HomeMy WebLinkAboutITEM V-C-2 CI7'Y OF * AGENDA BILL APPROVAL FORM WASHINGTON Agenda Subject: Date: May 10, 2010 Final Pa Estimate No. 5 to Contract 06-26 DeparEment: Attachments: Budget Status Sheet, Budget Impact: Public Works _ Final Pa Estimate No. 5 $ 0 Administrative Recommendation: Gity Council approve Final Pay Estimate No. 5 to Contract No. 06-26 in the amount of $26,862.85 for a total contract price of $7403617.75 with Signal Electric and accept construction of Project No. C307B, C' ide lntelli ent Trans ortation S stem ITS Phase 1 B. Background Summary: Thi"s project provided for the expansion of the existing Intelligent Transportation System (ITS) for efficient realtime traffic management and ineident management on specifie comdors within the City and added 13 cameras and over 30 existing signals to the ITS system. The work includes the following elements: • A communication system thaf enables signal coordination, Video transmission and data collection along the Aubum Way North and the S 277th Street Corridors. • Gonnections and upgrades to existing communications sysfems on 37th St NW, 45th St NW, . Harvey and M Streef and all of downtown. • Provide for a fi6er optic connection between the Washington Department of Transportation (WSDqT) and King Gounty ITS infrastructure allowing for data and video sharing as appropriate between the City of Aubum, WSDOT and King County Traffic Control Centers. This will also allow for the display of traffic conditions in the City of Aubum on the WSDOT and King County commuter web pages. • Provided for replacement of the existing signal power cabinets providing 12 new Battery Backup systems and uninterruptible signal power supplies along the S 277th and Aubum Way North corridors. A project budget contingency of $2,430 remains in the 102 fund. W0517-6 04.10.2 C3076 Reviewed by Council 8 Committees: • Reviewed by Departments & Divisions: ❑ Arts Commission GOUNCIL COMMITTEES: O Buitding ❑ M&O ' ❑ Airport ❑ Finance ❑ Cemetery ❑ Mayor ❑ Hearing Examiner ❑ Municipal Serv. ❑ Finance ❑ P_arks _ 0 Human Services ❑ Planning & CD . ❑ Fire ❑ Planning ❑ Park Board OPubliaWorks ❑ Legal ❑ Police . ❑ planning Comm. ❑ Other 0 Public Works ❑ Human Resources Action: Committee Approval: ❑Yes ❑No Council Approval: ❑Yes ❑No Call for Public Hearing Referred to Until Tabled Until Councilmember: Wa ner Staff: Dowd Meetin Date: : Ma 17, 2010 Item Number: V.C.2 AUBURN*MOR.E THAN YOU IMAGINED BUDGET STATUS SHEET lProject No: C3078 Pro a nne: Clty wme imew M rrans non s mms irs Phase Ie ProJeet Manager., Seott Nulter - . , 0 ConsulfaMAgreement . . IniUaOon Dater Seotember 17: 2007 0 Pennision to AdveRba Date: April 29, 2010 ACvertisement.Date: -Aori18.2009.. Q CorHradAward Award Date: Aueust 12009 Q Change O[der Approval I& Contrad Flnal Acwpfance Funds Bud eted Funds Available . Fundin , PriorYeare 2009 . 