Loading...
HomeMy WebLinkAboutCP1709 / 18-07 Seismic Control Valve Dq . 11 . 1 CITY OF AUBURN* Nancy Backus, Mayor WASH I NGTON 25 West Main Street * Auburn WA 98001-4998 * www.auburnwa.gov * 253-931-3000 December 3, 2018 CERTIFIED MAIL RETURN RECEIPT REQUESTED Mr. Vito Alia R. L. Alia Company 107 Williams Avenue South Renton, WA 98057 NOTICE TO PROCEED RE: Project No. CP1709, Reservoir No. 1 Seismic Control Valve, Contract#18-07 You are hereby notified to proceed as of December 3, 2018 with the work on the above- referenced project, within the time period specified, in accordance with the provisions of the contract documents, copy enclosed. This project has 105 working days for completion. If you have any questions, please contact the inspector for the project, Debra Alvarez at 253-876-1922 or the Contract Administration Specialist, Michelle Thompson at 253-288-4327. Sincerely, Jai H.K. Carter, P.E. Project Engineer Public Works Department JC/mt/as Enclosure cc: Shawn Campbell, City Clerk Jacob Sweeting, Assistant Director of Engineering/City Engineer Debra Alvarez, Project Inspector File 13.11 (CP1709) ENG-017, Revised 8/18 AUBURN * MORE THAN YOU IMAGINED CITY OF AuBuRNT Nancy Backus, Mayor WASH[N GTON 25 West Main Street * Auburn WA 98001-4998* www.auburnwa.gov * 253-931-3000 October 28, 2019 CERTIFIED MAIL RETURN RECEIPT REQUESTED Mr. Vito Alia R. L. Alia Company 107 Williams Avenue S Renton,WA 98057 RE: Contract No 18-07 Project No. CP1709, Reservoir No. 1 Seismic Control Valve Contract Completion and Acceptance Dear Mr. Alia: In accordance with Section 1-05.12 of the Contract Specifications, the above referenced contract is considered complete and accepted as final. The one-year warranty period begins as of the date of this letter. Enclosed is your Final Pay Estimate in the amount of$0.00 for the above-referenced project. The total contract amount for this project, as shown on your Final Pay Estimate is $475,669.87. Your Contract Bond must remain in full effect until the expiration of the lien period and there are no liens pending, then the penal sum of this bond, may be reduced to either ten percent(10%)of the value of the improvements to the City or two thousand dollars ($2,000.00), whichever is greater. Your retainage in the amount of$21,621.36 will be released within 60 days provided all necessary releases have been received and there are no outstanding claims against the retainage. If you have any questions, please contact Michelle Thompson, Contract Administrative Specialist at 253-288-4327. Sincerely, Jacob Sweeting, P.E. City Engineer/Assistant Director of Engineering Services Public Works Department JS/mt/as cc: Shawn Campbell, City Clerk Matt Larson, Senior Project Engineer Jai Carter, Project Engineer File 13.11 (CP1709) ENG-075, Revised 03/19 Au BU RN * MORE THAN YOU IMAGINED) t. CITY oF. . * ; * Construction Contract Final Payment 4IJBTJ No. 7, Cover Sheet / *$ . -mss WASHINGTON Project Name: Reservoir No.1 Seismic Control Valve Project Number: CP1709 Contractor: R.L.Alia Pay Period: 6/27/19-8/22/19 Retainage Option: City held retainage Retainage%(R): 5.000% Final Payment Summary Original Contract Value(A): $407,794.20 Contract Change Orders(B): $87,450.00 Current Contract Value(A+B): $495,244.20 Amount Earned to Date Including Tax and Retainage(C): $475,669.87 Amount Previously Invoiced.Including Tax and Retainage(D): $475,669.87 Amount Earned this Period Including Tax and Retainage(E=C-D): $0.00 Previous Sales Tax(X): $43,242.72 Current Period Sales Tax(Y): $0.00 Total Sales Tax(X+Y): $43,242.72 Previous Retainage Amount Held(PR): $21,621.36 Current Period Retainage Amount(CR=R*(E*(1-T))): $0.00 Total Retalnage Held(PR+CR): $21,621.36 Total Payment Amount Less Retainage(E-CR): $0.00 Total Contract Amount Spent Percentage 