Loading...
HomeMy WebLinkAboutITEM V-C-3 A TY OF, UBU. _ N AGENDA BILL APPROVAL FORM WASHINGTON Agenda Subject: Date: Final Pa Estimate No. 5 to Contract 10-18 January 10, 2011 Department: Attachments: Budget Status Sheet, Budget Impact: Public Works Final Pa Estimate #5 and Ma $ 0 Administrative Recommendation: City Council approve Final Pay Estimate No. 5 to Contract 10-18 in the amount of $14,479.52, for a total. contract price of $1,026,374.35, with Northwest Asphalt, Inc. and accept construction of Project No. CP1012, 2010 Arterial & Collector Pavement Preservation. Background Summary: The 2010 Arterial & Collector Pavement Preservation project rehabilitated and rebuilt deficient pavement on 1.5 miles of arterial and collector streets throughout the City. This rehabilitation was accomplished by patching damaged pavement on 1 mile of City streets and rebuilding the travel lanes on 0.5 miles of I St NE (see attached map). This project also improved the pedestrian crossings at the intersection of 8th St NE and Pike St NE as part of the City's Traffic Calming Program. These crossing improvements consisted of replacing wheelchair ramps and refreshing and installing new crosswalk markings. These crossing improvements were funded by the 328 (Capital Improvement) Fund. A contingency of $19,461 remains in the (105 Arterial/Collector Preservation) fund for 2010. A project budget contingency of $114 remains in the 328 (Capital Improvement) fund. W0118-4 04.10.2 CP1012 Reviewed by Council & Committees: Reviewed by Departments & Divisions: ❑ Arts Commission COUNCIL COMMITTEES: ❑ Building ❑ M&O ❑ Airport ❑ Finance ❑ Cemetery ❑ Mayor ❑ Hearing Examiner ❑ Municipal Serv. ❑ Finance ❑ Parks ❑ Human Services ❑ Planning & CD ❑ Fire ❑ Planning ❑ Park Board ®Public Works ❑ Legal ❑ Police ❑ Planning Comm. ❑ Other ® Public Works ❑ Human Resources Action: Committee Approval: ❑Yes ❑No Council Approval: ❑Yes ❑No Call for Public Hearing Referred to Until Tabled Until Councilmember: Wagner Staff: Dowd Meeting Date: January 18, 2011 Item Number: V.C.3 AUBURN *MORE THAN YOU IMAGINED BUDGET STATUS SHEET Project No: CP1012 Project Title: 2010 Arterial/Collector Street Pavement Preservation Project Manager: Seth Wickstrom O Initiation/Consultant Agreement Initiation Date: April 19. 2010 O Permission to Advertise Date: January 10, 2010 Advertisement Date: June 8. 2010 O Contract Award Award Date: Auqust 16, 2010 O Change Order Approval Q Contract Final Acceptance The "Future Years" column indicates the projected amount to be requested in future budgets. Funds Bud eted Funds Available Funding Prior Years 2009 2010 2011 Total 105 Fund - ArteriallCollector Pavement Preservation Fund 1,500,000 1,500,000 (Funds budgeted in 2010) 105 Fund - Arterial/Collector Pavement Preservation Fund 105,000 105,000 (Carry-Forward from the 2009 budget) 328 Fund - Capital Improvement Fund (A Portion of the 2010 Traffic Calming Budget. For pedestrian crossing 40,000 40,000 improvements at 8th and Pike St NE. Total 0 0 1,645,000 0 1,645,000 Estimated Cost Funds Needed Activity Prior Years 2009 2010 2011 