AGREEMENT FOR PROFESSIONAL SERVICES
AG-C-280
THIS AGREEMENT made and entered into by and between the CITY OF AUBURN, a
Municipal Corporation in King County, Washington, hereinafter referred to as "CITY" and
Casne Engineering, Inc. whose address is 10604 NE 38th Place, Suite 205, Kirkland, WA
98033, hereinafter referred to as "CONSULTANT."
In consideration of the covenants and conditions of this Agreement, the parties hereby
agree as follows:
1. SCOPE OF WORK.
See Exhibit A, which is attached hereto and by this reference made a part of this
Agreement.
2. TERM.
The CONSULTANT shall not begin any work under this Agreement until authorized in
writing by the CITY. The work identified by this Agreement is anticipated to be completed in the
years 2007 and 2008. All work under this Agreement shall be completed by March 31, 2008.
The established completion time shall not be extended because of any delays
attributable to the CONSULTANT, but may be extended by the CITY in the event of a delay
attributable to the CITY, or because of unavoidable delays caused by an act of GOD or
governmental actions or other conditions beyond the control of the CONSULTANT. A prior
supplemental Agreement issued by the CITY is required to extend the established completion
time.
3. COMPENSATION.
The CONSULTANT shall be paid by the CITY for completed services rendered under
the approved Scope of Work identified in Exhibit A. Such payment shall be full compensation
for work performed or services rendered and for all labor, materials, supplies, equipment and
Agreement for Professional Services AG-C-280
March, 2007
Page 1 of 11
incidentals necessary to complete the work. The CONSULTANT shall submit an itemized
invoice to the CITY prior to payment, in a form similar to that attached as Exhibit C of this
Agreement.
Compensation for the work identified will be on a time and material basis, not to exceed
the following totals for the current year and succeeding years combined.
Tasks 1 to 7 $ 285,000.00
Task 8 (Optional) $ 20,000.00
• Requires separate notice to proceed
Total Authorized Compensation $ 305,00.00
Expenditure of Management Reserve Funds must be authorized by the CITY as set
forth in Section 4 of this Agreement. Compensation for work performed shall be based on the
Schedule outlined in Exhibit B of this Agreement. Exhibit B is attached hereto and by reference
made a part of this Agreement.
Compensation shall include all CONSULTANT expenses including, but not limited to,
direct salary, overhead, profit and direct non-salary. The CONSULTANT shall be paid by the
CITY for direct non-salary cost per Exhibit B. These charges may include, but are not limited to
the following items: reproduction fees, communication fees, and mileage. The billing for non-
salary cost, directly identifiable with the project, shall be submitted as an itemized listing of
charges supported by copies of the original bills, invoices, expense accounts and miscellaneous
supporting data retained by the CONSULTANT. Copies of the original supporting documents
shall be supplied to the CITY upon request. All above charges must be necessary for the
services provided under the Agreement.
In the event services are required beyond those specified in the Scope of Work, and not
included in the compensation listed in this Agreement, a contract modification shall be
negotiated and approved by the CITY prior to any effort being expended on such services or
Agreement for Professional Services AG-C-280
March, 2007
Page 2 of 11
work shall be authorized in writing under the Management Reserve Fund as detailed in Section
4.
4. MANAGEMENT RESERVE FUND.
The CITY may establish a Management Reserve Fund to provide flexibility of
authorizing additional funds to the Agreement for allowable unforeseen costs, or reimbursing
the CONSULTANT for additional work beyond that already defined in this Agreement. Such
authorization(s) shall be in writing, prior to the CONSULTANT expending any effort on such
services, and shall not exceed $30,000.00. This fund may be replenished in a subsequent
supplemental agreement. Any changes requiring additional costs in excess of the Management
Reserve Fund shall be negotiated and approved by the CITY prior to any effort being expended
on such services.
5. SUBCONTRACTING.
The CITY permits subcontracts for those items of work necessary for the completion of
the project. The CONSULTANT shall not subcontract for the performance of any work under
this AGREEMENT without prior written permission of the CITY. No permission for
subcontracting shall create, between the CITY and subcontractor, any contractor or any other
relationship.
Compensation for any subconsultant work is included in Section 3 of this Agreement
and all reimbursable direct labor, overhead, direct non-salary costs and fixed fee costs for the
subconsultant shall be substantiated in the same manner as outlined in Section 3. All
subcontracts exceeding $10,000 in cost shall contain all applicable provisions of this
AGREEMENT.
