Loading...
HomeMy WebLinkAboutITEM II-CCITY OF AGENDA BILL APPROVAL FORM * WASHINGTON Agenda Subject: Change Order No. 2 to Contract 09-08 Date: February 23, 2010 Department: Attachments: Budget Impact: Public Works Bud et Status Sheet & Map $ 0 Administrative Recommendation: City Council approve Change Order No. 2 in the amount of $59,260 to Contract 09-08 with Global Contractors, LLC for work on project CP0904, 2009 Citywide Sidewalk Repair Project. Background Summary: The purpose of this project is to repair damaged sidewalks on approximately 7.3 miles of streets throughout the City with an emphasis on fixing potential tripping hazards. This will mainly be accomplished by removing and replacing damaged concrete sidewalk panels. Sidewalks located in the white area (with a grey outline) shown on the attached map are part of the original project scope and have been comprehensively repaired as part of this project. Sidewalks located in the grey area (with a black outline) shown on the attached map will be added to the project as part of Change Order #2. These project areas were selected based on the severity of the sidewalks, citizen complaints, and coordination with past SOS street improvements. Tree roots that are damaging the sidewalk will be pruned. Trees will only be removed if root pruning would be insufficient to properly fix the sidewalk (if the tree is located too close to the sidewalk for example). All tree removals will be coordinated with the adjacent property owner. $210,700 is budgeted in the 328 Fund for sidewalk improvements in 2009. Approximately $3,000 of this budget was spent on sidewalk repairs as part of the R Street SE Utility Improvement Project (Project C504A). The remaining $207,700 will fund this project. A project budget contingency of $30,084 remains in the 328 fund. Approximately $45,000 from the 103 (Local Street) Fund will be utilized for wheelchair ramp replacements. W0301-3 Reviewed by Council & Committees: Reviewed by Departments & Divisions: ❑ Arts Commission COUNCIL COMMITTEES: ❑ Building ❑ M&0 ❑ Airport ❑ Finance ❑ Cemetery ❑ Mayor ❑ Hearing Examiner ❑ Municipal Serv. ❑ Finance ❑ Parks ❑ Human Services ❑ Planning & CD ❑ Fire ❑ Planning ❑ Park Board ®Public Works ❑ Legal ❑ Police ❑ Planning Comm. ❑ Other ®Public Works ❑ Human Resources Action: Committee Approval: ❑Yes ❑No Council Approval: ❑Yes ❑No Call for Public Hearing I l Referred to Until I l Tabled Until I I Councilmember: Wa ner Staff: Dowd Meetin Date:: March 1, 2010 Item Number: k t + •1~ BUDGET STATUS SHEET Project No: CP0904 Project Title: 2009 Citywide Sidewalk Improvements Project Manager: Seth Wickstrom Project Initiation Initiation Date: _February 2, 2009 0 Permission to Advertise Date: February 23, 2009 Advertisement Date: _September 24, 2009 0 Contract Award Award Date: November 2, 2009 0 Change Order Approval 0 Contract Final Acceptance The "Future Years" column indicates the projected amount to be requested in future budgets. Funds Budgeted (Funds Available) Funding Prior Years 2009 2010 Future Years Total 328 Fund -Capital Improvement Fund 175,000 175,000 328 Fund -Capital Improvement Fund 10,700 10,700 (carry-forward from 2008) 328 Fund -Capital Improvement Fund (remaining balance from Project C504A - 22,000 22,000 R St SE Utility Improvement Project) 103 Fund -Local Street Fund 45,000 45,000 (for wheelchair ramps