Total C504A- R St SE Utility Improvements 8,557 11,700 (to repair the pavement on M St SE between Auburn Way N and 17th St SE) CP0907 - 2009 Arterial/Collector Street Pavement Patching (far pavement patching that was done on A St SE between 3rd St SE and 6th St SE 349,569 349,569 and on West Valley Hwy between 15th St NW and 29th St NW) CP1017 - 2010 Arterial/Collector Crackseal Project 69,037 69,037 CP1002 - 2010 Local Street Pavement Preservation 136,700 136,700 (to repair pavement on 1st St NE between Auburn Way N and Auburn Ave) CP1012 - 2010 Arterial/Collector Street Pavement Preservation Design Engineering - City Costs 8,188 8,188 Construction Contract Bid 1,089,476 1,089,476 Change Order #1 (to remove Terrace Drive NW and Lea Hill Road from the project; and to install (126,632) (126,632) geotextile fabric on I St NE) Change Order #2 (for T and 22nd St NE bike lane striping and concrete pavement panel 23,263 23,263 replacement associated with the 8th/Pike St NE wheelchair ramp installations) Line Item Changes 40,278 40,278 Construction Engineering - City Costs 27,000 27,000 CP1012 Subtotal 1,061,562 1,061,562 Total 0 0 1,625,425 0 1,628,568 105 Arterial/Collector Street Budget Status Prior Years 2009 2010 2011 Total "105 Funds Budgeted 0 0 (1,605,000) 0 (1,605,000) 105 Funds Needed 0 0 1,585,539 0 1,585,539 "105 Fund Project Contingency 0 0 19,461 0 19,461 105 Funds Required 0 0 0 0 0 328 Capital Improvement Street Budget Status Prior Years 2009 2010 2011 Total '328 Funds Budgeted 0 0 (40,000) 0 (40,000) 328 Funds Needed 0 0 39,886 0 39,886 '328 Fund Project Contingency 0 0 114 0 114 328 Funds Required 0 0 0 0 0 • ( # ) in the Budget Status Sections indicates money the City has available. W0118-4A Page 1 of 1 CITY OF AUBURN CO. NO. 10-18 CP1012 2010 Arterial'&.Collector Pavement Preservation f PAY ESTIMATE #5 & FINAL : SCHEDULE A: Street Improvements ITEM ESTIMATE TOTAL PERIOD UNIT PERCENT EST. - NO. ITEM DESCRIPTION UNIT COST TOTAL COST PERIOD COST QUANTITY QUANTITY QUANTITY TYPE QTY. , 1 Minor Changes 1 0.95 Eq: Adj. 5000 $ 4,733.36 $ - 95% 2 _ Mobilization 1 1 LS'- 15000 $ 15,000.00 $ - 100% 3 Traffic Control Supervisor 1 _ 1 LS 10000 $ 10,000.00 $ - 100% 4 Traffic Control Labor (Min. Bid $34.00 per hour) 1100 1282.5 76 HR 40 $ 51;300.00 $ 3,040.00 117% 5 Portable Changeable Message Sign 50 46 DAY 40 $ 1,840.00 $ - 92% 6 Sequential Arrow Sign' 50 ' 44 DAY 50 $ 2,200.00 $ - 88% 7 Outside Agency Uniformed Police Flagging Labor 1 0 Eq. Adj. 2500 - $ - 0% 8 Removal of Concrete Sidewalk and Driveway 540 820.36 SY 35 $ 28,712.60 $ - 152% 9 Removal of Curb and Gutter. .1100 .1303.8 LF 13 $ 16,949.40 $ - 119% 10 Roadway Excavation Including Haul for'I' St NE Reconstru 5350 4835.16 CY 11.25 $ 54,395.55 $ - 90% 11 Unsuitable Foundation Excavation Including Haul 50 128.27 CY 9 $ 1,154.43 $ 257% f 2 Crushed Surfacing Top Course 1400. 29.37 TON 15.75 $ 462.58 $ - 2% 13 Crushed Surfacing Base Course 4250 5240.9 TON 15.75 $ 82,544.18 $ - 123% 14 Pavement Repair Excavation Including Haul 7600 6164.58 SY 2.01 $ 12,390.81$ - 81% 15 HMA Class B for T St NE Reconstruction 1400 1395.99 TON 71.6 $ 99,952.88 $ - 100% 16 HMA Class B for Patching. 