Loading...
HomeMy WebLinkAboutCP1301 Trinity Contractors Inc0 qj z I CITY OF AUBURN CONTRACT CHANGE ORDER AGREEMENT NO. 1 Contract No., Project No. and Project Title: 13 -20, CP1301: Citywide Sidewalk Repair Contractor Name and Address: Trinity Contractors, Inc PO Box 1348 Marysville. WA 98270 The Contractor is hereby directed to make the changes to the Contract as described herein. ']'his document and all attachments are a supplement to the contract. All work, materials,measurements and unit bid prices for the type of construction involved shall be in accordance with the contract documents of the above named project unless stated otherwise in this change order. Summary of Proposed Changes: This change order adds working days and an additional plan sheet (Sheet 12 attached) to the Contract to account for additional tree and stump removals that were not included in the original contract and to provide the removal and replacement of the concrete curb ramp at the SE corner of 3rd Street NE and A Street NE that was not included in the original contract. All costs associated with the additional work shall be paid at original unit bid prices for the applicable items. The Contract time is extended by 5 days. Item Sch. Sec. No. Item Description Quantity ( + / -) Units Unit Price (S) Total Price ( + /-) Sales Tax (Y /N) CO -1 $ - Increase Bid Item #6 "Removal of Trees" 5 EA 1,000.00 $ 6,000.00 N CO -2 4. Revised Contract Amount $ Increase Bid Item #7 "Removal of Stump" 6 EA 500.00 $ 3,000.00 N N Subtotal $ 9,000.00 Washington State Sales Tax (9.5 %) on applicable items $ TOTAL $ 9,000.00 This change order constitutes full and complete compensation for all labor, equipment, materials, overhead, profit, any and all indirect costs, and time adjustment to perform the above described changes. All other costs are non- compensible. All other terms and conditions of the contract remain unchanged. H: \Forms \FCO25.x1s (Revised 05/2012) Base Amount I Total incl. Tax I. 'Total Cost this C/O $ 9,000.00 $ 9,000.00 2. Total Cost Previous C/O $ - $ - 3. Original Contract Amount $ 184,265.00 $ 184,265.00 4. Revised Contract Amount $ 193,265.00 $ 193,265.00 This change order constitutes full and complete compensation for all labor, equipment, materials, overhead, profit, any and all indirect costs, and time adjustment to perform the above described changes. All other costs are non- compensible. All other terms and conditions of the contract remain unchanged. H: \Forms \FCO25.x1s (Revised 05/2012) CITY OF AUBURN CONTRACT CHANGE ORDER AGREEMENT NO. I Contract No., Project No. and Project Title: 13 -20, CP1301: Citywide Sidewalk Repair Contractor: Inspector: Project Manager: City Engineer: Approved by: H:1Forms1FCO25.xls (Revised 05/2012) ADRYURN C ITY O1' WASHINGTON September 24, 2014 CERTIFIED MAIL RETURN RECEIPT REQUESTED J.R. Chapman Trinity Contractors, Inc P.O. Box 1348 Marysville, WA 98270 Nancy Backus, Mayor 25 West Main Street - Auburn WA 98001 -4998 * www.aulnunwa.gov * 253- 931 -3000 RE: Contract No 13 -20 Project No. CP1301: 2013 Citywide Sidewalk Repair Contract Completion and Acceptance Dear Mr. Chapman; All of your obligations in regard to this project have been met in accordance with Section 1 -08.5 of the Standard Specifications. The one -year warranty period begins as of the date of this Contract Completion and Acceptance Letter. The total contract amount for this project, as shown on your Final Pay Estimate is $161,441.15. Your retainage in the amount of $8,072.06 will be released approximately 60 days after this date, provided all necessary releases have been received, and there are no outstanding claims against the retainage. All approved Labor & Industries Affidavits of Wages Paid from your firm and all subcontractors on the project have been received. If you have any questions, please contact Amanda DeSilver, Contract Administration Specialist, at 253 - 876 -1980. Sincerely, I a , P.E. Asst. Director of Engineering Services & City Engineer Community Development & Public Works Department IG /ad /mt cc: Dani Daskam, City Clerk Jai Carter, Project Engineer File 13.11 (CP1301) AUBURN * MORE THAN YOU IMAGINED