HomeMy WebLinkAboutITEM V-C-1
ACITYOF_.. rte"
AGENDA BILL APPROVAL FORMA
u.RN
WASHINGTON
Agenda Subject: Award Contract 10-17 Date: December 22, 2010
Department: Attachments: Budget Status Sheet Budget Impact:
Public Works Phase C, Budget Status Sheet $ 0
Phases A&B, Bid Tab Summary &
Ma
Administrative Recommendation:
City Council award Contract 10-17, Project No. CP0817 - 2009 Sewer and Storm Station Replacement -
Phase C, White River Storm Pump Station Maintenance and Repair Project to Pease & Sons, Inc. on
their low bid of $1,395,155.70 plus WA state sales tax of $132,539.79 for a total contract price of
$1,527,625.49.
Background Summary:
This project replaces or retrofits three storm and sewer pump stations that are at the end of their service
lives. The project has been phased to allow for separate construction contracts:
Phase A: Dogwood Sewer Station Replacement (Construction 2010)
Phase B: Ellingson Sewer Station Replacement (Construction 2010 - 2011)
Phase C: White River Storm Station Retrofit (Construction 2010 - 2011)
This.permission to award is for the Phase C construction contract only. The Phase C construction
contract includes maintenance, repairs, and retrofits to the existing White River Storm Station. The work
will include improvements to reduce, maintenance costs and improve safety, including replacement of the
existing backup generator, pumps, and electrical controls, and re-configuration of the station to allow
maintenance beneath high voltage power lines and to conform to current fire safety codes.
The 432 Storm Fund currently allocates $2,801,200 for the project (Phase C only). $2,650,000 of the
allocated funds is from Bond Proceeds. Phase C is expected to cost $2,375,100.
The project costs for Phases A, B, and C are expected to total $6,494,127, which leaves project
,i contingencies of $426,120 in the 432 Storm Fund and $586,973 in the 431 Sewer Fund.
W0103-2
04.6.3 CP0817
Reviewed by Council& Committees: Reviewed by Departments & Divisions:
❑ Arts Commission COUNCIL COMMITTEES: ❑ Building ❑ M&O
j ❑ Airport ❑ Finance ❑ Cemetery Mayor
❑ Hearing Examiner ❑ Municipal Serv. ❑ Finance ❑ Parks
❑ Human Services ❑ Planning & CD ❑ Fire ❑ Planning
❑ Park Board ®PublicWorks ❑ Legal ❑ Police
❑ Planning'Comm. ❑ Other ® Public Works ❑ Human Resources
Action:
Committee Approval: ❑Yes ❑No
Council Approval: ❑Yes ❑No Call for Public Hearing
j Referred to Until
Tabled Until
Councilmember: Wagner Staff: Dowd
Meeting Date: January 3, 2011 Item Number: V.C.1
AUBURN *MOPE THAN YOU IMAGINED
u
BUDGET STATUS SHEET
2009 Sewer and Storm Replacement Project - Phase C - White
Protect No: CP0817 Project Title: River Storm Station
Project Manager: Jacob Sweating
O Consultant Agreement
Initiation Date:12115/2008 Q Permislon to Advertise Date: December 22, 2010
Advertisement Date: 11/30/2010 * Contract Award
Award Date: Q Change Order Approval
® Contract Final Acceptance
The "Future Years" column indicates the projected amount to be requested In future budgets.
Funds Bud eted Funds Available
Prior Years
Funding (Actual) 2010 2011 Future Years Total
432 Fund (Storm) 151,220 151,220
Bond Proceeds -432 Fund (Storm) 446,185 2,203,815 2,650,000
Total 151,220 446,185 2,203,815 0 2,801,220
Estimated Cost Funds Needed
Prior Years
Activity (Actual) 2010 2011 Future Years Total
Design Engineering - City Costs 19,953 20,000 39,953
Design Engineering - Consultant Costs 131,267 416,185 547,452
Property Acquisition 0
Construction Contract Bid 1,527,695 1,527,695
Authorized Contingency 100,000 100,000
Construction Engineering - City Costs 5,000 50,000 55,000
Construction Engineering - Consultant Costs 5,000 100,000 105,000
Total 151,220 446,185 1,777,695 0 2,375,100
432 Storm Budget Status
2009 2010 2011 Future Years Total
'432 Funds Budgeted (151,220) 0 (2,203,815) 0 (2,801,220)
432 Funds Needed 151,220 446,185 1,777,695 2,375,100
' 432 Fund Project Contingency . O 0 4260120 0 426,120
432 Funds Required 0 446,185 0 0 0
• ( in the Budget Status Sections indicates Money the City has available.