replacements) Total 0 252,700 0 0 252,700 Estimated Cost (Funds Needed) Activity Prior Years 2009 2010 Future Years Total Design Engineering - City Costs* 305 305 Construction Estimate 55,398 80,012 135,410 Change Order #2 59,260 59,260 Authorized Contingency (20%) 27,082 27,082 Construction Engineering -City Costs* 558 558 Total 0 56,261 166,354 0 222,616 *City staff costs are charged against the Engineering Budget and not the Project Budget, and are not shown here. 328 Capital Improvement Budget Status Prior Years 2009 2010 Future Years Total **328 Funds Budgeted 0 (207,700) 0 0 (207,700) 328 Funds Needed 0 56,261 121,354 0 177,616 **328 Fund Project Contingency 0 (151,439) 0 0 (30,084) 328 Funds Required 0 0 121,354 0 0 103 Local Street Budget Status Prior Years 2009 2010 Future Years Total **103 Funds Budgeted 0 (45,000) 0 0 (45,000) 103 Funds Needed 0 45,000 0 45,000 **103 Fund Project Contingency 0 (45,000) 0 0 0 103 Funds Required 0 0 45,000 0 0 in the Budget Status Sections indicates Money the City has available. W0301-3A 1 of 1 z ~ ~ z ~ ~ ~ ~ aW ~ ~ ~ E z F PL NE w a z o 7th ST NE 6$ q 7th ST E ~f~~S ~ H FIE ~R 1 G ~ ~ ~ 3rd ST N~ z _ 6th ST ~~~o~l~~ 5th ST NE ~ ~ ~ ~ T~ 5th NE Stn s~ NE ~ ~ 2~c~ ~T N PARK ~ ~ l ~ PARK AVE ~ ~ sT ~ ~ N~ ~ 1~E ~ ~a 4th ~ ~ ~ ~ ~ s~, S~ N~ 3r5 A ~I~ ~I~1~ ~ 3~6 ST N~ ~ ~ 3r ST NE ~ ~ ~ ~ HI GPI ~ ~ ~ ~ 2n ~ ~ ~ ~ end ST NE ITY ~ w ~ ~ ST N SC~oo~ ~ 1st ST NE ~ AL1,~j m z Est ~ mz EAS S ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 2r~d GN~ ~ 2n ST ~ ~ ~ ~ SE ~ ~ ~ ~T4C~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 3E~d ~ ~ ~ ~ ~ ~~oN'S 4th ~ ST ~ ~ ~ SE ~ ~ ~ ~ BURLINGTON ~ NORTHER"I } ~ ~ ~ ~ ~ `fir ~L BI ENT L 6tN ST SE ~ BtJRLIi-GTON ~ NORTIHEY~N Oth SE ARx ~ ~ ~ Ttl~ ~ ST ~ SE ~ ~ Tth sE 8tN ST SE ~ ~ ~ sT SSE ~ 9th ~ sE ~~S =RAMP REPLACEMENT LOCATION nth ~ GOVE E-, ~ ~ ~ fl Oth ST ~ ~ ~ ,6th ST PARS ~ U1 F ~atn sE ~ Pr 11th ~ ~ ~ ~ t2th S't SE ~ ~ 13TE SE ~ w ~ 14th SE ~ Q ~ w ~ ~ ~ (I 15th SE ~ ~ ~ ~ " 2 ~ i i 16th SE W ~ ~ ~ - 1'7th ST ~ sE ~ ; ~ ~ w I) ~ G PL ~ ~ 18th ST ~ ~ ~ ~ ~ Rv 19th sT ~ sE = 1 ~ ' ~p~ ~ ~ ~ ~ ~ ~~T ;~E '0th ST SE 21stro~ ~ ~ SE pl ~ 2 TH CT U ~ +J odJ ~~Le~~ SE r ~i St ST SE ~ oU~'zr - - i ~ S~ SE III ~I c r~I SHAUCHNE''Y ~ CEDAR DR SE C~ ~J'l l W o I W ~ ~ 2~n~ sT SE ' PAE (III 2~T1d S~ SE ~ 23RD PLC ~ 23r8 ST SE ~ 3rd ~ ST SE ~ 23Ed S'Y' SE ~ ' ~~~U ~ z iiii Q ~ ~ 24th ~T x ~4th~ ST SE ~ ~ ~4ti- SE ~ ~ o 25tIa ST SE 5th ST SE L ~ ~ PoPEAR w ~ C~'~A~ ~ ~ ~ 26tH Q R(, ~y 26TH ST SE ~y ~~6th T SE ~~th S~ SE ~ H w ~ a Q ~ a, ~~1 r~ ry ~ ~ P~1 a a o - o wl ~ T. _ ~ rh ~T ~ a ~ ~ ~ I .,F. Q ~ ~ ~ ~ 2'~th ST SE ~ 1 r~t6 ST sr >>t6 sT _ ~ o ~ ~ ~ ~ w F ~ Q ~ ~ ~ 28th ST DR 28t1~ ST SE th ~"1' z ~ ~ t6 ST sr TT ~ D PL SE r r R Pr W i Cll~ Y ~~t~ ~T , U ~ ~ ~ RIDGE a ~ ~ w ~1 K ~ - - ~ ~ ~ 30t1~€~ ST SE AI ~ ~ 3~st S~ SE G`!~o~ ~ ~~~o ~ 32~ sE 3rd STtJCN h~IVER ~~IVE 33~ w ~ ~ ~ ~1 ~ M Pr o ~ 35th ST SE ~ F 3T SE ~ ~ ~ " ~ 37th PL ~ ~ ~ ~ ~ ~ ~ ~ ~ 3'7th ST SE ~ _ D PL SE ■ ■ ■ ■ ■ ~ wi e ~ ewa a air ro ec PRO]ECT AREA: Sidewalks in these OPTIONAL PRO]ECT AREA: Sidewalks areas will be repaired as part of this in these areas will be repaired as part of 0 850' 1,700' project, this project as the budget allows. Scale: 1" = 1,700' Printed On: 10/23/2009 Location: H:\PROJ\CP0904 2009 Citywide Sidewalk Repair Project\PWCCouncilInto\Award (PWC 11-2-09)\Map dwg I