2070 Totat 102 Fwnd - Unrestricted Street Fund $O $O $O $O IS ComrlCution, Prcportlonal sliare of Flber (Transter from 518 Fund) $61,000 $81,000 ' Eortion of Slpnal Improvement budget (Trensfer hom 328 Fund) , . $141,824 $141,824 Mudcleshoot Indlan TAba E300,000 , $300,000 Kinp CouMy $500,000 $500.000 FederalAidFunding $995,100 5242,431 $141,000 $1,378,531 Puhlic Worke Trtut Fund Phase 18 Only 5761,577 $2,142 $163,713 CAAAG Federel Grsiit 8290,000 $280,000 - ' . _TratACMiti atlon. _ S51,812 826.800 578.612 ' . - Total 52,008,483 5784,197 $141,000 $2,833.880 EstJmated Cost Funtls Needed , Activity PriorYears . 2008 2010 Total . Phase 1A _ DeBign EngineeAng - Clty Costs Phase 1A . $21.958 EO 521.958 Oesign Enpineenng - Consultent Costa Phase tA $297.640 $O . $297,640 IT Pmcuremerri Phase tA $366.752 SO 5368,152 Conslruction ConLrad Phase 1A $960.466 $O $980,468 , CcnatruiWon EngineeAng Phase 1A $32.990 - $O $32.990 Phase 16 Desipn Enpirreering In Houae Phase 18 $1,071 E14,709 EO $75,780 DaW0Fn En-9ineeat49 Consultant Ptiase t B $153,179 $29,483 SO $182,872 Permit PSE ( WSDOT Costs ' $7,320 $18,507 $592 $28,419 ITProwrementPhaselB $167,707 $19,190 $16,985 E203,882 . Construction C6ntraGBid $O S638,980 $72,276 E712.236 Change Order#1 $4,633 $4,633 Chanpa Order #2 $23,600 $23,600 Chanpe Order #3 S1,460 $1,400 Change Order#4 $2,884 $2,884 ChenpeOMer#5 . $15,544 S15,544 Lineitem Chanpes (S79,479) (S19,479) ConstruGion EngineaAng In House Phase 18 SO . $30,021 E52,652 $82,873 ConsWCtlan EnOineeAn9 (WSDO'n Phase 1B $O $0 $O $0 - - Totsl $2.008.483 5784.197 $138,570 52.931.250 102 Arterlal Street Bud et Prior Veara _2009. 2010 Total 102 Funtls BuGgeted E2,008,483 $703,197 , E141,000 52,933,680 _ 102 Funds Needed. $2,008,483 $703,197 $138,570 $2,931,250 102 Fuiid Pi-oled Contlngancy) $O $0 $2 430 $2 43Q 102 Funda Re ulred $O $0 $O $O . ' W0517-6A 1 of 1 , CITY OF AUBURN CO. N0. 08-26 C307B0 Citywidw ITS, Phase 1B PAY ESTIMATE #5 8 FINAL SCHEDULE A: IT3' Improvemenffi ITEM ESTiMATE TOTAL PERIOD PERCENT EST. NO. ITEM DESCRIPTION QUANTITY QUANTITY QUANTITY UNIT TYPE UMIT COST ' TOTAL COST PERIOD COST QTM. 1 nor ange 1 0.6864 sbma e . 5: $ -858:00 $ _ 69 - 2 ~ne=Year arran on TNroTFFiVVA-Eligiblej- f 1 S 2, 75 .00 $ 2,750:00 $ - 100% - 3- an 1, T S ,0 : 0 $ 1,000:00 $ - 100% - sPGG a rope es ora ion 1 0 stimate O,UO . 0. $ - $ - 096 _ _5o ilization--- _.._...._...._....--1 ---_.------1 LS 15,000.00 $ 15,000:00 $ - 100% - - - 6Va c on oor - 500 430.5 - 34.5 R' 48:00 $ 20,664:00 $ 1,656:00 86% 7 c. on upervisor 1 t 0 LS 25,000.00 $ 25,000:00 $ - 100% . 8_ . equen ia-I-Arrow ign - 60 109 Day 2:00 $ 2,180.00 $ - 182°r6 - g uTsiae gency n orme o ice F ag ig ng' ~ 1 o Estlmate ,000:00 $ - $ - 036 10 Tnci en 25. 14.58 Ton 250.00 $ 3,640.00 $ - 58q6 11 sp a o ix 25 24.09 on 100.00 $ 2,409:00 $ - 9696 emporary a er o u io rosion on of 1 0 Es imate 5, 0:00 $ - $ - 0°k 13 n scape es ora ion 1 2.48752 ~ 2.48752 Estimate 800.00 $ 1,990.02 $ 1,990.02 24996 14 n ustna an ommerc a nveway ron 90 124.66 28.38 Y 300.00 $ 37,398.00 $ 8,514:00 939% ~ 15 ement ncre e i ewa 336 : 338.62 -16:82 S 50: 0$ 18,931.00 $ (841:00) 101% is on u ipe nc ame er - 270 264 LF 3:00 $ 792:00 $ - 98% ~ 17 on u ipe - n iame er 700 418 LF 4.00 $ 1,672.00 $ - 60% - 18 ~ ren ng an a ing 725 638 L. 4. $ 2,552.00 $ - 88% -19 ' o ng un ion ox - ype 2 2 250.00 $ 500.00 - 100% 20- oc1. cingJun on ox - yPe 2 -2 • 1;000.00 $ 2,000.00 $ - 100% 21 re ona nng n on u 985 1016 L 44.00 $ 44,704.00 $ - 103°6 22 a~Finc nner ud 6050 4839 LF 3.00 $ 13,917.00 $ - 779b 23 Pu .