6. RESPONSIBILITY OF CONSULTANT.
The CONSULTANT shall be responsible for the professional quality, technical accuracy,
timely completion and the coordination of all studies, analysis, designs, drawings,
Agreement for Professional Services AG-C-280
March, 2007
Page 3 of 11
specifications, reports and other services performed by the CONSULTANT under this
Agreement. The CONSULTANT shall, without additional compensation, corrector revise any
errors, omissions or other deficiencies in its plans, designs, drawings, specifications, reports
and other services required. The CONSULTANT shall perform its services to conform to
generally-accepted professional engineering standards and the requirements of the CITY.
Any approval by the CITY under this Agreement shall not in any way relieve the
CONSULTANT of responsibility for the technical accuracy and adequacy of its services. Except
as otherwise provided herein, neither the CITY'S review, approval or acceptance of, nor
payment for, any of the services shall be construed to operate as a waiver of any rights under
this Agreement or of any cause of action arising out of the performance of this Agreement to
the full extent of the law.
7. INDEMNIFICATION/HOLD HARMLESS.
The CONSULTANT shall indemnify and hold the CITY and its officers and employees
harmless from and shall process and defend at its own expense all claims, demands, or suits at
law or equity arising in whole or in part from the CONSULTANT'S negligence or breach of any
of its obligations under this Agreement; provided that nothing herein shall require the
CONSULTANT to indemnify the CITY against and hold harmless the CITY from claims,
demands or suits based solely upon the conduct of the CITY, their agents, officers and
employees and provided further that if the claims or suits are caused by or result from the
concurrent negligence of (a) the CONSULTANT'S agents or employees and (b) the CITY, their
agents, officers and employees, this indemnity provision with respect to (1) claims or suits
based upon such negligence, (2) the costs to the CITY of defending such claims and suits, etc.
shall be valid and enforceable only to the extent of the CONSULTANT'S negligence or the
negligence of the CONSULTANT'S agents or employees. The provisions of this section shall
survive the expiration or termination of this Agreement.
Agreement for Professional Services AG-C-280
March, 2007
Page 4 of 11
8. INDEPENDENT CONTRACTORIASSIGNMENT.
The parties agree and understand that the CONSULTANT is an independent contractor
and not the agent or employee of the CITY and that no liability shall attach to the CITY by
reason of entering into this Agreement except as otherwise provided herein. The parties agree
that this Agreement may not be assigned in whole or in part without the written consent of the
CITY.
9. INSURANCE.
CONSULTANT shall procure and maintain for the duration of this Agreement, insurance
against claims for injuries to persons or damage to property which may arise from or in
connection with the performance of the work hereunder by the CONSULTANT, its agents,
representatives, or employees.
CONSULTANT'S maintenance of insurance as required by the Agreement shall not be
construed to limit the liability of the CONSULTANT to the coverage provided by such insurance,
or otherwise limit the City's recourse to any remedy available at law or in equity.
CONSULTANT shall obtain insurance of the types and in the amounts described below:
a. Automobile Liability insurance covering all owned, non-owned, hired and leased
vehicles, with a minimum combined single limit for bodily injury and property damage
of $1,000,000 per accident. Coverage shall be written on Insurance Services Office
(ISO) form CA 00 01 or a substitute form providing equivalent liability coverage. If
necessary, the policy shall be endorsed to provide contractual liability coverage.
b. Commercial General Liability insurance shall be written on ISO occurrence form CG
00 01 and shall cover liability arising from premises, operations, independent
contractors, and personal injury and advertising injury, with limits no less than
$1,000,000 each occurrence, $2,000,000 general aggregate. The CITY shall be
named as an insured under the CONSULTANT'S Commercial General Liability
Agreement for Professional Services AG-C-280
March, 2007
Page 5 of 11
insurance policy with respect to the work performed for the CITY using the
applicable ISO Additional Insured endorsement or equivalent.
c. Worker's Compensation coverage as required by the Industrial Insurance laws of the
State of Washington.
d. Professional Liability insurance appropriate to the CONSULTANT'S profession, with
limits no less than $1,000,000 per claim and $1,000,000 policy aggregate limit.
