electronic copy as an Adobe Acrobat *.PDF file.
• Five sets of Specifications will be in 8.5x11 page format, comb-bound and one *.PDF file.
Deliverab/es
1. TM 604.1 "90% Design Transm ittal."
2. 90% level design documents.
3. Written response to com ments.
4. ROC update. -
5. Agenda, meeting notes for one design review workshop. Subtask 604 Academy Boosfer Pump Station Bid Documents. Prepare Bid Documents :
comprising plans and specificat ions based on the results of the 90% design review.
Activities
1. Prepare drawings and specifications in accordance with the Design Submittal
Requirements, Exhibit A to this Scope.
2. Prepare Engineer's Estimate for transmittal to the City Clerk prior to bid opening.
3. Prepare and tra nsmit submittal documentation.
City Input
. Review Bid Documents for City approval and printing.
Assum ptions
• City will prepare the Bid Advertisement and Bid Proposal package.
• Completion level of documents at each submittal is listed in Attachment A, Design
Submittal Requirements, attached to this Scope of Work.
• One original full size set of Drawings in 24x36 inch 4-mil mylar copy format, unbound. • One original set of Bid Documents will be unbound hard copy and one electronic copy in
Adobe Acrobat *.PDF format.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 31 OF 46
8/26/09
pw:l\xo-pw-app:CarolblDocuments\ClienQWAWUbumllakeland Hdls Pump StationlProjecl ManagemennContractslExhibil A- Scopa
Deliverables
1. Bid Documents.
2. Engineer's Estimate.
CONSTRUCTION SERVICES
TASK 700 - LAKELAND HILLS ENGINEERING SERVICES DURING
CONSTRUCTION
Provide engineering services during construction. Provide office services such as bidding
services, submittal review, site visits, progress meeting attendance, and development vf record
drawings. The tasks associated with this section are described betow.
Subtask 701 Bid Period Services. Provide Bid Period Services.
Activities
1. Assist the City during the bid period. Answer questions, prepare addenda to the PS &E,
and provide ongoing consultati on and interpretation of the construction documents.
Develop and provide addenda f or distribution to plan holder s.
Cify Input
. Advertise for bid.
. Print and distribute documents to bidders.
. Conduct the bid opening.
. Award the bid.
Assumptions ,
. Up to three (3) addenda will be prepared.
. There will be one bid opening.
Deliverables
1. Addenda (up to three).
Subtask 702 Attend Pre-Construcfion Meeting. Attend the pre-construction conference and
answer questions as di rected by the City.
CAROLl.O ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 32 OF 46
8/26/09
pwlloco-pw-app:CarolblDOCUmentslClien0WAlAubumlLakeland Hills Pump StalbnlF'roject ManagemennContraclsExhibit A- Scope
Activities
1. Attend pre-construction conference.
City Input ,
. Conduct pre-construction conf erence.
. Prepare meeting notes.
Assum ptions
. There will be one pre construction conference.
Deliverables
1. None.
Subtask 703 Review Submitta/s. Receive, manage, review, and comment on contractor
submittals. Coordinate with City staff as appropriate for the submittal being reviewed.
Actfvities
1. Review and comment on submittals and re-submittals.
2. Log and return.submittals.
Cify Input
. Receive, log, transmit submittals.
. Manage and take final action on submittals.
Assum ptions
. Consuttant will receive four (4) copies of each submittal for review,
. Consultant will retain one copy for the ConsultanYs f ile. I
. Submittals will be hard copy.
. Assume up to 40 submittals and/or re-submittals with an average budget of 1.75 hours per
submittal ar re-submittal.
Deliverables
1. Submittal reviews.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 33 OF 46
8/26/09
pw:l\oco-pw-app:Carollo\DceumentslClienflWAWubumllakeland Hills Pump SlatbnlProject ManagemenflContractslFxhlbit A- Scope
Subtask 704 Prepare Design Clarifications. Respond to Contractor generated requests for
clarification and/or information (RFI). Receive and prepare answers to RFI. Coordinate with City
staff.
Activities
1. Prepare responses to RF I.
Assum ptions
. Consultant wili receive four (4) copies of each RFI for review.
. Consultant will retain one copy for the ConsultanYs file.
. RFIs will be hard copy.
City /nput
. Receive, manage, and take action on RFI. . Assume 10 RFI at 4 hours each.
Deliverab/es
1. RFI responses.
Subtask 705 Optional Task - Attend Progress Meetings. Attendance at progress meetings
will be authorized by the City as required, based on a proposed scope, schedule, and budget.
The work may include, but not be limited to the following activities. ,
Acfivit/es
1. Attend one (1) Pre B id meeting. Answer questions or discuss the intent of the plans and
specifications as requested by the City. Prepare notes from the meetmg and distribute
them in draft form for comment. Incorporate comments from the draft review and transmit
final notes.
2. Attend progress meetings as requested. ,
3. Make site visits.
City lnput
. Manage construction.
. Inspect construction.
. Arrange for and manage progress meetings.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 34 OF 46
8/26/09
pw.0ao-pw-app:CarolloWceumentslCllenllWAWuburnlLakeland Hills Pump SlafronlProject ManagementlContraclslExhibR A- Scope
• Prepare and distribute progr ess meeting notes.
Assum ptions
. Assume four (4) progress meetings or site visits at 4 hours each including travel.
Subtask 706 Startup and Commissioning. Attend startup activities. Assist the City in
commissioning the pump station.
Activities
1. Witness contractor equipment test. '
2. Attend final inspection.
3. Assist the City in commissioning of equipment. .
City Input
. Pertorm inspections. • Commission and operate equipment.
Assumptions
• City will perform inspections.
. City will operate equipment.
• Consultant will be available to answer questions and provide recom mendations on
adjustment of equipment during commissioning.
• Assume 8 hours for final inspection and equipment test.
. Assume 8 hours for equipment commissioning and adjustment.
Deliverables
1. Notes from startup and commissioning.
Subtask 707 Optional Task - Special Inspections. Provide special on-site inspections as
required by construction permits and the Specifications. Special inspections will be authorized
' by the City as required, based on a proposed scope, schedule, and budget. The following
special inspections may include but not be lim ited to:
• Special equipment as identified by the City. Assume one (1) $ hour effort.
• Special structural construction. Assume one (1) 8 hour effort.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 35 OF 46
8/26/09
pw:lloco-pw-app:CarolblDocumentslClientlWAWubumllakeland Hllls Pump SfafpnlProJecl AAanagemenflContractsExbibfl A -Scope
Activities
1. Provide engineer to perform special inspections. Assume two inspections with a budget of
8 hours each, total 16 hours.
2. Provide a written repoR. Assume two hours per report. ~
City Input
. Provide adequate notice af inspection.
Assum ptions
. City will determine if Special Inspection is required.
Deliverables
1. Written report of special inspection. .
Subtask 708 Review Change Order Requesfs. Review proposed Change Orders and make
recommendations to the City. Prepare specifications and drawings for Change Orders as
required.
Activities
1. Prepare drawings and specifications for Change Orders.
Clty Input
. Receive, manage, and take final action on Change Orders.
Assum ptions
. Assume up to 2 Change Ord er Requests with a budget of 16 hours per action. Deliverables
1. Change Order drawings and specifications.
Subtask 709 Provide Record Drawfngs. The Consultant will modify construction documents to
provide record draw ings based on C ontractor and field inspector-supplied redlines af ter final
acceptance of the Project by the City.
Activities
1. Incorporate redlines into construction documents. 2. Prepare one set of mylar Record Drawings and transmit to the Ciry.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 36 OF 46
8/26/09
pw:\loco-pw•app:CarollolDocumeMslCllenllWAlAubum\Lakaland Hills Pump StationWroject ManagemennConVactslExhibit A- Seope
City /nput
. Assure that construction drawing redlines are maintained regularly during construction to
accurately reflect as-constructed conditions.
