Loading...
HomeMy WebLinkAboutITEM II-ECITY OF -J AGENDA BILL APPROVAL FORM WASHINGTON Agenda Subject: Change Order No. 3 to Contract 10-26 Date: May 9, 2011 Department: Attachments: Budget Impact: Public Works Budget Status Sheet & Map $ 0.00 Administrative Recommendation: City Council approve Change Order No. 3 in the amount of $106,531.90 to Contract 10-26 with Mountain West Construction, LLC for work on project CP0920, 2009 AC Watermain Replacement. Background Summary: This project will provide for the replacement of 4,600 linear feet of asbestos concrete water main with 470 linear feet of 4-inch and 4,155 linear feet of 8-inch diameter ductile iron water main; replacement of 345 linear feet of storm drainage piping; installation of 1 pressure reducing valve station, air relief valves, and fire hydrants; also replaced are the adjoining water services and appurtenances in the Lea Hill service area. Change Order #3 will replace an additional 40% of the affected roads for a full width roadway repair in consideration of the existing pavement failures experienced during construction in this former unincorporated King County area. This change order will rubblize the existing asphalt pavement and reuse the planings for the road base and construct a new 4 inch pavement over the road base. The anticipated completion date of this project is June, 2011. The roads within this project were originally identified as possible candidates for Save Our Streets (SOS) improvements; additional work is based on the existing roadway conditions prior to the waterline construction. Staff believes it is appropriate for the SOS program to share in the pavement restoration costs. A project increase of $106,532 within the 103 Local Streets fund/account will be necessary; however it will not require a budget adjustment since it is anticipated that the budgeted expenditures in the 103 Local Streets fund/account will not be exceeded this year. W0516-6 Reviewed by Council & Committees: Reviewed by Departments & Divisions: ❑ Arts Commission COUNCIL COMMITTEES: ❑ Building ❑ M&O ❑ Airport ❑ Finance ❑ Cemetery ❑ Mayor ❑ Hearing Examiner ❑ Municipal Serv. ❑ Finance ❑ Parks ❑ Human Services ❑ Planning & CD ❑ Fire ❑ Planning ❑ Park Board ®Public Works ❑ Legal ❑ Police ❑ Planning Comm. ❑ Other ® Public Works ❑ Human Resources Action: Committee Approval: ❑Yes ❑No Council Approval: ❑Yes ❑No Call for Public Hearing Referred to Until Tabled Until Councilmember: Wagner Staff: Dowdy Meeting Date: : May 16, 2011 Item Number: * moRE THAN YQLJ IMAGINED Au.Bu BUDGET STATUS SHEET Project No: CP0920 Project Title: 2009 AC Water Main Replacement Project Manager: Robert Lee 0 Project Initiation Initiation Date: 2/7/2010 0 Permision to Advertise Date: May 9, 2011 Advertisement Date: _11/30/2010 0 Contract Award Award Date: 12/20/2010 0 Change Order Approval Contract Final Acceptance The "Future Years" column indicates the projected amount to be requested in future budgets. Funds Budgeted (Funds Available) Funding Prior Years 2010 2011 Future Years Total 430 Fund - Water Repair and Replacement 0 0 20,000 0 20,000 430 Fund - Water Bond 7,023 68,505 924,472 0 1,000,000 432 Fund - Storm Drainage Utility 0 0 50,000 0 50,000 103 Fund - Local Streets" 0 0 0 0 0 Total 7,023 68,505 994,472 0 1,070,000 **These funds are a portion of the 2011 Save Our Streets Program Estimated Cost (Funds Needed) Activity Prior Years 2010 2011 Future Years Total Design Engineering - City Costs 7,023 59,400 