Loading...
HomeMy WebLinkAboutBuno Construction, llc o CITY OF AUBURN CONTRACT CHANGE ORDER AGREEMENT NO. 4 �c Contract No., Project No. and Project Title: 10-23,CP0909, Lakeland Hills Booster f�7 Pump Station Improvements Contractor Name and Address: Bono Construction, LLC 20219 99th Avenue SE Snohomish, WA,98296 0 The Contractor is hereby directed to make the changes to the Contract as described herein. This document and all attachments arc a supplement to the contract. All work,materials and measurements for the type of construction involved shall be in accordance with the contract documents of the above maned project unless stated otherwise in this change order. Summary of Proposed Changes: 1 The Contractor shall install a fire hydrant along Nathan Ave SE between 57th Ct SE and Evergreen Way SE. Price includes all labor,equipment,and materials to install a complete fire hydrant assembly, including but not limited to mobilization,traffic control labor,wet tap of existing 12 inch diameter main,and installation of the ftre'hydrant assembly, including 6 inch diameter ductile iron pipe, temporary pavement patch,saw cutting,concrete sidewalk replacement,asphalt trench patch,and landscape restoration. Work shall conform to Section 7-14 of the Special Provisions. 2 working days are also added to the Contract. The Contract time is extended by 2 days. r Item Sch. Sec. No. Item Description Quantity Units Unit Price Total Price (+/-) ($) (+/-) 704-1 A 7-14 JHydrant Assembly Complete I LS 1 18613.06 $ 18,613.06 Subtotal $ 18,613.06 Washington State Sales Tax(9.5%)on applicable items $ 1,768.24 TOTAL $ 20,381.30 Base Amount Total Incl.Tax 1. Total Cost this C/O $ 18,613.06 $ 20,381.30 2. Total Cost Previous C/O $ 14,535.61 $ 15,916.49 3. Original Contract Amount $ 1,811,472.50 $ 1,983,562.39 4. Revised Contract Amount $ 1,844,621 17 $ 2,019,860.18 This change order constitutes full and complete compensation for all labor,equipment,materials,overhead,profit,any and all indirect costs,and time adjustment to perform the above described changes. All other costs arc non-compensible All other terms and conditions of the contract remain unchanged RECEIVED f _D Contractor, 11 G l� r Date` t Inspector: NOV- 2 202 to 2 Zu12 Project Manager- CITY of Aubm City Engineer- Date Public W^� D A d b _ ',I!, WORks DEPARTMENT Approved y Mayn , Auburn Date H AForm s\G hangeOrder.xls RECEIVED 0 Yry 011- CITY OF AUBURN QF9'6BG NOV - 9 2012 CONTRACT CHANGE ORDER AGREEMENT NO. 3 S'Oc9lj/ �CF Contract No.,Project No.and Project Title: 10-23,CP0909, Lakeland Hills Booster 1Uj city ofAubm Pump Station Improvements FLbhc Wo&DcPVn Kw Contractor Name and Address: Buno Construction, LLC 20219 99th Avenue SE Snohomish, WA,98296 The Contractor is hereby directed to make the changes to the Contract as described herein. This document and all attachments are a supplement to the contract. All work,materials and measurements for the type of construction involved shall be in accordance with the contract documents of the above named project unless stated otherwise in this change order. Summary of Proposed Changes: I Added Contract days only due to delays in the owner supplyed SCADA Control Panel and delays in critical material deliveries from suppliers which has affected the construction critical path. The Contract time is extended by 55 days. Sales Item Sell. Sec. No. Item Description Quantity Units Unit Price Total Price Tax $ Subtotal $ Washington State Sales Tax (9.5%)on applicable items $ TOTAL $ Base Amount Total Incl.Tax 1. Total Cost this C/O $ - $ 2. Total Cost All Previous C/O $ 14,535.61 $ 15,916.49 3. Original Contract Amount $ 1,983,562.39 4. Revised Contract Amount $ 14,535.61 $ 1,999,478.88 This change order constitutes full and complete compensation for all labor,equipment,materials,overhead,profit,any and all indirect costs,and time adjustment to perlirrm the above described changes. All other costs are non-compensible. All other terms and conditions of the contract remain unchanged. Contractor* d l{ b l Inspector- . l 111 S a Z are Project Manager- /t /3 tZ Date City Engineer- D= Approved by //43112- Mayor, Mtv of Auburn ' D"" H:\Forms\C ha ng eO rder.xl s CITY OF AUBURN CONTRACT CHANGE ORDER AGREEMENT NO. 2 Contract No., Project No. and Project Title: 10 -23, CP0909, Lakeland Hills Booster Pump Station Improvements Contractor Name and Address: Buno Construction, LLC 20219 99th Avenue SE Snohomish, WA, 98296 The Contractor is hereby directed to make the changes to the Contract as described herein This document and all attachments are a supplement to the contract All work, materials and measurements for the type of construction involved shall be in accordance with the contract documents of the above named project unless stated otherwise in this change order Summary of Proposed Changes: 1. Added days to contract due to a delay in the owner supplyed SCADA Control Panel which affects the construction critical path (35 days). The Contract time is extended by 35 days. Item Sch. Sec. No. Item Description Quantity ( +/ -) Units Unit Price (5) Total Price (+1-) Sales Tax (Y/N) CCC $ 1,811,472.50 $ 1,983,562.39 4 Revised Contract Amount C $1,999,478.88 CCC Subtotal $ Washington State Sales Tax (9.5 %) on applicable items $ TOTAL This change order constitutes full and complete compensation for all labor, equipment, materials, overhead, profit, any and all indirect costs, and time adjustment to perform the above described changes All other costs are non- compensible Contractor: Inspector: Project Manager: I /, ' Date _ City Engineer: Zi} Z /� Date Approved by: — Mayor, City of Auburn �SLtt. €r— yIlgb L Date y/I 6 %iZ 7/ate H \Forms \ChangeOrder xls 1► 4/27 /2 Date 11 j Base Amount Totals incl.Tax 1. Total Cost this C/O $ - $ - 2. Total Cost Previous C/O $ 14,535.61 $ 15,916.49 3. Ori_inal Contract Amount $ 1,811,472.50 $ 1,983,562.39 4 Revised Contract Amount $1,999,478.88 This change order constitutes full and complete compensation for all labor, equipment, materials, overhead, profit, any and all indirect costs, and time adjustment to perform the above described changes All other costs are non- compensible Contractor: Inspector: Project Manager: I /, ' Date _ City Engineer: Zi} Z /� Date Approved by: — Mayor, City of Auburn �SLtt. €r— yIlgb L Date y/I 6 %iZ 7/ate H \Forms \ChangeOrder xls 1► 4/27 /2 Date 11 j