. Field check redlines after completion to assure that all City-required changes that the City
prefers to be included in the Record Drawings are incorporated in the redlines.
. Provide redline drawings to the Consultant at the completion of construction.
Assumptions
. Twenty (20) drawings will be revised based on redlines. Assume two (2) CAD hours per
sheet. Assume 8 hours engi neer to coordinate preparation.
. No new drawings will be created.
. Assume all drawings will be annatated to remove engineer stam ps and add notes
reflecting as-constructed conditions. Assume 56 sheets at 0.25 hours CAD each.
. Typical drawings such as caver sheets, abbrev iations, typical details (unless modified by
construction) and similar sheets not assumed to require modification.
. Coordinate printing of mylar Record Drawings and transmit to City. Assume 4 hours CAD
and 2 hours Clerk.
. City will perform construction management and inspection.
Deliverables
1. Record Drawings as 2406 inch mylar.
Subtask 710 Maintenance and Operations Manuals. Receive and review contractor's
operation and maintenance (M&O) manual documents based on submittal information. Prepare
Maintenance and Operations m anual that includes and incorporates Contractor submittal
information.
Activities
1. Review contractor's M&O manual information for adequacy.
2. Prepare text and si mple schematic level graphics for each mechanical and electrical
system in the pump station that describes operation of the equipment.
3. Prepare text and graphics that sum marizes routine maintenance recommendations based
on submitted information.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 37 OF 46
8/26/09
pw.\bco-pw-app:CazollolDocuments\ClientlWAV+ubumltakeland Hllls Pump StaGonlProJect ManapemedContracfsExhibit A- Scope
4. Prepare a M&O manual that includes and incorporates contractor and Consultant M&O
information.
City Mput
. Obtain and provide contractor's M&O information.
. Review and comment on M&O manual contents.
Assum ptions
. M&O Manual will be 3-ring binders.
• Graphics will be based on design draw ings annotated with operational notes.
Deliverables
1. M&O 3-ring Binder, three (3) hardcopy and CD.
TASK 800 - ACADEMY ENGINEERING SERVICES DURING
CONSTRUCTION
Provide engineering services during construction. Provide office services such as bidding
services, submittal review, site visits, progress meeting attendance, and development of record
drawings. The tasks associated with this section are described below.
Subtask 801 Bid Period Services. Provide Bid Period Services.
Activities
1. Assist the City during the bid period. Answer questions, prepare addenda to the PS &E,
and provide ongoing consultati on and interpretation of the construction documents.
Develop and provide addenda f or distribution to plan holder s. '
City Input :
. Advertise for bid.
. Print and distribute documents to bidders.
. Conduct the bid opening.
. Award the bid.
Assum pfions
. Three (3) addenda will be prepared.
. There will be one bid opening.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 38 OF 46
8/26/09
pw.lbco-pw-app:CarollolDceumentslClientlWAlAubum\Lakeland Hills Pump SlationlProject ManagemenhContracLslFachibit A- Scope
Deliverables
1. Addenda (up to three).
Subtask 802 Attend Pre-Construction Meeting. Attend the pre-construction conference and
answer questions as di rected by the City.
Activities
1. Attend pre-construction conference.
City Input
. Conduct pre-construction conf erence.
. Prepare meeting notes.
Assumptlons
. There will be one pre construction conference.
Dellverables
1. None.
Subtask 803 Review Submitfals. Receive, manage, review, and comment on contractor
submittals. Coordinate with City staff as appropriate for the submittal being reviewed.
Activities
1. Review and comment on submittals and re-submittals. 2. Log and return submittals. •
Cify Input
. Receive, log, and transmit submittals.
. Manage and take final action on submittals.
Assumpfions
. Consultant will receive four (4) copies of each submittal for review.
. Consultant will retain one copy for the ConsultanYs file.
. Submittals will be hard copy.
. Assume up to 40 submittals and/or re-submittals with an average budget of 1.75 hours per
submittal or re-submittal.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 39 OF 46
8/26/09
pw 1Xoco-pw-app:CarolblDocuments\CIieM1WAlAuburMLakeland Hills Pump StaUOnWroject ManagemenhConVactsl6chibit A- Scope
Deliverab/es
1. Submittal reviews.
Subtask 804 Prepare Design Clarifications. Respond to Contractor generated requests for
clarification and/or information (RFI). Receive and prepare answers to RFI. Coordinate with City
staff.
Activities
1. Prepare responses to RF I.
Assum ptlons
. Consultant will receive four (4) copies of each RFI for review.
. Consultant will retain one copy for the Consultant's file.
. RFIs will be hard copy.
City Input
. Receive, manage, and take action on RFI.
. Assume 10 RFI at 4 hours each.
Deliverables
1. RFI responses.
Subtask 805 Optional Task - Aitend Progress Meetings. Attendance at progress meetings
will be authorized by the City as required, based on a proposed scope, schedule, and budget.
The work may include, but not be lim ited to the following activities.
Activities
1. Attend one (1) Pre B id meeting. Answer questions or discuss the intent of the plans and
specifications as requested by the City. Prepare notes from the meeting and distribute
them in draft form for comment. Incorporate comments from the draft review and transmit
final notes.
2. Attend progress meetings as requested.
3. Make site visits.
City Input
. Manage construction.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 40 OF 46
8/26/09
pw Hoco-pw-app:CarolblDocumentslClienflWAWuburnlLakeland Hills Pump StationlProjecl ManagemenllConVaclslExhfbit A- Swpe
• Inspect construction.
• Arrange for and manage progress meetings.
• Prepare and distribute progr ess meeting notes.
Assum ptions
• Assume four (4) progress meetings or site visits at 4 hours each including travel.
Subtask 806 Startup and Commissioning. Attend startup activities. Assist the City in
commissioning the pump station.
Activities
1. VVitness contractor equipment test.
2. Attend final inspection.
3. Assist the City in commissioning of equipment.
City Inpuf
• Perform inspections.
• Commission and operate equipm ent.
Assumptions
• City will perform inspections.
• City will operate equipm ent.
• Consultant will be available to answer questions and provide recom mendations on
adjustment of equipment during commissioning.
• Assume 8 hours for final inspection and equipment test.
• Assume 8 hours for equipment commissioning and adjustment.
Deliverables
1. Notes from startup and commissioning.
Subtask 807 Optional Task - Special Inspections. Provide special on-site inspections as
required by construction permits and the Specifications. Special inspections will be authorized
by the City as required, based on a proposed scope, schedule, and budget. The following
special inspections may include but not be lim ited to:
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 41 OF 46
8/26/09
pw;Hxo-pw-app:CarollolDaumenlslClienllWAV+ubumllakeland Hills Pump StatbnlProject ManagemenflCOntractslExhibil A- Scope
• Special equipment as identified by the City. Assume one (1) 8 hour effort.
• Special structural construction. Assume one (1) 8 hour effort.
Activities
1. Provide engineer to perform special inspections. Assume two inspections with a budget of
8 hours each, total 16 hours.
2. Provide a written report. Assume two hours per report.
Cify Input
. Provide adequate notice of inspection.
Assum ptfons
. City will determine if Special Inspection is required.
Deliverables
1. Written report of special inspection.
Subtask 808 Review Change Order Requests. Review proposed Change Order s and make
recommendations to the City. Prepare specifications and drawings for Change Orders as
required.
Activities
1. Prepare drawings and specifications for Change Orders.
City Input
. Receive, manage, and take final 'action on Change Orders.
Assumptions
. Assume up to 2 Change Ord er Requests with a budget of 16 hours per action.
