AIRPORT ADVISORY COMMITTEE PROJECT- GOAL MATRIX
# PROJECT LEAD Est. COST REVIEW EST. STATUS
DESCRIPTION DATE COMPL.
DATE
1 Airport Storm Reid $50,000 3/16/2010 1/31/2011 Don Barclay reported that RM is-waiting on direction from
Water Design Middleton/AMG the City if any Wing of the lines is to be done or not.
Update Otherwise everything is ready to be completed and sent to
the City.
3 Hangar Rows 9 & 10 Steve $200,000 3/16/2011 TBD City rejected all bids from small works rooster. All bids
roof Burke/AMG came in over $200,000. Bid package will be reviewed and
updated as required and City will open up the bidding by
advertising the project for competitive bids.
4 Runway Lighting Steve $350,000 -3/16/2011 TBD Meeting scheduleclJor February 17, 2011 to discuss timing
Replacement Burke/Reid and the beginning.of,the work on the project.
Middleton/AMG
5 Storm Water Robert 0 3/16/2011 TBD Earthwork completed. Netting needs to be installed to
Retention Ponds Lee/Storm remove and deter water fowl.
Water
6 Airport "Hangar AMG 0 3/16/2011 .2/28/2011 As of February 10, 2011, 73.out of 103(71%) voluntary
Inspection inspections,have been completed. A list of hangar not
inspected will be mailed to the associations," requesting a
' date prior to the end of the month to conduct those
inspections. A list of discrepancies will be-complied and
then a letter sent to the association reporting those
discrepancies and a window to have them resolved and if
re-inspection is required AMG will schedule that.
7 Noise Complaints AMG 0 3/16/2011 No noise complaints since last report. Two test reports
received.
8 Drainage Mitigation Tim Carlaw TBD TBD TBD Waiting for final Storm Water review from City
9 Condo Gate Review AMG TBD TBD TBD Research different security options
J
Last Revision Date: 2/11/2011
AIRPORT ADVISORY COMMITTEE PROJECT - GOAL MATRIX
COMPLETED
# PROJECT LEAD Est. COST REVIEW EST. STATUS
DESCRIPTION DATE COMPL.
DATE
2 Airport Rules and AMG 0 10/20/2010 9/20/2010 Second committee review (finance) for council approval on
Regulations 9/20/2010
7 MIA Appraisal AMG 0 10/20/2010 12/31/2010 MAI appraisal for raw and improved land leases at the
Auburn Airport for implementation 1/1/2011