2000. 2363.04 TON 80.25 $ 189,633.96 $ - 118% 17 HMA Class t for'I' St NE Reconstruction 4250 3888.59 TON 68.08 $ 264,735.21 $ - 91% 18 Rubberized Asphalt for Crack Sealing 1 0.7258 TON 4000 $ 2,903.20 $ - 73% ! 19 Adjust Manhole- 3 16 EA 450 $ 7,200.00. $ - 533% 20 Manhole Ring and Solid Cover, _ 3 16 EA 350 $ 5,600.00 - 533% ! 21 Adjust Valve Box 3 34 1 EA 300 $ 10,200.00 $ 300.00 1133% li 22 Temporary Water Pollution/Erosion Control 1 0.70 Eq. Adj. 3500 $ 2,445.10 $ - .70% 23 Topsoil Type A' 10 10 CY '60 $ 600.00 $ 100% 24 _ Law Sod 60 77.78 SY 20 $ 1,555.60 $ - 130% ! 25 Miscellaneous Roadside Restoration 1.78 0.13036 Eq. Adj. 5000 $ 8,890.13 $ 651.80 178% 26 Cement Concrete Traffic Curb'and Gutter 1100 1620 LF 17 $ 27,540.00 $ - 147% 4 27 Industrial and Commercial Driveway Apron 90 114 SY 49 $ 5,586.00 $ - 127% 28 Raised Pavement Marker Type 2 _ 400: 309 309 EA 4.25 $ 1,313.25 $ 1,313.25 77% 29_ Monument Type B, (Modified) _ 3 4 EA 500 $ 2,000.00 $ - 133% 30 Ce_m_ent Concrete Sidewalk 450 594.45 SY 51 $ 30,316.95 $ - 132% 31 Induction Loop Vehicle Detector 0 0 EA 488 $ - $ - 0% 32 Paint Line 24000 13345 6088 LF 0.2 $ 2,669.00 $ 1,217.60 56% - 33 Plastic Crosswalk Stripe and Stop Bar (24 inch wide) 1550 1463 570. LF 6 $ 8,778.00 $ 3,420:00 94% ' 34 Plastic Traffic Arrow 26 36 10 EA' 68 $ 2,448.00 $ 680.00 138% 35 Plastic Traffic Letter 20 88 32 EA 45 $ 3,960.00 $ 1,440.00 440% 36 Temporary Pavement Markings 5000 69 LF 0.25 $ 17.25 $ - 1 % CO-1 Decreased quantities BI#'s 4,14,16,31,33,34,35 COi-f Construction of Geotextile Fabric 12000 10547.73 SY 3.50 $ 36,917.06 $ - 88% C0_1-2 Induction Loop Vehicle Detector (Adjustment) 8 8 EA 848 $ 6,784.00 $ - 100% CO-2-1 Incidental HMA for Pike and 8th St NE Ramps 1 1.0011 1.0011 Eq. Adj. 1950 $ 1,952.15 $ 1,952.15 100% - SCHEDULE SUBTOTAL. $ 14,014.80 Begin: Nov. 21, 2010 End: Dec. 20, 2010 W0118-4B h:lprojlpe1CP1012 PE.xls 1 of 4 1/10/2011 at 9:10 AM CITY OF AUBURN CO. NO. 10-18 CP1012 2010 Arterial & Collector Pavement Preservation PAY ESTIMATE #5 & FINAL SCHEDULE A: Street.lmprovements ITEM ESTIMATE TOTAL PERIOD UNIT UNIT COST TOTAL COST PERIOD COST PERCENT EST. NO. ITEM DESCRIPTION QUANTITY QUANTITY QUANTITY TYPE QTY- CO-2-2 Remove and Install Cement Concrete Pavement Panels o 1 1 LS 16555 $ 16,555.00 $ - 100% CO_-2-3 Wide Painted Line 7500 7425 LF 0.28 $ 2,079.00 $ - 99% CO-2 Painted Bike symbol 40 25 EA 46.20 $ 1,155.00 $ - 63% CO-2-5 Removal of Pavement Markings 1 1.1309 0.5809 Eq. Adj. 800.00 $ 904.72 $ 464.72 113% SCHEDULE TOTAL $ 14,479.52 Begin: Nov. 21, 2010 End: Dec. 20, 2010 W0118-4B h:\proj\pe\CP1012 PE.xls 2 of 4 1/10/2011 at 9:10 AM CITY OF AUBURN CP1012, 2010 Arterial & Collector Pavement Preservation PROJECT SUMMARY CO. NO. 10-18 PAY ESTIMATE #5 & FINAL Original Contract Contract Change Amount Orders Total Payment This Period. Percent/Contract SCHEDULE A: Street Improvements Contract $ 1,089,475.00 $ (103,379.00) $ 1,026,374.35 $ 14,479.52 104% Sales Tax Not Applicable Bond in Lieu of Retainage SCHEDULE TOTAL $ 