Deliverables
1. Change Order drawings and specifications.
Subtask 809 Provide Recvrd Drawfngs. The Consultant will modify construction documents to
provide record drawings based on Contractor and field inspector-supplied redlines after final
acceptance of the Project by the City. Activities
1. Incorporate redlines into construction documents,
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 42 OF 46
8/26/09
pw.llxapw-app:CaroAOVocumentslClienflWAWu6urnlLakeland Hills Pump SladonlProject ManagementlContractslFxhibil A- Scope
2. Prepare one set of mylar Record Drawings and transmit to the City.
City Input
• Assure that construction drawing redlines are maintained regularly during construction to
accurately reflect as-constructed conditions.
. Field check redlines after completion to assure that all City-required changes that the City
prefers to be included in the Record Drawings are incorporated in the redlines.
. Provide redline drawings to the Consultant at the completion of construction.
Assum ptions
• Twenty (20) drawings will be revised based on redlines. Assume two (2) CAD hours per
sheet. Assume 8 hours engi neer to coordinate preparation.
• No new drawings will be created.
• Assume all drawings will be annotated to remove engineer stam ps and add notes
reflecting as-constructed conditions. Assume 56 sheets at 0.25 hours CAD each.
. Typical drawings such as cover sheets, abbrev iations, typical details (unless modified by
construction) and sim ilar sheets assumed not to require modification.
. Coordinate printing of mylar Record Drawings and transmit to City. Assume 4 hours CAD
and 2 hours Clerk.
. City will perform construction management and inspection.
Deil verables
1. Record drawings as 24x36 inch mylar.
Subtask 810 Malntenance and Operation Manuals Receive and review contractor's operation
and maintenance (M&O) manual documents based on submittal information. Prepare
Maintenance and Operations m anual that includes and incorporates Contractor subm ittal
information.
Activlties
1. Review contractor's M&O manual information for adequacy.
2. Prepare text and si mple schematic level graphics for each mechanical and electrical
system in the pump station that describes operation of the equipment.
3. Prepare text and graphics that sum marizes routine maintenance recommendations based on submitted information.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 43 OF 46
8/26/09
pw 1loco-pw-app:CarolblDocumentslCllentlWAlAubumllakeland Hills Pump StationlProject ManagemenllConVactsl6chibft A- Scope
4. Prepare a M&O manual that includes and incorporates contractor and Consuitant M&O information.
City lnput
. Obtain and provide contractor's M&O information.
. Review and comment on M&O manual contents.
Assum ptions
. M&O Manual will be 3-ring binders.
. Graphics will be based on design draw ings annotated with operational notes.
Deliverables '
1. M&O 3-ring Binder, three (3) hardcopy and CD.
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 44 OF 46
8/26/09
pwlbco-pw•app:CarollolDocumentslCliennWAWuburnlLakeland HiIIs Pump SWtionlProject ManagemeMlContract5lExhibft A- Scope
City of Auburn
Academy and Lakeland Hills Booster Pump Station Improvement
Project
SCOPE OF SERVICES
ATTACHMENT A
Design Submittal Requirements
30% Submittai Packaae
. Elements 90% complete;
- typical details
- standard sheets
- site plan
- electrical one lines
- P&ID
- Outline Specifications
- Two (2) 3D Illustrations of pump station exterior
. 30% Cost Estimate
60% Submittal PackaQe
. All elements 60% comptete except as noted
. Elements 90% Complete:
- Typical details
- Civil site plans '
- Architectural and structural floor plans
- Buried structure floor and wall plans, sections
- Mechanical floor plans
- Electricallayouts
- P&ID
. Elements 30% Complete:
- Architectural schedules
- Loop diagrams
. Specifications:
CAROLLO ENGINEERS SCOPE OF SERVIGES - VERSION 7.1 PAGE 45 OF 46
8/26/09
pw:lloco-pw-app:CarolblDocuments\ClienllWAVluburn0.akeland Hills Pump SW1bnlProjecl MaoagemenAContractslExhibil A- Scope
- Technical specifications 90% complete
. 60% Cost Estimate
90% Submittal Packaqe
. Ali elements 100% complete and checked
. Specifications com plete except for finai bid advertisem ent and bid form
• 90% Cost Estimate
END OF SCOPE OF SERVICES '
ACADEMY AND LAKELAND MILLS PUMP STATION PROJECT
CAROLLO ENGINEERS SCOPE OF SERVICES - VERSION 7.1 PAGE 46 OF 46
8/26/09
pw:\loco-pw-app:CarolblDocuments\ClienhWAWubumlLakeland Hills Pump StalionlProject ManagemennContraclsiFxhibit A- Scope
EXHIBIT B
FEE SCHEDULE
Exhibit B
Agreement No. AG-C-374
Page 1 of 1
EXHIBIT B
City of Auburn
CAROLLO ENGINEERS, PC
FEE SCHEDULE
As of March 1, 2009
~ Hourlv Rate
Engineers/Scientists
Assistant Professional $125.00
Professional 150.00
Project Professional 170.00
Senior Engineer 185.00
Principal 224.00
Technicians
Technicians 92.00
Senior Technicians 140.00
Support Staff
Document Processing / Clerical 92.00
Project Equipment Comm unication Expense 9.00
(PECE) Per DL Hour
Other Direct Expenses
Travel and Subsistence at cost
Mileage* .55/mile
Subconsultant cost + 10%
Other Direct Cost at cost
* May change, as IRS rate is modified
This fee schedule is subject to annual revisions due to labor adjustments.
CONSULTANT INVOICES
CONSULTANT invoices should contain the following information:
• On CONSULTANT letterhead.
• A cover letter stating the status of each task. This should include items completed, percent
completed during the billing periad and completion along with funding status.
• Internal invoice number and/or sequential numeric number (i.e.: progress payment # 10).
• Invoice date.
• Period of time invoice covers.
• Consultant Agreement # (i.e.: AG-C-115).
• Project number(s) listed (i.e.: PR562).
• CITY'S project manager listed.
• The hour(s) per person broken down by task(s) (attach timesheets, spreadsheet detailing
timesheets, or some other form of proofl along with type of work done (i.e.: design, right-of-
way, or construction) or task order number.
• Direct salary (base salaries).
. Indirect salary (benefits). • Direct non-salary (i.e.: mileage, reproduction fees (i.e.: printing, copying), communication
fees (i.e.: telephone), supplies, computer charges, subconsultants), indirect non-salary
(overhead). The CITY does not pay for CONSULTANT meals unless part of a task requires
travel outside of the greater Seattle, Tacoma, and Everett area. These costs are to be
broken down and backup information is to be attached to invoice. Project managers are to
inform CONSULTANTS as to what is required for break down information and if backup
information is to be attached. Break out the same for subconsultant charges.
• Previous and remaining base contract amounts left in each task and total contract - total
authorized amount (bottom line figure). Add amendments to this base contract amount for total authorized amaunt.
• Percentage of work completed to date compared to total amount of work (if required by the
project manager).
• Status of Management Reserve Fund (MRF) (i.e.: a certain task) until we can get an
amendment in place.
• Invoices for previous year are due by January 15tn
• For grant/special funded projects there might be other special information needed,
reference the LAG manuaL '
Consultant Invoices
Agreement No. AG-C-374
Page 1 of 2
SAMPLE INVOICE City of Auburn Invoice 5222 .
25 West Main Progress Payment 2
Auburn WA 98001 invoice Date: February 10, 2008
Attn: Scott Nutter, Project Engineer Project Name: Thomas Nelson Farm
Agency Agreement AG-C-010 Project PR562
Engineering Services performed during the period of: January 2002 '
SAMPLE ENGINEERING, INC. .