The insurance policies are to contain, or be endorsed to contain, the following provisions
for Automobile Liability, Professional Liability, and Commercial General Liability insurance:
a. The CONSULTANT'S insurance coverage shall be primary insurance as respects
the CITY. Any insurance, self insurance, or insurance pool coverage maintained by
the CITY shall be excess of the CONSULTANT'S insurance and shall not contribute
with it.
b. The CONSULTANT'S insurance shall be endorsed to state that coverage shall not
be cancelled by either party, except after thirty (30) days prior written notice has
been given to the CITY by certified mail, return receipt requested.
All insurance shall be obtained from an insurance company authorized to do business in
the State of Washington. Insurance is to be placed with insurers with a current A.M. Best rating
of not less than A-:VII.
The CONSULTANT shall furnish the City with certificates of insurance and a copy of the
amendatory endorsements, including but not necessarily limited to the additional insured
endorsement, evidencing the insurance coverage required by this section, before
commencement of the work. The CITY reserves the right to require that complete, certified
copies of all required insurance policies be submitted to the CITY at any time. The CITY will
pay no progress payments under Section 3 until the CONSULTANT has fully complied with this
section.
Agreement for Professional Services AG-C-280
March, 2007
Page 6 of 11
10. NONDISCRIMINATION.
The CONSULTANT may not discriminate regarding any services or activities to which
this Agreement may apply directly or through contractual, hiring, or other arrangements on the
grounds of race, color, creed, religion, national origin, sex, age, or where there is the presence
of any sensory, mental or physical handicap.
11. OWNERSHIP OF RECORDS AND DOCUMENTS.
The CONSULTANT agrees that any and all drawings, computer discs, documents,
records, books, specifications, reports, estimates, summaries and such other information and
materials as the CONSULTANT may have accumulated, prepared or obtained as part of
providing services under the terms of this Agreement by the CONSULTANT, shall belong to
and shall remain the property of the CITY OF AUBURN. In addition, the CONSULTANT agrees
to maintain all books and records relating to its operation and concerning this Agreement for a
period of six (6) years following the date that this Agreement is expired or otherwise terminated.
The CONSULTANT further agrees that the CITY may inspect any and all documents held by
the CONSULTANT and relating to this Agreement upon good cause at any reasonable time
within the six (6) year period. The CONSULTANT also agrees to provide to the CITY, at the
CITY'S request, the originals of all drawings, documents, and items specified in this Section
and information compiled in providing services to the CITY under the terms of this Agreement.
12. CERTIFICATION REGARDING DEBARMENT, SUSPENSION, ANDOTHER
RESPONSIBILITY MATTERS-PRIMARY COVERED TRANSACTIONS.
The prospective primary participant certifies to the best of its knowledge and belief, that
it and its principals:
(a) Are not presently debarred, suspended, proposed for debarment, declared ineligible,
or voluntarily excluded from covered transactions by any federal department or
agency;
Agreement for Professional Services AG-C-280
March, 2007
Page 7 of 11
(b) Have not within athree-year period preceding this proposal been convicted of or had
a civil judgment rendered against them for commission or fraud or a criminal offense
in connection with obtaining, attempting to obtain, or performing a public (federal,
state, or local) transaction or contract under a public transaction; violation of federal
or state antitrust statues or commission of embezzlement, theft, forgery, bribery,
falsification or destruction of records, making false statements, or receiving stolen
property;
(c) Are not presently indicted for or otherwise criminally or civilly charged by a
governmental entity (federal, state, or local) with commission of any of the offenses
enumerated in paragraph "(b)" of this certification; and
(d) Have not within athree-year period preceding this application/proposal had one or
more public transactions (federal, state, or local) terminated for cause or default.
Where the prospective primary participant is unable to certify to any of the statements in
this certification, such prospective participant shall attach an explanation to this proposal.
13. TERMINATION OF AGREEMENT.
This Agreement may be terminated by either party upon twenty (20) days written notice
to the other party, and based upon any cause. In the event of termination due to the fault of
other(s) than the CONSULTANT, the CONSULTANT shall be paid by the CITY for services
performed to the date of termination.
Upon receipt of a termination notice under the above paragraph, the CONSULTANT
shall (1) promptly discontinue all services affected as directed by the written notice, and (2)
deliver to the CITY all data, drawings, specifications, reports, estimates, summaries, and such
other information and materials as the CONSULTANT may have accumulated, prepared or
obtained in performing this Agreement, whether completed or in process.