W0103-2A
H:\PROACP0817 The Sewer and Storm Pump Station Replacement\Budget\CP0817 - Budget Status Sheet'klsf 1
BUDGET STATUS SHEET
Project No: CP0817 Project Title: 2009 Sewer and Storm Replacement Project -Phases A and B -
Dogwood and Ellingson Sewer Stations
O Consultant Agreement
Initiation Date:12/15/2008 Q Permislon to Advertise Date: November 04, 2010
Advertisement Date: 10/12/2010 * Contract Award
Award Date: O Easement Acquisition
® Contract Final Acceptance
The "Future Years" column Indicates the projected amount to be requested in future budgets.
Funds Bud eted Funds Available
Funding 2009 (Actual) 2010 2011 Future Years Total
431 Fund - Sewer and Storm Pump Station Replacement 521,600 2,545,900 1,638,500 4,706,000
Total 521,600 2,545,900 1,638,500 0 4,706,000
Estimated Cost Funds Needed - Do wood Station, Phase A
Activity 2009 (Actual) 2010 2011 Future Years Total
Design Engineering - City Costs 17,874 10,000 27,874
Design Engineering - Consultant Costs 326,250 136,958 463,208
Construction Contract Bid 734,108 734,108
Authorized Contingency 73,400 73,400
Construction Engineering - City Costs 30,000 30,000
Construction Engineering - Consultant Costs 45,000 45,000
Total 344,124 1,029,466 0 0 1,373,590
Estimated Cost Funds Needed) - Ellingson Station, Phase B
Activity 2009 (Actual) 2010 2011 Future Years Total
Design Engineering - City. Costs 14,536 15,000 29,536
Design Engineering - Consultant Costs 162,940 321,590 484,530
Property Acquisition - PSE Easement 42,000 42,000
Construction Contract Bid 200,000 1,644,371 1,844,371
Construction Contingency 100,000 100,000
Construction Engineering - City Costs 10,000 40,000 50,000
Construction Engineering - Consultant Costs 45,000 150,000 195,000
Total 177,476 633,590 1,934,371 0 2,745,437
431 Sewer Budge t Status
2009 (Actual) 2010 2011 Future Years Total
*431 Funds Budgeted (521,600) (2,545,900 (1,636,500) 0 (4,706,000)
431 Funds Needed 521,600 1,663,056 1,934,371 0 4,119,027
• 431 Fund Project Contingency 0 882,844 0 0 586,973
431 Funds Required 0 0 295,871 0 0
( # ) in the Budget Status Sections indicates Money the City has available.
H:\PROJ\CP0817 The Sewer and Storm Pump Station Replacement\Budget\CP0817 - Budget Status Sheetki3f 1
BID TABULATION
BID TOTALS SUMMARY _
Project Name: CP0817, White River Storm Pump Station Maintenance & Repair, Contract 10-17
Prepared by: City of Auburn
Bid Date: 12/16/10
ENGINEER'S ESTIMATE. $ 1,818,000.00
AVERAGE BASIC BID AMOUNT: $ 1,536,147.67
BASIC BID SPREAD AMOUNT: $ 355,594.30 Basic BID Amount Spread $ Spread %
LOW BIDDER: Award Construction (ACI) $ 1,395,155.70 -$422,844.30 -23.26%
Second Bidder: Boss Construction, Inc. $ 1,429,275.00 -$388,725.00 -21.38%
Basic BID (Tax not Included) Total BID (Tax Included)
Pease & Sons $ 1,395,155.70 $ 1,527,695.49
Boss Construction, Inc. $ 1,429,275.00 $ 1,565,056.13
Award Construction (ACI) $ 1,431,956.30 $ 1,567,992.15
Ceccanti, Inc. $ 1,512,265.00 $ 1,655,930.18
Construct Company LLC $ 1,516,564.00 $ 1,660,637.58
Platts Plus, Inc. $ 1,519,418.00 $ 1,663,762.71
Hisey Construction $ 1,531,745.00 $ 1,677,260.78
Stouder Construction $ 1,738,200.00 $ 1,903,329.00
R. L. Alia $ 1,750,750.00 $ 1,917,071.25
W0103-2H
12/17/2010 (10:44 AM)
h:\proj\bidtabs\CP0817C BT.x1s
U 1 T
~ 8I/NLOVCrpN
Stgt
3
PHASE A: DOGWOOD
MUCKLE51100T
SEWER STATION CEMETERY
6G
w
9 ~
Gr O
21S S MUCKLE5HOOT
CASINO
W
~ a
E
F -,IT, = ~s
N
U
37TH SE
ELLINGSON RD PHAS ELLINGSON
SEW R STATION
1 Q
PHASE C: ITE RIVER
STORM S TION
~F
RSFY
~qY
SEWER AND STORM PUMP STATIONS
~,nol
WASHINGTON REPLACEMENT PROJECT
A-UB RN PROJECT #CP0817 N
W0103-2C VICINITY MAP