Personnel Hours Hourl Rate Amount
Mike Jones, Princi al in Char e 1 $ 125.00 $ 125.00
Carla Maker, Architect 5 $ 72.00 $ 144.00
Joe Smith Word Processin 10 $ 48.00 $ 480.00
Consultant Personnel Subtotal $ 749.00
Ex enses see attached documentation Char es Multi lier Amount
Mike Jones Princi al in Char e 20 miles x1.1 $ 7•59
Carla Maker, Architect $ 30.00 x1.1 $ 33.00
Joe Smith, Word Processin $ 29.00 x1.1 $ 31.90
Consultant Ex enses Subtotal $ 72•49
Consultant Total: $ 821.49
SUB CONSULTANTS (see attached documentation)
Subconsultant Hours Hourl Rate Amount
ABC Environmental, Inc., Civil En ineer 10 $ 100.00 $ 1,000.00
Electrical Consultin , Electrical En ineer 5 $ 100.00 500.00
Mechanical Solutivns, Mechanical En ineer 10 $ 100.00 MRF 1,000.00
Movin Com an , Movin Consultant 2 $ 50.00 100.00
Subconsultant Subtotal $ 2,600.00
Subtotal x 1.1 Multi lier $ 2,860.00
Subconsultant Total: $ 2,860,00
.
TOTAL DUE THIS INVOICE $ 3~681 49
.
CONTRACT BREAKDOWN
Amount Totallnvoiced % % Amount
Task Authorized Prior Invoiced This Invoice To Date Ex ended Com leted Remainin
Original
Contract $ 22,000.00 $ 1,025.00 $ 2,681.49 $ 3,706.49 20% 25% $ 18,293.51
MRF* 2,500.00 0.00 1000.00 1,0000.00 40% 45% 1,500.00
TOTAL $ 24,500.00 $ 1,025.00 $ 3,681.49 $ 4 706.49 $ 19,793.51 I
Note: MRF=Management Reserve Fund
Received a written authorization of MRF on 1110101 for Mechanical Engineer task in the amount of
$2,000.00.
Consultant Invoices
Agreement No. AG-C-374
Page 2 of 2
AMENDMENT #1 TO AGREEMENT NO. AG-C-374 BETWEEN
THE CITY OF AUBURN AND CAROLLO ENGINEERS, PC
RELATING TO PROJECT CP0909, ACADEMY AND LAKELAND HILLS BOOSTER
PUMP STATION IMPROVEMENTS
THIS AMENDMENT is made and entered into this W day of , 20l ,
by and between the CITY OF AUBURN, a municipal corporation of the State of Washington
(hereinafter referred to as the "CITY"), and Carollo Engineers, PC (hereinafter referred to as the
"CONSULTANT"), as an Amendment to the Agreement between the parties for AG-C-310
executed on the 2nd day of September 2009.
The changes to the agreement are described as follows:
1. CONTRACT TERM: The term of the Agreement for Professional Services is extended to
December 31, 2011.
2. SCOPE OF WORK: There is no change in the scope of work.
3. COMPENSATION: There is no change to the amount authorized in the original agreement
or subsequent amendments
REMAINING TERMS UNCHANGED: That all other provisions of the Agreement between
the parties for AG-C-374 executed on the 2nd day of September 2009 shall remain unchanged,
and in full force and effect.
IN WITNESS WHEREOF the parties hereto have executed this Agreement as of the day
n.
and ye t j
CA LO E
, PC Geter BU N
By:
Authoriz signatur Lewis, Mayor
ATTEST (Optional): ATTEST:
By:
Its: Danielle E. Daskam, Auburn City Clerk
m•
Approved as to form (Optional): 7 M
Attorney for (Other Party) aniel B. 1-1`6' burn City Att
-
Amendment No. 1 for Agreement No. AG-C-374
Carollo Engineers, PC
Page 1 of 1
CITY OF
TT �-.
JBUl�I �1 Peter B. Lewis, Mayor
25 West Main Street * Auburn WA 98001-4998 * www.auburnwa.gov ov * 253.931-3000 WASHINGTON 9
December 29, 2010
Lara Kammereck
Carollo Engineers, P.C.
1218 Third Avenue, Suite 1600
Seattle, WA 98101
RE: Amendment No. 1 to Agreement No. AG-C-374
CP0909: Academy and Lakeland Hills Booster Pump Station
Dear Ms. Kammereck:
Enclosed is a fully executed original of the above-referenced Amendment. This
amendment extends the term of the agreement to December 31, 2011.
Our records indicate that your general liability and auto insurance, as required in Section
7 of the original agreement, expires on December 31, 2010. Please mail the required
certificate(s) of insurance, within two weeks, to Amanda DeSilver, Contracts
Administration Specialist, Auburn Public Works Department, at the address noted at the
top of this letterhead.
For the City's tracking and record keeping purposes, please reference AG-C-374 on all
correspondence, invoices, and related material.
As the project manager, I am the designated contact for this agreement and all
amendments, questions, assignments and coordination shall be routed through me. You
can contact me directly at 253-931-3086.
Si - ely,
t'yan Vondrak, P.E.
Project Manager
Public Works Department
RV/ad/hg
Enclosure
cc: City Clerk
AG-C-374
AUBURN * MORE THAN YOU IMAGINED
AMENDMENT #2 TO AGREEMENT NO. AG-C-374 BETWEEN
THE CITY OF AUBURN AND CAROLLO ENGINEERS WASHINGTON, PC
RELATING TO PROJECT CP0909, ACADEMY AND LAKELAND HILLS BOOSTER PUMP
STATION IMPROVEMENTS
THIS AMENDMENT is made and entered into this aq ~~ay of , 2011, by and
between the CITY OF AUBURN, a municipal corporation of the State of Washington (hereinafter
referred to as the "CITY°), and Carollo Engineers Washington, P.C. (hereinafter referred to as the
"CONSULTANT"), as an Amendment to the Agreement between the parties for AG-C-374 executed
on the 2nd day of September 2009 and amended by agreement dated the 16th day of December 2010.
The changes to the agreement are described as follows:
1. CONSULTANT: Change CONSULTANT'S name from °Carollo Engineers, P.C." to
°Carollo Engineers Washington , P.C.".
2. CONTRACT TERM: There is no change to the contract term.
3. SCOPE OF WORK: Change to the Scope of Work shown in Exhibit A-1.
4. COMPENSATION: An additional $150,000.00 has been added to the amount authorized in
the original agreement.
REMAINING TERMS UNCHANGED: That all other provisions of the Agreement between the
parties for AG-C-374 executed on the 2nd day of September, 2009, shall remain unchanged, and in
full force and effect.
IN WITNESS WHEREOF the parties hereto have executed this Agreement as of the day and year
first ab written.
CA OL ENGI ERS WASHINGTON, PC CITY OF
By:
Authoriz gna a Peter B. Lewis, Mayor
By: ATTEST:
Author zed signature 19
I Danielle E. Daskam, Auburn City Clerk
Approved as t rm:
/I y
Dan' Heid, ur ity ttney
Amendment No. 2 for Agreement No_ AG-C-374
Carollo Engineers, PC
Page 1 of 1
EXHIBIT A-1
AMENDMENT NO. 2
City of Auburn
Academy Booster Pump Station Improvement Project
The City of Auburn (City)'s Academy Booster Pump Station (ABPS) will serve a new pressure
zone in the Academy Service Area. The City will move customers from the current 531 zone to
the new 578 zone to improve customer water pressure and increase operational aspects of the
utility system. To implement this rezone requires evaluation of current piping and service
connections to confirm the proposed new zone piping and customer modifications. This effort
will be referred to as the "Off-site Water Main Design".
It is anticipated that the Off-site Water Main Design will include the following:
• Isolate zone piping at the Auburn Way South and 32nd Street SE intersection.