Agreement for Professional Services AG-C-280
March, 2007
Page 8 of 11
14. GENERAL PROVISIONS.
14.1. This Agreement shall be governed by the laws, regulations and ordinances of the
City of Auburn, the State of Washington, King County, and where applicable, Federal laws.
14.2. All claims, disputes and other matters in question arising out of, or relating to, this
Agreement or the breach hereof, except with respect to claims which have been waived, will be
decided by a court of competent jurisdiction in King County, Washington. Pending final
decision of a dispute hereunder, the CONSULTANT and the CITY shall proceed diligently with
the performance of the services and obligations herein.
14.3. In the event that any dispute or conflict arises between the parties while this
Agreement is in effect, the CONSULTANT agrees that, notwithstanding such dispute or conflict,
the CONSULTANT shall continue to make a good faith effort to cooperate and continue work
toward successful completion of assigned duties and responsibilities.
14.4. The CITY and the CONSULTANT respectively bind themselves, their partners,
successors, assigns, and legal representatives to the other party to this Agreement with respect
to all covenants to this Agreement.
14.5. This Agreement represents the entire and integrated Agreement between the
CITY and the CONSULTANT and supersedes all prior negotiations, representations or
agreements either oral or written. This Agreement may be amended only by written instrument
signed by both the CITY and the CONSULTANT.
14.6. Should it become necessary to enforce any term or obligation of this Agreement,
then all costs of enforcement including reasonable attorneys fees and expenses and court
costs shall be paid to the substantially prevailing party.
14.7. The CONSULTANT agrees to comply with all local, state and federal laws
applicable to its performance as of the date of this Agreement.
Agreement for Professional Services AG-C-280
March, 2007
Page 9 of 11
14.8. If any provision of this Agreement is invalid or unenforceable, the remaining
provisions shall remain in force and effect.
14.9. This Agreement shall be administered by Kenneth L. Albinger on behalf of the
CONSULTANT, and by the Mayor of the CITY, or designee, on behalf of the CITY. Any written
notices required by the terms of this Agreement shall be served on or mailed to the following
addresses:
City of Auburn Casne Engineering, Inc.
Attn: Robert E. Lee, III Attn: Kenneth L. Albinger, P.E.
25 W Main Street 10604 NE 38th Place, Suite 205
Auburn WA 98001 Kirkland, WA 98033
Phone: 253.804.5071 Phone: 425.522.1030
Fax: 253. 931.3010 Fax: 425.828.2622
E-mail: rlee@auburnwa.gov E-mail: ken.albinger@casne.com
14.10. All notices or communications permitted or required to be given under this
Agreement shall be in writing and shall be delivered in person or deposited in the United States
mail, postage prepaid. Any such delivery shall be deemed to have been duly given if mailed by
certified mail, return receipt requested, and addressed to the address for the party set forth in
14.9 or if to such other person designated by a party to receive such notice. It is provided,
however, that mailing such notices or communications by certified mail, return receipt requested
is an option, not a requirement, unless specifically demanded or otherwise agreed.
Any party may change his, her, or its address by giving notice in writing, stating his, her,
or its new address, to any other party, all pursuant to the procedure set forth in this section of
the Agreement.
14.11. This Agreement may be executed in multiple counterparts, each of which shall
be one and the same Agreement and shall become effective when one or more counterparts
have been signed by each of the parties and delivered to the other party.
Agreement for Professional Services AG-C-280
March, 2007
Page 10 of 11
AU
B. Lewis, Mayor
ATTEST:
Danielle E. Daskam, City Clerk
Agreement for Professional Services AG-C-280
March, 2007
Page 11 of 11
Date APR ' 3 2007
Casne Engineering, Inc.
BY: 2 / ,
Title: ~~dlG an~
Federal Tax ID #
APPROVED AS TO FORM:
Exhibit A
Scope of Work
During the term of this AGREEMENT, Casne Engineering, Inc. (CONSULTANT) will
perform the following professional services for the City of Auburn (CITY):
Task 1-Evaluation of Planned Facility and Security Improvements
1.1 Review any plans and/or studies the City may have for upgrading and/or
renovating its water, stormwater, and wastewater utility telemetry/ SCADA
system.