1,089,475.00 $ (103,379.00) $ 1,026,374.35 $ 14,479.52 TOTAL CONTRACT AMOUNT TO DATE (including Sales Tax) $ 1,026,374.35 TOTAL PAYMENT TO CONTRACTOR $ 1,026,374.35 $ 14,479.52 PAYMENT DUE CONTRACTOR: $ 14,479.52 Period Dates Begin: Nov. 21, 2010 End: Dec. 20, 2010 W0118-4B h:\proj\pe\CP1012-PE.x1s 3 of 4 1/10/2011 at 9:10 AM CITY OF AUBURN CO. NO. 10-18 CP1012 2010 Arterial & Collector Pavement Preservation PAY ESTIMATE # 5 & FINAL - CONTRACTOR: Northwest Asphalt, Inc PO Box 2260 Renton, WA, 98056 Phone: (425)254-1820 The undersigned has reviewed and approved this final pay estimate. 1 agree that it is a true and correct statement showing all monies due me from the City of Auburn under this contract, that I have carefully examined the final pay estimate es.Umate :and.:;understand it and that I hereby release the City of Aubum from any and all claims of whatsoever nature which'..] may have, arising out of this contract, which are not set forth in this estimate. PAY DUE TO CONTRACTOR" $ 14,479.52 Signatures: Contractor Date 1/10/2-011 Inspector Date Project Manager Date 1 /10 12011 City Engineer Date W0118-4B h:\proj\pe\cP1012 PEAs 4 of 4 11.10/2011 at 9:10 AM I, m n BE 289th w Su - le zesrx Br) z ' m a a 9 2871h 9T z 43~d w BE 288th 3T th ' tTP 9 286t < 3 287th ~I S I - B - °w - Y C m BE 28 th 9T ° y a y x o m SE z90th BT ¢ 9E ` a z 8 282nd BT y 3 th 8 292nd 3T BT N^~ •C wvBB IBIV la n la r - i ;a~~49 _ m 38th _ V E 3 296th 3T ! $ 31; pwj-1 y a _ m s F 5( I 'k 10~ AUBURN GOLF Q a m COURSE a _ ~J 30th ST NM 30th BT NE Yyu ° 7 - GG4.~ 3T • Y ~ D W >n NII i ~ ~ ~ O~v P_ / 3o J - BRANNAN P I B QYI QY 6T PARR _ gm- T 302nd PL ° g of _ AUBURN o ' J y 6th .y° 3E 304th 8 308t1✓ BT sB 4~ 1 2w o o 0 . _ 'pd SM ` ST m 0~ 1 Z p MUNICIPAL 24th g~ NE 1 ~ g ~e 1' I~ aTM b a e ~1 Q c WB _ _8 i 1 m Y s tmn z 22. d BT 4 W _ tD ~ 0 23rdN8 z ~ n € ~ R °~9 ~ R g 6T z ~21pt 2. BT P ti P w s < n.• / Bf All rc 20th 3f 2 ( I ~vbn, n p~ ° i l/ c 9 z AIRPOR O i F = 27et Nen . IS I`/vI' C a zoth t T NE 3T NE 3E 910th 9T 19th 18th 3T Lh DA , NE - 9 312t 6. 15th _-_NIL_ 17th \JJ7'''~~ w 8th 9~T NE_ IF th 9E 912th a it 4th 15th T 151H m z I y,,.=~ ➢s °~I ~af= 20 fii~ le 3f NM z z 3 318th 3T 3E 318th d- 61~h3~ I Pedestrian Crossing 3 318th ET I • F Olh 3T NE Improve t~-Tl~ 3 3 9r 2 ^ N ^e' BE 320th ° s C ~I °I 4 W BRBIIR ~ u R w ~L e Part of Project w\ aNPR m JV a r <i a • VETERANS 810 WW c~a _ - ° '3 ° a R s CP1002 - 2010 Local 'xp EMOMAL e i S N mPAR avs P ~m E 3 a Street Pavement o NE F vrd i B 'SCY by @ o j Preservation Stn sT~" _ Z ~I AUBURNF m RICH °j z °J zpd let NEI- gog GREEN RIVER NW m m s 0 1,250' 2,500' zna q sT COMMUNI E € b SCHOOL ~~tn .6T c z ° °•iw ? I TY MApy s o _ a a m. ° COLLEGE u u. is j a s I~ SCALE: 1 inch = 2,500 feet MA] a 1011 37 slr gi w °i~ m w m m MT. V"' CEMETERY,,,~ ~j VICINITY MAP .FINAL PAY ESTIMATE CP 1012 - 2010 Arterial and Collector Pavement Preservation ® Project Street (Pavement Patching) W0118-4C Project Street (Reconstruct Driving .Lanes) worm: DM bm L7,2010 wcwon: HAPROAU1012-7010 NtuW & Coll O Pa-e P6\M000L d I. o\Rd PE (1-3-2011)\Vld;IIV Mr dg