• Install piping for two master meters for the Auburn Academy customers at 32nd Street SE
and Wyman Drive.
• Relocate all meters to public right-of-way along 32nd Street SE.
• Isolate zone piping in 32nd Street SE.
• Extend the current 12 inch pipeline eastward for service zone 531 approximately 300
linear feet (LF).
• Remove the Janssen's Addition Booster Pump Station and install piping to bypass the
system (originally, the pump station was to be left in-place).
SCOPE OF SERVICES
The scope of services broken down by task for the additional Off-site Water Main improvements
and specifications work are included below. The same project assumptions and project
considerations outlined in the original Exhibit A - Scope of Services applies to this scope of
services.
A budget for the tasks outlined in this Amendment No. 2 is included at the end of this document.
CAROLLO ENGINEERS AMENDMENT NO. 2 PAGE 1 OF 7
3/8/11
TASK 100 - PROJECT MANAGEMENT
Manage the work of the project team from notice to proceed to project closeout. Plan for and
carry out regular communication with the City during the project. Plan for and carry out quality
management.
Subtask 109 Project Administration. Administer contracts and manage the project team.
Activities
1. Prepare and administer subcontracts with consultant team members:
2. Manage the project team to track time and budget, work elements accomplished, work
items planned for the next period, manpower, scope changes, time and budget needed to
complete this Scope of Services.
TASK 605 - OFF-SITE WATER MAIN AND ADDITIONAL SERVICES
Subtask 605.1 Off-site Water Main Survey Services. Perform field survey and mapping
services for off-site pipelines to include all piping and utilities in 32nd Street SE and Auburn Way
South in Project Area. Survey on 32nd Street SE, which becomes Academy Drive SE, will begin
at the intersection with Auburn Way South and extend east approximately 2,500 feet where the
road turns south. Additional survey will include 200 feet of the private drive, at the east end of
the survey limit on Academy Drive SE, to locate a water meter. All survey in the public right-of-
way will be full right-of-way width, as indicated by the City.
Activities
Complete field survey and mapping for the selected off-site area, and incorporate information in
the existing base map for the Academy Booster Pump Station Improvement Project.
City Input:
• City will obtain rights of entry.
• City will establish and mark public right-of-way boundaries.
• City will perform all property acquisition including appraisal, negotiations, and recording of
final documents.
CAROLLO ENGINEERS AMENDMENT NO. 2 PAGE 2 OF 7
3/8/11
i
E
1
i
E
i
Assumptions
• Datum is City of Auburn current datum.
• Surveyor will obtain horizontal and vertical control information.
• Surveyor will attempt to locate sanitary sewer manholes on the property adjacent to the
pump station that uses the same access road. It is assumed that locating the manholes
will require no more than one hour.
• Surveyor will hire a private utility locating company. No potholing or ground penetrating
radar will be used to locate utilities.
• Survey will include all trees with trunk diameters greater than 4 inches within the public
right-of-way.
• Survey will include all surface improvements and utilities to the limits of public rights-of-
way as appropriate for pipelines.
• Right-of-way markings established by the City will be assumed accurate.
• Topographic survey will be to 1-foot contour interval accuracy.
• Project vertical control points (2) will be established at each site and along each pipeline
alignment.
• Prepare base maps in AutoCAD 2006.
• Mapping and related plans will comply with Auburn Design Standards.
Deliverables
1. Base mapping for off-site pipelines.
2. Base mapping pipeline alignment (hard copy and electronic).
CAROLLO ENGINEERS AMENDMENT NO.2 PAGE 3 OF 7
3/8/11
Subtask 605.2 Off-site Water Main Construction Documents. Prepare design and
construction documents for the off-site pipeline. Prepare submittals for review by the City at the
50%, 90% and final bid documents stages of design completion.
Perform internal quality management during preparation of documents, and provide a formal,
internal, coordinated review prior to review by the City.
Prepare and submit probable estimates of construction cost of the additional off-site pipeline,
and an Engineer's Estimate with the Bid Documents.
Provide an electronic Microsoft Excel spreadsheet comment response form to record Consultant
response to City comments made on drawings. Respond in writing to written comments that
require discussion or elaboration using the Excel form. Provide hard copy and electronic form
responses to the City. Update the Record of Comment (ROC) throughout the construction
document preparation process.
Activities
1. Prepare drawings and specifications in accordance with the Design Submittal
Requirements, Exhibit A of the original Scope of Services.
2. Prepare probable estimate of construction cost at a level commensurate with the
completion level of the design documents.
3. Perform formal internal coordinated check of documents to determine that documents
meet design intent, City of Auburn Design Standards, standards of the industry, City staff
equipment and materials preferences, are consistent with the specifications and are
otherwise ready for bid.
4. Prepare and transmit submittal documentation.
5. Review City comments on the submittal and respond in writing to comments within five
working days of receipt of comments.
6. Update the ROC.
City Input
• Receive and transmit design submittal documents to City staff for review.
• Manage and coordinate comments on submittal documents prior to transmittal to the
Consultant.
• Comment on the design submittal according to the agreed schedule in the spreadsheet
comment response form.
CAROLLO ENGINEERS AMENDMENT NO. 2 PAGE 4 OF 7
3/8/11
Assumptions
• Completion level of documents at each submittal is listed in Attachment A, Design
Submittal Requirements, in Exhibit A of the original Scope of Services.
• Demolition of the Jannsen's Addition Booster Pump Station will remove mechanical and
electrical from the vault. Electrical will be removed back to the service feed. Vault lid will
be removed and vault will be cut down two feet below ground surface. The resultant void
will be backfilled with Gravel Borrow and Bark Mulch. No landscape design will be
provided.
• Relocation of water meters along 32"d Avenue to public right-of-way is assumed to include
twelve meters.
• Isolation piping associated with the two master meters is assumed to include a total of 150
total feet of pipe.
• Assume no more than 6 Sheets.
Deliverables
1. 50%, 90% and bid level design documents for Off-site Water Main improvements.
2. Engineer's estimate for Off-site Water Main improvements for each submittal.
TASK 700 - LAKELAND HILLS ENGINEERING SERVICES DURING
CONSTRUCTION
Subtask 703 Review Submittals. This effort provides additional services to increase the
number of submittals for review originally scoped under Task 703. The services for this task
remain the same as the original scope.
Assumptions
• 85 additional hours are proposed for submittal review, this increases the total time to
review submittals from 70 hours to approximately 155 hours. This budget is not based on
the number of submittals, as the length to review a submittal can vary from 1 hour to 8
hours. The status of the hours will be reviewed monthly with the client.
Subtask 710 Intermittent Construction Observation. This effort provides intermittent
construction observation services to support the City in an effort to maintain the overall quality of
the constructed project. Services can generally be described as the following:
• Provide on-site field observation and monitoring to observe the quality and progress of the
construction with the following goals:
CAROLLO ENGINEERS AMENDMENT NO. 2 PAGE 5 OF 7
3/8/11
To help determine if the provisions of the construction contract documents are being
fulfilled.
- To responsibly carry out the program of intermittent inspection to guard the City
against defects and deficiencies in the work of the construction contractor.
To advise both the City and the construction contractor when defects and
deficiencies are observed in the work.
• Consultant shall direct its efforts toward determining that the completed Project will
conform to the plans and specifications, but Consultant shall not be responsible for the
means, methods, techniques, or procedures of construction selected by the construction
contractor or for the safety precautions and programs incident to the work of the
construction contractor or for any failure of the construction contractor to comply with
laws, ordinances, rules or regulations applicable to the construction work. Consultant and
City recognize that the construction contractor is primarily responsible for ensuring that
construction is in accordance with the plans and specifications.