Review these items to assist in developing the list of future improvements. Planned
items will be included in a master list of planned improvements to be discussed in the
meeting under Task 4 below.
1.2 Briefly review the Water, Sewer and Storm water Comprehensive Plans to
quantify the number of future water, storm and sewer facilities being planned
which should be included in future Telemetry System growth.
Review these plans and develop a list of proposed improvements. Planned items will be
included in a master list of planned improvements to be discussed in the meeting under
Task 4 below.
1.3 Review the City Water Vulnerability Analysis and Security Improvements Plan.
Roth Hill will review the vulnerability assessment and the proposed list of improvements
in consultation with ACSI and other team members, as well as with the City. The order
of improvements will be coordinated with the SCADA improvements priority list in order
to achieve efficiency and compatibility. Deliverable consists of prioritized list of security
improvements, potentially divided into items dependent on telemetry/communication
systems and those unrelated to this communication network.
1.4 Meet with City to discuss and decide which improvements will be included in the
present project. All of the existing water, storm and wastewater sites will be
included in the scope of this feasibility study.
As mentioned for items above, this meeting will focus on prioritizing and phasing the
master list of improvements. Roth Hill will facilitate this meeting to develop criteria,
attach definitions and then prioritize the improvements. Deliverables include a meeting
agenda, the initial master list of improvements, a meeting summary and a prioritized
version of the master based on the meeting. Additional telephone and remote
correspondence may be necessary to complete this task.
Exhibit A
Agreement No. AG-C-280
Page 1 of 8
1.5 Identify, discuss and categorize the funding available for the project and City's
desired timeline for implementation.
Research possible loan, grant and cooperative funding (cost-sharing) sources for the
proposed improvements.
Task 1 Deliverables
The following deliverables will be included in task 1.4:
1.1 Brief summary of (and reference to the name and date of the study) the plans for
upgrades to the existing water, storm and wastewater telemetry SCADA system.
1.2 Brief summary of the number and type of new water, storm water and waste
water facilities and upgrades planned for the future from the Comprehensive
Plans and any other City planning input.
1.3 Brief summary of the number and type of security improvements by water station
outlined in the Water System Vulnerability Analysis. (This will be kept confidential
as required)
1.4 Brief summary of the number and type of security improvements as approved by
city staff. (This will be kept confidential as required)
1.5 Identify the desired project schedule, available funding and possible additional
funding for this project.
1.6 Categorize the funding available for the project and show the City's desired
timeline for implementation.
Task 2 Preliminary Design of the Water Security Improvements
2.1 From 1.4 above, provide a preliminary design of the water system security
improvements at each site. This will include a plan drawing on existing station
backgrounds, showing only enough detail to define the security improvements
required. The components will be defined as to type. Assess alternative security
measures, provide preliminary design of alternatives and show on similar
sketches.
2.2 From 1.2 above, provide written description of security provisions for future
stations.
Exhibit A
Agreement No. AG-C-280
Page 2 of 8
2.3 Estimate the construction costs of the security improvements for the existing and
future water system sites.
2.4 Determine the video quality required for police to adequately assess whether a
response is necessary.
2.5 Determine the network requirements for video and other security information to
be reliably transmitted from the remote water sites to the Police and/or M&O
monitoring stations.
2.6 Determine the network requirements for SCADA system operations to each
remote facility and the M&O monitoring station. Also consider the network
requirements associated with central PLC programming and diagnostics.
Task 2 Deliverables
The following deliverables will be included in task 2.
2.1 A plan drawing of each water facility (secured) to identify the water security
improvements planned.
2.2 A written description of water system security at secured sites including future
water sites.
2.3 Estimated construction costs for the existing and future secured water system
sites.
2.4 Document the acceptable rates of video transmission and other attributes for
security improvements at remote water sites, the Police and/or M&O monitoring
stations.
2.5 Document the network requirements for video and other security information,
and SCADA system operation from each site to the central stations.
Task 3 Evaluation of Telemetry Hardware and SCADA Software Options
3.1 Draft criteria and features by which telemetry hardware and SCADA software will
be evaluated.
3.2 Submit draft criteria to City for comment and issue approved evaluation criteria.
3.3 Evaluate the existing station telemetry hardware for what should be reused and
what options for upgrade should be recommended. Site visits for photo
documentation will be required.