0 0 66,423 Design Engineering - Consultant Costs 0 8,576 0 0 8,576 Construction Contract Bid 0 0 713,832 0 713,832 Change Order #1 0 0 0 Change Order #2 0 0 10,396 0 10,396 Change Order #3 0 0 106,532 0 106,532 Authorizied Contingency (10°x) 0 0 71,383 0 71,383 Construction Engineering - City Costs 0 528 35,000 0 35,528 Construction Engineering - Consultant Costs 0 0 2,250 0 2,250 Total 7,023 68,505 939,283 0 1,014,811 1U3 LOCa l JLreeLS tsuq ei status Prior Years 2010 2011 Future Years Total *103 Funds Budgeted 0 0 0 0 0 103 Funds Needed 0 0 106,532 0 106,532 *103 Fund Project Contingency 0 0 0 0 0 103 Funds Required 0 0 106,532 0 106,532 430 Water Budget Status Prior Years 2010 2011 Future Years Total *430 Funds Budgeted 0 (1,020,000) 430 Funds Needed 7,023 68,505 889,283 0 964,811 *430 Fund Project Contingency 0 55,189 0 55,189 430 Funds Required 0 0 0 0 0 432 Storm Drainage Budget Status Prior Years 2010 2011 Future Years Total *432 Funds Budgeted 0 0 0 (50,000) 432 Funds Needed 0 0 50,000 0 50,000 *432 Fund Project Contingency 0 0 0 0 0 432 Funds Required 0 0 0 0 0 * ( # ) in the Budget Status Sections indicates Money the City has available. W0516-6A 1 of 1 35th ST NN t m 37th 3f NF a ' - anee NhP Gl~ w N 5 t ~ 35th S 298th 3f Y U 2 n t; ^ w AUBURN .xw+* m : F' , t a GOLF a un w i ..a L c z n eP COURSE na 5 'a 30th ST NM 3 t„ f T_ 3 l so c 30th NE a suc ~ _ ? r.nO` 300th , 28th. sr nr ST 0 28th ST _ NE PAeK _a+ rt~3Ana 28th ST AUBURN 2 z h . NE ^ x aE_"T N► Fzi 4 y O 3T S 305th ST y C 3 Z nt. pt O`+x a _8E ^ 304th yt h L w. q R x m `b d x t,sn; 3' n 2 O MUNIClPA O m lath. S7!.. & ;t 2 f,w 'q Z F z 22nd ST z W w a m a a ~ ..a•nn- ~ ,uat 'F^ p z3taNe m`, ~ a~.ex = ' ~ ~ r x-,,, ~g ~ s y I:Hp a 20th ST 22vd. iE s N a P t ~ a AIRPOR O z zjand gT Ne +mma w a p z sT Ne "T a .wu"s' g.. Cam.. N a 20!ry SINE < SE 310th ST 19th OR i a i 3l2tty. 15th Ieth 3T w. o- NE '4ae gl.. Fz gE NN 3E 312th ra ifth 14th 2 e• w rc 15th-. ST. x A's ,nnny-n > kE 14th ST q s 318tH IT .,:a. y {,-.s. 2th aT l' JE ~i a e.n [ 5 ~ aFC 5E 318th 31' p :<°v b nw 9 ,T~ c ...a: a.~e, d f 9 3IBth ST B € aR ^ f 10tH ST "E $ " ~ 5 t ¢ § s s 3z3th sr e~ :r"" w F ~ s w ~,r :,w a , g w N ST sCtiMtP SE "u^a 320th g ae n to sr x t 4 t $T stn sr yw ."a Nc. A o w. 3 E C . a.a k M NE.' +w~ ~'Iw a. a. W GREEN RIVER Proposed NE z •'S' COMMUNITY a +w<.e R PL ys, v Pi t COLLEGE 9 929th sc.... torm Drain HAIN o SC awns a a+a<w ~ ~v w n c S 33 s Proposed W Location ' v S 297TH ST w L ' 4th 9T 5 SE t w F PEAS Storm Drain .Li a w as 1 Q t t ,w ~ d~ ~'br, B`~R~1CTO Locations ,Y 336th ST _ O RV a STq:E N:RRTHrRa a a..n m u°i 0th ST a sF .n scENlc _DR 13 19TH 8TS SE 298TH ST 3E s a~aesne A P:uas+w an mw ~w 15th 9T ti 1t1 is 9~ht s-10th SC a 348th. , 1T D`-T 9E 3E C c 18th SP z - 199 h ar a w,mme awaaw a. s.a W 13 to o vFi 20th ST SE 3-1 NUCKLESHOOT 8 `SE ~x 299TH ST a~~aB o i W ! O W CASINO k 22ndm~ w .f.,ar q 352x8 sr > a>b.m _ aI~+J xo g'&* r at z G roPl.,a 35 n S' ~ ~ F 7 V E $ S 63 M~ 00 II a «w 353th SC b p w k 6cwrca ,m A s j'--SE 299TH PL w n n 353[h ST LI AUBURN FART! Otn $ L k n a an«: Proposed ° n wn a+w` 9p STUCK RIVER DRIVE , .3B3nd RT m th Watermaln an TH Y filth S''^•. oQQ :w. 3'Ib th al. m WP Location a P tt S' F nd NT mw.are ,r ce ~'n 41 ~ a 99 x ea r .w t 7'4% a=SE 9 .PONJJd 9. 47th 3R0 AVE v € R wnrne sei 'a0 4 F, 3R0 5 AVE a n 9E a.m v.- ,r E°; w?. 9 N 41 AVE SN= 4TH ' ' CP0920 AC Watermain Replacement Project N VICINITY MAP NOT TO SCALE W0516-6B JANUARY, 2010