• Notwithstanding any interferences, references, or omissions to the contrary contained
within this amendment, City understands that Consultant will not direct any contractors,
subcontractors, etc... at the job site, and it is hereby agreed that Consultant will assume
no obligation for any acts, errors or omissions of parties other than Consultant.
Assumptions
• Construction Observation will be requested by City Staff 48 hours in advance.
• Intermittent construction observation is estimated at 300 hours, based on 10 hours per
day for a period of 30 days.
• Construction observation is anticipated to occur during the months of June through
October of 2011.
• Consultant will attend construction progress meetings at the request of the City, but will
not facilitate meetings.
Deliverables
• Daily construction observation logs with photographs documenting the nature of the work
during that day, any noted discrepancies, any verbal or written communication with the
Contractor related to defects and deficiencies observed in the work, and recommended
corrective action(s), if necessary.
CAROLLO ENGINEERS AMENDMENT NO. 2 PAGE 6 OF 7
3/8/11
BUDGET
The following payment is requested as part of the services outlined in Amendment No. 2 below:
Subtask 100 Project Administration $7,500
Subtask 605.2 Off-site Water Main Survey Services $14,200
Subtask 605.3 Off-site Water Main Construction Documents $56,900
Subtask 703 Lakeland BPS Submittal Review $13,600
Subtask 710 Lakeland BPS Intermittent Construction Observation $42,000
Management Resource Fund $15,800
Total $150,000
CAROLLO ENGINEERS AMENDMENT NO. 2 PAGE 7 OF 7
3/8/11
A3 Ib 9j
AMENDMENT #3 TO AGREEMENT NO. AG-C-374 BETWEEN
THE CITY OF AUBURN AND CAROLLO ENGINEERS WASHINGTON, PC
RELATING TO PROJECT CP0909, ACADEMY AND LAKELAND HILLS BOOSTER
PUMP STATION IMPROVEMENTS
THIS AMENDMENT is made and entered into this 2c' day of r l! , 2011 by
and between the CITY OF AUBURN, a municipal corporation of the State of Washington
(hereinafter referred to as the"CITY"), and Caro llo Engineers Washington, PC (hereinafter
referred to as the"CONSULTANT"), as an Amendment to the Agreement between the parties
for AG-C-310 executed on the 2nd day of September 2009 and amended by agreement dated
the 16th day of December 2010 and the 24th day of March, 2011
The changes to the agreement are described as follows:
1 CONTRACT TERM: The term of the Agreement for Professional Services is extended to
December 31 2012.
2. SCOPE OF WORK. There is no change in the scope of work.
3. COMPENSATION: There is no change to the amount authorized in the original agreement
or subsequent amendments
REMAINING TERMS UNCHANGED: That all other provisions of the Agreement between
the parties for AG-C-374 executed on the 2nd day of September 2009 shall remain unchanged,
and in full force and effect.
IN WITNESS WHEREOF the parties hereto have executed this Agreement as of the day
and year first above written.
C a •O , ENGINEE S WASHINGTON, PC TY OF A RN
By a 1 �• Jam'
Brian 1`-'•*rj' "re ent Peter B. "s, Mayor
ATTEST (Optional): ATTEST ��
By. 4,�
Its: Da "-Ile E. Daskam, Auburn City Clerk
Approved as to form (Optional): Apt ov d a- to • :
LSJ
Attorney for(Other Party) Thiel B. He A° ity A'omey
Amendment No. 3 for Agreement No.AG-C-374
Carollo Engineers Washington, PC
Page 1 of 1
AMENDMENT #5 TO AGREEMENT NO AG-C-374 BETWEEN
THE CITY OF AUBURN AND CAROLLO ENGINEERS, INC.
RELATING TO PROJECT CP0909, ACADEMY AND LAKELAND HILLS BOOSTER
PUMP STATION IMPROVEMENTS
THIS AMENDMENT is made and entered into this�day of��' 2012, by
and between the CITY OF AUBURN, a municipal corporation of the State of Washington
(hereinafter referred to as the "CITY"), and Carollo Engineers, Inc. (hereinafter referred to as
the "CONSULTANT"), as an Amendment to the Agreement between the parties for AG-C-310
executed on the 2nd day of September 2009 and amended by agreement dated the 16'h day of
December, 2010, the 24'h day of March, 2011, the 8th day of November, 2011, and the 15'h day
of May, 2012.
The changes to the agreement are described as follows,
1 CONSULTANT Change CONSULTANT'S name from "Carollo Engineers Washington, PC"
to Carollo Engineers, Inc.
2. CONTRACT TERM: The term of the Agreement for Professional Services is extended to
December 31, 2013
3 SCOPE OF WORK. There is no change in the scope of work.
4 COMPENSATION: There is no change to the amount authorized in the original agreement
or subsequent amendments, however Amendment#5 shifts the remaining funds allocated
to design services for the Academy Booster Pump Station project into construction services.
The amount of remaining Academy design services funds being transferred to Academy
construction services is $35,774 66. The Consultant's fee schedule is also changed to
reflect current 2012 rates, see attached.
REMAINING TERMS UNCHANGED- That all other provisions of the Agreement between
the parties for AG-C-374 executed on the 2nd day of September 2009 shall remain unchanged,
and in full force and effect.
IN ESS W EREOF the parties hereto have executed this Agreement as of the day
an ear fir t above ritten.
CA OL ENGIN RS, INC Cl Y OF N
By
Brian M so , is rest ent Peter ewis, Mayor
ATTEST (Optional) ATTE�ST�\
By,
Its. Danielle E. Daskam, Auburn City Clerk
Approved as to form (Optional) Appr d as fs
Attorney for (Other Party) Da el B Heid, Auburn City At y-
-----------------------------------------------------------------
Amendment No. 5 for Agreement No.AG-C-374
Carollo Engineers, Inc
Page 1 of 1
City of Auburn
CAROLLO ENGINEERS, INC.
FEE SCHEDULE
As of November 2012
Hourly Rate
Engineers/Scientists
Assistant Professional $13300
Professional $160.00
Project Professional $185.00
Senior Engineer $200.00
Principal $230.00
Technicians
Technicians $98.00
Senior Technicians $140.00
Support Staff
Document Processing /Clerical $92.00
Project Equipment Communication Expense $9.90
(PECE) Per DL Hour
Other Direct Expenses
Travel and Subsistence at cost
Mileage` $0.55/mile
Subconsultant cost+ 10%
Other Direct Cost at cost
" May change, as IRS rate is modified
This fee schedule is subject to annual revisions due to labor adjustments.
pw tlCarol]o DommenlJC6enVNA/AuburN5341Al OfProlect NanagementBudgel/CUOIb Fee Schedule dot
*
CITY OF
AD-Bu Peter B. Lewis, Mayoi
WASHINGTON 25 West Main Street * Auburn WA 98001-4998 * www.auburnwa.gov * 253-931-300(
December 19, 2012
Lara Kammereck
Carollo Engineers, Inc.
1218 Third Avenue, Suite 1600
Seattle, WA 98101
RE. Amendment No 5 to Agreement for Professional Services, AG-C-374
Project No CP0909, Academy and Lakeland Hills Booster Pump Station
Improvements
Dear Ms. Kammereck:
Enclosed please find an executed copy of the above-referenced Amendment No. 5. This
amendment changes the Consultant's name, extends the term of the agreement to
December 31, 2013, shifts remaining funds and attaches the Consultant's current fee
schedule.
For the City's tracking and record keeping purposes, please reference AG-C-374 and
Project No. CP0909 on all correspondence and related material. Our records indicate
that your Insurance, as required in Section 10 of the original agreement, will expire on
December 31, 2012. Please mail the required certificate(s) of insurance, within two
weeks, to JoAnne Andersen, Contracts Administration Specialist, Auburn Public Works
Department, at the address noted at the top of this letterhead.
