Loading...
HomeMy WebLinkAboutCP1224 Rodarte Construction Contract 13-04• CITY OF AUBURN • CONTRACT CHANGE ORDER AGREEMENT NO. 1 Contract No., Project No. and Project Title: Contractor Name and Address: 13 -04, GP1224: 2013 Local Street Pavement Reconstruction Rodarte Construction 17 East Valley Highway East Auburn. WA 98082 The Contractor is hereby directed to make the changes to the Contract as described herein. This document and all attachments are a supplement to the contract. All work, materials,measurements and unit bid prices for the type of construction involved shall be in accordance with the contract documents of the above named project unless stated otherwise in this change order. Summary of Proposed Changes: Per the attached revisions, remove two sections of curb and gutter and install new curb and gutter at lower grades on H St NE from station 20 +00 to 22 +20 and station 23 +52.50 to 24 +82.09. Grind and rebuild portions of the pavement as indicated on the revisions to match into the new curb and gutter grades. Stockpile the existing crushed surfacing base course onsite and reuse. Install one new catch basin at the new low point in the curb and gutter at station 20 +75 and connect it to existing catchbasin at station 20 +50. The Contract time is extended by days. Item Sch. Sec. No. Item Description Quantity ( + / -) Units Unit Price (S) Total Price ( + / -) Sales Tax (Y/N) 11 A 2 -02 Removal of Curb and Gutter 320 LF 3.00 $ 960.00 N 12 A 2 -03 Roadway Excavation Including Haul 75 CY 1B.00 $ 1,350.00 N 16 A 2 -06 Subgrade Preparation 322 SY 1.25 $ 402.50 N 16 A 2 -12 Construction Geotextile for Soil Stabilization 322 SY 1.75 $ 563.50 N 18 A 4 -04 Crushed Surfacing Base Course 10 TON 19.00 $ 190.00 N 25 A 5 -04 Planing Bituminous Pavement 275 SY 12.50 $ 3,437.50 N 27 A 7 -04 Solid Wall Polyvinyl Chloride (PVC) Storm Pipe, SDR -35, 12 inch Diam. 25 LF 30.00 $ 750.00 N 33 A 7 -05 Catch Basin Type 1 1 EA 900.00 $ 900.00 N 37 A 7 -05 Connect to Existing Catchbasin 1 EA 850.00 $ 850.00 N 53 A 8 -04 Cement Concrete Traffic Curb and Gutter 320 LF 14.50 $ 4,640.00 N C01 -1 A 1 -09 Mobilization for Change Order No. 1 1 LS LS $ 2,500.00 N C01 -3 A 4 -04 Remove and Install Existing Crushed Surfacing Base Course 1 LS LS $ 3,200.00 N COI -2 A 5 -04 HMA CI. 1 -inch PG 64 -22 (Class E) for Change Order No. 1 74 TON 85.00 $ 6,290.00 N Subtotal $ 26,033.50 Washington State Sales Tax (9.5 %) on applicable items $ - TOTAL $ 26,033.50 H: \Forms \FCO25.xls (Revised 05/2012) • CITY OF AUBURN • CONTRACT CHANGE ORDER AGREEMENT NO. I Contract No., Project No. and Project Title: 13 -04, CP1224: 2013 Local Street Pavement Reconstruction This change order constitutes full and complete compensation for all labor. equipment. materials, overhead, profit. any and all indirect costs. and time adjustment to perform the above described changes. All other costs are non- compensible. All other terms and conditions of the contract remain unchanged. H: \Forms \FCO25.xls (Revised 05/2012) Contractor: Inspector: Project Manager: City Engineer: Approved by: l Da1r O Dare 6 fl 1 3 Daw ,l Date _/ v Mnp rtp ofAuburnr Date Base Amount Total Incl. Tax 1. Total Cost this C/O $ 26,033.50 $ 26,033.50 2. Total Cost Previous C/O $ - $ - 3. Original Contract Amount $ 2,004,90T40 $ 2,055,875.57 4. Revised Contract Amount $ 2,030,940.90 $ 2,081,909.07 This change order constitutes full and complete compensation for all labor. equipment. materials, overhead, profit. any and all indirect costs. and time adjustment to perform the above described changes. All other costs are non- compensible. All other terms and conditions of the contract remain unchanged. H: \Forms \FCO25.xls (Revised 05/2012) Contractor: Inspector: Project Manager: City Engineer: Approved by: l Da1r O Dare 6 fl 1 3 Daw ,l Date _/ v Mnp rtp ofAuburnr Date C-' � • � �' � � � � �� � ;, ���� �� �� � ��� � � ' _ � � � �� ��T ����, r � � � I _-- =''� ._- - H STA. 21 +00.00 2.00 L i I I - - Cf�OWN 74.89 H STA.!2 �+ 25.00. 2.00' Ll __ I ` ' GRAD � EAK 74.97 � �Z � ' H_ STA. 21 +75 0�'� . 00� LT � H STA 21 +00.00�0�,, 9 �T GRF� E�BREAK 75.05 CROWN 75.26 � GRADt BREAI< 74.85� o �- t I i� H STA. 2 i +7: 00 UI.00 LT ��i �,TG. ?0+50:00. �.00' LT �� �' GRADE BREAK 74.93.-� � I H ,BTA. 1 +50.00 200' LT GRADE BREAK; 75.: � I CROWN 74.64 �4 z -• GRADE BREAK 7.,.3•J�I oU vc I � ADE �iREAK 75.10 � � H STA. 20+75.00 D.Q��E=1r � �� �RADE BREAK 75.18 H SiA. 20+50.00 0.00� L I H S I�+. ?i +� ,.00. � c, GRADE BREAK 74J2 GftADE BREAK 7�L.60 c� 2 00' I_T , ; �� GRADE BREAK 74.80 l CROWN 75 39 GRA D E BR E A K 74.68 ` C � OWN 75.P1 fi S T A. 2 1 +5 0.0� i � H S7/�� ?� 75.00 ?f'vJ' LT � � 10' LT � - - _ _ � � CROW�J �a 76 � � � �� i �h�J'NN 7�.1 4 / � �� _ , i ;� � = .. .. �yt �- z�_ -- --�� - - - - - _�- - -- - --= - -` - - ,, ., --� � �� ..-' . . . .. y e • i . � � , _-_ - . � . _-. ..:.> >� :.' �� i i _ , � _ � . � ..� - ^ � f _ _ ,. � _ ' . . , . _ �_, -�. , . > �� ' i �- "��' -. � -_ _ ^ U� . ',i� �. � �' = L. . '-' I� .. I - -�. �, „ -_ _ �:.. _ :��, ��� :. � '_ -. . -_._ ,�- - �,� - � _ _- '_ _ �- i ___ �., _ _ o . __ _. ,r `_ :v' _ -'- � � _ !" _. _ __,; _ ---- _ f_ - _ -_ __ _ _ __ E� ST�. �Q��Q�.