Exhibit A
Agreement No. AG-C-280
Page 3 of 8
3.4 Evaluate the existing SCADA software application and all system peripherals.
Make recommendations for short term and long term improvements. Estimate
costs of these improvements.
3.5 Compile a table of recommended equipment and estimate telemetry hardware
and software upgrade costs. For hardwired sites with tone telemetry, we will
identify station upgrades to implement PLC control wiring. Estimate construction
costs for station upgrades.
Task 3 Telemetry and SCADA Evaluation Deliverables
3.1 Meet with City personnel to discuss the criteria to be used for evaluating
telemetry hardware and SCADA software. Publish a list of these features and
open it for comment.
3.2 Finalize by discussing and incorporating comments.
3.3 Evaluate and recommend telemetry hardware in use that should continue to be
used to replace existing and recommend ways that these improvements can be
phased in.
3.4 Evaluate and recommend SCADA software improvements for the short term and
long term and provide costs estimates for each improvement.
3.5 Prepare a table of telemetry hardware and software upgrade costs, with station
upgrades to implement PLC control wiring costs.
Task 4 Evaluation of Communications Options
4.1 Obtain from the City Information Services staff the location and characteristics of
existing or planned network infrastructure within the City.
4.2 Review the City fiber optic network including extensions to downtown businesses
and the Auburn Environmental Park, the ITS network, available Commercial
fiber, the Police Wifi and Clearwire's wireless access.
4.3 Evaluate the proximity of existing network infrastructure to utility facilities and the
feasibility of supporting telemetry and security communication needs.
4.4 Obtain from City utility staff the currently available location of possible used and
unused water, storm and wastewater piping, spare conduits and other raceway
that could be used for installing new network cabling. Obtain currently available
data for water sewer piping plans and street maps.
Exhibit A
Agreement No. AG-C-280
Page 4 of 8
4.5 Discuss with the City utility staff whether they will require PLC programming and
diagnostics form a central location and if so, for which stations. Add this
bandwidth requirement.
4.6 Determine the technically feasible options for security & telemetry
communications. For each option, develop summary of likely components and
physical path. Determine each option's strengths, weaknesses and estimated
comparative construction costs.
Options considered will be licensed and unlicensed radio, microwave, power line
carrier, leased line and frame relay phone connections, cable network, cellular
back channel, copper and fiber optic network cabling by trenched cable in
conduit, by direct burial, by road pavement cutting, by aerial, and by installation
into gravity wastewater piping.
4.7 Meet at 40% to evaluate and discuss options with the City staff. This review will
focus the team on the options the City wants investigated to more detail and
those options that will be eliminated from consideration.
4.8 Evaluate the remaining feasible options for communication.
4.8A Provide a written description of each communication option with its
performance and reliability characteristics, its strengths and weaknesses,
and general installation methods.
4.8B Compare the network requirements with the features and limitations of
each communication option on astation-by-station basis in table format.
4.8C Provide a comparative construction cost estimate for each viable option
at each station based on average installation costs per foot and standard
equipment costs.
4.8D Total the comparative construction costs for each viable communication
option.
4.8E Prepare along-term cost benefit analysis of each option.
4.8F Provide an in house vulnerability review of each option.
4.9 Detail the chosen options and show the most likely composites of options for the
City's selection. Sketch the composites and estimate the costs of each
communication option.
4.10 Compile the above into a Communications Plan. Issue to the City for comment.
4.11 Incorporate City comments and publish Communication Plan.
---------------------------------------------------------------
Exhibit A
Agreement No. AG-C-280
Page 5 of 8
Task 4 Communication Options Deliverables
4.1-3 Document the existing City network infrastructure and how existing networks
could support the telemetry and security communication needs.
4.4 Document the existing City piping & conduits and how they could support the
telemetry and security communication needs.
4.5 Determine whether utilities PLC programming and diagnostics can be
programmed from a central location and if so, for which stations. Add this
bandwidth requirement.
4.6 Determine the technically feasible options for communications.
4.7 Meet to evaluate and discuss options with the City staff. List the options the City
wants investigated to more detail and those options that will be eliminated from
consideration.
4.8 Evaluate the remaining feasible options for communication
4.8A A written description of each communication option with its performance and
reliability characteristics, strengths and weaknesses, and general installation
methods.
