HomeMy WebLinkAboutITEM III-CCITY OF AUBURN
PUBLIC WORKS COMMITTEE
January 4, 2010
1. CALL TO ORDER
WASHINGTON
DRAFT MINUTES
Chairman Rich Wagner called the meeting to order at 3:30 p.m. in Room 3, located on the second
floor of Auburn City Hall, 25 West Main Street, Auburn, Washington. Committee members present
were: Chairman Rich Wagner, Vice-Chair Sue Singer, and Member Bill Peloza. Also present
during the meeting were: Mayor Peter B. Lewis, Public Works Director Dennis Dowdy, City
Engineer/Assistant Director Dennis Selle, Assistant City Engineer Ingrid Gaub, Traffic Engineer
Pablo Para, Storm Drainage Engineer Tim Carlaw, Utilities Civil Engineer Joel Chalmers, Office
Assistant Heather Mustain, Citizen Wayne Osborn, and Department Secretary Jennifer Rigsby.
II. CONSENT AGENDA
A. APPROVAL OF MINUTES
Vice-Chair Singer verified that it has been declared a felony to tamper with the flood
preparedness apparatuses. Mayor Lewis explained there are two charges that can be brought
against an individual, trespassing and malicious mischief, the later being the charge that will be
sought. Mayor Lewis stated there is a route to charge individuals with a felony and the City is
prepared to do so, if necessary.
It was moved by Vice-Chair Singer, seconded by Chairman Wagner, that the Committee
approve the Public Works Committee minutes for date, December 21, 2009.
Motion carried 3-0.
B. APPROVE CHANGE ORDER NO. 1 AND FINAL PAY ESTIMATE NO. 2 TO CONTRACT NO.
08-19 IN THE AMOUNT OF $32,490.37 FOR A TOTAL CONTRACT PRICE OF $191,869.85
WITH R.W. SCOTT CONSTRUCTION CO. AND ACCEPT CONSTRUCTION OF PROJECT
NO. CP0743, 2007 LOCAL STORM IMPROVEMENT PROJECT
Storm Drainage Engineer Carlaw was present. Vice-Chair Singer asked if a developer would
ordinarily be responsible to complete this project. Carlaw answered this project was completed
to improve the existing flooding conditions within the existing road right-of-way that was
unrelated to recent development.
It was moved by Vice-Chair Singer, seconded by Member Peloza, that the Committee
recommend that Council approve Change Order No. 1 and Final Pay Estimate No. 2 to
Contract No. 08-19 and accept construction of Project No. CP0743, 2007 Local Storm
Improvement Project.
Motion carried 3-0.
Page 1
Public Works Committee Minutes Januarv 4, 2010
DRAFT MINUTES
III. ISSUES
There were no issues for action.
IV. DISCUSSION AND INFORMATION
A. REPORT OF THE CITY'S PAVEMENT DATA BASE
Street System Engineer Wickstrom provided a summary of the pavement data base for the
Committee. Wickstrom stated there are two parts to the data base; 1) the data on the streets in
the City and the condition of the pavement and 2) the ability to run budget scenarios. Director
Dowdy pointed out that the program has the City's most recent average cost data, costs per
square foot, in order to complete budgeting scenarios and the reports were used to provide
data to the Citizens' Arterial Task Force.
Street System Engineer Wickstrom responded to questions from Chairman Wagner regarding
the WSDOT standards used to collect visual inspection data.
Vice-Chair Singer asked if the measurements used were common among the Valley Cities.
Director powdy stated the State does the pavement ratings for smaller cities and therefore the
smaller cities are not familiar with the process. Mayor Lewis commented some of the Valley
Cities do not map and plan as the City of Auburn does.
Wickstrom described the pavement distress type, raveling, following questions asked by
Chairman Wagner. Director powdy explained that UV damage primarily contributes to raveling
of pavement.
Street System Engineer Wickstrom explained how the street system is divided into sections
within the database and these sections are not related to the miles of streets within the City.
Chairman Wagner asked how staff determines which streets to include in pavement
preservation projects using the Street Saver data. Wickstrom answered staff not only uses the
PCI data from Street Saver, but also conducts on site visual inspections. Assistant Director/City
Engineer Selle stated engineering staff also collects data from street maintenance staff
regarding streets that require significant maintenance efforts.
Assistant Director/City Engineer described the thick overlay with fabric treatment, in response to
questions asked by Member Peloza. Director powdy spoke about the double chip seal process
and how staff determines which streets are candidates for the double chip seal treatment.
Assistant City Engineer Gaub spoke about the cost of treatment per square yard estimates
within the database and how those costs do not include other work normally completed with a
reconstruction project such as utility work. Assistant Director/City Engineer Selle explained the
cost per square foot is an average. Director powdy spoke about the need to complete as much
deep patching as possible to avoid complete street rebuilds. Selle stated complete rebuilds are
not only expensive, but also inconvenient to the traveling public.
B. FLOOD PREPAREDNESS STATUS UPDATE
Director powdy reported that King County is completing work at the Auburn Golf Course. The
Committee discussed the capping of culverts. Director powdy stated staff has reviewed the
location for pumps in the case of a flood event.
