Loading...
HomeMy WebLinkAboutITEM III-DCITY OF -J AGENDA BILL APPROVAL FORM WASHINGTON Agenda Subject: Change Order No. 2 to Contract 10-04 Date: March 15, 2011 Department: Attachments: Budget Impact: Public Works Budget Status Sheet & Map $ 29,169.21 Administrative Recommendation: City Council approve Change Order No. 2 in the amount of $29,169.21 to Contract 10-04 with Totem Electric of Tacoma, Inc. for work on Project No. CP0701, 8th St NE and R St NE Signal Project. Background Summary: The 8th St NE and R St NE Signal project consists of constructing a new traffic signal system, installing an intelligent transportation system (ITS), and road channelization at the intersection of 8th St NE and R St NE Change Order No. 2 includes trenching across the southern 8th St NE planter strip from R St NE to M St NE to facilitate the installation of conduit for ITS due to field conditions, installing 2 advanced detection video cameras on the newly installed signal to improve traffic flow and safety at the 8th St NE and R St NE intersection, and adding quantity to the bid item for Traffic Control Labor to address pedestrian safety issues during construction. The budget impact of $29,169.21 for this project is included in the proposed 2011 Budget Amendment #2. W0321-6 Reviewed by Council & Committees: Reviewed by Departments & Divisions: ❑ Arts Commission COUNCIL COMMITTEES: ❑ Building ❑ M&O ❑ Airport ❑ Finance ❑ Cemetery ❑ Mayor ❑ Hearing Examiner ❑ Municipal Serv. ❑ Finance ❑ Parks ❑ Human Services ❑ Planning & CD ❑ Fire ❑ Planning ❑ Park Board ®Public Works ❑ Legal ❑ Police ❑ Planning Comm. ❑ Other ® Public Works ❑ Human Resources Action: Committee Approval Council Approval: Referred to Tabled ❑Yes ❑No ❑Yes ❑No Call for Public Hearing Until Until / / Councilmember: Wagner Staff: Dowdy Meetinq Date: : March 21, 2011 Item Number: * moRE THAN YQLJ IMAGINED Au.Bu BUDGET STATUS SHEET Project No: CP0701 Project Title: 8th St NE and R St NE Signal Project Project Manager: Ryan L Vondrak O Project Update Initiation Date: October 23, 2006 O Permision to Advertise Date: March 15, 2011 Advertisement Date: June 1, 2010 O Contract Award Award Date: July 6, 2010 O Change Order Approval O Contract Final Acceptance The "Future Years" column indicates the projected amount to be requested in future budgets. Funds Budgeted (Funds Available) Funding Prior Years 2010 2011 2012 Total Federal Grant 141,803 108,197 250,000 102 Fund" 259,110 169,300 428,410 328 Fund 5,714 5,714 Total 141,803 367,307 175,014 0 684,124 "Reflects the current request in Budget Amendment #2 being considered by Council. Estimated Cost (Funds Needed) Activity Prior Years 2010 2011 2012 Total Design Engineering - City Costs 45,375 25,855 71,230 Design Engineering - Consultant Fees 95,047 37,044 132,091 State Fees 5,500 5,500 ROW 1,381 1,381 Construction Contract Bid 254,483 48,905 303,388 Change Order #1 27,176 27,176 Change Order #2 29,169 29,169 Authorized Contingency (15%) 45,508 45,508 Construction Engineering - City Costs 22,750 20,750 43,500 Construction Engineering - Consultant Costs 13,853 13,853 Total 141,803 367,307 163,686 0 672,796 102 Arterial Street Budget Status Prior Years 2010 2011 2012 Total '102 Funds Budgeted (141,803) (367,307) (169,300) 0 (678,410) 102 Funds Needed 141,803 367,307 157,972 0 667,082 "102 Fund Project Contingency 0 0 (11,328) 0 (11,328) 102 Funds Required 0 0 0 0 0 328 Capital Improvements Budget Status Prior Years 2010 2011 2012 Total '102 Funds Budgeted 0 0 (5,714) 0 (5,714) 102 Funds Needed 0 0 5,714 0 5,714 "102 Fund Project Contingency 0 0 0 0 0 102 Funds Required 0 0 0 0 0 ( # ) in the Budget Status Sections indicates Money the City has available. W0321-6A H:\PROJ\CP0701-8thRStNESignal\Budget\8th and R St Budget Status Sheet.xls 1 of 1