4.86 A comparison of the network requirements in Task 2.5 with each communication
option.
4. 8C A comparative construction cost estimate for each viable option at each station
based on equipment costs and linear prices.
4.8D Totalized construction cost estimates for each viable communication option.
4.8E Prepare along-term cost benefit analysis of each option.
4.8F Summary of results for the vulnerability analysis performed for each viable
communication option.
4.9 Document the best composite communication options for City selection.
4.10 Compile the communications plan for City review.
4.11 Incorporate City Comments and publish Communications Plan.
Exhibit A
Agreement No. AG-C-280
Page 6 of 8
Task 5 Staffing Analysis
5.1 Meet with City M&O management and on-call staff who support PLC &SCADA
to evaluate their current skill set.
5.2 Meet with City IS staff who will support the expanded City communications
system to evaluate their current skill set.
5.3 Provide job descriptions and technical skill requirements for the operation of the
proposed facilities by Public Works, IS, and Police staff.
5.4 Document needed staff skills to support recommended SCADA upgrades. Make
recommendation for additional training of current staff and/or hiring of new staff
needed to support recommended technical upgrades. Recommend overall
staffing levels for management of system based on comparable systems at other
municipalities.
Task 6 System Improvement Guide
6.1 Compile from the study effort decisions a System Improvement Guide that will
clearly illustrate the sequential improvements that have been agreed on to
accomplish the improvements outlined by the City.
6.2 From the construction cost estimates, options for phasing and timelines for
implementation of the project will be discussed and documented. Issue the
Guide as a draft and solicit City comments.
6.3 Incorporate the comments into a final issue.
Task 7 Finalize Feasibility Report and Planning Next Phase of Design
7.1 Publish the draft Feasibility Report for comment by City staff.
7.2 Meet with City staff to discuss comments on the report.
7.3 Issue the Feasibility Report final.
Task 7 Finalize Feasibility Report -Deliverables
7.1 Publish the draft report with Table of Contents,
including all backup calculations, cost estimating
Introductions and context sections will be
each section shown above,
and sketches and drawings.
written for each section.
Exhibit A
Agreement No. AG-C-280
Page 7 of 8
Recommended improvements, estimated project costs and priorities will be
included.
7.2 Meet to discuss the City's comments on the draft report.
7.3 Issue the final feasibility report incorporating the City's comments. Provide a
dozen copies of the final report and provide two electronic versions (pdf & word).
Report will be stamped and signed by the supervising professional engineers.
Task 8 Estimate Relocating SCADA Headquarters (optional)
8.1 Meet with City to discuss possible relocation of M&O Operational Base and
subsequent relocation of all SCADA related servers, computers, and
communication facilities.
8.2 Provide logical sequencing of equipment relocation that minimizes disruption of
system monitoring functions.
8.3 Provide cost estimate of moving SCADA equipment of either pre or post upgrade
(as determined by City). Cost Estimate should include costs of the physical
movement of equipment, providing temporary monitoring while equipment is in
transit, and constructing physical infrastructure. Estimate should analyze aerial
and underground facilities for communication extension separately and provide
an overall cost for the identified location or as per linear foot cost for an unknown
location.
8.4 Issue the Relocation Report incorporating the City's comments. Provide 6
copies of the final report and provide two electronic versions (pdf & word).
Exhibit A
Agreement No. AG-C-280
Page 8 of 8
EXHIBIT B
FEE SCHEDULE
Casne Engineering, Inc.
CHARGES: Charges for employees are determined by the hourly rates listed below. Charges
for reimbursable expenses are specified below or in individual task order proposals.
Labor Rates
Labor Category Hourly Rate
Project Manager $ 136.00
Sr. Telemetry $ 128.00
Sr. Technology $ 128.00
Controls Engineer $ 128.00
CADD $ 78.00
Administrative Asst. $ 64.00
Ex ense Rates
Expense Category Billing Rate
Mileage $0.485/mile or current IRS rate
Outside Photocopies/Printing Cost + 10%
Transportation by Public Carrier Cost + 10%
Outside Services or Subcontractors Cost + 10%
Materials and Supplies Cost + 10%
Exhibit B
Agreement No. AG-C-280
Page 1 of 1
EXHIBIT C
CONSULTANT INVOICES
CONSULTANT invoices should contain the following information:
• On CONSULTANT letterhead.