�O. - . _ _ _ � ��I �_ � ���� - - �. - i "_ _ - _ _ _ - �� ���� � I I ���NU �.n� � - _�i � �, H �STREET��� NE _ " ��� �• '_� � � � -[� - � �CROWN �74.g3 � I �� � � I � --i5 - - C;f I i i � _�- - 0 00' LT � � - !_U",,�7 I v' � � � :-- �� CROWN /�.J3 r -� _ 1 = - _ __ . _ - - _ - ��. -� ` �- - ! -- �' I L2+00 � ` .. � r -- - - - - - - - _ '. - i - -- ' �_�__ - -� _ - . � � [�� $ G� � �: b� o I C' o ' - - - � - �� �� �F-j-1l� --- �I - - -� = - � - - r � '. VJ � � �75 � r�'1 _. N. _ � _ � b� N ! � r7 � . . .__ - _ .-� - W _ �_9 - = I _ p : _ 15" �SD � ', ;. `' I � ri r� `- ' r� �- � � - - _ --- - J- _ 0.�3��� 15 ' SD S' SD 0 5� ,� � �0.50� 0.50� 0.50% 0 79� _ 0.79� 0. 9� 0.5 0 �5 0. % ,. - � ;, -- �.: . , ,\ -- � � , - , � - . � C� � � ,� � � i - - � � --- � '�i.�� � I � � � � � �� � � i � T ���.� , ���, f � , ,;_ �I ,� � �' I �, � � � � I _ � ..� - ` � ,� ���� ,,I hI S��#. 23+75.00 H STA� 24+"L5.OQ H STA. 24+75.00 � � � ���� � I I 0.0 ' I LT O.GO' T O.OU' �T I "��i c�z wN 75.24 CROWN 74.99 CROWN 74J4 � � �; � � ` I � H STA. 23.+52.5' H STA. 24+00.�?0,_ H STA. 24+50.OG. � I _ � — � P — � - - =0.b0� LT� - - � - - 0.00' LT I I 000' LT � � � OWN 7 19 CROWN 75.1 2 L — CROWN 74.87 � ` I � I � = � r � -� „ _ - - - — __ — i - ` ° ,° ' -� � ` --=�'._ `- ' ; J � _ --- , __ - >- . — � - �—:� ' . .-' , - ,_'. , -� � _ _ _ _ �- � °_ �� e,:=. — - - - ° — � --- --- - - - : - - - -� - G' H STRE I -- - � -- , � �� ` I _ , , v�� sr __-_� - - � RIND 0C1 �� ��T � E Y � � � � - - �, - � �� �� � � ? � I , �J / �f 1� f I .l - - 23 C!0 _ �I�— �� �� - - � � '��7 6 �'"��, : � _ � 1 ' � , _ i � ' 1�_ ?� m - ,� w� � I � � � � _�) _ � , )� �l Y �y� - � . ._- -� �i _�-. ._�.p - �. . �/:��, � E\ _ k. c. — .� __ . ��I � � _ _� . .. . 0. q N - __�� _� ��� SD 0.5� 0 12'� SDC�. ;o N 0.5 12 SD 0.5� - -12'I SD , �I __ � � I I _ -- `� � I ; _ �� ►� , � 0.5% � 12" SD +� h�� a - t- — -- _ I;' :_- .r.-- - — --�'"� _ - -_-- - —. � �— __ _ - - — -- n:5i � c, 5" t�� + - _ .� - - - .. ,_ . - __ _ - F.�� - � _ �y .•f _ —�—- 1' ' � r -- - .. � -� _ ;�.\� � f ��—� ' I i . 1 �� � �\ j . ` � �i�� i H STA. ��+52.SG � �, � � FL 74.�,� , � - - � � �i_Oi Ivt4k N STA. 4+SQ00 i � � � �`�� � 1I � GRIND 0. i 7' FL 74.34 � I� = � I � � � FL 74.51 � '� '- li STA. 24+O�OD �_0 ' P�1P.X � � � � H STA_ ) `+f 5.00 j �,� i I -o J i \ �-_ I FL 74. � ' I FL 74.59 �TA. 2 1 75.00 "`�'r�ir , �C o FL 74_85 � FL 74.76 � �� F i 74.22 � �° � 1 � �" � H TA. L4+25.00� e I \ FL 74.38 ,`�"� � � � � �a �� i �� � - - FL-�9.4 7 �U��*+ A z ° I FL 74.63 CB-D309 T'YPE i � � \ � H SiA. 24+8209 (17.05' R I) � i � � ��� �i � � RR.1 74.18 ` �� � �� _ I , IE 69.36 (12'� W OUT) � I ��I, I I � ( ! I-� I I��dC � � /' ;� � � � I�J�� � I I I I �' � � � I �' I I - - - - - - - . � -{ �' r'�=�" � _ LEGEND. , >..