HomeMy WebLinkAboutITEM III-1AIRPORT ADVISORY COMMITTEE PROJECT - GOAL MATRIX # PROJECT LEAD Est. COST REVIEW EST. STATUS DESCRIPTION DATE COMPL. DATE 3 Hangar Rows 9 & Steve $200,000 1/18/2012 TBD Request to move bid schedule before May 2012 to 10 roof Burke /AMG /Robert secure contractor. Bob Jones spoke with Steve Burke Jones regarding the process needed to make certain funds are budgeted. 7 Noise Complaints AMG 0 1/18/2012 No noise complaints since last report 9 Airport Security AMG TBD 1/18/2012 TBD Dec 2012 meeting have statement of work available and Update * ** if there is any grant monies available for security system. 10 Aircraft Wash Rack Tim Carlaw /Chris TBD 1/18/2012 TBD Identify requirements. Email to come from Chris. Chris Anderson /AMG to work with Reid Middleton for scope of work. Chris advised that scope of work and contract in place with Reid Middleton. 11 Airport Master Plan Coleman /AMG TBD 1/18/2012 TBD Bill Thomas to come to the November meeting and Mid -Term Update make presentation on the outlook for the next 20 years. 12 Occupancy Rates AMG -0- 1/18/2012 NA • Row 9/10 36/40 (90 %) no change • Row 2 Full (14) (100 %) no change • Row 8 5/6 (6) (83 %) down 1 • Rows 3 -7 57/85 (67 %) no change • Storage Units 10/12 Full (83 %) no change • Tie down 36/100 full (36 %) down 1 13 General Airport Board Only TBD 1/18/2012 NA Event to showcase Auburn Airport, e.g. WWI —II Event aircraft. Static display /food /sale vendors/ flights. 14 Fuel Dispenser AMG $10,000 1/18/2012 3/31/2011 Fuel station down to one operating station with two Replacement delivery hoses. Other station used to keep this station operable. Order placed for fuel dispenser 15 Aircraft Accident AMG TBD 1/18/2012 3/31/2012 Review current plan and revise as required. Add to Emergency Plan that plan an Aircraft Recovery Plan. and Recover Plan 16 Update Airport Tim Carlaw /Chris TBD 1/18/2012 3/31/2012 Mr. Anderson will work the Reid Middleton and Last Revision Date: 11/14/2011 AIRPORT ADVISORY COMMITTEE PROJECT - GOAL MATRIX Storm water Anderson /RM update the plan for implantation at the airport. "SWWPP" Plan Documents given to Anderson and RM. Contract with RM is in place to update the SWWPP and scope of work COMPLETED # PROJECT LEAD Est. COST REVIEW COMPL. STATUS DESCRIPTION DATE DATE 2 Airport Rules and AMG 0 10/20/2010 9/20/2010 Second committee review (finance) for council approval on Regulations 9/20/2010 7 MIA Appraisal AMG 0 10/20/2010 12/31/2010 MAI appraisal for raw and improved land leases at the Auburn Airport for implementation 1/1/2011 1 Airport Storm Reid $50,000 4/20/2011 Completed Water Design Middleton /AMG Update 4 Runway Lighting Steve $350,000 7/20/2011 6/2/2011 Construction Completed. Waiting on Punch List and FAA Replacement Burke /Reid inspection. Middleton /AMG 5 Storm Water Robert 0 4/8/2011 Project Completed Retention Ponds Lee /Storm Water /Coleman 6 Airport Hangar AMG 0 9/7/2011 Completed Inspection 8 Drainage Mitigation Tim Carlaw TBD TBD TBD Recent observation — no change since last report. No standing water. Monitoring and will update as necessary 17 Repair of storm AMG $25,000 11/11/2011 The most deteriorated catch basins to be identified and Water Catch Basins repaired as required. Twenty (22) catch basin were repaired at cost of $23,794.35 (Note: 2 failing catch basins were repaired at the AFS shop which AFS Shop is paying for). Last Revision Date: 11/14/2011