As the project manager, I am the designated contact for this agreement and all
amendments. Questions, assignments and coordination shall be routed through me.
You can contact me at 253 931 3086.
Sincerely,
Ryan Vondrak, P E.
Project Engineer
Department of Public Works
RV/ja/mh
Enclosure
cc: Dani Daskam, City Clerk (copy letter only)
AG-C-374
CP0909 (2.20)
AUBURN *MOPE THAN YOU IMAGINED
tz,\, 3 \Lo 1
AMENDMENT #6 TO AGREEMENT NO. AG-C-374 BETWEEN
THE CITY OF AUBURN AND CAROLLO ENGINEERS, INC.
RELATING TO PROJECT CP0909, ACADEMY AND LAKELAND HILLS BOOSTER
PUMP STATION IMPROVEMENTS
THIS AMENDMENT is made and entered into this day of 2013, by
and between the CITY OF AUBURN, a municipal corporation of the State of W shington
(hereinafter referred to as the "CITY"), and Carollo Engineers, Inc. (hereinafter referred to as
the "CONSULTANT'), as an Amendment to the Agreement between the parties for AG-C-310
executed on the 2nd day of September 2009 and amended by agreement dated the 161h day of
December, 2010, the 24'h day of March, 2011, the 81" day of November, 2011, the 15" day of
May, 2012, and the 17 In day of December 2012.
The changes to the agreement are described as follows:
1 CONTRACT TERM: The term of the Agreement for Professional Services is extended to
December 31, 2013.
2. SCOPE OF WORK. Change to the Scope of Work shown in Exhibit A-1
3 COMPENSATION. An additional $82,600.00 has been added to the amount authorized in
the original agreement.
REMAINING TERMS UNCHANGED: That all other provisions of the Agreement between
the parties for AG-C-374 executed on the 2nd day of September 2009 shall remain unchanged,
and in full force and effect.
IN WITNESS WHEREOF the parties hereto ha e e ted this Agreement as of the day
and ye jr above LRS .
CAR LL GINE NC. ITBy
Brian Ma n Vlce reser Peter B L ayor
ATTEST (Optional). AT'TT1�E/�ST(��
By
Its Danielle E Daskam, Auburn City Clerk
Approved as to form (Optional): Ap ov a r i
Attorney for (Other Party) Daniel B. Hei , ubur y A _
--------------------------------------------------------------
Amendment No 6 for Agreement No.AG-C-374
Carollo Engineers, Inc.
Page 1 of 1
EXHIBIT A-1
AMENDMENT #6
City of Auburn
Academy Booster Pump Station Construction Services
SCOPE OF SERVICES
Amendment No. 6 provides for additional engineering services during construction of the
Academy Booster pump Station project. The amendment includes a supplement to Task 100
and revisions to Task 800 within the scope of services of agreement AG-C-374 The
supplement to Task 100 and revisions to Task 800 are shown below
TASK 100 - PROJECT MANAGEMENT
Manage the work of the project team from notice to proceed to project closeout. Plan for and
carry out regular communication with the City during the project. Plan for and carry out quality
management.
Subtask 101 Project Administration. Administer contracts and manage the project team.
Activities
• Manage the project team to track time and budget, work elements accomplished, work
items planned for the next period, manpower, scope changes, time and budget needed to
complete this Scope of Services.
TASK 800 - ACADEMY ENGINEERING SERVICES DURING
CONSTRUCTION
Provide engineering services during construction. Provide office services such as bidding
services, submittal review, and development of record drawings. The tasks associated with this
section are described below
Subtask 803 Review Submittals. Receive, manage, review, and comment on contractor
submittals Coordinate with City staff as appropriate for the submittal being reviewed.
Activities
• Receive, log, and transmit submittals.
• Review and comment on submittals and re-submittals.
• Submit each submittal/re-submittal to City for approval.
• Submit responses to contractor upon City approval
CAROLLO ENGINEERS SCOPE OF SERVICES-VERSION 7 1 PAGE 1 OF 3
5/1/13
pv,1\000-p-app Camllol:kaumenls!QsNM'AVmburnlLa4.eland Htlls Pump Slalwn Prgecl MwgemenllCcntrxMExhibil A-Scope
City input
• Review Consultant responses.
Assumptions
• Consultant will receive either five (5) hard copies or one (1) electronic copy of each
submittal for review from the Contractor
• Consultant will retain one copy of each reviewed submittal/re-submittal for the
Consultant's file and one copy for City's file and return two (2) reviewed hard copies to the
Contractor if the submittals were received by mail or return one (1) reviewed electronic
copy to the Contractor (cc City of Auburn) if the submittals were sent electronically
• Assume up to a total of 200 submittals/re-submittals with an average budget of 2.5 hours
per submittal/re-submittal.
• City approval of Consultant responses will require no more than three (3) business days.
Deliverables
• Submittal reviews, either one (1) electronic copy or two (2) hard copies.
i
• Hard copy and electronic copy (CD) of all submittals/resubmittals at conclusion of
construction.
Subtask 804 Prepare Design Clarifications. Respond to Contractor generated requests for
clarification and/or information (RFI). Receive and prepare answers to RFL Coordinate with City
staff.
Activities
• Receive, manage, and take action on RFIs
• Prepare responses to RFIs.
City Input
• Review Consultant responses.
Assumptions
• Consultant will receive RFIs from the City
• Consultant will retain one copy for the Consultant's file
• Assume 20 RFIs at 4 hours each.
• City approval of Consultant responses will require no more than two (2) business days.
CAROLLO ENGINEERS SCOPE OF SERVICES-VERSION 7 1 PAGE 2 OF 3
5/1/13
pe\Iao-pry Aelanl Hills Poop Slalion'8wgecl MwagemenllConhacLSlExhiM A-Scope
Deliverables
• Electronic RFI responses.
Subtask 805 Attend Progress Meetings. Attendance at progress meetings will be authorized
by the City as required, based on a proposed scope, schedule, and budget. The work may
include, but not be limited to the following activities.
Activities
• Attend an average of two progress meetings per month over the course of a 12 month
period (total of 24 meetings)
City Input
• Coordinate timing of progress meetings and site visits
• Prepare and distribute progress meeting notes.
Assumptions
• Assume each progress meeting and/or site visit at 8 hours each including travel.
BUDGET
The following payment is requested as part of the services outlined in Amendment No. 6 below'
Subtask 100 Project Administration $13,710
Subtask 800 Engineering Services During Construction $68,890
Total $82,600
END OF SCOPE OF SERVICES
ACADEMY AND LAKELAND HILLS PUMP STATION PROJECT
CAROLLO ENGINEERS SCOPE OF SERVICES -VERSION 7 1 PAGE 3 OF 3
5/1/13
ao rloco-pN Hiles Purnp SlalionNrojm1 ManagrmenLConlractsTxh W A-Scepe
+ i
AlAURN Peter B. Lewis, Mayor
WASHINGTON
25 West Main Street * Auburn WA 98001-4998 * www.auburnwo.gov * 253-931.3000
May 8, 2013
Lara Kammereck
Carollo Engineers, Inc.
1218 Third Avenue, Suite 1600
Seattle, WA 98101
RE. Amendment No. 6 to Agreement for Professional Services, AG-C-374
Project No. CP0909, Academy and Lakeland Hills Booster Pump Station Improvements
Dear Ms. Kammereck:
Enclosed please find an executed copy of the above referenced Amendment No, 6. This
amends the scope of work as described in Exhibit A-1 and includes additional compensation in
the amount of$82,600.00.
For the City's tracking and record keeping purposes, please reference AG-C-374 and Project
No. CP0909 on all correspondence and related material.