- [;,.� � �� � i � ; � ;.��� �;.� � i�ini :H (�;, i,�l- �i ; �� or< XX.XX ORIGINALLY PROPOSED ELEVATIONS CEMENT CUfJt.kETE n ���i' 2�' 40' CURE3 AND GUTTER TO �E REPLACEG HATCH (SYME3DL) FOR ASPHALi CONCRETE GRIND AND OVERLAY � — HJ=lI��li.l�—�'--,' `_ �.'�I_�_ � � • � � n SEC. 18, T 21 N. , R. 05 E, W.M. � W -: �I � z ;F �- I w �� ��i� � I _ sr- e: � n:9 H r, . � r � � � �' � � �I _ 91�.i.. 2:9... 212.',?2'.1. � � ;EWIVAM1�LCCCVI ENLSOEWi�k _� � -- — G�C'OVEL� EL[v = �saJ' I � 0� --- I _ M �—N I � ' p �� _ "' c O �— � � II if Ei f tl �Ik E v INlert Lii�IJbl � V1 . �� -� � o�ii U.U�f _`6';' � I � ' -�- . a __ . � o , o � �� � �� � � � — 3 ,,,�, �,_� - � �� �- , �y � cA HS! ]�fyltBC Li F1MaRCWiNE� ] o�� ' I � - �OII/B v I t H S� I i51 q (iBOJ Li RAMP RCw INE � P<35 � -� OOOtl ' I I I p I H 4X. i E91$ {1q2ii Li) RPM ROWLWE �SpO I { I � , � � H 14 i�lIJ2 (,.3 J3 Li) FAM_ ROWLRIf ]:P6 ! . I H 4 G II IOOJ Pil H M1 I ]<.]] . . I I II ] H [•f Z ]] ('CT ei) H Ln2 ]<.]5 I � r> I CO- Fi) X lN£ l ➢2 � J (� OG FT1 X LME ]<F �`T-Lyr. EI f.l.:✓ FEk W i�i - � - 1 � 1.� H * L�C Ff1 H LNG < � . \ � St4vy.Fp Fl b F-a0.1 01 FNO PER I I H S� �] I (0p0 Fi) H ING ]629 (RIP 4 c�', umflnsiurrs s�owF on -E vinry �� sta zr eew (:<sT u) [oF >ac (wnr i-�[�� I o� � i u e rn uo e (z_ ul [oa in (�t�i� [�;. � � 7��� e : 2 �5ac ( eo'' LT) I FoF a � �unro- f��' �I • — n 2a.63R �SCr: _-- - ( R'? I GaVG �.A.. .�r iatl i - N � I � _— ,-� . �ra �:ai;iz (ie� a.+uo r�c��._�:- j r�-� - HS � TREET NE � ' _ � � " cT>. $•�6�IZ ( BG�� FIf PAM ' I ib�j�'�� W � ^1 I � ii s?a z9 -n(i�(ia s �ei 1 aAMN v orvunc �.av �. i � F G H � , � I, K � ; �� S,a s<� �,< H,�— - EoP , � �M� � E., � . _ �i � l H ciP 25 OC E ('a 2 Fil � EU�' I (A0. (�� -. , /' i :., .• .y I H >i t .rn r '. W � F� — _ _ —— _ — I ' d'. .. . �� i '., - _ E.� (n `.P _ ` '_I < _ I . (, : G. I � "' `�_ I —. _ _ . — I__ _ .. ; �� _ -- — � � I � -_ �/ �I _ — � � � 12 " S D ,�� ■ � �, __ _ ,� . — _, ;�n _ _ — o - P ��. I I � ---- —— , ------- — — � — 6.8% �� o 'Q—� _ I � 1 � I I — o� . a �6 �� .i ��, �� N�_ � 7.�% � �_ ��� � _ — — l i •'� _ � .;�1 E � ����.� �n R S I �W T� � �� i IfEry.l A� .LE F�'lli / 4 ` I r �- \� LJ S � '_ P Ji' F C�F � � I ' I r m � I I r ._ __ n � i��e r„ : �� u�+�� a k I �� �._�7 u � l��� i � i _ :��_ � ��; � � � E� E ��r��,�� F-_ F��, �u���F�P������� '1.90G]2J hisi r+,:. o.;i> rt ��::i„i, .v��.._.n�=.;ca=nu,eecrsrv,.e��UV,ePaa��rn,v av on�e Rewewt_nsv: onre 2013LOCALSTREETPAVEMENT veoxc. � - i I�.co � i — -- �+uuaEr. - — L ,= rqn[wnbme P � . Etao. � I — $o ` ,"" "'""""'�-°"' . �!M1�'„ '� uTr°FT T PuBUC WORKS DEPaR7n7ENr _ RECONSTRUCTION PROJECT cPi22�t . f. .n9- � . A T T LL T T� C sl clio F ..'t=_��r CON�hCi --- 5 � E'. �' ��+ H � ` 25 West Main Street -- H STREET NE r+uueER ' ° l iU 1J U 1\1 qiiF�urn,Washinglon ���0� 13-04 I p,� _�•�����_ '��_^� �+"'�" , �VASHINGTON INTERSECTION DETAIL oa � r nsor-mwn w�i i i-rr.siF�on sr�r34 --- ,;..� , � H STREET NE AND 3TH STREET NE o� 3B CITY OF AUBURN CONTRACT CHANGE ORDER AGREEMENT NO. 2 Contract No., Project No.and Project Title: 13-04, CP1224: 2013 Local Street Pavement Reconstruction Contractor Name and Address: Rodarte Construction 17 East Valley Highway East Auburn, WA 98082 The Contractor is hereby directed to make the changes to the Contract as described herein. This document and all attachments are a supplement to the contract. All work,materials and measurements for the type of construction involved shall be in accordance with the contract documents of the above named project unless stated otherwise in this change order. Summary of Proposed Changes: Contract time is extended by 22 days due to the following reasons: 1. 3rd party delay while waiting for Puget Sound Energy,Century Link and Comcast to relocate their utility poles on H St NE. 2. 3rd party delay while waiting for Puget Sounds Energy to relocate the gas service at 1210 23rd St SE. 3. Delay while waiting for the City to determine the revised replacement limits for the sidewalk on H St NE and additional time needed for the removal and installation of the additional sidewalk determined to be needed by the City. The Contract time is extended by 22 days. Item Sch. Sec.No. Item Description Quantity Units Unit Price Total Price (+/-) (5) (+/-) Time Extension Only. No Changes to Bid Items. Subtotal $ - Washington State Sales Tax(9.5%)on applicable items $ - TOTAL $ - Base Amount Totals incl.T'ax 1. Total Cost this C/O $ - $ - 2. Total Cost Previous C/O $ 26,033.50 $ 26,033.50 3. Original Contract Amount $ 2,004,907.40 $ 2,055,875.57 4. Revised Contract Amount $ 2,030,940.90 $ 2,081,909.07 This change order constitutes full and complete compensation for all labor,equipment,materials,overhead,profit,any and all indirect costs,and time adjustment to perform the above described changes. All other costs are non-compensible. All other terms and conditions of the contract remain unchanged. Contractor: /�=r/6,. 2.e■/ 1( ' Date Inspector: • Project Manager: � 14. 'ate 1., City Engineer: ��Ii��l Date f �� Date Approved by: '��� r . ,ra Mayor, • . of Auburn late H:\Forms\FCO25.xls (Revised 05/2012) `