96.05% By signing below,the Contractor agrees and affirms to the following:"I have reviewed and approved this final pay estimate.I agree that it is a true and correct statement showing all monies due me from the City of Auburn under this contract;that I have carefully examined the final pay estimate and understand it and that I hereby release the City of Auburn from any and all claims of whatsoever nature which I may have,arising out of this contract,which are not set forth in this estimate."This final payment does not constitute Final Contract Acceptance/Completion by the City. Contractor: Inspector: f Project Manager: City Engineer: By:4i y Pte(<e ala.. By://c.I4r1. Alt)' 1? - By: i.; ,� iv By: e.,1 f Signed: "/� . �P Signed: `j Sig •: Signed: ,Date: Date: Date: Date: / . /emrd --/? /v r al,/ . 20/ I 10/24/19 41>1/i7 10/15/2019 Page 1/3 CITY Or * _ . ; ,* Construction Contract Final Payment ic, `" Q� ot No. 7, Schedule A - Water Improvements " WASHINGTON Project Name: Reservoir No.1 Seismic Control Valve Project Number: CP1709 Contractor: R.L.Alia Pay Period: 6/27/19-8/22/19 Retainage Option: City held retainage Retainage%(R): 5.000% Schedule Sales Tax Rate%(T): 10.000% Summary Original Contract Value(A): $407,794.20 Contract Change Orders(B): $87,450.00 Current Contract Value(A+B): $495,244.20 Amount Earned to Date(C): $475,669.87 Amount Previously Invoiced Including Retainage(D): $475,6.69.87 Amount Earned this Period Including Retainage(E=C-D): $0.00 Previous Sales Tax(X): $43,242.72 Current Period Sales Tax(Y=E*T): $0.00 Total Sales Tax(X+Y): $43,242.72 Previous Retainage Amount Held(PR): $21,621.36 Current Period Retainage Amount(CR=R*[E*(1-T)]): $0.00 Total Retainage Held(PR+CR). $21,621.36 Schedule Payment Amount Less Retainage(E-CR): $0.00 10/15/2019 Page 2/3 City of Auburn-Construction Contract Payment ..,,.,-_.* / Project No.CP1709,Project Name:Reservoir No.1 Seismic Control Valve,Contract No. CITY OF ---...40 .,•4.1.40-* 18-07 Itt. 0 .'" Schedule:A-Water Improvements Payment No.7-Final Atj-117. Sales Tax Rate:10.000% Period pates:Be in 6/27/19 End 8/22/19 b� Begin WASHINGTON Previous Current Contract Periods Period Total STD 94 Contract Item 0 or SP Sec# Description Qty Unit Unit Price Qty Amt Qty Ann Qty Mit Quantity C01-3 STD 0-00 Crane Rental 1.00 LS $5,000.00 0 *0.00 0 $0.00 0 $0.00 0.00% C01-2 STD 8-30 Seismic Control Valve 1.00 is $276,500.00 1.00 $276,500.00 0 80.00 1.00 $276,500.00 100.00% Alternate C01-1 STD 7-09 Connect to Existing 2.00 EA $25,000.00 2.00 $50,000.00 0 $0.00 2.00 $50,000.00 100.00% Water Malls 1 STD 1-04 Minor Changes 10000.00 EST $1.00 9,360.49 *9,360.49 0 $0.00 9,360.49 $9,360.49 93.60% 2 STD 1-07 SPCC Plan 1.00 LS $500.00 1.00 $500.00 0 *0.00 1.00 $500.00 100.00% 3 SP 1-07 Utility Potholing 1,00 EA 85,000.00 1.00 $5,000.00 0 $0.00 1.00 $5,000.00 100.00% 4 STD 1-09 Mobilization 1.00 LS $25,000.00 1.00 *25,000.00 0 $0.00 1.00 $25,000.00 100.00% 5 STD 2-09 Shoring or Extra 1220.00 SF $0.10 600.00 $60.00 0 $0.00 600.00 $60.00 49.18% Excavation Class 8 6 SP 7-08 CSTC for Select Trench 100.00 TON $60.00 119,11 $7,146.60 0 $0.00 119.11 $7,146.60 119.11% Backfill and Pipe Bedding 7 SP 8-01 Erosion Water Pollution 12000.00 EST *1.00 860.06 $86006 0 $0.00 860.06 $860,08 7.17% Control 8 STD 8-02 Seeding and Fertilizing 700.00 SY $3.00 0 $0.00 0 80.00 0 $1100 0.00% by Hand 9 STD 8-30 Seismic Control Valve 0.00 LS $252,000,00 0 80.00 0 80.00 0 $0.00 100,00% Vault,Complete 10 SP 8-30 Electrical and Controls 1.00 L5 $58,000.00 1.00 *58,000,00 0 $0.00 1.00 $58,000,00 100.00% - Subtotal $450,222.00 Subtotal $432,427.15 Subtotal $0.00 Total%complete 96.05% ._,_.___.__,..___.__,��.-__...._...._..__. •-•'----�--�-- Tax-,- $45,022.20 Tax-.-$43,242.72 -._ Tax $0.00 Total $495,244.20 Total $475,669.87 Total $0.00 10/15/2019 Page 3/3