Page 2
Pubiic Works Committee Minutes Januarv 4, 2010
DRAFT MINUTES
C. CAPITAL PROJECT STATUS REPORT
Item 9- Proiect No. CP0815 - Mary Olson Farm Phase III: Member Peloza asked why the
project is in suspension. Assistant City Engineer Gaub stated the current contract is a material
procurement contract and as materials are being procured the project is in suspension and
once the materials are obtained, the project timeline will begin again as they are delivered and
installed by others.
Item 14 - Proiect No CP0819 - Mill Creek/Peaslev Canvon Culvert Replacement: Staff
verified the location of the failing culvert in response to questions asked by Member Peloza.
Assistant Director/City Engineer Selle describe the current deteriorated condition of the culvert.
Chairman Wagner asked what the plan is in the event of complete failure. Selle answered the
road would need to be closed while staff devised a solution for diverting water and repairing the
roadway. Assistant Director/City Engineer Selle said the primary concern is collapse of the
road, which is why the steel plate improvements are in place.
Vice-Chair Singer described the lack of demarcation between the Park and Ride lot and
Peasley Canyon Road and staff agreed to go look at the problem and work on delineating the
lot from the street.
Item 18 - Proiect No. C524A - SCADA Svstem Improvements: Assistant City Engineer Gaub
answered questions asked by Chairman Wagner regarding the preliminary design for the
project and the completion of design which will be executed by the selected vendor. Chairman
Wagner stated the Committee should revisit the project before implementation contracts are
authorized.
Member Peloza asked about security at the pump stations. Director powdy responded the
focus of the project is to bring the pump stations on line and get the new software online.
Assistant Director/City Engineer Selle explained the flexibility of the new system will allow for
addition of security components in the future.
Item 19 - Proiect No CP0817 - 2009 Sewer & Storm Pump Station Replacement - Phase B,
Ellinqson: Chairman Wagner asked if poor design led to the need to replace the pump station.
Assistant City Engineer Gaub answered design was not a primary factor, the pump is at the end
of its life and it is time for replacement.
Item 21 - Proiect No CP0956 - Lea Hill Pump Station. Decommissioninq: Member Peloza
asked for clarification on the location of the Verdana Development which is within Kent's
jurisdiction in the Lea Hill area.
Item 23 - Proiect No CP0803 - 37th Street SE/R Street Pedestrian Connector: Assistant City
Engineer Gaub answered questions asked by Chairman Wagner regarding the dedication of
Right-of-Way and the Quit Claim Deed Agreement that staff is working on with Segale for an
area of property indicated as Right-of-way by the County assessor but no dedication of the area
ever occurred.
Item 24 - Proiect No C5076 - Auburn/ Pacific Trail Phase 2: Assistant City Engineer Gaub
answered questions asked by Chairman Wagner regarding the portion of the project funding
being provided by the City of Pacific. Vice-Chair Singer commented that Pacific received a
grant to fund the project.
Page 3
Public Works Committee Minutes Januarv 4, 2010
DRAFT MINUTES
Assistant City Engineer Gaub answered questions asked by Member Peloza regarding
amending the agreement with Pacific.
Vice-Chair Singer asked if the ITS project, for which the City just received funding, is included
on the current Capital Project Status Report (CPS). Assistant City Engineer Gaub stated the
CPS report includes the current active projects and when that particular phase of the ITS
project moves forward, it will be included on the report. Chairman Wagner verified the project is
included in the Transportation Improvement Program and the city's Capital Facilities Plan. The
Committee and staff discussed the scope of the project. Chairman Wagner discussed the
possible need to review the intersection at 41St Street SE.
Item 27 - Proiect No. CP0915 - Well 1 Improvements: Assistant City Engineer Gaub answered
questions asked by Chairman Wagner regarding the budget discrepancy, stating the report still
needs to be updated to incorporate the recently approved 2010 budget amendments.
Item 29 - Proiect No CP0916 - West Vallev Hiqhwav - SR 18 to W Main: Chairman Wagner
asked what is involved in consultant scoping. Assistant City Engineer Gaub answered that the
consultant has been selected and staff is negotiating the contract for design work and will then
bring it to Committee for discussion and approval.
Item 30 - Proiect No C518A - Downtown Water Qualitv Facilitv: Assistant City Engineer Gaub
answered questions asked by Member Peloza regarding the movement of stormwater around
the Auburn Environmental Park.
Item 34 - Project No. CP0901 - 2009 Local Street Pavement Preservation; Assistant City
Engineer Gaub responded to questions asked by Member Peloza regarding Save Our Streets
funding and how the funds are represented on the CPS report. Revisions to future reports will
be made to indicate the total SOS program value.
V. ADJOURNMENT
There being no further business to come before the Public Works Committee, the meeting was
adjourned at 4:17 p.m.
Approved this day of
2010.
Rich Wagner
Chairman
Jennifer Rigsby
Public Works Department Secretary