~l! ox - 8 s EA 1,600.00 $ 9,600.00 $ - 100% Zq a e auff---- 11 10 EA 3,000.00 $ 30,000.00 $ - 91% 25 essenger a e 12745 15483 LF 2. 0$ 38,707.50 $ - 121°6 26 Liuy n~- 7 4 200.00 $ 800.00 $ - 5756 27- ervice a ine vn a ery ac up e roi - 6 6 EA 9,000.00 $ 54,000.00 $ - 100% ---28 ernce a ne with a ery ackupRetrofit 5 5 EA 10,000:00 $ 50,000.00 $ - 100% 29 ean an ssess oc e on u 1 2.833754 1.507054 stimate 000.00 S 13,188.77 $ 7,53527 2639b gp - uiaTrary~ommumca ons a ne 2 2 E4 5,900:00 14,800.00 $ - 1o09b --3~--- CClVCamera S`ysfem - 12 12 ----EA 5,550.00 $ 68,600.00 $ - 100% 32 C`ommunica-fion y- s~fem ------------1 ~ 1 S 38,853.00 $ 36.853.00 $ - 100% 33 i er p ic a e- ran 3745 3173 .30 S 4,124.90 $ - 85% 34 - i~e~ Qpfic:CaTife -~S~rand3`1VIFt3_..--------_. ..---~-30 31618 LF 3.34 $ 105.604.12 $ - 102% '35 FiWr-Cfpfic3`plice ~an 17 14 EA 3,050.00 $ 42,700.00 $ - 82% 38 a~Fic Panefin a ne 18 18 3,098.00 $ 49,568.00 $ - 100% - 3~ - Patch*l~aneftn'TM~----- - 1 1 EA 12,810.00 S 12.810.00 $ - 10096 - - C01-1~ Ledderl~ack for Cit~r HalTfermi'~ion - ~ - _ _ 1 _ - - 1,37 .95 $ 1,371.95 $ 10096 - - - -fo vmlf racr ® if~Aall---------- - 1-~-- t LS 971.37 $ 971.37 $ - 100% COt-2 ange• C01-3 ange, o conneC ors r City a 1 1 2,288.9 $ 2,288.99 $ - 100-A SCHEDULE SUBTOTAL $ 18,854.29._ Period Datea Begin: Jan 21, 2010 • - End: Mar 05, 2010 h:lprojlpe1C307B0 PE.)ds 1 of 5 4121/2010 at 1:42 PM CITY OF AUBURN CO.;NO. 08-26 C307B0 , Citywide ITS, Phase 16 PAY ESTIMATE(#5.& FINAL SCHEDULE A: JITS:Improvements ITEM ESTIAAATE TOTAL PER10D PERCENT EST. NO. ' ITEM DESCRIPTION QUANTITY QUANTITY QUANTITY UNIT TYPE UNIT COST TOTAL COST PERIOD COST QTM. C0-2. e u em 27- evice: a in a ery - 0 , $ - $ - o% CO-2 0 i em rvi ce a n a ery 4 0 10,000:00 $ - $ - o% C0-2-1 Tnsai~Photocel o ng aps 1 1 LS 1,600.00 $ 11600.00 $ - 700% Remove old arterial inteconned on Aubum CO-3 Way:Soutti2nd SE,to,N.of 1st NE 1 1 LS 1,400:00, $ 1,400.00 $ - 100% CO-a Additional Testing and Fiber Splicing 1 1 LS 2,683.52 $ 2,683.52 $ - 1o09k CO-5 F'etCO Arm Mounts RFI #3 1 1 1 LS 1,530.65 $ 1,530.85 $ 1,530.85 100% C0-5 Trenching at Bank of America 1. 1 1 LS 3,101.41_ $ 3,101.41 $ 3,101.41 100q6 C0-5 Repair Qwest damaged conduit 1 1 1 LS . 2,712.38 $ 2,712.38 $ 2,712.38 100% C0-5 Sawcutting at Bank America 1 1 1 lS 664.12 g 664.12 $ 664.12 100% 60-5 Sid Item ~ -4icrease-~dolrrs fior `C(eari and . . ~ ~ - 0 _ LS 7,535.27 $ - $ - 0% SCHEDULE TOTAL $ 26,862.85 Period Dates Begin: Jan 21..2010 ' End: Mar 05, 2010 h:lprojN)e1C30760 PE.xls 2 of 5 4/21/2010 at 1:42 PM cmroF AuBURN cso7so PAY E3TIAAATE #5 & FINAL NIATERIALS ON HAND ITEM TOTAL PERIOD UNIT NO. ITEM DESCRIPTION qUANTITY QUANTITY 7ypE UNIT C03T TOTAL COST PERIOD C08T 22. Fabric:lnnerduct Material'aaHand 3988.57 LF 3.00 11,959.71 - .Material installed 3.00 - - - TOTAL 0.000 • 37 CC7Y Camere S tem Material on Hand 10.180264 EA $ 5,550.00 58:500.47 • Materlalinstalled S 5,550:00 TOTAL:. 