AIRPORT ADVISORY COMMITTEE PROJECT- GOAL MATRIX
# PROJECT LEAD Est. COST REVIEW EST. STATUS
DESCRIPTION DATE COMPL.
DATE
3 Hangar Rows 9 & Steve $300,000 08/17/2011 TBD Received updated pricing on different options as
10 roof Burke/AMG/Robert reviewed before. See pro/cons sheet for details. To
Jones date costs for design.and bid specification from A.R.T
estimated at $18.000.00.
5 Storm Water Robert Lee/Storm 0 4/8/2011 Project Completed
Retention Ponds Water/Coleman
6 Airport Hangar AMG 0 08/17/2011 3/31/2011 One inspection has yet to be completed. City Legal and
Inspection Code Enforcement is to notify the association and the
individual owners of non-compliance of the lease terms.
Compliance document being prepared for review by City
and follow up by AMG.
7 Noise Complaints AMG 0 08/17/2011 No Change since last report.
8 Drainage Mitigation Tim Carlaw TBD TBD TBD Recent observation - no standing water. Suspect
cleaning out storm ponds may have helped with this
issue. Wade from Reid Middleton visited site and plans
on having preliminary report to City in two weeks.
9 Condo Gate Review AMG TBD TBD TBD Waiting for written report from Convergint Technologies
on options.
10 Aircraft Wash Rack Chris TBD 08/17/2011 TBD Chris Anderson City Environmental Manger discussed
Anderson/AMG the rain garden concept with DOE and the ground water
section. Chris to make report at AAB meeting.
11 Airport Master Plan Coleman/AMG TBD 08/17/2011 TBD Garcia has contacted FAA on timing of grant monies for
Mid-Term Update this project. Found update was not planned for in 2011.
Funding for this is available in June 2012; although many
preliminary steps can be taken now and reimbursed
with the grant. Appointment with FAA personnel will be
scheduled late July or first part of August.
12 Occupancy Rates AMG -0- 8/17/2011 NA . Row 9/10 39/40 occupied
Last Revision Date: 7/18/2011
9 AIRPORT AD.VIS,O.RY: COMMITTEE PROJECT- GOAL.MATRIX,-• Row 2 Full (14)
• Row 8 Full (6)
• Rows 3-7 56/85 full
• Storage 2 available
• Tie down 39/100 full
COMPLETED
# PROJECT.- LEAD Est. COST REVIEW COMPL. STATUS
DESCRIPTION DATE DATE'
2 Airport Rules and AMG 0 10/20/2010 9/20/2010 .Second committee review (finance) for council approval on
Regulation`s 9/20/2010
7 MIA Appraisal AMG 010/20/2010 12/31/2010 MAI,appraisal for raw and improved land leases at the
Auburn Airport for implementation 1/1/2011
1 Airport Storm Reid $50,000 4/20/2011 Completed
Water Design Middleton/AMG
Update
4 Runway Lighting Steve $350,000 7/20/2011 6/2/2011 Construction Completed. Waiting on Punch List and FAA
Replacement Burke/Reid inspection.
Middleton/AMG
Last Revision Date: 7/18/2011