• A cover letter stating the status of each task. This should include items completed, percent
completed during the billing period and completion along with funding status.
• Internal invoice number and/or sequential numeric number (i.e.: progress payment # 10).
• Invoice date.
• Period of time invoice covers.
• Consultant Agreement # (i.e.: AG-C-115).
• Project number(s) listed (i.e.: PR562).
• CITY'S project manager listed.
• The hour(s) per person broken down by task(s) (attach timesheets, spreadsheet detailing
timesheets, or some other form of proof) along with type of work done (i.e.: design,
right-of-way, or construction) or task order number.
Direct salary (base salaries)
• Indirect salary (benefits)
• Direct non-salary (i.e.: mileage, reproduction fees (i.e.: printing, copying), communication
fees (i.e.: telephone), supplies, computer charges, subconsultants), indirect non-salary
(overhead). The CITY does not pay for CONSULTANT meals unless part of a task requires
travel outside of the greater Seattle, Tacoma, and Everett area. These costs are to be
broken down and backup information is to be attached to invoice. Project managers are to
inform CONSULTANTS as to what is required for break down information and if backup
information is to be attached. Break out the same for subconsultant charges.
• Previous and remaining base contract amounts left in each task and total contract -total
authorized amount (bottom line figure). Add amendments to this base contract amount for
total authorized amount.
Percentage of work completed to date compared to total amount of work (if required by the
project manager).
• Status of Management Reserve Fund (MRF) (i.e.: a certain task) until we can get an
amendment in place.
• Invoices for previous year are due by January 15tH
• For grant/special funded projects there might be other special information needed,
reference the LAG manual.
Exhibit C
Agreement No. AG-C-280
Page 1 of 2
SAMPLE INVOICE
City of Auburn
25 West Main
Auburn WA 98001
Attn: Scott Nutter (Project Engineer)
Agency Agreement #: AG-C-010
Invoice #: 5222
Progress Payment #: 2
Invoice Date: February 10, 2002
Project Name: Thomas Nelson Farm
Project #: PR562
Engineering Services performed during the period of: January 2002
SAMPLE ENGINEERING, INC.
Personnel Hours Hourl Rate Amount
Mike Jones, Princi al in Char e 1 $ 125.00 $ 125.00
Carla Maker, Architect 5 $ 72.00 $ 144.00
Joe Smith, Word Processin 10 $ 48.00 $ 480.00
Consultant Personnel Subtotal $ 749.00
Ex enses see attached documentation Char es Multi lier Amount
Mike Jones, Princi al in Char e 20 miles x1.1 $ 7.59
Carla Maker, Architect $ 30.00 x1.1 $ 33.00
Joe Smith, Word Processin $ 29.00 x1.1 $ 31.90
Consultant Ex enses Subtotal $ 72.49
Consultant Total:
821.49
SUB CONSULTANTS (see attached documentation)
Subconsultant Hours Hourl Rate Amount
ABC Environmental, Inc., Civil En ineer 10 $ 100.00 $ 1,000.00
Electrical Consultin ,Electrical En ineer 5 $ 100.00 500.00
Mechanical Solutions, Mechanical En ineer 10 $ 100.00 MRF 1,000.00
Movin Com an ,Movin Consultant 2 $ 50.00 100.00
Subconsultant Subtotal $ 2,600.00
Subtotal x 1.1 Multi tier $ 2,860.00
Subconsultant Total:
TOTAL DUE THIS INVOICE
$ 2,860,00
$ 3,681.49
CONTRACT BREAKDOWN
%
Amount
Task Amount
Authorized Prior Invoiced This Invoice Totallnvoiced
To Date %
Ex ended Com leted Remainin
Original
Contract
$ 22,000.00
$ 1,025.00
$ 2,681.49
$ 3,706.49
20%
25%
45%
$ 18,293.51
00
500
1
MRF* 2,500.00 0.00 1,000.00 1,0000.00 40% .
,
51
793
$ 19
TOTAL $ 24,500.00 $ 1,025.00 $ 3,681.49 $ 4,706.49 .
,
Note: MRF=Management Reserve Fund
* Received a written authorization of MRF on 1110101 for Mechanical Engineer task in the amount of
$2,000.00.
Exhibit C
Agreement No. AG-C-280
Page2of2