As the project manager, I am the designated contact for this agreement and all amendments.
Questions, assignments and coordination shall be routed through me. You can contact me at
253-931-3086.
Sincerely,
e ondrak, P.E.
Project Engineer
Department of Public Works
RV/ja/mh
Enclosure
cc: Dani Daskam, City Clerk (copy letter only)
AG-C-374
CP0909 - 2.20
AUBURN * MORE THAN YOU IMAGINED
AMENDMENT #7 TO AGREEMENT NO. AG-C-374 BETWEEN
THE CITY OF AUBURN AND CAROLLO ENGINEERS, INC.
RELATING TO PROJECT CP0909, ACADEMY AND LAKELAND HILLS BOOSTER
PUMP STATION IMPROVEMENTS •
/ JI
THIS AMENDMENT is made and entered into this /day of y..tab , 2013, by
and between the CITY OF AUBURN, a municipal corporation of the State of Washington
(hereinafter referred to as the "CITY"), and Carollo Engineers, Inc. (hereinafter referred to as the
"CONSULTANT"), as an Amendment to the Agreement between the parties for AG-C-374
executed on the 2nd day of September 2009 and amended by agreement dated the 16th day of
December, 2010, the 24th day of March, 2011, the 8th day of November, 2011, the 15th day of
May, 2012, the 17th day of December 2012 and amended by agreement the 7th day of May
2013.
The changes to the agreement are described as follows:
1. CONTRACT TERM: The term of the Agreement for Professional Services is extended
to December 31, 2014.
2. SCOPE OF WORK: There is no change in the scope of work.
3. COMPENSATION: There is no change to the amount authorized in the original
agreement or subsequent amendments.
REMAINING TERMS UNCHANGED: That all other provisions of the Agreement between
the parties for AG-C-374 executed on the 2nd day of September 2009 shall remain unchanged,
and in full force and effect.
IN WITNESS WHEREOF the parties hereto have executed this Agreement as of the day
and year first above w itten.
CAR* LO ' NGINEE"S, INC. CIT OF -
_Jr
By:
� L
Brian Ma • , enior Vice President Peter B. Lewis, Mayor
ATTEST (Optional): ATTEST:
By: C1, (s.1 �
Its: Danielle E. Daskam, Auburn City Clerk
Approved as to form (Optional): Appro - >' as
Attorney for (Other Party) Da7iir B Hei.;•uburn rAt orney
Amendment No.7 for Agreement No.AG-C-374
Carollo Engineers.Inc.
Page 1 of 1
CITY 01 ,
T T Peter B. Lewis, Mayor
WASHING IO N 25 West Main Street * Auburn WA 98001-4998 * www.auburnwa.gov * 253-931-3000
December 10, 2013
Lara Kammereck
Carollo Engineers, Inc.
1218 Third Avenue, Suite 1600
Seattle, WA 98101
RE: Amendment No. 7 to Agreement for Professional Services, AG-C-374
Project No. CP0909 Lakeland Hills Booster Pump Station Improvements
Dear Ms. Kammereck:
Enclosed please find an executed copy of the above-referenced Amendment No. 7. This
amendment is for a time extension only. This amendment extends the term of the agreement
to December 31, 2014.
For the City's tracking and record keeping purposes, please reference AG-C-374 and Project
No. CP0909 on all correspondence and related material. Our records indicate that your
Insurance, as required in Section 10 of the original agreement, will expire on December 31,
2013. Please mail the required certificate(s) of insurance, within two weeks, to JoAnne
Andersen, Contracts Administration Specialist, Auburn Community Development & Public
Works Department, at the address noted at the top of this letterhead.
As the project manager, I am the designated contact for this agreement and all amendments.
Questions, assignments and coordination shall be routed through me. You can contact me at
253-931-3086.
Sincerely, )--: -
(Ryan Vondrak I
Sr. Project Engineer
Community Development & Public Works Dept.
RV/ja/mh
Enclosure
cc: Dani Daskam, City Clerk (copy letter only)
AG-C-374
CP0909 (2.20)
tJIMRN , tvOR1 TI IAN YOU IMA(!INII)
AMENDMENT #8 TO AGREEMENT NO. AG -C -374 BETWEEN
THE CITY OF AUBURN AND CARDLLO ENGINEERS, INC.
RELATING TO PROJECT NO. CP0909, ACADEMY & LAKELAND HILLS
BOOSTER PUMP STATION IMPROVEMENTS
THIS AMENDMENT is made and entered into this day of 4X '2014, by and
between the CITY OF AUBURN, a municipal corporation of the State of Washington (hereinafter referred
to as the "CITY "), and CAROLLO ENGINEERS, INC. (hereinafter referred to as the "CONSULTANT'), as
an Amendment to the Agreement between the parties for AG -C -374 executed on the 2nd day of
September 2009; amended by agreement dated the 18" day of December 2010; amended by agreement
dated the 24' day of March, 2011; amended by agreement dated the 8'" day of November, 2011;
amended by agreement dated the 15'" day of May, 2012; amended by agreement the 17'" day of
December, 2012; amended by agreement the 7" day of May 2013 and amended by agreement the 9d'
day of December, 2013.
The changes to the agreement are described as follows:
1. CONTRACT TERM: The term of the Agreement for Professional Services is extended to June 30,
2015.
2. SCOPE OF WORK: There is no change in the scope of work.
3. COMPENSATION: There is no change to the amount authorized in the anginal agreement.
REMAINING TERMS UNCHANGED: That all other provisions of the Agreement between the parties
for AG -C -374 executed on the 2nd day of September 2009 shall remain unchanged, and in full force and
effect.
IN WITNESS WHEREOF the parties hereto have executed this Agreement as of the day and year
first above written.
CIAROLLO ENGINEERS, INC. CITY F AUBURN
L.cj, -Vc,- ,
Lara Kammereck, Vice President ancy Back Mayor
ATTEST (Optional): ATTEST:
By: ka4>d
Its: Danielle E. Daskam, Auburn City Clerk
Approved as to form (Optional): Appro 4daa6to
Attorneyfor(OtherParty) D or ney
Amendment No. 8 for Agreement No. AG -C -374
Carollo Engineers, Inc.
Page 1 of 1
A-0-AukN Nancy Backus, Mayor
_ WASHINGTON 25 West Maln Street # Auburn WA 98001 -4998 1, www,auburnwa.gov s 253- 931 -3000
November 26, 2014
Lara Kammereck
Carollo Engineers, Inc.
1218 Third Avenue, Suite 1600
Seattle, WA 98101
RE: Amendment No. 8 to Agreement for Professional Services, AG -C -374
Project No. CP0909, Academy & Lakeland Hills
Booster Pump Station Improvements
Dear Ms. Kammereck:
Enclosed please find an executed copy of the above - referenced Amendment No. 8. This
amendment is for a time extension only. This amendment extends the term of the
agreement to June 30, 2015.
For the City's tracking and record keeping purposes, please reference AG -C -374 and
Project No. CP0909 on all correspondence and related material. Our records indicate that
your insurance, as required in Section 10 of the original agreement, will expire on
December 31, 2014. Please mail the renewal certificate(s) of insurance, to JoAnne
Andersen, Contracts Administration Specialist, Auburn Community Development & Public
Works Department, at the address noted at the top of this letterhead.
As the project manager, I am the designated contact for this agreement and all
amendments. Questions, assignments and coordination shall be routed through me.
You can contact me at 253 - 931 -3086.
Sincerely,
yan Vondrak, P.E.
Capital Projects Manager
Community Development & Public Works Department
RV /ja /mt
Enclosure
cc: Dani Daskam, City Clerk (copy letter only)
AG -C -374
CP0909 (2.20)