32 Communication:System Material.on Hand 0.1 LS $ 36,853.00 2,327.52 Material InstaUed E 38.853.00 TOTAL 33 Fiber dc Cable-12 Strand SMFO MateHal on Hand 2,379.5 Lf $ 1.30 $ 3,093.40 Material Inatalled $ 1:30 TbTAL - - - 34 Fiber Optlc Ceble-288 Strartd SMFO V Material on Har►d 19,48828 LF . $ 3.34 $ 65,094.20 Materiallnstalled $ 3:34 --------TOTAL 96 Fiber O dc S lice Case-288 Strand Matedal on Hand 0.248482 EA E 3,050:00 $ 760.92 ' Materiallnstalled $ 3,050.00 TOTAL - 36 Patch Panei in Cabinet - MateHal on Hand 0.122783 EA $ 3;098.00 $ 380.32 Matedallnstalied $ 3,098.00 TOTAL - - 37 Patch Panel (n TMC Material on Hand 0.128918 EA $ 12;810.00 $ Material Installed $ 12,810.00 TOTAL - SCHEDULE TOTAL 3 - CO, NO. 08-26 CITY OF AUBURN C307B0, Cttywide ITS, Phase 1 B . Citywide ITS, Phase 18 PROJECT SUMMARY , CO. NO, 08-26 PAY ESTIMATE #5 & FINAL Original Contract Contract Change Amount Orders TotaPPayment . This Period PercenUContrad : SCHEDULE A: ITS Improv.ements - Gontract $ 712,236.20 $ 47,858.76 $ 740,617.70 $ 26,862.85 ' 97% Materials on Hand $ 0.05 - NO TAX ' $ - • ` Bond tn Lieu $ - $ - 3CHEDULE TOTAL $ 712,236.20 $ 47,858.76 $ 740,617.75 $ 26,862:85 i TOTAL CONTRACT AMOUNT TO DATE $ 740;617.75 TOTAL PAYMENT TO CONTRACTOR $ 740,617.75 $ 261862.85 PAYMENT DUE CONTRACTOR: $ 26;862.85 Begin: Jan21, 2010 . , End: Mac 05, 2010 h:lprojlpMC30760 PE:xls 4 of 5. 4121l2010 at 1:42.PM CITY OF AUBURN CO. NO: 08-26 C307B0 . , PAY ESTIMATE # 5 & FINAL ~ . CONTRACTOR: - Signal Electric, Inc. PO Box 6209 ¢ Kent, WA 98064 Phone: 253-872-7177 The undersigned has reviewed and approved this final pay estimate. I agree that it is a tn.ie and correct statement showing all monies due me from the Ciry of Aubum under this contract; that 1 have carefully examined the final pay estimate estimafe,and understand it and that I hereby release the City of Auburn from any and ali,claims of whatsoever . natur.e which I may haye, arising out of this contract, which are not set forth in this estimate. • PAYMENT DUE TO CONTRACTOR = $ 26,862.85 Signatures: Contractor Date y- 2 6- l4 • , Inspector 0~ ~~'00'~~ ~ Date /r~ Project Manager Date City Engineer Date h:lproj"1C30780 PE:xis ° 5 of 5 40/2010 at 1:42 PM I ~ . ~ bwe Avs a a I °R . m ~ • • ~ e sr iva s CyMAy ~ ~ ♦ • ~ ~ em e n yr L L HIGHIILY CR d tr P Y I L L L7Ptld f rtus w. cuY ar I, ~ ~ ~ ~ Q~ ■ II ~ 41 d ~ C 1! 0 X I 1J-. a 9[ 8I H ur (:~GOO Im.tAViQ 3t. PAUL P4CVIC Z r, A aN. EURM mM DMV m ~ o zM m "v srs r- Rer.n ~ 5 noinrs c ST l(W J n ae ~ n ~ BURLLimN NORTfEtN R.R. A ST ~ B A KE c ar ps ys Ng ■ 8r [R m 8i h I 9f J 8f [ S[ ~ L L !R R Y S p Q ~ Ner- ~ G o ,~s ~ g f c E ~ ~ o " a ~ ~ • ~s L S a g ST ~ lR • ~ ~ , ~ ~ ~ ~ T 9f v ~ rsr . a ar ~ E ~ ~ t PL Bz ~ iosw ve as I i ' i08"h oVIL AYg II 1YL t0l1h II lOf I