HomeMy WebLinkAboutMatrixAIRPORT ADVISORY COMMITTEE PROJECT - GOAL MATRIX
#
PROJECT
LEAD
Est. COST
REVIEW
EST.
STATUS
DESCRIPTION
DATE
COMPL.
DATE
3
Hangar Rows 9 &
Steve
$300,000
7/20/2011
TBD
AMG purchased 4,100 seals and has begun installing on
10 roof
Burke/AMG/Robert
the worst hangars first. This will continue as weather
Jones
permits.
4
Runway Lighting
Steve Burke/Reid
$350,000
7/20/2011
6/2/2011
Construction Completed. Waiting on Punch List and FAA
Replacement
Middleton/AMG
inspection.
5
Storm Water
Robert Lee/Storm
0
7/20/2011
4/8/2011
6/7/2011. M & O has installed the net supports and
Retention Ponds
Water/Coleman
is now waiting for the nets to be fabricated. Approx.
two weeks to complete.
6
Airport Hangar
AMG
0
7/20/2011
3/31/2011
One inspection has yet to be completed. City Legal has
Inspection
handed this off to Code. Code Enforcement is to notify
the association and the individual owners of non-
compliance of the lease terms.
7
Noise Complaints
AMG
0
7/20/2011
No Change since last report.
8
Drainage Mitigation
Tim Carlaw
TBD
TBD
TBD
Standing water on west side. Reid Middleton contract
extended until September 2011 to assist in this project
9
Condo Gate Review
AMG
TBD
TBD
TBD
Waiting for written report from Convergint Technologies
on options.
10
Aircraft Wash Rack
Chris
TBD
7/20/2011
TBD
Chris Anderson City Environmental Manger and AMG to
Anderson/AMG
work to find solution. AMG contacted Reid Middleton to
see if they do this kind of work and was advised they do.
AMG will follow up with RM.
11
Airport Master Plan
Coleman/AMG
TBD
7/20/2011
TBD
Garcia has contacted 3 local companies that have
Mid-Term Update
experience in Airport Master Plans. CH2M Hill
(Bellevue), JUB (Seattle) and Century West (Ellensburg &
Portland)
Last Revision Date: 6/13/2011
AIRPORT ADVISORY COMMITTEE PROJECT - GOAL MATRIX
COMPLETED
#
PROJECT
DESCRIPTION
LEAD
Est. COST
REVIEW
DATE
COMPL.
DATE
STATUS
2
Airport Rules and
Regulations
AMG
0
10/20/2010
9/20/2010
Second committee review (finance) for council approval on
9/20/2010
7
MIA Appraisal
AMG
0
10/20/2010
12/31/2010
MAI appraisal for raw and improved land leases at the
Auburn Airport for implementation 1/1/2011
1
Airport Storm
Water Design
Update
Reid
Middleton/AMG
$50,000
4/20/2011
Completed
Last Revision Date: 6/13/2011